Sieve Analysis Summarecon

6
Sieve Analysis of Base Course A ASTM D422 Proyek : Sample : Kontrakto : Lokasi : Berat (gr): Ayakan No. No.200 No. 40 No. 10 No. 4 1" 1½" mm 0.075 0.425 2.000 4.750 9.525 25.400 38.100 Contoh Tertahan (gr) Komulatip (gr) % Tertahan % Lolos Batas Atas 8 17 30 44 58 85 100 Batas Bawah 2 7 17 29 44 79 100 ⅜" Spesifikas i (%) Batas Atas Batas Bawah Sample 0.010 0.100 1.000 10.000 100.000 0 10 20 30 40 50 60 70 80 90 100 Sieve Analysis Graph of Base Course A Grain Size ----------> mm Passing -----> % Batas Atas Batas Bawah

description

Sieve Analisys

Transcript of Sieve Analysis Summarecon

Base A & BSieve Analysis of Base Course ASieve Analysis of Base Course BASTM D422ASTM D422

Proyek:Sample :Kontraktor:Proyek:Sample :Kontraktor:Lokasi:Berat (gr):Lokasi:Berat (gr):AyakanNo.No.200No. 40No. 10No. 4"1"1"AyakanNo.No.200No. 40No. 10No. 4"1"1"2"mm0.0750.4252.0004.7509.52525.40038.100mm0.0750.4252.0004.7509.52525.40038.10050.8

ContohTertahan (gr)ContohTertahan (gr)Komulatip (gr)Komulatip (gr)% Tertahan% Tertahan% Lolos% LolosSpesifikasi (%)Batas Atas81730445885100Spesifikasi (%)Batas Atas8204055658595100Batas Bawah2717294479100Batas Bawah281525307088100

Batas Atas Batas Bawah Sample

Batas Atas Batas Bawah Batas Atas Batas Bawah

Base B Sport ClubSieve Analysis of Base Course BASTM D422Proyek:Sport Club The SpringSample :Base Course "B"Kontraktor:PT Sirtu Alam MakmurLokasi:Summarecon SerpongBerat (gr):2,333.7SieveNo.No.200No. 40No. 10No. 4"1"1"2"mm0.0750.4252.0004.7509.52525.40038.10050.8

SampleTertahan (gr)41.477.6173.4296.0937.2547.8244.30.0Komulatip (gr)2,317.72,276.32,198.72,025.31,729.3792.1244.30.0% Tertahan99.397.594.286.874.133.910.50.0% Lolos0.72.55.813.225.966.189.5100Spesifikasi (%)Batas Atas8204055658595100Batas Bawah281525307088100Gradasi material tidak masuk amplop spesifikasi Base Course "B", posisi berada di bawah amplop.Kekurangan material halus seperti Abu Batu (Dust Stone).Sieve Analysis of Base Course BASTM D422Proyek:Sport Club The SpringSample :Base Course "B"Kontraktor:PT Sirtu Alam MakmurLokasi:Summarecon SerpongBerat (gr):2,333.7SieveNo.No.200No. 40No. 10No. 4"1"1"2"mm0.0750.4252.0004.7509.52525.40038.10050.8

MaterialTertahan (gr)41.477.6173.4296.0937.2547.8244.30.0Komulatip (gr)2,317.72,276.32,198.72,025.31,729.3792.1244.30.0Komposisi Campuran% Tertahan99.397.594.286.874.133.910.50.0% Lolos0.72.55.813.225.966.189.510065%SampleDust Stone1.819.069.092.510010010010035%Dust StoneCombine1.18.227.941.051.877.993.2100100%TotalSpesifikasi (%)Batas Atas8204055658595100Batas Bawah281525307088100Dengan menambah Abu Batu (Dust Stone) sebanyak 35% terhadap campuran material, diperoleh material kombinasi yangbaik didapat 99% masuk amplop spesifikasi Base Course "B".

Batas Atas Batas Bawah Sample

Batas Atas Batas Bawah Material Kombinasi

Base A ScientiaSieve Analysis of Base Course AASTM D422

Proyek:Jl Boulevard Scientia BaratSample :Base Course AKontraktor:PT Putri Intan AnugerahLokasi:Summarecon SerpongBerat (gr):2,114.2Sample:Dust StoneWt. of Dry Sample:1,000gramSieveNo.No.200No. 40No. 10No. 4"1"1"SieveNo.No.200No. 50No. 30No. 16No. 8No. 43/8"1/2"3/4"1"11/2"mm0.0750.4252.0004.7509.52525.40038.100mm0.0750.30.61.182.364.759.512.71925.437.5

SampleTertahan (gr)62.485.9181.7286.7859.36310WeightRetain7718424621618475- 0Komulatip (gr)21072044.61958.717771490.36310Cum. Retain98290572147525975- 0% Tertahan99.796.792.684.170.529.80.0PercentageRetain98.290.572.147.525.97.50.0% Lolos0.33.37.415.929.570.2100Passing1.89.527.952.574.192.5100Spesifikasi (%)Batas Atas81730445885100Batas Bawah2717294479100

Gradasi sample tidak masuk spesifikasi Base Course "A", posisi berada di bawah amplop.Sample kekurangan material halus seperti material Abu Batu (Dust Stone).Sieve Analysis of Base Course AASTM D422Proyek:Jl Boulevard Scientia BaratSample :Base Course AKontraktor:PT Putri Intan AnugerahLokasi:Summarecon SerpongBerat (gr):2,114.2SieveNo.No.200No. 40No. 10No. 4"1"1"mm0.0750.4252.0004.7509.52525.40038.100

MaterialTertahan (gr)62.485.9181.7286.7859.36310Komulatip (gr)21072044.61958.717771490.36310Kombinasi campuran% Tertahan99.796.792.684.170.529.80.0% Lolos0.33.37.415.929.570.210068%SampleDust Stone1.819.069.092.510010010032%Dust StoneCombine0.88.327.140.452.179.7100100%TotalSpesifikasi (%)Batas Atas81730445885100Batas Bawah2717294479100Dengan menambah Abu Batu (Dust Stone) sebanyak 32% terhadap material kombinasi, diperoleh gradasi Base Course "A"yang baik (99% masuk spesifikasi amplop Base Course "A").

Batas Atas Batas Bawah Sample

Batas Atas Batas Bawah Sample Batas Atas Batas Bawah Material kombinasi