SHIPLEY’S HOIE DAM REHAILITATION
Transcript of SHIPLEY’S HOIE DAM REHAILITATION
SHIPLEY’S CHOICE DAM REHABILITATION PROJECT UPDATE
Greater Severna Park Council Meeting
February 13, 2018
Presentors Sheri Lott – Engineering Manager Larry Mathena – Project Manager
Agenda
1. Project Background
2. Project Features
3. Road Closure
4. Recent Activities
5. Schedule
6. Project Updates to HOAs
7. Questions
2/9/2018 2
Project Background – Shipley’s Dam
2/9/2018 3
• Dam built in 1980
• Seepage & Settlement Issues
• MDE deemed dam unsafe & directs County to remove
Project Background – Construction Phases
2/9/2018 4
Phase 1 Culvert Replacement
Phase 2 Shipley’s Dam Removal
Project Features – Phase 1 Culvert
2/9/2018 5
New 7’x10’ Concrete Box
Culvert
Road Closure – Detour Plan
2/9/2018 6
Road Closed between Pixie Dr & Severnside Dr
Project Features – Phase 2 Dam Removal
2/9/2018 7
Stream Restoration
Dam Removal & Regrading
Recent Activities – Overhead Line Relocation on West Benfield Road
• Temp. Relocate OH Line around New Culvert
• BGE, Comcast, Verizon to relocate lines
• OH lines replaced after Culvert construction
2/9/2018 8
Recent Activities – Overhead Line Relocation
2/9/2018 9
Recent Activities – Coordination w/ BGE Gas Line Relocation
2/9/2018 10
Recent Activities – Preconstruction Home Surveys
2/9/2018 11
23 Properties within 500’ of new culvert
Recent Activities – Preconstruction Home Surveys
2/9/2018 12
• Home surveys conducted by County’s contractor Seismic Surveys
• Preconstruction survey of homes and other structures – Document existing conditions
• Post-construction survey also conducted
• Need pre/post surveys to help determine if damage occurred during construction
• Vibration levels will be monitored during pile driving operations
Tentative Schedule
• Late Feb Tree trim for OH line relocation W Benfield Rd
• Early Mar BGE sets new poles and relocates overhead line
• Mid Mar Comcast & Verizon relocate their overhead lines
• Mid Mar Shipley’s Dam construction project put out to bid
• Mid May Construction Contract Award; Contractor submits schedule • Early Jun Construction begins w/ Culvert on W. Benfield Rd
W. Benfield Rd Closed 4 – 5 months
• Early 2019 Begin removal of Shipley’s Dam
• Late Summer Construction complete 2019
2/9/2018 13
Project Updates to HOAs
• Monthly Shipley’s Dam Project Updates will be emailed to the following HOAs & Organizations:
– Shipley’s Choice HOA & Community Assoc, Greater Severna Park Council, Point Field Landing Community Assoc, Crain West, Ben Oaks/Severn River Assoc
• Monthly Proejct Update will include:
– Updated schedule, latest activities, road closure updates
2/9/2018 14
Questions or Comments?
2/9/2018 15