SHIPLEY’S CHOICE DAM REHABILITATION PROJECT UPDATE Greater Severna Park Council Meeting February 13, 2018 Presentors Sheri Lott – Engineering Manager Larry Mathena – Project Manager

Transcript of SHIPLEY’S HOIE DAM REHAILITATION

Page 1: SHIPLEY’S HOIE DAM REHAILITATION

SHIPLEY’S CHOICE DAM REHABILITATION PROJECT UPDATE

Greater Severna Park Council Meeting

February 13, 2018

Presentors Sheri Lott – Engineering Manager Larry Mathena – Project Manager

Page 2: SHIPLEY’S HOIE DAM REHAILITATION

Agenda

1. Project Background

2. Project Features

3. Road Closure

4. Recent Activities

5. Schedule

6. Project Updates to HOAs

7. Questions

2/9/2018 2

Page 3: SHIPLEY’S HOIE DAM REHAILITATION

Project Background – Shipley’s Dam

2/9/2018 3

• Dam built in 1980

• Seepage & Settlement Issues

• MDE deemed dam unsafe & directs County to remove

Page 4: SHIPLEY’S HOIE DAM REHAILITATION

Project Background – Construction Phases

2/9/2018 4

Phase 1 Culvert Replacement

Phase 2 Shipley’s Dam Removal

Page 5: SHIPLEY’S HOIE DAM REHAILITATION

Project Features – Phase 1 Culvert

2/9/2018 5

New 7’x10’ Concrete Box

Culvert

Page 6: SHIPLEY’S HOIE DAM REHAILITATION

Road Closure – Detour Plan

2/9/2018 6

Road Closed between Pixie Dr & Severnside Dr

Page 7: SHIPLEY’S HOIE DAM REHAILITATION

Project Features – Phase 2 Dam Removal

2/9/2018 7

Stream Restoration

Dam Removal & Regrading

Page 8: SHIPLEY’S HOIE DAM REHAILITATION

Recent Activities – Overhead Line Relocation on West Benfield Road

• Temp. Relocate OH Line around New Culvert

• BGE, Comcast, Verizon to relocate lines

• OH lines replaced after Culvert construction

2/9/2018 8

Page 9: SHIPLEY’S HOIE DAM REHAILITATION

Recent Activities – Overhead Line Relocation

2/9/2018 9

Page 10: SHIPLEY’S HOIE DAM REHAILITATION

Recent Activities – Coordination w/ BGE Gas Line Relocation

2/9/2018 10

Page 11: SHIPLEY’S HOIE DAM REHAILITATION

Recent Activities – Preconstruction Home Surveys

2/9/2018 11

23 Properties within 500’ of new culvert

Page 12: SHIPLEY’S HOIE DAM REHAILITATION

Recent Activities – Preconstruction Home Surveys

2/9/2018 12

• Home surveys conducted by County’s contractor Seismic Surveys

• Preconstruction survey of homes and other structures – Document existing conditions

• Post-construction survey also conducted

• Need pre/post surveys to help determine if damage occurred during construction

• Vibration levels will be monitored during pile driving operations

Page 13: SHIPLEY’S HOIE DAM REHAILITATION

Tentative Schedule

• Late Feb Tree trim for OH line relocation W Benfield Rd

• Early Mar BGE sets new poles and relocates overhead line

• Mid Mar Comcast & Verizon relocate their overhead lines

• Mid Mar Shipley’s Dam construction project put out to bid

• Mid May Construction Contract Award; Contractor submits schedule • Early Jun Construction begins w/ Culvert on W. Benfield Rd

W. Benfield Rd Closed 4 – 5 months

• Early 2019 Begin removal of Shipley’s Dam

• Late Summer Construction complete 2019

2/9/2018 13

Page 14: SHIPLEY’S HOIE DAM REHAILITATION

Project Updates to HOAs

• Monthly Shipley’s Dam Project Updates will be emailed to the following HOAs & Organizations:

– Shipley’s Choice HOA & Community Assoc, Greater Severna Park Council, Point Field Landing Community Assoc, Crain West, Ben Oaks/Severn River Assoc

• Monthly Proejct Update will include:

– Updated schedule, latest activities, road closure updates

2/9/2018 14

Page 15: SHIPLEY’S HOIE DAM REHAILITATION

Questions or Comments?

2/9/2018 15