Shugart Valley Place Solar Project - Maryland · MD Solar 1 – Permit Application Summary Table...
Transcript of Shugart Valley Place Solar Project - Maryland · MD Solar 1 – Permit Application Summary Table...
![Page 1: Shugart Valley Place Solar Project - Maryland · MD Solar 1 – Permit Application Summary Table Public Hearing Impact # Impact Type Impact Description Impact Amounts LF R3 SF R3](https://reader035.fdocuments.in/reader035/viewer/2022070922/5fbaa20aea183848522be853/html5/thumbnails/1.jpg)
www.origisenergy.com
Project OverviewShugart Valley Place Solar Project
MD Solar 1
February 27, 2019
![Page 2: Shugart Valley Place Solar Project - Maryland · MD Solar 1 – Permit Application Summary Table Public Hearing Impact # Impact Type Impact Description Impact Amounts LF R3 SF R3](https://reader035.fdocuments.in/reader035/viewer/2022070922/5fbaa20aea183848522be853/html5/thumbnails/2.jpg)
www.origisenergy.com
MD Solar 1 - Project Overview
Public Hearing
• 4850 Shugart Valley Place• 32.5 MWAC photovoltaic solar facility• 249-acre project area, within two
parcels totaling 588 acres
![Page 3: Shugart Valley Place Solar Project - Maryland · MD Solar 1 – Permit Application Summary Table Public Hearing Impact # Impact Type Impact Description Impact Amounts LF R3 SF R3](https://reader035.fdocuments.in/reader035/viewer/2022070922/5fbaa20aea183848522be853/html5/thumbnails/3.jpg)
www.origisenergy.com
MD Solar 1 – Permit Application Overview
Public Hearing
![Page 4: Shugart Valley Place Solar Project - Maryland · MD Solar 1 – Permit Application Summary Table Public Hearing Impact # Impact Type Impact Description Impact Amounts LF R3 SF R3](https://reader035.fdocuments.in/reader035/viewer/2022070922/5fbaa20aea183848522be853/html5/thumbnails/4.jpg)
www.origisenergy.com
MD Solar 1 – Permit Application Summary Table
Public Hearing
Impact # Impact Type Impact DescriptionImpact Amounts
LF R3 SF R3 SF PFO Acres
1 Permanent stream and buffer disturbance
Improvement and extension of existing culvert road crossing for emergency and
maintenance vehicle access40 240 0 0.006
2 Temporary stream, buffer, and floodplain disturbance
Installation of a temporary span bridge over Ward's Run for construction vehicle access 22 1,320 0 0.030
3Conversion of Palustrine Forested
wetlands (NT) to Palustrine Emergent wetlands (NT)
Installation of a utility line and tree clearing within a 70' wide easement. No structures
or fill will be placed in the wetlands.0 0 4,550 0.104
Total - - 62 1,560 4,550 0.140