Single Balance Commissioning Plan
Transcript of Single Balance Commissioning Plan
![Page 1: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/1.jpg)
127 September 202127 September 2021 1
Single Balance Commissioning Plan
Version 1.5
![Page 2: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/2.jpg)
227 September 2021
• Purpose of this document is to describe on a high-level how the introduction of the Single balance model affects
• Imbalance Settlement model
• the market participants’ operations and
• eSett’s interfaces
• This document describes what will change when the Single balance model will be taken into use:
• How imbalances are calculated, and the single balance position defined
• How the imbalance price is formed
• Describes the visible technical changes for the market participants in the operations between market participants and eSett
• Specifies the changes on Online Service user interface
• Summaries the changes in reporting of imbalance settlement results from eSett to BRP
• This document is an initial commissioning plan, and it will be updated based on the updated informationconcerning Single balance model
Commission plan for Single Balance – Single Price Model
![Page 3: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/3.jpg)
327 September 2021
Single Position –Single Price ModelHigh level concept
![Page 4: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/4.jpg)
427 September 2021
From two balances and single/dual pricing to single position and single price
• The new single balance model is introduced in the European regulation and Electricity Balancing Guideline
• The current imbalance settlement model will be changed from two balance model to single position – single price model
• Future imbalance settlement model (single price is used)
Financial settlement is
achieved by using dual price in
production and single price in
consumption
Financial settlement is
achieved by using single price
Curr
ent
New
![Page 5: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/5.jpg)
527 September 2021
The components of the new model will mainly remain the same in the formula
Metered and profiled consumption per metering grid
area per retailer per hour.
Consumption is divided into the following types:
grid losses, interruptible consumption, industry
consumption over 50MW, pumped storage and PU
own consumption.
Production on hourly basis.
Production is divided into two categories, Normal and
Minor. Following production types are defined:
hydro, wind, nuclear, thermal, solar and other.
Trade includes:
PX market trade, the electricity trade
concluded on the NEMO(s) – Day-ahead or
Intraday.
Bilateral trade, the electricity trade that has
been agreed upon between two market
participants.
Imbalance adjustment means the correction
applied to the position of a BRP (or later a
BSP) by TSO for the calculation of the
imbalance volume.
eSett calculates the MGA imbalance based
on reported values from the Metered Data
Aggregator. MGA Imbalance is calculated as
follows:
MGA Imbalance = Consumption + Production
+ MGA exchange import per adjacent MGA +
MGA exchange export per adjacent MGA
![Page 6: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/6.jpg)
627 September 2021
• Here below is presented an example of the BRP’s imbalance calculation (input values part). The example is made from the BRP’s perspective.
Example: Calculation of Imbalance Volumes (input values)
Imbalance MWh
Metered production 60
Profiled consumption -5
Metered consumption -15
Bilateral trades (purchase) 5
Day-ahead trades (sale) -25
Intraday trades (purchase) 5
MGA Imbalance -30
Imbalance adjustment (up regulation, sale to TSO) -10
![Page 7: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/7.jpg)
727 September 2021
• Here below is presented an example of the BRP’s imbalance calculation (calculation part). The example is made from the BRP’s perspective.
Example: Calculation of Imbalance Volumes (calculation)
Imbalance calculation [MWh]
Imbalance
calculation
Metered
Production
Metered +
Profiled
consumption
Bilateral +
Day-ahead +
Intraday
trades
Imbalance
Adjustments
MGA
imbalanceImbalance
Delivery
period60 -20 -15 -10 -30 -15
As a result of the BRP’s imbalance calculation there is a -15 MWh deficit in the BRP’s
imbalance. The BRP buys 15 MWh from eSett.
![Page 8: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/8.jpg)
827 September 2021
The main principles in the settlement will remain the same
• No changes to the market roles
• No changes to the reporting responsibilities
• No changes to the settlement cycle
• No changes to gate closures
• No changes to invoicing process
![Page 9: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/9.jpg)
927 September 2021
Imbalance price
• Imbalance is priced according to a single price model, which means that positive and negative imbalances have the same price per MBA.
• The imbalance price has now been proposed by the Nordic TSOs to be the same as the mFRRprice in the dominating direction.
• This is the same imbalance price as for the current consumption imbalance. This is technically achieved using the incentivising component.
• More information about imbalance prices can be found from Common Market Design description.
![Page 10: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/10.jpg)
1027 September 2021
Minor production structure changes
• In Finland and Norway, minor production is modelled in consumption balance in two balance model -> In single balance model minor production is modeled in a similar manner as normal production
• This change might lead to structure changes and RBR changes
• In Denmark and Sweden, all the production is using production type normal
• Retailer of minor Production Unit valid after Go-Live date must have valid Retailer Balance Responsibility (RBR) for production in the MGA where the PU is located
• In two balance model there needs to be a valid RBR for consumption in the MGA where the PU is located so in some cases there needs to be done adjustments
• eSett has identified three different scenarios:• Valid RBR for consumption and production (same BRP)➢ As valid RBR exist no changes needed
• Only valid RBR for consumption➢ BRP needs to create a new RBR for production
• Valid RBR for consumption and production (different BRPs)➢ eSett will contact the market participants and the correct changes will be done in
co-operation
![Page 11: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/11.jpg)
1127 September 2021
Production unit’s RE change in Finland exact on Go-live timestamp
• In general structures are created starting from 00:00 and ending to 24:00 with respecting the local time zone (in Finland EET)
• Norway and Denmark use CET, so no affect
• Sweden uses SNT which is during winter time same as CET, so no affect
• As single balance go-live is taking place at 00:00 CET, this might create a small manual adjustment need if a RE needs to be changing exact on the timestamp 1.11.2021 00:00 CET.
• If there occurs such a need for the PU’s retailer change for exact GL timestamp in Finland, please create an email to [email protected] where you inform clearly which PU(s) and RE(s) needs to be changed.
• eSett will adjust the change for the correct timestamp (1.11.2021 00:00 CET).
• Requests still need to respect the normal structural changes related gate closures which can be found from the Handbook.
![Page 12: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/12.jpg)
1227 September 2021
• eSett has been publishing Key Performance Indicators (KPI) and advanced settlement reports for BRPs since the beginning of year 2019
• Advanced settlement reports offers statistics and graphs to review performance and identify potential issues
• BRP imbalance KPI report provides data for benchmarking and general information about the performance of BRPs
• The main principles will be kept the same as today and only formulas will be adjusted to reflect changes caused by the single balance model
• Old KPIs will be used for business days before the Go-Live day and new KPIs will be used for business days after Go-Live
• As the production plan component is removed from imbalance calculations, a new KPI/formula will be established for monitoring long-term quality of production plans, Production Plan KPI:
• Calculate KPI for aggregated values per MBA per PU type (solar etc.)
Market Monitoring - Key Performance Indicators will be modified to fit to the new model
![Page 13: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/13.jpg)
1327 September 2021
• Imbalance Result:
• Imbalance Factor
• Imbalance Skewness
Adjusted formulas on Single balance model
![Page 14: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/14.jpg)
1427 September 2021
• Relative Imbalance
• Production Imbalance Loss KPI is no longer relevant as single price is used instead of dual pricing
Adjusted formulas on Single balance model
![Page 15: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/15.jpg)
1527 September 2021
Advanced Settlement Report (Week/Month) changes
Old charts will be removed, and
new charts will replace them
![Page 16: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/16.jpg)
1627 September 2021
BRP Imbalance KPI Report (Own Data/Country) changes
![Page 17: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/17.jpg)
1727 September 2021
BRP Imbalance KPI Report new formula
New BRP Imbalance KPI Report’s threshold values per
country will be the same as current threshold values on
Consumption Imbalance side
![Page 18: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/18.jpg)
1827 September 2021
• eSett will start to use the new model after the Single balance model Go-Live date (GL) is introduced
• Delivery days before GL will be calculated using the two balance model (e.g. where there is separate Consumption and Production imbalance)
• Delivery days after GL will be calculated using the single balance and single price model
• eSett will report settlement results based on which model the delivery day is using (before or after GL). During the transition period the settlement results consist of:
• Two balance model results
• Single balance results
• Some attributes will be changed in the dataflows due to the Single balance model
Transition phase reporting
![Page 19: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/19.jpg)
1927 September 2021
Imbalance Settlement Agreement’s Appendices will be amended
• The Imbalance Settlement and Pledge and Right of Disposal of Cash Account will not be amended
• Appendices will be amended to reflect the changes of the model
• eSett will notice the market participants at least one (1) month beforehand
• New appendices will be published on www.eSett.com
• No resigning of the agreements required
• Single price version of NBS Handbook has been published
Agreement / Appendix
Imbalance settlement agreement No changes
Appendix 1 FeesMinor updates,
see next page
Appendix 2 CollateralsMinor updates,
see next page
Pledge and Right of Disposal of Cash Account Agreement No changes
On-Demand Guarantee No changes
![Page 20: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/20.jpg)
2027 September 2021
Amendments due to Single Balance Model in Agreement Appendices
Appendix 1 Fees Appendix 2 Collaterals
• The applicable fee rates per fee category and country are amended
Volume Fee
Imbalance Fee
Weekly Fee
Peak Load Reserve Fee
• Collateral formula will remain as today.
• Fees and prices will be updated to reflect single balance model used
Consumption Fee
Production Fee
Consumption Imbalance Fee
Weekly Fee
Peak Load Reserve Fee
Two balance Single balance
![Page 21: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/21.jpg)
2127 September 2021
Balance Agreement update needs
• Balance agreements will be updated in Finland in September-October 2021
• Fingrid will terminate the current Balance Agreement on 1.11.2021 01:00 EET
• eSett will co-ordinate the renewal
• Electronic signing will be used
• In Denmark, Norway and Sweden, the change will not require changes to the Balance agreement.
21
![Page 22: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/22.jpg)
2227 September 2021
Commissioning time scheduleC
om
mis
sio
nin
g
2020 2021
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Single balance compactible NBS Handbook available
(English version)
Development of internal processes and IT-systems
Go-Live
1.11.2021
Agreement updates Minor production
structure changes
will be done before
Go-Live date
As the changes in communication/data change are very limited,
eSett sees that there are no need for market testing period
Customer
CommitteeCustomer
Committee
![Page 23: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/23.jpg)
2327 September 2021
Changes to the Market Participants
![Page 24: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/24.jpg)
2427 September 2021
Changes to BRPs - Settlement
• Minor Production Unit Structures
• Retailer of minor Production Unit valid after Go-Live date must have valid Retailer Balance Responsibility for production in the MGA where the PU is located.
• Possible changes to RBR relations will be adjusted co-operation with BRP and eSett
• Prices
• Consumption Imbalance Purchase price, Consumption Imbalance Sales price, Production Imbalance Purchase price and Production Imbalance Sales price will be replaced by Imbalance Purchase price and Imbalance Sales price
• Price for Imbalance Purchase and Sales will be the same per imbalance settlement period (hour)
![Page 25: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/25.jpg)
2527 September 2021
Changes to BRPs - Fees
• Fees
• Consumption Imbalance Fee will be removed
• New Imbalance Fee will be introduced
• Consumption Fee and Production Fee will be removed
• New Volume Fee will be introduced
• Based on total consumption and production volumes
• Does not apply to Denmark as this fee will be collected through the grid tariffs instead
• More information about Fees can be found from Common Market Design description
The picture above is taken from Single price and Single position –implementation
in the Nordics Common Market Design description document
![Page 26: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/26.jpg)
2627 September 2021
Changes to BRPs - Invoice content will change to reflect new model
• Invoicing period and schedule remain the same
• Just a few invoice products will be changed
• Old invoice products will be used for business days before the Go-Live day and new Invoice products will be for used business days after Go-Live
Old Invoice product New Invoice product
Sold consumption imbalanceSold imbalance
Sold production imbalance
Purchased consumption imbalancePurchased imbalance
Purchased production imbalance
Consumption FeeVolume Fee
Production Fee
Consumption Imbalance Fee Imbalance Fee
![Page 27: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/27.jpg)
2727 September 2021
• Main principle will be kept the same in the dynamic collateral calculation
• Two-balance model related components will be replaced by single balance model components
• The dynamic collateral model will not apply during the transition period, and a manual collateral demand will be applied until there is sufficient data to calculate the dynamic collateral demand according to single balance model components
Changes to BRPs – Dynamic Collateral model will be adjusted to new model
Before GL Transition period After transition period
Calculation of Collateral Demand for
two-balance model regime will be
used
Calculation of Collateral Demand will
be paused. Instead, manually set
demand will be used (5 full weeks)
Calculation of Collateral Demand for
singe balance model regime will be
used
![Page 28: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/28.jpg)
2827 September 2021
Collaterals during transition period 1.11.2021 – 5.12.2021
• The collateral demand formula's components, except price component “P”, from week 43 will be applied as a manual collateral demand for the next 5 weeks until there is sufficient data for the collateral formula .
• eSett monitors the prices and will evaluate if a new collateral demand needs to be published to mitigate the counterparty risk.
• A new collateral demand will be published for a BRP if there is a significant increase in imbalance prices.
• The dynamic formula will be in use again on week 49.
![Page 29: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/29.jpg)
2927 September 2021
• Single balance will reduce the amount of dataflows but the content of the dataflows will be the same
• The changes are the same for Online Service Data packages and Information service in dataflows
Changes to BRPs – number of data package will decrease
Old Data package New Data package
Consumption Imbalance – Preliminary ResultsImbalance – Preliminary Results
Production Imbalance - Preliminary Results
Consumption Imbalance – Final ResultsImbalance – Final Results
Production Imbalance – Final Results
Consumption Imbalance – Invoiced ResultsImbalance – Invoiced Results
Production Imbalance – Invoiced Results
Consumption imbalance per BRP per MBA (volume and amount)Imbalance per BRP per MBA (Volume and Amount)
Production imbalance per BRP per MBA (volume and amount)
Example on how data packages will be sent on day D+2 (where D is the Go-live day)
![Page 30: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/30.jpg)
3027 September 2021
Changes to BRPs – Online Service views
• Adjusted Market Reports and KPIs will be used (detailed description available in the updated NBS Handbook and in this document)
• New “Imbalance” view will be added which uses same principles as Consumption/Production Imbalance view under Settlement part
• New “Imbalance” radio button will be added which uses same principles as Consumption or Production radio button in Balance Report view
• Invoicing Report will work as before, all related invoice products for selected time period will be presented
• New Data Packages will be included in the list in Data Packages Management view
• New Fees will be visible on the Fees view
![Page 31: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/31.jpg)
3127 September 2021
Settlement – Imbalance viewUsername
![Page 32: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/32.jpg)
3227 September 2021
Settlement – Balance Report view
REsMGAs
Market
Parties
Username
![Page 33: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/33.jpg)
3327 September 2021
Finance – Invoice Report viewUsername
![Page 34: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/34.jpg)
3427 September 2021
Production plans in Online Service
• Even though production plans are not part of theimbalance settlement calculation in single balancemodel, the structures and input data will be visiblein Online Service also in the future.
• TSOs continue reporting production plan values to eSett.
• The data packages with production plans will continue to be sent to the BRPs as they are now.
![Page 35: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/35.jpg)
3527 September 2021
For DSO and datahubs – single balance model introduces only minor changes
• Structures for Minor Production Unit
• Retailer of minor Production Unit valid after Go-Live date must have valid Retailer Balance Responsibility for production in the MGA where the PU is located.
• These RBR relations need to be adjusted in co-operation with the BRP and eSett if needed.
• Merged Production message (MEPI) can’t be sent for time period which covers both two balance and singe balance settlement days
• When sending MEPI, it is needed to split validity for the days before GL date and the days after GL date
• If MEPI’s validity covers days both side of GL date, it will get rejected
![Page 36: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/36.jpg)
3627 September 2021
Changes for RE
• Minor Production Unit structures
• Retailer of minor Production Unit valid after Go-Live date must have valid Retailer Balance Responsibility for production in the MGA where the PU is located.
• These RBR relations need to be adjusted co-operation with the BRP and eSett if needed.
• Online Service views
• New “Imbalance” radio button will be added which uses same principles as Consumption or Production radio button in Balance Report view.
![Page 37: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/37.jpg)
3727 September 2021
Key documents provide detailed information on changes
• NBS Handbook (Single balance compatible version)
• Link
• Online Service – User guideline
• Single Balance related Data Package examples
• Link
• NBS Business Requirement Specifications (BRS) –document
• Single price and Single position – implementation in the Nordics: Common Market Design description
• Link
![Page 38: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/38.jpg)
3827 September 2021
Version Date Changes
1.0 27.5.2020 - First version of the Single Balance commisioning plan released
1.1 16.10.2020 - Information about Imbalance price updated
- Commisioning time schedule updated
- Information about new Fees updated
- MEPI-message information concerning DSO/Datahubs added
1.2 12.4.2021 - Example: Calculation of Imbalance Volumes
1.3 17.5.2021 - Information about agreement renewal updated
- Commissioning time schedule updated
- Key documents updated: Link to the Single Balance Handbook and data package examples
1.4 15.9.2021 - Information about transition period collaterals updated
- Online Service views’ examples added
- Information about Production plans added
1.5 28.9.2021 - Slide about Production unit’s RE change in Finland exact on Go-live timestamp added
Change Log
![Page 39: Single Balance Commissioning Plan](https://reader031.fdocuments.in/reader031/viewer/2022013000/61c9a130b698704a902cd034/html5/thumbnails/39.jpg)
3927 September 2021
WE SETTLE, TOGETHER!
• Create Customer Service Request on www.esett.com/contact
• Send email to [email protected]
• Call +358 10 5018500
In case you need more information, please contact
eSett Customer Service