Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From...

14
Shutdown Summer 10 4- week

Transcript of Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From...

Page 1: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

Shutdown Summer 104-week

Page 2: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

Who

Main InjectorDuration

Mike Frett/John Featherstone  Remove Sand From MI40 penetrations Install when finished (PLUS) 4wJohn Featherstone/Mike FrettRauchmiller MichaelMoore Jack ( CT)Zolli Tim (CT)Johnson SeanMain Injector Corrosion repair (beam tubes) 4d-6dJohn Featherstone/Mike FrettBurk DaveCampbell MattChlebek MarkFolkie Jim

Page 3: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

Who

Tevatron  Duration

Scott McCormick  

Warm A3 (PLUS) 4w

Scott McCormick

Dymond Bill

Williams James

Aponte, Sabina

Lambert Dan (ct)

Plant Derek

Greskoviak Jason

Warm Straights (PLUS) 4w

Scott McCormick

Sylejmani Sali

Jones Robert

Stone Brent

Page 4: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

Who

P-Bar Duration

Henry Gusler  

New gauges and leak check Ln2 rough vacuum 2d

Henry Gusler

Crabtree Phil

Shaffer Earl

Sellberg Greg

Rehose SMA Magnets 2w

Kelly Doug

Samayavong Inpeng

Sorenson Steve

Page 5: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

WhoDave Augustine (ALL)•Ext: 4451•Pager (630) 905-5081•[email protected]

John Featherstone (MI)•Ext: 5605•Pager (630) 266-5457•[email protected]

* Taking over for Merill Albertus

Scott McCormick (Tev)•Ext: 3691•Pager (630) 722-6795•[email protected]

Mike Frett*(MI)•Ext: 4663•Pager (630) 722-1057•[email protected]

Henry Gusler•Ext: 2675•Pager (630) 722-5209•[email protected]

Oliver Kiemschies (TD)•Ext: 3925•Cell (630) 364-6533•[email protected]

Page 6: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

What

MI (Team 1) (~4 weeks)• Install lead blankets at MI40 kickers• Leak check flourinert side of MI40 kickers • Remove Sand from MI40 penetrations; install when finished • Install shield Wall 307 • Remove lead blankets from MI40 kickers

MI (Team 2) (4-6 days)• Corrosion repair; Replace beam tube clamps on the MI Beam tube

ring wide. Some areas will be hot. Buff off any rust on beam tube

Page 7: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

WhatPBar (Team 1)• New Gauges and Leak Check LN2 rough vacuum (2 days)

Pbar (Team 2)• Rehose SMA Magnets (~2 weeks)

Tev• Talk to Scott• A1 warm up and repair cold leaks, F1 warm up only if time allows. E0: Install

V-Goniometer, repair leaky bellows and install Pixel detector. E11- replace flying wire, E17 replace flying wire, B48 install e-cloud detector, A0 TEL2 install new beam screen and F sector has 2 turbo 151 installations

Page 8: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

Where

•Usually keys are given out in MCR (Tev may get from Scott early)•There WILL be permanent shutdown keys (i.e. keys that you don’t have to turn in at the end of the day) for most•You will be given a card by a task master with which to get a key with.

Page 9: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

Location of the MCR

Page 10: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

Layout of MCR

<- Keys

<- TeV LOTO

MI & Booster LOTO ->

<- NuMI LOTO

Usually RWP’s are next where keys are.At the beginning of this shutdown, the RWP’s will be in the room next to the MCR, along with RSO’s

Page 11: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

LOTO

Page 12: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

When

• Day 0 (Sunday, July 18th) Tev – We are setting up a meeting with Scott McCormick Thursday or Friday to work out details

• Day 1 (Monday, July 19th) Everyone Else. No access until 8am• Some people may be shuffled as jobs complete

Page 13: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

Why

• We will try to have separate job & task numbers for tunnel jobs

(http://tdserver1/project/jobfiles/Current_Jobs/TD_work_for_AD/refmenu.htm)

• AD Pays for OT (see me for the task number)• Still working on approval process (doesn’t sound like

you’ll have to “hand” a sheet to anyone though)

Page 14: Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

Good Luck!

Stay Safe!

This presentation can be found at:http://tdserver1.fnal.gov/AcceleratorSupport/Shutdown/