Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of...

13
European Journal of Scientific Research ISSN 1450-216X / 1450-202X Vol. 150 No 4 November, 2018, pp. 496-508 http://www. europeanjournalofscientificresearch.com Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim Cesar Augusto da Cunha Vilela Pontifícia Universidade Católica de Goiás (PUC/GO), Goiânia, GO E-mail: [email protected] Ricardo Luiz Machado Pontifícia Universidade Católica de Goiás (PUC/GO), Goiânia, GO E-mail: [email protected] Karolline Fernandes Siqueira Pontifícia Universidade Católica de Goiás (PUC/GO), Goiânia, GO E-mail: [email protected] Abstract The research aims to reduce the arrival rate of concrete mixer trucks by enhancing the process of unloading the concrete to concrete slabs, applying the computational simulation. The process is carried out by truck-mixers aided by a pump-lance assembly to discharge the concrete into the slabs. The data were collected in the field, quantifying the time of arrival, the beginning and the end of the concrete discharge by concrete mixer trucks, checking the waiting times. The results of the simulation found a rate of reduction of the time between arrivals of 20%, reducing idleness of the observations by 34% for a mean time of permanence of the truck between arrival and end of discharge of 29.30 minutes below the limit prescribed by NBR7212 / 12 of 30 minutes. The application of this work provides a model to reduce the loss of time (idleness) by assisting in the supply of the concrete machined in the concreting of the vertical constructions using truck-mixer trucks with pump-lance, providing precedents for future studies in this area. Keywords: Queue Concrete Discret event Flexsim.Simulation 1. Introduction The construction industry has increasingly required practices that contribute to the optimization of procedures, reduction of waste and delivery of higher quality products. In this context, it is essential to carry out internal evaluations of the practices adopted at the building site. The analysis and simulation of the supply chain can contribute to the improvement of the methods used in the construction industry. In Brazil, the construction industry and its supply chain play an essential role in the economy handling 5.6% of Brazil's Gross Domestic Product (GDP) (IBGE, 2017). Akhavian and Behzadan (2014) recognize that many activities in which queues arise in the construction process are almost inevitable. Delays generated by lines cause disruptions in the work schedule, affecting the flow of financial resources designed. In dealing with productivity, problems of the concreting process studies have recognized the importance of simulation for an adequate supply of concrete at the construction site. Smith (1998) has developed a concrete supply model using coded Visual Basic for Excel. Wang, Teo & Ofori (2001)

Transcript of Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of...

Page 1: Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

European Journal of Scientific Research

ISSN 1450-216X / 1450-202X Vol. 150 No 4 November, 2018, pp. 496-508

http://www. europeanjournalofscientificresearch.com

Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

Cesar Augusto da Cunha Vilela Pontifícia Universidade Católica de Goiás (PUC/GO), Goiânia, GO

E-mail: [email protected]

Ricardo Luiz Machado Pontifícia Universidade Católica de Goiás (PUC/GO), Goiânia, GO

E-mail: [email protected]

Karolline Fernandes Siqueira Pontifícia Universidade Católica de Goiás (PUC/GO), Goiânia, GO

E-mail: [email protected]

Abstract

The research aims to reduce the arrival rate of concrete mixer trucks by enhancing

the process of unloading the concrete to concrete slabs, applying the computational

simulation. The process is carried out by truck-mixers aided by a pump-lance assembly to

discharge the concrete into the slabs. The data were collected in the field, quantifying the

time of arrival, the beginning and the end of the concrete discharge by concrete mixer

trucks, checking the waiting times. The results of the simulation found a rate of reduction

of the time between arrivals of 20%, reducing idleness of the observations by 34% for a

mean time of permanence of the truck between arrival and end of discharge of 29.30

minutes below the limit prescribed by NBR7212 / 12 of 30 minutes. The application of this

work provides a model to reduce the loss of time (idleness) by assisting in the supply of the

concrete machined in the concreting of the vertical constructions using truck-mixer trucks

with pump-lance, providing precedents for future studies in this area.

Keywords: Queue Concrete Discret event Flexsim.Simulation

1. Introduction The construction industry has increasingly required practices that contribute to the optimization of

procedures, reduction of waste and delivery of higher quality products. In this context, it is essential to

carry out internal evaluations of the practices adopted at the building site. The analysis and simulation

of the supply chain can contribute to the improvement of the methods used in the construction industry.

In Brazil, the construction industry and its supply chain play an essential role in the economy handling

5.6% of Brazil's Gross Domestic Product (GDP) (IBGE, 2017).

Akhavian and Behzadan (2014) recognize that many activities in which queues arise in the

construction process are almost inevitable. Delays generated by lines cause disruptions in the work

schedule, affecting the flow of financial resources designed.

In dealing with productivity, problems of the concreting process studies have recognized the

importance of simulation for an adequate supply of concrete at the construction site. Smith (1998) has

developed a concrete supply model using coded Visual Basic for Excel. Wang, Teo & Ofori (2001)

Page 2: Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

Simulation of Ready Mixed Concrete Supply Chain in the

Building Industry using the Software Flexsim 497

presented a simulation model using the @Risk spreadsheet integration software. Akhavian and

Behzadan (2014) have used the @Risck programs to adjust distributions simulating row discipline in

STROBOSCOPE. Zayed and Halpin (2001) performed simulations using microCYCLONE and

highlighted optimal supply areas around a construction site demonstrating a more efficient resource

allocation with minimum delivery time.

Anson and Wang (1998) reported that there is considerable difficulty in supplying concrete

promptly due to the limited number of trucks and traffic conditions because it has many variables

involved generating a lot of unpredictability. Meanwhile, Smith (1998) in his study on modeling and

simulation in the concrete supply process concluded that one of the factors to maximize performance in

the concreting method would be to reduce the arrival rate of concrete mixer trucks. Smith found that

the difficulty in supply would lie in the interaction between the times between the arrivals of the

concrete and the rate of rejection.

In this regard, Azambuja and Chen (2014) conducted a simulation to assess supply chain risks

to identify vulnerabilities and measure the impact of ruptures in the machined concrete supply chain.

For this, they implemented a tool for fault diagnosis, effects and critical analysis (FMECA). They

concluded that in real industrial environments, the sources of uncertainties are numerous and to obtain

reliable results, we need to have a reliable estimate of these possibilities. For example, a variation in

the time between arrivals of the trucks in work to obtain more favorable scenarios.

Richard and John (2017), in their study on green logistics and the management of the concrete

supply chain, used a dynamic model of supply proposing less waste of time in the supply process. They

observed 100 concrete delivery events generating an average time of arrival in the queue of twenty

minutes and forty-five seconds and the discharge period of fifteen minutes and fifty-four seconds.

Costa et al. (2013) observed 31 deliveries of concrete for three building sites, finding an

average waiting time of 2 hours and 30 minutes, which means that the teams were idle or underutilized

during this period, generating a loss of time and physical and financial resources. The authors also

report the average time for unloading concrete in a slab at twenty-one minutes.

Wang, Teo & Ofori (2001) observed 50 arrivals and departures of concrete mixer trucks,

verifying an average arrival time of trucks of eleven minutes. The authors noted that longer arrival

times reduced the number of trucks on building site. However, it contributed to the reduction of

utilization rates of the concreting process.

Park et al. (2010) developed a dynamic simulation model for the concrete supply process at the

building site where they analyzed 100 deliveries of concrete mixer trucks to the construction site

obtaining an average arrival time in the queue of twenty minutes and five seconds. In their study, the

authors noted that the information generated by the model allows optimum supply of concrete while

maintaining a desirable number of trucks waiting in line to meet the concrete process at the building

site. This dynamic model developed through simulation could be used as a useful automated tool to

assist concrete suppliers in procurement planning.

In concreting operations, the Brazilian Association of Technical Standards (ABNT, 2012)

establishes that the unloading of the concrete must take place until thirty minutes after the arrival of the

truck mixer in the building site. In situations where it is not possible to obtain this reference time, a

technical solution must be evaluated to avoid compromising the quality of the concrete as well as its

validity.

The objective of this study was to find an arrival rate of concrete mixer trucks that potentiates

the concreting process through simulations using the FLESXIM computational tool. For this, we

collected the truck-mixer arrival periods and their respective times of unloading of concrete. From the

identification of the times, we proposed a new configuration of the concrete supply system, to improve

the performance of this process in the building site. We present the results comparatively through the

analysis of several scenarios to identify the best configuration about the parameters prescribed by

ABNT (2012), assisting managers of works in decision-making.

Page 3: Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

498 Cesar Augusto da Cunha Vilela, Ricardo Luiz Machado and Karolline Fernandes Siqueira

2. Theoretical Foundation 2.1 The Construction Industry Supply Chain

According to Oliveira (2007), the construction process involves a scheduled progression for the

execution of activities. Planning must take place correctly to gain productivity and, consequently,

speed. This harmonic sequence must begin at the foundation and go through the various stages of the

building site. The construction processes represent value creation of a business and can translate to

efficient, regular and timely delivery. With the influence of total quality and time-based competition,

many companies were encouraged to take steps to reduce their costs and process cycle times.

Machado (2003) conducted a survey of information for the improvement of the production

process influencing the construction planning. He found restrictions that hindered the flow of the

existing production processes in the building site under study, causing losses of time. Subsequently, he

proposed a treatment of information, transforming them into management actions, which called

anticipations, which should then be inserted into the production plan.

Moon (2014) observed field operations for a concreting process that generated problems in the

activity flow. He found information failures causing interruptions in the process, lack of preparation

until the concrete unloaded, lack of identification of the location of the concrete launched, delays in the

arrival of the trucks with the concrete, and loss of critical information such as the traceability of the

concrete in the structure.

The author proposed a model aimed at improving the quality of the operational process to

minimize waste of time generated by inactivity (idle or wait time), which in turn can cause high costs

for the project.

The study of the construction supply chain has grown in importance over the years, signaling

that the proper management of this chain can have a significant impact on local and national

economies, given the high volume of business that moves nationally. However, experiments with

supply chains can be complicated, and computational simulation becomes a tool with high potential for

their study (WALSH et al., 2004).

2.2. Queue and Simulation Systems According to Mesquita and Hernandez (2006), two current topics in research on management science

are queuing theory and discrete event simulation. The queuing method refers to the development and

implementation of analytical models of closed shape and standby lines. A dedicated simulation

software usually performs the discrete event simulation. Queuing theory presents a closed form that is

not capable of analyzing most of the complex systems that are in practice, and the simulation of

discrete events emphasizes simulation software features rather than basic concepts of discrete events.

Bateman et al. (2013) report that the increasing use of modeling and simulation is a good

indicator that this idea has been used to generate useful results. Almost all studies that intend to use

this method has produced some model to facilitate understanding. Therefore, it is increasing the

number of models designed to explain business principles and engineering.

According to Law (2010), most real-world systems are too complex to evaluate realistic models

analytically. These models should be studied by observing scenarios proposed by simulations. In a

simulation, we use a computer to assess a model numerically, and the data is collected to estimate the

characteristics of reality.

For Bateman et al. (2013) many companies are worried about failure in operations. It ends up

obstructing the managers to offer suggestions based on their knowledge, ideas, and creativity.

Therefore, the simulation is an excellent tool to overcome this fear. The possibility of analyzing a new

proposal by a simulation model allows testing the impact of the suggestions. The use of this device,

therefore, is essential so that there are changes to the decision makers.

Akhavian and Behzadan (2014) argue that the interest of an operations manager on the queue is

to know the waiting time, which resource delays, the length of service and the logistics of the line. Such

Page 4: Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

Simulation of Ready Mixed Concrete Supply Chain in the

Building Industry using the Software Flexsim 499

knowledge is critical for allocating resources, layout, production forecasts, and determining the duration

of individual operations. For this, simulation models have been widely used in queuing systems.

2.3. Modeling and Simulation

Simulation Models are logical descriptions of the interactions among the elements of a decision

problem or sequence of events occurring in a system. They capture the probabilistic behavior and allow

statistically estimate the probability distributions or averages that cannot be derived analytically. The

simulation models capture the dynamics and functioning of interacting elements of a system. The

variances occurring in the system drive these models (Evans, 2000).

Bateman et al. (2013) discuss the simulation as being the experimentation of a real system

through models, generating the possibility of creating and simulating desired phenomena. The process

of the conference and analyzing changes contributes to decision making. For these authors, the

beginning of the simulation is uncertain, but its importance and application as a tool is evident.

Simulation is the best tool to observe a real operating system, allowing study the situation even

when you cannot experience it. It is a significant benefit when the system does not exist or when it is

too expensive or difficult to implement it. Thus, we can consider simulation an experimental

application that, applied to a methodology, seeks to describe the behavior of a system and use the

model to predict its future behavior (Shannon, 1998).

Chwif and Medina (2010) state that we use the simulation model to obtain answers since it can

capture more accurately the characteristics of real systems. The simulation model allows analyzing

virtually the behavior that a system would present when subjected to the same conditions of reality

through repetition in a computer.

According to Law (2007), it is often practically unfeasible to evaluate a production system

within its real environment. A simulation model is ideal to minimize this difficulty. Models can

involve discrete event simulation, continuous simulation, and Monte Carlo simulation. The discrete

and continuous simulations consider the evolution of the system over time.

The discrete event simulation (DES) uses a logical or mathematical model to analyze state

changes at precise points that are discrete over the simulated time. In the late 1950s, DES evolved to

become one of the most commonly used modeling techniques coupled with the development of

computing (ROBINSON, 2004).

According to Montevechi et al. (2007), the DES comprises three stages: design, involving the

development of a conceptual model; implementation by generating the computational model; and

analysis, obtaining the operating model. In this work will be used a theoretical modeling technique,

called IDEF-SIM. Leal et al. (2008) proposed this method, who used and adapted logical elements of

the IDEF0 and IDEF3 modeling techniques, allowing the elaboration of conceptual models with useful

information to the computational model. A hierarchical series of diagrams support the technique,

which show levels of detail for describing functions and interface with the system.

To prepare the computer model a suitable choice of the simulation software is essential.

Currently, there are several software options available, which differ in its primary applications, vendor

and user criteria, model translation, animation and specific tools. Banks et al. (2010) identify some of

options: AnyLogic®, Arena®, AutoModTM, Enterprise Dynamics®, exteNdTM, Flexsim,

ProModel®, and SIMUL8®.

2.4. FLEXSIM Simulation Software

According to Tijan, Aksentijević, HACA (2014), the Flexsim is a tool used mainly to simulate discrete

events. The system behavior is described a non-continuous way, as a sequence of different events and

activities. We use discrete simulations primarily to model and analyze systems with waits and compare

them with the actual system and its resources.

Page 5: Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

500 Cesar Augusto da Cunha Vilela, Ricardo Luiz Machado and Karolline Fernandes Siqueira

Flexsim is a software for this type of application, used to model and simulate different systems

from different industries. Furthermore, it provides options to adjust the original data, model input data,

build graphical models, perform simulation experiments, run the model, optimize the results and

generate animation files in 3D. Its structure allows simulation model interface with other

computational tools, such as ExperFit and spreadsheet Microsoft Excel, besides the evaluation

scenarios focusing on the optimization by the Experimenter (Chen et al., 2013).

We can define and program the FlexSim® objects in four classes. The fixed resource class

comprises the principal objects of the simulation, determining the flow of the simulation model

(arrival, queues, processors, means of transport and output). The task execution class, which mainly

assign tasks to other objects, such as operators and carriers. The node class includes objects used to

design the route of work. We use the class of visual object to display the objects and collect incoming

and outgoing messages, such as diagrams and texts (Flexsim, 2017).

The use of computer modeling programs and simulation systems in the construction sector is an

important initiative to boost the competitiveness of companies in this industry, through the

identification and resolution of production bottlenecks as well as possible and with the least time. In

this work, we selected the Flexsim software to indicate the interventions to benefit the concreting

system.

3. Scientific Methodology We adopted a modeling and simulation approach aiming at creating and experimenting a physical

system of the concreting process through a computer model.Four building sites were adopted to study

with constructive characteristics presenting similarities regarding their nature, construction process,

technique, number of floors, and the constructed area as showed in Table 1.The launch of concrete was

performed using a pump truck striker, who received concrete and pumped through metal pipes to the

location of the slabs. After dumping the concrete, the teams began the process of densification,

regularization (leveling) and molding of the concrete.

Table 1: Characteristics of the building sites

Building site Nature Number of floors Constructed area (m2)

1 Residential / Commercial 28 2,800

2 Residential 33 2,000

3 Residential 40 1,800

4 Residential / Commercial 36 2,500

Source: The authors (2018)

Through field observation, we collected the times involved in the study process, using a

stopwatch and a form. We gathered the date of collection, information on weather conditions, the

number of internal control mixer truck, instant record that the mixer truck arrived at the queue,

beginning and completion of the unloading of the concrete mixer truck, and return to the concrete

manufacturing plant.

Initially, we selected a pilot sample of 50 observations as showed in Table 2, based on the

studies of Wang, Teo & Ofori (2001) and Costa et al. (2013).

Page 6: Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

Simulation of Ready Mixed Concrete Supply Chain in the

Building Industry using the Software Flexsim 501

Table 2: Samples extracted from the building sites for arrivals and discharges times

Time between arrivals (hour) Time between discharges (hour)

Building site 1

Building site 2

Building site 3

Building site4

Building site 1

Building site 2

Building site 3

Building site 4

0.000 0.000 0.000 0.000 0.133 0.417 0.600 0.233

1.000 0.933 0.033 0.183 0.250 0.617 0.667 0.317

0.633 0.483 0.100 1.083 0.217 0.333 0.317 0.500

0.283 0.750 1.150 1.117 0.267 0.450 0.200 0.533

0.250 0.517 0.600 1.300 0.283 0.500 0.217 0.550

0.683 0.317 0.333 1.900 0.233 0.233 0.150 0.333

0.500 0.833 0.167 1.000 0.217 0.633 0.283 0.300

0.583 0.333 0.517 0.233 0.250 0.217

0.483 0.783 0.600 0.217 0.250 0.183

0.267 0.467 0.000 0.217 0.417 0.283

1.200 0.833 0.000 0.267 0.250 0.133

0.450 0.167 0.483 0.217 0.250 0.250

0.317 0.333 0.200 0.250

0.817 1.583 0.333 0.333

0.900 0.333 0.250

1.467 0.383

Source: The authors (2018)

Then, to certify that the sample dimension was appropriated, we considered the Equation 1 to

calculate the minimum sample size. We found a standard deviation for the pilot sample of 27.32

minutes. We considered a 95% confidence interval and a sampling error of 7.5 minutes. These

parameters revealed from the equations (1) and (2) a sample with a minimum size of 50 observations

coinciding with the size of the pilot sample preliminarily suggested.

� =��/� .

√�= �. � � ��.�

√��= 7,5 minutes (1)

� = ��/� .!²

#²= $�. � � ��.�%²

�.�² = 50 records (2)

Where:

Zα/2 = confidence interval for 95%;

σ = standard deviation;

E = sample error;

n = sample size.

Each mixer truck could transport a volume of 8 m³ of concrete. The concrete was pumped

through metal pipes to the programmed locations of discharge into slabs.After the concrete was

discharged, the teams began the process of densification, regularization (leveling) and molding of the

concrete.

To perform the modeling of the concreting process, we adopted the proposal presented by

Tijan, Aksentijević&Hlaca (2014), as shown in Picture 1. For these authors, it is important to exclude

all elements that make the model more complicated and do not contribute significantly to the quality of

the responses obtained.

Page 7: Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

502 Cesar Augusto da Cunha Vilela, Ricardo Luiz Machado and Karolline Fernandes Siqueira

Picture 1: Modeling process, from problem definition to results analysis

Source: The authors (2018)

We use the IDEF-SIM methodology to create the conceptual model (Picture 2). The purpose of

this resource is to create a theoretical model of the process containing elements necessary to the

computational modeling phase, facilitating the elaboration of the model. This model follows the

concrete supply flow assessing the time of arrival, waiting in the queue and unloading the concrete in

the system according to Picture 2.

Picture 2: IDEF-SIM Conceptual Model of Machined Concrete Supply Process

Source: The authors (2018)

We used the FlexSim software to develop the current computational model and its simulation

(Picture 3). The ExpertFit® software was also associated with Flexsim to perform the function to find

the probability distribution models that best fit together in the set of data entered into the system.

Problem definition

Analysis of the

production system

Model creation

Validation

Simulation

Analysis of results

Truck

Input

Line Discharge

OutputDisplacement

Page 8: Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

Simulation of Ready Mixed Concrete Supply Chain in the

Building Industry using the Software Flexsim 503

Picture 3: Computational model of the machined concrete supply process

Source: The authors (2018)

Picture 3 shows the three processes (Arrival, Line and Discharge) considered in the

computational model developed to represent the actual concreting process. The mix concrete supply

system starts in the output of the mixer trucks of plants (Arrival) and reaches the places prepared for

discharge (Line) in the building sites. The concrete is dumped into lops (Discharge) from which it is

pumped through metal pipes to the discharge site. After the end of discharge (Output), the truck returns

to the concrete factory.

To evaluate the best arrival rate, with the decrease of the idleness of the process and increase of

its use, we created six scenarios about the collected distribution. For this analysis, we considered

reductions in the arrival rate of 10%, 15%, 20%, 30%, 35% and 40% for each scenario and maintained

the same discharge distribution.

4. Analysis of the Results According to the described methodology, we chose the building sites considering the similarities in the

execution process and the concrete supply. The number of trucks varied in each building site due to the

size of the slabs, changing the volume of concrete supplied, as shown in Table 1.

Table 1: Arrival times, unloading beginning and ending

Building site Observations Arrival time (min) Discharge time (min) Total time

(min) Total Median Total Median 1 16 590.00 32.50 240.00 14.00 830.00

2 15 505.00 29.00 326.00 20.00 831.00

3 12 239.00 15.00 210.00 14.00 449.00

4 7 335.00 66.00 148.00 25.00 483.00

Total 50 1669.00 29.00 924.00 15.00 2593.00 Source: The authors (2018)

For the building sites 1, 2, 3 and 4, the samples were, respectively, 16, 15, 12 and 7

observations, totaling 50, taking into account the minimum sample size for this research. The sample

produced a median between arrivals of 29 minutes and a median of 15 minutes for the discharges. The

total time of the observations, considering the arrival until the end of the discharge was 2593 minutes.

By simulating the discharge times of the sample in Flexsim, we obtained the log-logistic

distribution,classified as continuous, as shown in Picture 4.

Arrival Line Discharge Output

Page 9: Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

504

Source: The authors (2018)

fat

defined as continuous as well as the log

Source: The authors (2018)

from minimum and maximum, having the function of characterizing times for s

for planning.

discharge process, without exceeding the queuing and discharge time of 30 minutes, as predicted by NBR

7212 (2012), the distrib

and 40%. For each proposed reduction, we simulated a new distribution, as presented in Table 2.

Table 2:

Sample

Reductionof 10%

Reductionof 15%

Reductionof 20%

Reductionof 30%

Reductionof 35%

Reductionof 40%

Source: The authors (2018)

504

Source: The authors (2018)

The distribution shown in Picture 4 is commonly used in reliability analysis in cycles until

fatigue failure, material resistance, and probabilistic design with variable loads.

The simulation of the distribution of inter

defined as continuous as well as the log

Source: The authors (2018)

The parameters of the sample of the arrival times of the truck mixers in the building sites differ

from minimum and maximum, having the function of characterizing times for s

for planning.

In order to discover a time distribution between arrivals that would enhance the use of the

discharge process, without exceeding the queuing and discharge time of 30 minutes, as predicted by NBR

7212 (2012), the distrib

and 40%. For each proposed reduction, we simulated a new distribution, as presented in Table 2.

Table 2: Time distributions between arrivals generated by Flexsim

Sample

Reductionof 10%

Reductionof 15%

Reductionof 20%

Reductionof 30%

Reductionof 35%

Reductionof 40%

Source: The authors (2018)

Cesar Augusto da Cunha Vilela, Ricardo Luiz Machado and Karolline Fernandes Sique

Picture 4:

Source: The authors (2018)

The distribution shown in Picture 4 is commonly used in reliability analysis in cycles until

igue failure, material resistance, and probabilistic design with variable loads.

The simulation of the distribution of inter

defined as continuous as well as the log

Picture 5

Source: The authors (2018)

The parameters of the sample of the arrival times of the truck mixers in the building sites differ

from minimum and maximum, having the function of characterizing times for s

In order to discover a time distribution between arrivals that would enhance the use of the

discharge process, without exceeding the queuing and discharge time of 30 minutes, as predicted by NBR

7212 (2012), the distribution times between sample arrivals were reduced to 10%, 15%, 20%, 30%, 35%

and 40%. For each proposed reduction, we simulated a new distribution, as presented in Table 2.

Time distributions between arrivals generated by Flexsim

beta (0.068798, 219.9000954, 1.710780, 8.006745, 0)

Reductionof 10% beta (0.068798, 198.500213, 1.720651, 8.084879, 0)

Reductionof 15% beta (0.068798, 186.827081, 1.727140, 8.008743, 0)

Reductionof 20% beta (0.068798, 175.153950,

Reductionof 30% beta (0.013139, 154.697481, 1.688946, 7.926009, 0)

Reductionof 35% weibull (0.000000, 28.032194, 1.537840, 0)

Reductionof 40% beta (0.034399, 131.351218, 1.705269, 7.942720, 0)

Source: The authors (2018)

Cesar Augusto da Cunha Vilela, Ricardo Luiz Machado and Karolline Fernandes Sique

Picture 4: Simulation of the distribution of the concrete discharge process

The distribution shown in Picture 4 is commonly used in reliability analysis in cycles until

igue failure, material resistance, and probabilistic design with variable loads.

The simulation of the distribution of inter

defined as continuous as well as the log

Picture 5: Simulation of the distribution of sample arrivals

The parameters of the sample of the arrival times of the truck mixers in the building sites differ

from minimum and maximum, having the function of characterizing times for s

In order to discover a time distribution between arrivals that would enhance the use of the

discharge process, without exceeding the queuing and discharge time of 30 minutes, as predicted by NBR

ution times between sample arrivals were reduced to 10%, 15%, 20%, 30%, 35%

and 40%. For each proposed reduction, we simulated a new distribution, as presented in Table 2.

Time distributions between arrivals generated by Flexsim

beta (0.068798, 219.9000954, 1.710780, 8.006745, 0)

beta (0.068798, 198.500213, 1.720651, 8.084879, 0)

beta (0.068798, 186.827081, 1.727140, 8.008743, 0)

beta (0.068798, 175.153950,

beta (0.013139, 154.697481, 1.688946, 7.926009, 0)

weibull (0.000000, 28.032194, 1.537840, 0)

beta (0.034399, 131.351218, 1.705269, 7.942720, 0)

Cesar Augusto da Cunha Vilela, Ricardo Luiz Machado and Karolline Fernandes Sique

Simulation of the distribution of the concrete discharge process

The distribution shown in Picture 4 is commonly used in reliability analysis in cycles until

igue failure, material resistance, and probabilistic design with variable loads.

The simulation of the distribution of inter

defined as continuous as well as the log-logistic distribution.

Simulation of the distribution of sample arrivals

The parameters of the sample of the arrival times of the truck mixers in the building sites differ

from minimum and maximum, having the function of characterizing times for s

In order to discover a time distribution between arrivals that would enhance the use of the

discharge process, without exceeding the queuing and discharge time of 30 minutes, as predicted by NBR

ution times between sample arrivals were reduced to 10%, 15%, 20%, 30%, 35%

and 40%. For each proposed reduction, we simulated a new distribution, as presented in Table 2.

Time distributions between arrivals generated by Flexsim

beta (0.068798, 219.9000954, 1.710780, 8.006745, 0)

beta (0.068798, 198.500213, 1.720651, 8.084879, 0)

beta (0.068798, 186.827081, 1.727140, 8.008743, 0)

beta (0.068798, 175.153950, 1.742098, 8.101247, 0)

beta (0.013139, 154.697481, 1.688946, 7.926009, 0)

weibull (0.000000, 28.032194, 1.537840, 0)

beta (0.034399, 131.351218, 1.705269, 7.942720, 0)

Cesar Augusto da Cunha Vilela, Ricardo Luiz Machado and Karolline Fernandes Sique

Simulation of the distribution of the concrete discharge process

The distribution shown in Picture 4 is commonly used in reliability analysis in cycles until

igue failure, material resistance, and probabilistic design with variable loads.

The simulation of the distribution of inter-arrival times generated a beta distribution (Picture 5)

logistic distribution.

Simulation of the distribution of sample arrivals

The parameters of the sample of the arrival times of the truck mixers in the building sites differ

from minimum and maximum, having the function of characterizing times for s

In order to discover a time distribution between arrivals that would enhance the use of the

discharge process, without exceeding the queuing and discharge time of 30 minutes, as predicted by NBR

ution times between sample arrivals were reduced to 10%, 15%, 20%, 30%, 35%

and 40%. For each proposed reduction, we simulated a new distribution, as presented in Table 2.

Time distributions between arrivals generated by Flexsim

Distribution tibeta (0.068798, 219.9000954, 1.710780, 8.006745, 0)

beta (0.068798, 198.500213, 1.720651, 8.084879, 0)

beta (0.068798, 186.827081, 1.727140, 8.008743, 0)

1.742098, 8.101247, 0)

beta (0.013139, 154.697481, 1.688946, 7.926009, 0)

weibull (0.000000, 28.032194, 1.537840, 0)

beta (0.034399, 131.351218, 1.705269, 7.942720, 0)

Cesar Augusto da Cunha Vilela, Ricardo Luiz Machado and Karolline Fernandes Sique

Simulation of the distribution of the concrete discharge process

The distribution shown in Picture 4 is commonly used in reliability analysis in cycles until

igue failure, material resistance, and probabilistic design with variable loads.

arrival times generated a beta distribution (Picture 5)

Simulation of the distribution of sample arrivals

The parameters of the sample of the arrival times of the truck mixers in the building sites differ

from minimum and maximum, having the function of characterizing times for s

In order to discover a time distribution between arrivals that would enhance the use of the

discharge process, without exceeding the queuing and discharge time of 30 minutes, as predicted by NBR

ution times between sample arrivals were reduced to 10%, 15%, 20%, 30%, 35%

and 40%. For each proposed reduction, we simulated a new distribution, as presented in Table 2.

Time distributions between arrivals generated by Flexsim

Distribution times of arrivalsbeta (0.068798, 219.9000954, 1.710780, 8.006745, 0)

beta (0.068798, 198.500213, 1.720651, 8.084879, 0)

beta (0.068798, 186.827081, 1.727140, 8.008743, 0)

1.742098, 8.101247, 0)

beta (0.013139, 154.697481, 1.688946, 7.926009, 0)

beta (0.034399, 131.351218, 1.705269, 7.942720, 0)

Cesar Augusto da Cunha Vilela, Ricardo Luiz Machado and Karolline Fernandes Sique

Simulation of the distribution of the concrete discharge process

The distribution shown in Picture 4 is commonly used in reliability analysis in cycles until

igue failure, material resistance, and probabilistic design with variable loads.

arrival times generated a beta distribution (Picture 5)

Simulation of the distribution of sample arrivals

The parameters of the sample of the arrival times of the truck mixers in the building sites differ

from minimum and maximum, having the function of characterizing times for schedules of activities

In order to discover a time distribution between arrivals that would enhance the use of the

discharge process, without exceeding the queuing and discharge time of 30 minutes, as predicted by NBR

ution times between sample arrivals were reduced to 10%, 15%, 20%, 30%, 35%

and 40%. For each proposed reduction, we simulated a new distribution, as presented in Table 2.

mes of arrivals

Cesar Augusto da Cunha Vilela, Ricardo Luiz Machado and Karolline Fernandes Sique

Simulation of the distribution of the concrete discharge process

The distribution shown in Picture 4 is commonly used in reliability analysis in cycles until

arrival times generated a beta distribution (Picture 5)

The parameters of the sample of the arrival times of the truck mixers in the building sites differ

chedules of activities

In order to discover a time distribution between arrivals that would enhance the use of the

discharge process, without exceeding the queuing and discharge time of 30 minutes, as predicted by NBR

ution times between sample arrivals were reduced to 10%, 15%, 20%, 30%, 35%

and 40%. For each proposed reduction, we simulated a new distribution, as presented in Table 2.

Cesar Augusto da Cunha Vilela, Ricardo Luiz Machado and Karolline Fernandes Siqueira

The distribution shown in Picture 4 is commonly used in reliability analysis in cycles until

arrival times generated a beta distribution (Picture 5)

The parameters of the sample of the arrival times of the truck mixers in the building sites differ

chedules of activities

In order to discover a time distribution between arrivals that would enhance the use of the

discharge process, without exceeding the queuing and discharge time of 30 minutes, as predicted by NBR

ution times between sample arrivals were reduced to 10%, 15%, 20%, 30%, 35%

Page 10: Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

Simulation of Ready Mixed Concrete Supply Chain in the

Building Industry using the Software Flexsim 505

The beta distribution appeared in reductions of 10%, 15%, 20%, 30% and 40%. The Weibull

distribution appeared only in the 35% reduction. Both distributions are continuous, which have the

characteristic of describing times to complete tasks in the planning and design of systems. These

distributions have been applied to model the behavior of random variables limited to finite-size

intervals.

The simulation performed showed that the average queue and discharge times increased due to

the increase in the arrival rate. Consequently, the total time of the system increased, as shown in Table

3:

Table 3: Average time of arrival of the queue and the end of the discharge (minutes)

Process Sample Arrival time reduction

10% 15% 20% 30% 35% 40% Line 7,60 8,60 9,40 11,00 13,90 13,50 25,30

Discharge 18,70 18,8 18,60 18,30 19,60 19,50 19,90

Total 26,30 27,40 28,00 29,30 33,50 38,00 45,20 Source: The authors (2018)

The results obtained from field observations indicated that the total average stay of trucks

between arrival and the end of discharge is 26 minutes and 30 seconds. The 20% reduction is closest to

the limit established by the standard, recording a residence time of 29 minutes and 30 seconds.

Table 4 shows the performance results of the concrete discharge system, considering the six

scenarios constructed.

Table 4: System performance and its optimizations according to scenario

Process Sample Time reductionbetweenarrivals

10 % 15% 20% 30% 35% 40% Queue 17,2% 20,0% 23,4% 24,1% 42,7% 43,3% 58,7%

Discharge 54,7% 56,4% 61,2% 66,2% 80,4% 83,1% 88,2%

Idleness 45,3% 43,6% 38,8% 33,8% 19,6% 16,9% 11,8%

Source: The authors (2018)

We can see in Table 4 that the probability of the system is in service for the analyzed

distributions increased, from 54.7% to 88.2%, as the rate of arrival is reduced. However, queue

processing rose from 17.2% to 58.7%, increasing the probability of queue generation.

After the start of delivery (or arrival at the building site), the time limit for unloading should be

no more than 30 minutes after the truck arrives at the building site to ensure that the concrete does not

lose its mechanical properties (NBR 7212, 2012). Chart 1 highlights this limit of time for unloading

after the arrival of the truck to building site compared to the results obtained in the simulations of

distributions.

Page 11: Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

506 Cesar Augusto da Cunha Vilela, Ricardo Luiz Machado and Karolline Fernandes Siqueira

Chart 1: Comparison of the time of permanence in the system and the reductions

Source: The authors (2018)

In the verification of the time limit for the start of unloading after arrival in the work obtained

in the simulations, it was observed that the 30%, 35%, and 40% reductions distributions exceeded 30

minutes, despite obtaining a system idleness of 19.6%, 16.9% and 11.8% (according to Table 4).

In analyzing the parameters of the line generated by the reduction of 20% of the arrival rate we

found a idlenessof 33.8% and an increase in discharge processing to 66.2%. According to the data in

Table 4, this arrival rate reduced the idle rate by 34% about the actual arrival rate of the sample.

5. Conclusion The results obtained through the simulation using the Flexsim software and its Expertfit tool for the

production of statistical distributions proved to be quite useful since through samples collected with

real production data distributions were presented comparing the parameters of the queue.

This study can demonstrate that by obtaining a processing rate (supply) with a good predefined

efficiency and interfering in the arrival rate, reducing it we can measure a reduction in significant

idleness, reducing idle machine and equipment times and generating gains for the project.

The data presented brought us the certainty that the concreting process by truck-mixer vehicles

aided by pump-launches for the execution of slabs requires interventions to improve the time of

unloading of the concrete in the building sites.

Despite the development of the of civil construction production chain in recent years, there are

still detectable restrictions and problems in time losses, causing idleness and capacity decrease and the

productive index of the works.

There is still a lot of variability and many restrictions on the workflows in construction. A

short-term planning using software for the simulation to re-adjust the realities and minimize the

variability of the actions performed in the processes can be one of the initiatives for a better relocation

of the operations of improvement in the construction of the building sites.

ON BEHALF OF ALL AUTHORS, THE CORRESPONDING AUTHOR STATES THAT

THERE IS NO CONFLICT OF INTEREST.

0

5

10

15

20

25

30

35

40

45

50

Amostra 10% 15% 20% 30% 35% 40%

LEN

GH

T O

F S

TA

Y (

MIN

UT

ES

)

DISTRIBUTION OF ARRIVALS

Limit - NBR 7212/12

Sample

Page 12: Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

Simulation of Ready Mixed Concrete Supply Chain in the

Building Industry using the Software Flexsim 507

Bibliographic References [1] ANSON, M.; WANG, S.; Performance of concrete placing in Hong Kong buildings. Journal of

Construction Engineering and Management, v. 124, p.116–124, march/april 1998.

[2] AKHAVIAN, Reza & BEHZADAN, Amir H. Evaluation of queuing systems for knowledge-

based simulation of construction processes. Automation in Construction, v. 47, p. 37–49, 17

July 2014.

[3] AZAMBUJA, M.; CHEN, X; Risk Assessment of a Ready-Mix Concrete Supply Chain.

Construction Research Congress, ASCE, p. 1695-1703, 2014.

[4] BANKS, J.; CARSON, J.S.; NELSON, B.L.; NICOL, D.M. Discrete-event system simulation. 5 ed., New Jersey: Prentice Hall, 2010.

[5] BATEMAN, R. E. et al. Simulação de Sistemas: aprimorando processos de logística, serviços e manufatura. 1. ed. Rio de Janeiro: Elsevier, 2013.

[6] BERTRAND, J. Will M.,FRANSOO, J.C,; MODELLING AND SIMULATION – Operations

management research methodologies using quantitative modeling.

InternationalJournalofOperationsandProduction Management, v. 22, 2002.

[7] CAMPOS, G. L. O uso da Teoria das Filas no acesso rodoviário aos terminais de contêiner. 77 f. Dissertação (Departamento de Engenharia Civil). Pontifícia Universidade

Católica do Rio de Janeiro, 2012.

[8] CHEN, L., HU, D., XU, T. Highway freight terminal facilities allocation based on Flexsim. Procedia – Social andBehavioralSciences, 96:368-381, 2013.

[9] CHWIF, L.; MEDINA, A.C. Modelagem e Simulação de Eventos Discretos: teoria e

aplicações. 3.ª ed. rev. São Paulo, 2010.

[10] COSTA, Dayana Bastos et al; Indicadores de Produtividade e Perdas para Processos à Base de Cimento. Salvador-Bahia: Universidade Federal da Bahia, 2013 (Manual de Utilização).

[11] EVANS, J.R..Spreadsheets as a Tool for Teaching Simulation. Informs TransactionsOn Education, v. 1, p.27-37, Institute for Operations Research and the Management Sciences, set.

2000.

[12] FLEXSIM PROBLEM SOLVED: A Empresa / 1993. Disponível em: <

https://www.flexsim.com/pt/company/> Acesso em: 17jun. 2017.

[13] IBGE - INSTITUTO BRASILEIRO DE GEOGRAFIA E ESTATÍSTICA. PIB Brasil e Construção Civil. Disponível em: http://www.cbicdados.com.br/menu/pib-e-investimento/pib-brasil-e-construcao-civil.Acesso em: 18 de jun. de 2017.

[14] LAW, A. M.; KELTON, W. D. Simulation modeling and analysis. New York: McGraw-Hill,

1991.

[15] LAW, A. M. Simulation modeling and analysis. 4th ed. New York, McGraw-Hill, 2010.

[16] LONDON, K. A.; KENLEY, R. An industrial organization economic supply chain approach for the construction industry: a review. Construction Management andEconomics,

v. 19, p. 777-788, 2001.

[17] LEAL, F., ALMEIDA, D. A. DE, MONTEVECHI, J. A. B.Uma proposta de técnica de modelagem conceitual para a simulação através de elementos do IDEF. In: Simpósio

Brasileiro de Pesquisa Operacional, João Pessoa-PB: Anais XL,2008.

[18] MACHADO, Ricardo Luiz; A sistematização de antecipações gerenciaisno planejamento da produçãode sistemas da construção civil. Tese (Doutorado – Programa de Pós Graduação do

Departamento de Engenharia de Produção), Universidade Federal de Santa Catarina, 2003.

[19] MESQUITA, Marco Aurelio& HERNANDEZ, AlvaroEuzebio. Discrete-event simulation of queues with spreadsheets: a teaching case.

[20] MONTVECCHI, J. B.; PINHO, A. F.; LEAL, F.; MARINS, F. A. S. Application of design of experiment on the simulation of a process in anautomotive industry. In: Proceedings of the

Winter Simulation Conference. Washington, DC, USA, 2007.

Page 13: Simulation of Ready Mixed Concrete Supply Chain in the Building … · 2018-12-29 · Simulation of Ready Mixed Concrete Supply Chain in the Building Industry using the Software Flexsim

508 Cesar Augusto da Cunha Vilela, Ricardo Luiz Machado and Karolline Fernandes Siqueira

[21] MOON, Sungkton; Dynamic control of supply chain quality to improve process performance in construction. A thesis in fulfilment of the requirements for the degree of

Doctor of Philosophy, School of Civil and Environmental Engineering, Faculty of Engineering,

February 2014.

[22] ABNT – Associação Brasileira de Normas Técnicas. NBR 7212: Execução de concreto dosado em central.Rio de Janeiro: ABNT, 2012. 7p.

[23] PARK, M.; KIM, W.; LEE, H.; HAN, S. Supply chain management model for ready mixed

concrete. Automation in Construction, v. 20, p. 40-44, 3-05-2010. [24] Richard, A. O;John, L. T. GREEN LOGISTICS AND SUPPLY CHAIN MANAGEMENT

EFFECTS ON GREEN READY MIX CONCRETE (A CASE STUDY OF FACTOR FOR

ORDER FULFILMENT). Journal of Built Enviroment, Technology and Engineering, v. 2,

march 2017.

[25] ROBINSON, S.; Simulation the practice of model development and use. Wiley, Hoboken,

2004.

[26] SHANNON, R. E. Introduction to the art and science of simulation. In:

ProceedingsoftheWintersimulationconference, pp. 7–14, 1998

[27] SILVA, L.C.; COELHO, C. J.; DANTAS, M. J. F.; Aplicação da teoria de filas e simulação em sistemas de produção com ênfase na teoria das restrições. XIX Simpósio de

administração da Produção, Logística e Operações Internacionais Tema: Operações e

Prosperidade: O Desafio da Criação de Valor, agosto/2016. In: PERIN FILHO, C. Introdução à simulação de sistemas. Campinas, SP: Editora da UNICAMP, 1995.(ISSN: 1518-6539).

[28] SMITH, S. Modeling and experimentation of the concrete supply and delivery process. Civil Engineering and Environmental Systems, vol. 16, p. 93–114, 14-09-1998.

[29] SZTRIK, J.; Basic Queueing Theory: Foudations of System Performance Modeling: Ed. Do

Autor, 2012. Disponível em: <http://irh.inf.unideb.hu/user/jsztrik> Acesso em 08/04/2017.

[30] TIJAN, E.; AKSENTIJEVIĆ, S.; HLACA, B.;Simulation of administrative labour costs in

seaport clusters. Scientific Journal of Maritime Research,v. 28, p 22-30, 14-04-2014.

[31] WALSH, K. D.; HERSHAUER, J. C.; TOMMELEIN, I. D.; WALSH, T. A. A strategic

positioning of inventory to match demand in a capital projects supply chain. Journal of Construction Engineering and Management, ASCE, p. 818-826, Nov./Dec. 2004.

[32] WANG, S; TEO, C.; OFORI, G.; Scheduling the truckmixer arrival for a ready mixed concrete

pour via simulation with @Risk. Journal of Construction Research, v.2, p. 61-71, 2001.

[33] ZAYED, T.; HALPIN, D.; Simulation of concrete batch plant

production.JournalofConstructionEngineeringand Management,v.127, 132–141, 2001.