sharafat housing project civil works technical specifications
Transcript of sharafat housing project civil works technical specifications
1
SHARAFAT HOUSING PROJECT
CIVIL WORKS
TECHNICAL SPECIFICATIONS
TABLE OF CONTENTS
SECTION TITLE
SECTION A GENERAL
SECTION B EXCAVATIONS, EARTHWORKS & ASPHALT
SECTION C CONCRETE WORKS
SECTION D STONE WORKS
SECTION E METAL WORKS
SECTION F SANITARY WORKS
SECTION G ELECTRICAL WORKS
SECTION H FIRE FIGHTING WORKS
2
SECTION A: GENERAL
A 1 SCOPE OF WORK
UNDP/PAPP has been entrusted by the Government of Italy a Grant of US$ 1.5 million for
the implementation of social housing projects. It is envisaged that the Grant will contribute to
improve the physical and social infrastructure services in the selected areas of the Jerusalem
area.
The Latin Patriarchate of Jerusalem has been selected for this project as one of the impact
areas and the activities will consist of Landscaping, Construction and Finishing Works within
the already running project „Sharafat Social Housing‟ in Beit Safafa.
The entire project is comprised of construction of 80 residential units served with the
infrastructure like; roads, sewerage, water network and electricity network.
A 2 DRAWINGS
A list of Contract Drawing available at the date of tender is included on the front page of the
Drawing Book and at the end of these Specifications
A 3 CONTRACTOR'S PRICE
The Contractor's price shall include for all materials labour and plant requirements necessary
for the completion of the Contract in accordance with the Contract Drawing and
specifications with exception only of items supplied by e Employer.
A 4 USE AND PROTECTION OF SITE
The Contractor shall take such measures and exercise such are to protect the Site as shown on
the Site Plan during the course of the Works as directed by and to the entire satisfaction of the
Engineer. All temporary buildings and work areas such as Site Offices, Workshops Store
Buildings and Yards, Living Accommodation, Messrooms, etc. shall be constructed in
position approved by the Engineer.
The contractor shall confine his apparatus, the storage of materials and the operations of his
workmen to limits indicated by law, ordinances, permits or directions of the Engineer. The
Contractor shall erect suitable temporary fences as required by the Engineer.
The Contractor shall not load or permit any part of the structures to be loaded with a weight
that will endanger its safety.
On commencement of the Contract, the Contractor shall clear the Site and adjacent area of all
rubbish and debris to the satisfaction of the Engineer. Upon completion of the Contract, the
Site and any adjacent areas affected by the building operation shall be properly cleared of all
temporary works, debris another rubbish and all disturbed works and ground made good to
the entire satisfaction of the Engineer.
A 5 MATERIALS FOUND ON SITE
Any sand, gravel or other building material found on the Site shall not be used in the
execution of the Works without the prior written consent of the Engineer which shall not be
unreasonably withheld.
3
A 6 TEMPORARY STORMWATER DRAINAGE
The Contractor shall ensure that the whole of the Site, is kept free from the risk of stormwater
flooding and shall provide such temporary ditches, gullies an? the like as may be necessary
and shall at completion of the Works backfill such excavation and make good all works
disturbed.
A 7 SHOP DRAWINGS
If at any time before the commencement or during the progress of the work it appears to the
Contractor that for the proper execution of specific part of the works, shop drawings are
necessary, these drawings shall be prepared by the Contractor and submitted to the Engineer
for approval. On the other hand, the Engineer shall have authority to order at any time and the
Contractor agrees to provide any number of shop drawings which in the opinion of the
Engineer are necessary for the proper execution of a specified work, the Contractor shall not
proceed with the above mentioned work unless these shop drawings are approved by the
Engineer.
Shop drawings shall be fully detailed and drawn to proper scale. Unless otherwise
specifically required in the drawings or Specifications, shop drawings shall be supplied in
four copies with dark lines on a white background.
Shop drawings shall be approved or returned to the Contractor for alternation or amendment
within four (4) weeks of their receipt by the Engineer. Shop Drawings returned for alternation
or amendment shall be resubmitted for approval. Altered or amended shop drawings shall
show the nature of the alternation or amendment in a revision block on the drawings with a
revision number or letter and the date of the revision.
A 8 " AS BUILT " DRAWINGS
All prints of the Drawings, where required, shall be corrected by the Contractor and
submitted to the Engineer for approval as the works proceed. Upon the completion of the
Works, the Contractor shall prepare a completely new set of drawings for the project as
executed and submit same in duplicate to the Engineer for approval.
When approved by the Engineer, the Contractor shall submit one transparency and six copies
of all drawings duly marked "As-Built". The final payment shall not be made except for the
actual works that have been completed in accordance with the Specifications and have been
duly presented on the "As- Built Drawings".
The Contractor shall not be entitled to any extra payment or extension of time for the
correction, preparation and supplying of the above mentioned drawings and transparencies.
A 9 SCAFFOLDING
The Contractor shall provide, erect, maintain, and dismantle any clear away at completion
proper and adequate scaffolding including that required for Sub-Contractors and Specialists.
Putlong holes shall be made good to match the adjacent surface as the scaffolding is
dismantle. The Contractor shall be entirely responsible for all safety precautions in
connection with the scaffolding and for its entire sufficiency for the work.
A 10 PROTECTION
In the pursuance of his obligations under the Conditions of Contract, the Contractor shall
wherever required or directed by the Engineer cover up and protect the Works form the
weather and from damage by him or other workmen performing subsequent operations. He
shall provide all necessary dust sheets, barriers and guard rails and clear away same? at
4
completion. The Contractor shall take all reasonable and proper steps for the protection of all
places on or about the Works, which may be dangerous to his workmen or any other persons
or to traffic. The Contractor shall provide and maintain warning signs, red warning lamps and
barricades as necessary in all such places.
A 11 SEPARATE CONTRACTS
The Employer reserves the right to let other separate contracts in connection with the work
under similar conditions. The Contractor shall afford other contractors reasonable opportunity
for the introduction and storage of their materials and the execution of their work, and shall
properly connect and co-ordinate his work with theirs. If any part of the Contractor's work
depends for proper execution or results upon the work of any other contractor, the Contractor
shall inspect and promptly report to the Engineer and defects in such work shall render it
unsuitable for such proper execution and results. His failure so to inspect and report shall
constitute an acceptance of the other Contractor's Works as fit and proper for the reception of
this work, except as to defects which may develop in the other Contractor's work after the
execution of his work. To ensure the proper execution of his subsequent work, the Contractor
shall measure work already in place and shall at once report to the Engineer any discrepancy
between executed work and the Drawings.
A 12 DEFINITIONS
"Approved "directed "selected” means the approval, direction or selection by the Engineer.
"Instructions means the instructions in writing of the Engineer or Engineer's Representative
unless specified otherwise. ”Manufacturer's Recommendation” means the Manufacturer's
recommendations or instructions, printed or in writing and current at the date of tender.
“Or approved equal” means that materials of different manufacturer may be substituted if
proper approval has been obtained. The rates or prices will be held to be based on the
materials specified. Where an item is denoted as N.I.C. on the Drawings it shall mean that
item indicated is not included in the Contract.
Where the terms Architect or Engineer is used in this Contract they shall have the same
meaning. Where the terms Architect's Representative or Engineer's Representative are used
they shall have the same meaning.
A 13 STANDARDS
In the Contract reference is made to the Standards, Codes of practice and Specifications
issued by the following organizations, hereinafter referred to by the following abbreviations:
AASHO Means the American Association of State Highway Officials.
ACI Means the American Concrete Institute.
AFNOR Means the Association Francaise de Normalisation.
AISC Means the American Institute of Steel Structure.
ASA Means the American Standards Association.
ASHRAE Means the American Society of Heating, Refrigerating and Air-Conditioning
Engineers
ASTM Means the American Society for Testing and materials.
AWWA Means the American Water Works Association.
B S Means the British Standards Institution.
CMA Means the Cable Manufacturers Association.
DIN Means the Deutscher Normanusschuss.
NEM Means the National Electrical Manufactures Association.
NFPA Means the National Fire Protection Association.
5
VDE Means the Verban Deutscher Electrotechniker.
EU&CE Euronormes.
These references shall in every case be deemed to include the latest edition or issue of such
standards.
The Contractor upon receiving instructions shall supply the Engineer‟s Representative with
single copies of all standards referred to on the Drawings or Specification and shall arrange
for further copies for his own use.
A 14 MATERIALS GENERALLY
All materials and manufactured goods are to be the best of their respective kinds and as
described in the Specifications and the Contractor shall submit for the approval of the
Engineer a list of names and addresses of the manufacturers, the trademarks and types of all
materials and articles he proposes to employ together with all specifications and descriptions
that may be required in this connection before any orders are placed. Samples are to be
provided if requested by the Engineer. Where a particular proprietary product, supplier's
catalogue is referred to in the Specifications or shown on the drawings the material specified
may be obtained from another source provided it is similar, equal and approved by the
Engineer.
If during the course of the Contract certain materials required for use in the Works should be
unobtainable despite the best efforts of the Contractor, then the Contractor may offer for the
approval of the Engineer substitute materials. The use of these substitute materials shall be at
the sole discretion of the Engineer. In the event of the acceptance of the substitute materials a
suitable price reduction shall be made in the respect of decrease in quality or value but no
price addition shall be made in respect of increase in quality or value. In the event of refusal
of the substitute materials the Contractor shall not be relieved of any of his obligations under
the Contract and shall be solely liable for any delay or loss occasioned by his failure to
provide materials as specified.
Where manufacturers recommendations have been entered into the contract documents, it is
for the purpose of giving an indications to the contractor of the Engineer‟s intentions on the
application and use of the material. It is deemed that the successful Contractor will make
direct contact with the manufacturer m to ensure that he is carrying out the works in
accordance with their recommendations.
A 15 CONTRACTOR TO VERIFY SITE MEASUREMENTS
The Contractor shall check and verify all site measurements wherever requested by other
specialist contractors or by nominated or other subcontractors to enable them to prepare their
own shop drawings, and pass on the information with sufficient promptness as will not in any
way delay the Works. A copy of all such information passed or shall be given to the
Engineer.
A 16 SAMPLES
The Contractor shall furnish for approval, with reasonable promptness all samples of
materials and workmanship required by the Engineer. The Engineer shall check and approve
such samples with reasonable promptness for conformance with the design concept of the
works and for compliance with the information given in the Contract Documents. The Work
shall be in accordance with approved samples.
6
a) All material samples shall be delivered to the Engineer‟s office with all charges in
connection with therewith paid by the Contractor.
b) Duplicate final approval samples, in addition to any required for the Contractor‟s use shall
be furnished to the Engineer.
c) Samples shall be furnished so as to delay fabrication allowing the Engineer reasonable
time for consideration of the sample submitted.
d) Each sample shall be properly labelled with the name and quality of the material,
manufacturer‟s name, name of project, the Contractor‟s name and the date of submission and
the Specification number to which the sample refers.
A 17 CUTTING AND PATCHING
The Contractor shall be responsible for all cutting, patching and making good in all trades for
all work and his prices will be deemed to include for all such cutting and patching and
making good.
A 18 SITE OFFICES, LATRINES, ETC.
The Contractor shall provide and maintain on the Site for the duration of the Contract the
following:
a) A temporary office for the accommodation of his Agent/Engineer and Staff, including all
necessary sanitary facilities, such offices shall be open at all reasonable hours to receive
instructions, notices or other communications. Electrical and Telephone installations with an
external line for internet, E-mail and fax shall be provided.
b) A suitable and adequate temporary office shall be provided and furnished by the
Contractor for the sole use of the Engineer and his staff. Such office shall be to the approval
of the Engineer.
c) Adequate fire fighting equipment to the approval of the Local Fire Authority and the
Engineer.
d) An approved sign board, written in Arabic and English. The size of signboard and lettering
including to wordings shall be as directed by the Engineer.
A 19 ATTENDANCE ON THE ENGINEER
The Contractor shall for the duration of the Contract supply sufficient attendance for the
Engineer‟s supervisory staff and shall maintain and pay all water, electricity, and telephone
charges shall keep the Site Office and supervision cabins in a clean and sound condition at all
times. The Contractor shall be responsible for the security of the Site Office and its contents
at all times and shall employ watchman for this purpose.
A 20 TESTING
The Contractor shall allow in his rates and prices for the cost of carrying our tests necessary
for compliance with the Specification in independent laboratories outside the Site.
A 21 TEMPORARY BUILDINGS
The Contractor shall provide and maintain on the Site sheds, offices, messrooms, sanitary
accommodation and other temporary works of any kind whatsoever for the Contractor‟s
supervisory staff and work people and for Sub-Contractor‟s staff employed upon the works.
The Contractor‟s site office shall be open during working hours to receive instructions
notices or other communications. Sheds shall be suitable to store all materials equipment and
furniture which in the opinion of the Engineer needs protecting from the weather.
7
The Contractor shall provide and maintain in approved positions on the Site Adequate
sanitary accommodation for his staff workmen and sub- Contractors. This sanitary
accommodation shall be kept in a clean and orderly condition to the approval of the Public
Health Authority and the Engineer to ensure that no nuisance is caused.
A 22 TEMPORARY WORKS AND REINSTATEMENT
The Contractor shall provide and maintain all temporary roads and tracks necessary for
movement of plant and materials, and clear same away at completion and make good all
works damaged or disturbed. The Contractor shall submit drawings and full particulars of all
Temporary Works to the Engineer before commencing same. The Engineer may require
modifications to be made if he considers them to be insufficient and the Contractor shall give
effect to such modifications but shall not be relieved of his responsibilities for the sufficiency
thereof.
The Contractor shall divert as required, at his coast and to the approval of the Engineer, all
public utilities encountered during the progress of the Works, except those specially indicated
on the drawings as being included in the Contract. Where diversions of services are not
required in connection with the permanent Works, the Contractor shall uphold, maintain and
keep the same in working order in existing locations. The Contractor shall make good, at his
own expense, all damage to telephone, telegraph and electric cable or wires, sewers, water, or
other pipes except where the Public Authority or Private Party Owing or responsible for the
same elects to make good the damage. The cost incurred in so doing shall be paid by the
Contractor to the Public Authority or Private Party in demand.
All injury to the surface of the land, to the beds if water courses, projecting banks, etc. where
disturbed by the Works (other than where specifically ordered by the Engineer) shall be
repaired by the Contractor or the authorities concerned, at the Contractor‟s expense. All such
making good shall be to the approval of the Engineer. All requirements detailed above shall
be provided and maintained at the expense of the Contractor. The Employer shall not be
liable for loss or injury to and Temporary Works.
A 23 WATER FOR THE WORKS
The Contractor shall make all necessary arrangements and provide all water for the proper
execution of the Works, together with all transport temporary plumbing, storage and
distribution, pay all charges and alter adapt and maintain temporary work as necessary
remove and make good at completion.
A 24 ELECTRICITY FOR THE WORKS
The Contractor shall make all necessary arrangements and provide all artificial lighting and
power for the proper execution and security if the Works and its protection.
With all meters temporary wiring and fittings, pay all charges and alter, adapt and maintain
the temporary works as necessary and remove and make good at completion
A 25 PROVISION OF PLANT AND TOOLS
The Contractor shall provide and install all necessary hoists, ladders, scaffolding. Staging,
tackles, tarpaulins, tools, vehicles, and other plant (mechanical and otherwise) and allow for
altering adapting and maintaining them in good condition as necessary and eventually
removing from site and making good.
8
A 26 TEMPORARY BARRIERS, FENCING ETC...
The Contractor is to provide all temporary barriers, fencing, hoarding, guard rails, gates, and
the like as may be necessary to protect the public and others, for proper execution of the
Works and shall remove and clear away at completion of the Works and make good all work
disturbed.
A 27 INCONSISTENCY IN CONTRACT DOCUMENTS
The Contractor shall execute the Works according to the provisions of the Contract
Documents. Any work indicated in one of the documents but omitted and/or stated in one or
more of the other documents shall be treated as though it were included in all of them.
If any two documents of the Contract conflict as to the quality of the work to be carried out,
the discrepancy shall be brought to the notice of the Engineer, who shall instruct the
Contractor which of the two conflicting documents to regard as correct.
If the Contractor should discover that any work has been omitted and/or not indicated entirely
or partially from all the documents, but that such work is essential to the safety or proper
functioning of the works, he shall report the facts immediately to the Engineer. If the work is
something which in the opinion of the Engineer could not have been foreseen by an
experienced Contractor, the Engineer should issue to the Contractor a variation order
stipulating the details of the work to be done.
Save as aforesaid in the above paragraph, no additional payment shall be made in respect of
work carried out in connection with discrepancies between the various Contract Documents.
A 28 ERRORS IN COMPUTING CONTRACT DOCUMENTS
The Contractor shall be responsible for any error which he makes in computing any quantities
of material and labour required or costs involved or through any lack of knowledge of the
Site or misunderstanding of anything shown or implied on the Drawings or in the
Specifications and/or the Bills of Quantities.
The Contractor must refer any discrepancy in the Drawings or the Specifications to the
Engineer before proceeding in any of the Works otherwise the decision of the Engineer as to
the interpretation of the discrepancy will be final. Any item or items of work not specifically
shown on the Drawings or referred to in the Specifications but which would be necessary for
the proper construction of the works in accordance with the best practice is implied and must
be included for as incidential to the Contract Sum. Any item for which the Contractor has not
inserted a price in the Bills of Quantities shall be deemed to be covered by other prices or
rates therein.
A 29 SITE MEETINGS
During the course of the Works, site progress meetings shall be held at regular intervals at
least once every two weeks in the presence of the Engineer for the purpose of co-ordinating
the Contractor‟s work and to insure that full compliance with the various sequences of the
contract are maintained. Minutes of such Site meetings will be recorded, copies will be
distributed to all persons concerned and full effect shall be given to all instructions contained
therein Prior to such meetings the Contractor shall give to the Engineer‟s representative
details in writing of that portion of the Works he proposes to construct during the coming two
weeks with details of the plant and methods he proposes to employ. These proposals shall be
discussed at the meeting and no work based on such proposals shall proceed without the
approval of the Engineer‟s Representative
The Contractor shall have no claim against the Employer for costs incurred by him in
changing the method of working or in the provision and use of other additional plant.
9
A 30 DAILY REPORTS
The Contractor shall deliver daily to the Engineer‟s Representative a report as to the number
of workpeople employed on the Works in each Trade and copies of delivery notes of all
materials and goods to the Site during the day.
A 31 ACCESS FOR THE ENGINEER
The Contractor shall provide at all times during the execution of the Works and the
Maintenance Period proper means of access with ladders, gangways etc., and the necessary
attendance to move and adapt same as directed for the inspection or measurement of the
Works by the Engineer or the Engineer‟s Representative.
A 32 SETTING OUT AND LEVELLING
Prior to commencement of any site work the Contractor shall arrange to record on an
approved grid existing site ground levels and agree with the Engineer‟s Representative the
accuracy thereof by preparing a record drawing signed by the Contractor‟s Agent and the
Engineer‟s Representative. The Contractor shall set out and level the Works and obtain the
approval of the Engineer‟s Representative before commencing construction.
A 33 PROGRAMME TO BE FURNISHED
The Contractor shall prepare a program for the Works, including the work of subcontractors
and other work concurrent with the Contract, using the critical path network method. The
Contractor shall submit three (3) copies of programme to the Engineer with his tender.
Submission of programme will not relieve the Contractor of his obligations to apply in
writing for instructions as required by the Conditions of Contract. Receipt of programmes by
the Engineer shall neither affect the Contract completion date no relieve the Contractor of his
responsibility to complete the Works by this date. The Contractor shall review the
programme once each month to take account of any circumstances which arise affecting the
progress of the Works, and shall produce a revised programme and submit copies to the
Engineer.
A 34 CANCELLATION DUE TO SLOW PROGRESS
If the Engineer shall be of the opinion that having regard to the state of the Works at any
time, the Contractor will be unable to complete any section of the Works by the time
specified or by such extension thereof as he may be entitled to under the Contract and the
Contractor has failed to carry out steps and to expedite the work in accordance with the
Conditions of Contract or, if the Engineer is of the opinion that such steps are inadequate, the
Engineer may, by written order omit the whole or any part of the uncompleted work included
in that section and the Employer shall be at liberty to execute such omitted work by his own
workman or by other Contractors.
If the cost of such omitted or uncompleted work shall exceed the sum which would have been
payable to the Contractor on the completion of the said work, then the Contractor shall, upon
demand, pay to the Employer the amount of such excess and it shall be deemed a debt due by
the Contractor to the Employer and shall be recoverable accordingly.
10
A 35 DELAYS
The Contractor will be deemed to have allowed for all delay caused by difficulty in obtaining
labour and materials or by suspension of part or the whole of the Works due to adverse and
inclement weather conditions.
A 36 NON-PRODUCTIVE TIME
The Contractor shall allow for all costs incurred by non-productive time and all other
expenses in connection with overtime.
A 37 SAFETY, HEALTH AND WELFARE
The Contractor shall comply with enactments regulations and working rules relating to safety
health and welfare of workpeople.
A 38 CONTRACTOR'S SITE REPRESENTATIVE
The Contractor‟s Representative in charge of the Works shall be a duly graduated Engineer
having at least Three (3) years experience in the superintendence of similar works and shall
be required to have a proper command of the Arabic and English languages.
A 39 ATTENDANCE
The Contractor shall allow for and be responsible for the general attendance of one trade
upon another.
A 40 OFFICIAL VISITORS
The Contractor shall at all times when authorized by the Engineer give free undisputed access
and all facilities to any authorized employee of the Employer, any representative of the
French Consulet in Jerusalem or any person authorized by the U.N.D.P. wishing to view or
inspect any part of the\ Works or the materials to be incorporated therein.
A 41 CARE OF THE WORKS, ETC.
The Contractor shall keep all persons (including those employed by Sub-Contractors) under
control and within the boundaries of the Site.
He will be held responsible for the care of the existing premises and of the works generally
until their completion, including all work executed and materials, good and plant (including
those Sub- Contractors and Suppliers) deposited on the Site; together with all risks arising
from the weather, carelessness of work people, damage or loss by theft or any other cause;
and he shall make good at his own expense or such damage and lose.
A 42 WORK AT COMPLETION
The Contractor shall clean the Works thoroughly inside and out removing all splashes,
deposits, rubbish and surplus material.
The Contractor shall remove all temporary markings, coverings and protective rappings
unless otherwise instructed.
The Contractor shall touch up minor faults in painted surfaces carefully matching color and
brushing out edges. He shall repaint badly marked areas back to suitable breaks and
junctions.
The Contractor shall adjust, ease and lubricate all doors, windows, drawers hardware,
equipment, appliances controls and other moving parts as necessary to ensure easy and
efficient operations.
The Contractor shall leave the Works secure with all access locked. He shall account for all
keys and shall hand over to the Employer with
11
SECTION B: EXCAVATIONS, EARTHWORKS & ASPHALT
Part 1 - General
1.1 Description
a. Work Included: Furnish all labor, materials and equipment necessary for and
incidental to the completion of excavating, grading, micropiles drilling, filling,
backfilling, and grading work shown on the drawings and specified herein, pertaining
to the execution of all the earthworks normally carried out for the erection of
buildings, underground piping, underground structures, retaining walls, trenches, etc.,
complete in every respect, including all related items necessary to complete the work
shown on the drawings, described in this specification and as directed by the
Engineer.
b. Related work: Drawings and general provisions of contract, including General and
Supplementary Conditions, Bills of Quantities and Specification sections, apply to
work of this section.
1.2 Quality Assurance
a. Use adequate numbers of skilled workmen who are thoroughly trained and
experienced in the necessary crafts and who are completely familiar with the specified
requirements and the methods needed for proper performance of the work of this
Section.
b. Use equipment adequate in size, capacity, and numbers to accomplish the work of this
Section in a timely manner.
c. Codes and Standards: Perform excavation work in compliance with applicable
specifications and Local Codes. Further to the requirements of the general conditions
regarding the compliance of all materials and products with the latest issue or
revisions of all standards, the following is a list of the standards that are applicable to
this specification.
1. ASTM-C-136 Sieve or screen analysis of fine and coarse aggregates.
2. ASTM-C-127 Specific gravity and absorption of coarse aggregates.
3. ASTM-D-854 Specific Gravity of Soils.
4. ASTM-C-142 Friable particles in aggregates.
5. ASTM-D-1556 Density of soil in place by the sand-cone method.
6. B.S.1377 Methods of tester soil for Civil Engineering purposes.
7. ASTM-D-2216 Laboratory determination of moisture content of soil.
8. ASTM-D-423 Liquid limit of soils.
9. ASTM-D-424 Plastic limit and plasticity Index of soils.
10. ASTM-D-427 Shrinkage factors of soils.
d. In addition to complying with requirements of governmental agencies having
jurisdiction, comply with the directions of the soil engineer.
e. Materials Testing:
12
1. In general, the quality control of materials and workmanship shall be carried out as
specified in the "Special Conditions" section. An approved independent and
authorized materials testing office shall carry out all necessary testing and reporting.
2. Preliminary series of tests such as Density/Moisture/CBR, etc., shall be carried out in
an authorized laboratory. The results of completed tests that are in accordance with
the specification shall require the approval of the Engineer, prior to the contractor's
making use of the material or product tested.
3. Compacting Testing
a. Sampling:
1. After a layer has been correctly graded and made even it shall be sampled for testing
the quality of the workmanship. The Engineer will determine the points where
samples shall be taken. Sampling shall be performed regularly for the approval of
each layer. The above shall be carried out in accordance with the relevant
requirements of the Specification.
2. In every case where the quality of a layer does not meet the requirements, it shall be
corrected or demolished and executed anew, as laid down in the specification. After
these corrections have been completed, the layer shall be retested. The Contractor
shall keep a check on the performance of tests and any objections shall immediately
be brought to the attention for the Engineer. Objections lodged at a later time will not
be considered. Work shall not start on a new layer until the previous one has been
approved. For any work or layer, the Engineer will determine the area for testing and
approval shall be obtained before a new layer may be placed thereon.
3. The cost of all above testing shall be met by the contractor whether the test results are
satisfactory or not.
b. Rate of density
1. The rate of density is the percentage ratio between the field density (without
correction for material passing the 3/4" sieve) and the calculated density multiplied by
100, as follows:
D = ____100______
Pc + Pf
Gs rDf
The value of the compaction will be a percentage rounded off to a whole number.
Where,
D - Calculated density T/cu.m.
Pc - Percentage of aggregates larger than 3/4"
Pf - Percentage of aggregates smaller than 3/4"
Df - Maximum density obtainable according to ASTM-D-1557-70 (method
D0 T/cu.m.)
Gs - Bulk specific Gravity of aggregates larger than 3/4", according to
ASTM-C-127-59.
13
r- Correction factor, given in the following table:
Table of Correction Factors:
Pc% R
20 of less 1.00
21-25 0.99
26-30 0.98
31-35 0.97
36-40 0.96
41-45 0.95
46-50 0.94
51-55 0.92
56-60 0.89
61-65 0.86
66-70 0.63
Table extracted from AASHTO-T-224-67
c. Compliance With Requirements:
1. All works shall be done in accordance with the design levels and dimensions without
exceeding vertical deviations, as follows:
2. Subgrade and ditches - minus 30mm.
3. Fill under slab - minus 20mm.
4. The deviations shall apply to each layer and shall not be cumulative. Any increase in
this of one or more structural layers (above the subgrade) necessary because of the
a/m deviations shall be at the Contractor's expenses.
5. Repairs shall be made in areas where the deviations exceed the permissible limit. At
bulges the surplus material shall be removed and the rolling executed again. At
depressions the deficient material shall be added after disking the underlying layer to
a depth of 20cm and the rolling shall be executed again.
1.3 Submittals
If excavation is over 3.0 meters in depth it shall be sheeted and shored, submit
working drawings and calculation for the design of the sheeting and shoring.
1.4 Job Conditions
a. Existing Utilities: If utilities are to remain in place, provide adequate means of
protection during earthwork operations.
b. Should unanticipated utilities be encountered during excavation, cease work and
consult the Engineer immediately.
Resume work only after agreement has been reached as required by the General
Conditions. Repair damaged utilities to the satisfaction of the Engineer.
c. Demolish and completely remove from site existing underground utilities indicated to
be removed.
14
1.5 Site Clearing
a. The Contractor shall carry out site clearance which shall include clearing out the
whole site area of all kinds of vegetation, debris rubbish, etc., including the grubbing
out of roots, including loading and carting away to an approved dumping area prior to
any site preparation and/or setting out is begun.
1.6 Site Inspection And Investigation
a. The Contractor shall visit the site prior to submittal of his tender price and make all
investigation which he deems necessary to ascertain the nature of the existing ground
and the sub-soil to be excavated. Permit to drill boreholes will be granted to
Contractor.
b. The Contractor shall examine the contract drawings and other contract documents and
promptly notify the Engineer of any discrepancy, error or omission that he may
discover. Correction instructed in this respect will be compiled with all in accordance
to the provisions of the contract documents.
Part 2 - Products
2.1 Soil Materials
a. Sub-base material: AASHTO M 147, Grade B or equivalent Local standards.
b. Drainage Fill: Washed, uniformly graded mixture of crushed stone, or crushed or
uncrushed gravel, with 100% passing a 38mm sieve and not more than 5% passing a
sieve No. 200.
c. Backfill and Fill Materials Classified as A-1, A-2, or A-3, in accordance with
AASHTO M 145 or equivalent Local Standards. All materials shall be free of rock or
gravel larger than 50 mm in any dimension, debris, waste, organic material, and other
deleterious matter. Do not use material with particles larger than 25 mm within 600
mm of structures and in the bottom 200 mm of trenches. The following tests shall be
used to ensure the fill meets the above requirements:
ASTM-D 2487: Classification of soils for Engineering purposes.
ASTM-D 422 : Particle - size analysis of soils.
ASTM-D 423 : Liquid limits of soils.
ASTM-D 424 : Plastic limit and plasticity index of soil.
Part 3 - Execution
3.1 Workmanship
a. Levels:
1. The Contractor shall satisfy himself of the accuracy of the existing ground levels as
shown on the drawings before commencing work on the site and no claim will
subsequently be allowed because of his failure to do so. All excavations shall be made
15
to the depths, levels and dimensions shown on the working drawings submitted by the
Contractor and approved by the Engineer all as may be directed.
b. Excavation Generally:
This work shall comprise excavation to any depth, as shown on the drawings, in
unclassified ground including all hard and rock layers, temporary earthwork supports
and any work below the normal water table. It includes also the satisfactory removal
and the position of all materials excavated, regardless of their nature and consistency
and including grubbing up old roots, drain pipes, hardcore and all other obstruction
below ground level. No extras will be allowed either on account of the condition of
the materials at the time it is excavated, the manner in which it is excavated or any
other cause whatsoever.
2. Excavation shall be carefully planned to ensure the adjacent ground and works are
adequately supported at all times, and their safety shall be Contractor's responsibility.
3. Excavation may be by machine or by hand at the discretion of the Contractor. Under
no circumstances will a claim be entertained for the extra cost of one type of
excavation over the other. Rock shall be removed with compressed air hammers or
other special plant. Blasting will not be allowed without written permission from the
Engineer, who must be fully informed by the Contractor as to steps taken to safeguard
the surrounding property, and the Contractor must take all responsibility for any
damage or annoyance caused by reason of blasting. In case permission is not granted
to use explosives, no claims for any additional costs or delays whatsoever shall be
considered.
4. Where excavation works are carried out by power excavating equipment such as mini
power shovels and mini back-hoes, jack hammers, power drills, or any other
equipment which the trade Contractor may propose to use, sufficient depth shall be
left unexcavated to enable the exact depth required to be obtained by hand
excavation.
c. Engineer's Approval:
1. The setting out shall be approved before work is commenced and the Contractor is to
notify the Engineer when the excavations are ready to receive the concrete foundation
and these shall not be laid until Engineer has signified his approval in writing that a
proper foundation strata has been obtained.
2. Covering up of foundations is not to be carried out until the foundations have been
inspected and approved. The Contractor is to give the Engineer three days notice of
his intention to cover up any foundation.
d. Shoring and Bracing:
1. Provide materials for shoring and bracing such as sheet piling, up rights, stringers and
cross-braces in good serviceable condition. Provide permanent steel sheet piling
wherever subsequent removal of sheet piling might permit lateral movement of soil
under adjacent structures. Cut-off tops at 400 mm below final grade and leave
permanently in place.
e. Drainage:
16
1. The Contractor shall be responsible, and shall provide all necessary equipment, for
keeping all excavation and subsequent concreting operations dry.
f. Liability of Excavation:
1. Any excavation which have been excavated in good ground beyond the level and
sizes shown on the drawings or required by the Engineer are to be filled by the
Contractor with the same mix as specified for the foundations at the Contractor's own
expense. Any soft pockets which in the Engineer's opinion should be excavated shall
be filled with concrete of characteristic strength 20 N/mm2 and measured and valued
at contract rates.
2. No heavy plant or equipment shall be placed adjacent to excavations unless by written
agreement of the Engineer. No such agreement given or implied shall relieve the
Contractor of his contractual responsibility.
g. Trimming excavations:
1. The bottom and sides of excavations shall be sufficiently trim, clean, and dust free
prior to pouring any concrete.
2. Importance is attached to keeping dry and clean the excavated surfaces upon or
against which concrete or brickwork is to be deposited or built. Adequate precautions
are to be taken to prevent water from washing out cement or particles falling in, or in
any other way injuring the work.
h. Backfilling:
1. No backfilling is to be done until construction below ground has been approved,
underground utilities systems have been inspected, tested and approved, forms
removed and the excavation cleaned of debris and rubbish.
2. Where floor slabs are designed as ground bearing it is particularly important that the
backfilling beneath these should be uniformly and thoroughly compacted to 95%
Proctor, this stipulation applies to trenches for retaining walls and foundations.
3. Filling behind basement or retaining walls shall not be placed in position until 14 days
after they have been constructed unless otherwise approved, or until the suspended
floor abutting the wall at the top or at intermediate levels has been cast and set, and
shall be placed with very great care to insure that the water-proofing membrane is not
damaged.
4. All materials used for back filling shall, unless otherwise ordered, be selected hard,
dry, material from the excavations or imported thoroughly compacted in 20 cm layers
with a heavy roller or other approved mechanical plant. The Contractor shall submit
his proposals for compacting the fill for approval before commencing work.
5. If the excavated material is not approved for use as fill, then clean well graded
hardcore or other granular fill shall be provided by the Contractor. Details of all
imported filling materials shall be submitted for approval before starting work, no
material will be approved which does not comply with the specifications.
17
6. If directed the top surface shall be well brushed and blinded with fine material to
receive concrete.
i. Trench Excavation and Filling:
1. Trenches for underground utilities systems and drain lines shall be excavated to the
required alignments and depths. The bottoms of trenches shall be tamped to secure
the required slope and shall be tamped if necessary to provide a firm pipe bed.
Recesses shall be excavated to accommodate bells and joints so that pipe will be
uniformly supported for the entire length. Rock, where encountered, shall be
excavated to a depth 15 cm below the bottom of the pipe, and the over depth shall be
back filled with approved material. Bottoms of trenches to receive PVC pipes shall be
excavated for sewer and water pipes, and underground electrical and communication
services unless otherwise indicated. Care shall be exercised to minimize disturbance
to the compacted subgrade.
2. The Contractor is to provide all timbering, steel sheets piling or other approved
supports, and support the sides of excavations, trenches and pits in such a way as well
be sufficient to secure them from falling and to prevent any movement.
3. The Contractor shall submit for approval details of his scheme and methods of
excavation shoring and filling before starting work. Such approval shall in no way
relieve the Contractor of his responsibilities for the sufficiency of his methods. The
Contractor is to be responsible for timing and removal of timber, steel sheet piling or
other materials ensuring and trenches.
4. Care must be taken in excavating service trenches etc., along side foundations.
Particular attention shall be given to all excavations and fillings which extend to
depths sufficient to fall within a dispersion angle o 45 from the underside of any
foundations.
5. Lower portion of trenches shall be backfilled in 15 cm maximum thickness layers and
compacted with suitable tampers to the density of the adjacent ground until there is a
cover of not less than 80 cm over drain pipe and 30 cm over other utilities unless
otherwise noted. The backfill in this portion of the trench shall consists of a selected
material at moisture content that will facilitate compaction, free from stones larger
than 2.5 cm in any dimension and hard clods and conglomerates larger than 15 cm in
any dimension.
j. Crushed Stone Filling:
1. The stone for filling is to be clean, dry, hard stone broken to pass 5 cm mesh, free
from all foul materials, vegetable matter and rubbish and is to be deposited in layers
no exceeding 15 cm thickness each layer well rammed and consolidated.
2. The surface of crushed stone filling or beds are to be leveled or other graded and
blinded with approved fine material to fill all interestics.
18
3. Should any crushed stone filling or beds be damaged by water, mud or other cause
before being covered they are to be cleaned of and reformed as directed at the
Contractor's own expense.
k. Settlement:
The Contractor shall be responsible for making good any settlement of filing that may
occur and for any consequential damage up to the end of the period of maintenance.
The slopes, backfilled areas, etc., shall be formed to such levels as to ensure that the
final lines and levels after settlement shall be as shown on the drawings or directed.
l. Disposal of Surplus Material:
Load and cart away from the site all surplus excavated materials and deposit on tip to
be provided by the Contractor and pay all charges in connection therewith.
Base Coarse
Part 1 - General
1.1 Description
This work shall consist of performing all operations in connection with the complete
construction of crushed limestone base course to the thickness, lines and grades
shown on the plans and cross-section.
1.2 Materials
Aggregate material for base shall consist of hard, durable, crushed aggregated
retained on sieve No. 4 shall have 80% by weight of at least two fractured faces, be
mechanically crushed by approved crushing plant and shall be free from organic
matter or other deleterious substances and free from clay balls. Base course aggregate
shall conform to the following gradation:
AASHTO Sieve Percent Passing
3” -
2” (50.800mm) -
1.5” (38.100mm) 100
1” (25.400mm) 75-100
¾” (19.100mm) 60-90
½” (12.700mm) 45-80
3/8” (9.520mm) 40-70
No.4 (4.760mm) 30-65
No.20 (2.000mm) 20-40
No.40 (0.420mm) 8-20
No.200 (0.075mm) 5-10
The fractions passing the No.200 sieve shall not be greater than 70% of the fractions
passing No. 40 seive.
The aggregate shall conform to the following tests requirements:
19
California Bearing Ratio (ASTMD 1883) 80% Min. at
(4 days soaking 100% M.D.D. AASHTO T-180)
Los Angeles Abrasion (AASHTO T-96) 40 maximum
Sand Equivalent (AASHTO-T-176) 30 minimum
Liquid Limit (AASHTO T-98) 25 maximum
Plasticity Index (AASHTO T-90) 2 mim.-6 max.
Flaky and elongated particles (B.S.S. 812) 25% max. each
The following tests shall also be performed:
A. To determine the presence of soft materials in the base materials, an abrasion test at
two different revolution shall be performed; namely at 100 revolutions and at 500
revolutions. Then the ratio of passing sieve No. 12 will be calculated as follows:
Passing sieve No. 12 after 100 revolutions.
Passing xieve No. 12 after 500 revolutions.
The above ratio should not exceed 0.22. If such ratio is more than 0.22, then the
material of base shall be rejected.
In the above test, the sample is sieved after 100 revolutions on sieve No. 12 then the
same sample is put back into the same apparatus to complete to 500 revolutions and
then sieved on sieve No. 12 then the ratio is calculated using the above formula. Sample
shall not washed in either stage, unlike the normal abrasion test where samle is washed
on sieve No. 12 after the end of test to calculate the normal abrasion percentage.
The soundness (ASTM C88) of coarse aggregate when tested by sodium sulphate
method shall not exceed 12% loss. The soundness of coarse aggregate when tested by
magnesium sulphate shall not exceed 16% loss.
C. Sieve analysis tests shall be performed on samples of base course aggregate where
and as directed by the engineer as follows:
1. Gradation tests shall be performed on samples of base course taken after mixing with
water and spreading before compaction and shall comply with Clause 14.02 with
maximum % passing sieve No. 200 being 10%
2. Gradation tests shall be performed on samples of base course taken after the required
compaction and the maximum allowable percentage passing sieve No. 200 shall not
exceed by more than 3 with the maximum material passing sieve 200 shall not
exceed 13 provided that gradation shall comply with Clause 14.02
The thickness of the compacted layer(s) shall be measured and recorded when
performing field density test; and sieve analysis test on samples taken from compacted
layer in place.
1.3 Construction
Aggregate for base course shall be delivered to the roadbed as uniform mixtures and
shall be spread in layers or windows. Segregation shall be avoided and the base shall be
free from pockets of coarse or fine materials.
Where the required thickness is 20 cm or less the base material shall be spread and
compacted in one layer. Where the required thickness is more than 20cm the base
material shall be spread and compacted in 2 or more layers of approximately equal
thickness, and the maximum thickness shall not exceed 20cm. The base course shall be
spread by graders or other approved mechanical method, watered shaped, and
compacted to the required grade and cross-section. The finished surface of the base
course shall not vary at any point more than 1 cm above or blow the grade established
by the Engineer. In addition to level checking, longitudinally the surface shall be
20
checked with a straight edge of 4 meter long, irregularities in this direction shall not
vary more than 1 cm. A minimum of 12 levels of the base every 100m shall be taken
and if 3 or more of these levels exceed the tolerance given then the Contractor shall
regrade the entire 100m length. If less than 3 of the levels exceed the tolerance then the
Contractor shall make good these points. The aggregate base shall be compacted to not
less than 100% of the maximum density determined in accordance with the latest
modified AASHTO T-180-D.
the base course shall be maintained in a condition satisfactory to receive and
subsequent base or surfacing material. Aggregate base course which does not conform
to the above requirement shall be reshaped or reworked, watered and thoroughly
recompacted to conform to the specified requirements.
1.4 Method Of Measurement
Base course shall be measured according to Drawings and paid for per Bill of quantities
in place, acceptably laid and compacted.
21
SECTION C: CONCRETE WORKS
Part 1 - General
1.1 Description
a. Work included: The extent of work required under this section of the specification
consist of the provision of all labor, plant and equipment and performing all
operations in connection with all concrete and precast concrete work, complete in
every respect shown on the drawings, described in this specification, and as directed
by the Engineer.
b. Related work: Drawings and general provisions of Contract, including General and
Supplementary Conditions, Bills of Quantities and Specification sections, apply to
work of this section.
1.2 Quality Assurance
a. Codes and Standards:
1. The following abbreviations covering the standards used for the works under the
contract shall have the significance set forth opposite each :
BS : British Standards Specifications.
CP : Code of Practice.
ASTM : American Society for Testing and Materials.
ACI : American Concrete Institute.
ISO : International Standards Organization.
JS : Jordanian Standards.
2. These works have been designed to incorporate and utilize economically goods,
materials and workmanship to various specifications which are detailed herein.
Reference is commonly made to British Standards (BS) and British Standard Codes of
Practice (CP) and Jordanian Standards (JS) and to the American Society for Testing
and Materials Standards (ASTM). Different national or international standards (DIN
or ISO etc.) that correspond to the specified standard may be used provided that their
requirements are not less stringent, and provided that the Contractor presents copies
of such standards translated into English. If any redesign of the works is necessitated
by the adoption of such alternatives the costs incurred shall be borne by the
Contractor. Those references shall in every case be deemed to include the latest
edition or issue of such standards.
3. Definitions: Reference in the specification to the term Local Authority is deemed to
denote the Local Building Authorities with statutory powers to control the quality of
work in the area concerned.
Part 2 - Products
2.1 Materials
22
a. Aggregates Generally: The Contractor's attention is particularly drawn to the
importance of ensuring that all naturally occurring aggregates are free from all traces
of chloride. All aggregates shall be thoroughly washed water in accordance with BS
2148 or any other equally approved standard and from an approved source.
b. Fine Aggregate:The fine aggregate shall comply in all respects with BS 882 or any
equally approved standard and shall consist of well graded course sand, mainly
passing a 4.75 mm BS test sieve as defined therein.
c. Coarse Aggregate: The coarse aggregate shall comply in all respects with BS 882 and
shall be retained at 4.75 mm BS test sieve, and shall be well and evenly graded.
d. Cement: Ordinary Portland cement shall conform to Jordanian Standards.
Sulfate resisting Portland cement shall conform to Jordanian Standards.
e. Waterproofing Agents: Water proofing liquid shall be Vandex or equivalent.
f. Lightweight Aggregates: The coarse and fine lightweight aggregates shall comply in
all respects with BS 3797 or JS. The coarse aggregate shall be 20 mm nominal size
graded aggregate.
g. Water: All water to be used in the works shall be clean and free from all harmful
matter in suspension or solution. The Contractor shall at his own cost have the water
analyzed by a laboratory approved by the Engineer, and obtain a certificate for each
source of water that it contains no chemical or organic impurities in suspension or
solution harmful to concrete, steel, finishing and all other parts of the works. If a
water supply cannot be found which is free from such impurities the Contractor shall,
at his own expense, treat the water to remove all such impurities. In either case,
analyses of the water shall be carried out during the construction of the works upon
the instructions of the Engineer.
h. Steel Bar and Fabric Reinforcement: All reinforcement shown on the
drawings unless otherwise specifically mentioned shall be hot rolled or cold worked
high yield deformed bars with a minimum characteristic yield strength of 414 N/mm2
complying with Jordanian Standards. Bar diameter 10mm or less shall have a
characteristic yield strength of 276 N/mm². Steel fabric reinforcement shall be square
mesh fabric complying with BS 4483.
i. Binding Wire: Binding wire where used for connecting reinforcement shall be No. 16
gauge soft annealed iron wire.
j. Concrete strength shall be as follows:
1. B-200 for blinding beds- Class D. (20 N/mm2).
2. B-300 for reinforced concrete- Class A. (30 N/mm2).
3. B-250 for reinforced concrete- Class B. (25 N/mm2).
k. PVC Water-Stop: The PVC for PVC water-stops shall be high grade virgin polyvinyl
chloride containing no filler nor reclaimed or scrap material. It shall comply with the
requirements of BS 2571 for type A3 Class 1 but shall have improved tensile
qualities. The minimum tensile strength shall be 2,000 p.s.i. (140 kg/cm²) and the
23
minimum elongation at break shall be 300 per cent. The BS softness shall be 45
degrees. They shall be obtained from a manufacturer approved by the Engineer, and
stored in accordance with the manufacturer's instructions.
l. Cellular Polystyrene:
1. Cellular polystyrene shall have a density greater than 24 kg/m³, a minimum
compressive strength at 5%, deformation of 0.2 N/cm² and maximum water
absorption of 2% by volume and shall be approved by the Engineer before fixing. It
shall be pre-cut to the requisite sizes and carefully placed to ensure conformity with
the drawings. It shall be properly fastened, braced and anchored to reinforcement to
prevent displacement of floatation during placing of concrete.
2. Polystyrene sheets for forming expansion joints between beam faces and between
walls, and for forming cavities in concrete walls shall be an approved material.
Thickness of sheets shall be comparable with the requirements shown on the
drawings.
m. Releasing Agents: Only chemical release agents, mould creams or mould oils which
contain a minimum amount of surfactant will be permitted. Water Soluble emulsions
and oils without surfactant additive must not be used. When concrete surfaces are to
receive an applied finish the Contractor shall ensure that release agent used will not
affect the finish of bonding to the concrete. Details of the releasing agent proposed by
the Contractor shall be submitted to the Engineer for approval, at least 14 days before
it is required for use.
2.2 Storage Of Materials
a. Aggregates: The aggregates shall be stored in approved containers or on a concrete
slab in such a way that contamination from other materials and intermixing of the
various gradings will be prevented. The aggregate shall be deposited in a way that
will prevent segregation through dropping on to the peak of a high heap.
b. Cement: The cement shall be stored in a weatherproof shed exclusively for this
purpose. The shed shall be large enough to allow proper aeration and effective
separation of the various consignments and separate stacking of different types.
Cement shall be stored on site for not more than 21 days, after this it must be removed
from site at the Contractor's expense. Alternatively, the cement be stored in silos of
approved design.
c. Reinforcement: The reinforcement should be clear of the ground without distortion
and should be protected from contamination by other materials.
d. Releasing Agents: All releasing agents must be stored strictly in accordance with the
manufacturer's instructions.
e. Formwork: When formwork is not used it shall be protected against damage and the
effects of weather.
2.3 Testing Equipment
24
a. The Contractor shall provide on site the following equipment:
1. Sufficient 150 mm cast iron test cube moulds to enable the Engineer to carry out the
test requirements of this specification.
2. Slump cone, baseplate and tamping rod.
3. Maximum and minimum thermometers and aggregate thermometers.
The following items shall also be provided if and when specifically requested by the
Engineer.
Suitable graduated measuring tubes for measuring the moisture content of fine
aggregate.
4. A set of British Standard grading sieves.
5. Suitable weighing scales.
6. Compacting Factor Test equipment.
7. Aggregate drying oven.
2.4 Concrete Mixes
a. Generally: The Contractor shall use his own specially designed mix to comply with
the requirements of this specification in respect of the strength and of the finish
qualities of concrete.
b. Mix Design for Special Concrete Mixes:
1. Mix proportions shall be designed by the Contractor for each special concrete mix
except where, in factory work it can be shown that over a period of time the specified
works cube strength of the concrete has been consistently attained.
2. The mix shall be designed generally in accordance with the requirements of the
Jordanian Standards.
3. The mixes shall be designed to have sufficient workability to allow concrete to be
placed and properly compacted by the methods to be used on site.
4. Complete calculations for the mix proportions and the information and assumptions
on which they are based, shall be submitted to the Engineer before any preliminary
strength cubes are made.
5. When the mix has been approved by the Engineer no variations shall be made in the
proportions, the original source of the cement and aggregate or in the type, size and
grading zone of the latter without the consent of the Engineer.
a. All mixes to contain 20mm aggregate unless otherwise noted on the drawings.
b. All mixes shall be vibrated.
c. Batching:
25
1. Aggregate and cement shall be batched by weight. The moisture content of the coarse
and fine aggregate shall be determined daily when concreting is in progress and
appropriate allowance made to the quantity of water delivered to the mixer.
2. All weight batching plant shall be to the Engineer's approval. If bulk storage of
cement is used it shall be supplied to the mixer by weighed delivery from an approved
storage hopper. For bagged cement, the aggregate used in each batch shall be so
arranged that one or more whole bags of cement are used in each batch.
d. Mixing on site if applicable:
1. All mixing shall be carried out in a power driven machine fitted with a water supply
device capable of being controlled so that the correct measured quantity of water is
delivered to each batch. The accuracy and calibration of this device shall be rigidly
maintained, within the tolerances described in BS 1305. The quantity of water used
shall be varied to suit the moisture content of the fine aggregate. The water/cement
ratio shall be approved by the Engineer before using.
2. The materials shall be mixed well and uniformly distributed. The mass shall be of
uniform consistency and color, but in no case shall the mixing time be less than two
minutes after all the materials have been added to the drum. The drum of all mixers
shall revolve at the speeds recommended by the manufacturer. Hand mixing will only
be permitted in an emergency and if written permission has been given by the
Engineer. A 50% increase in cement weight for a particular mix will also be required.
Before changing one mix for another using a different type of cement and after each
day's work, all mixers, plant, tools, etc., are to be thoroughly washed and cleaned to
remove all traces of cement.
2.5 Concrete Tests
a. Concrete Strength Test: 150 mm concrete test cubes shall be made, cured and tested
in accordance with BS 1881 from samples of concrete taken from the point of
deposition of works Cubes and from samples of materials for Preliminary Cubes.
b. Concrete Slump Tests:
1. A slump test shall be carried out on every pour of concrete and a record kept on site of
all slump tests taken, which shall be submitted to the Engineer at weekly intervals.
2. The respective slumps to be used for various of the structure shall be subject to the
approval of the Engineer and shall normally have a value of 50 mm with a tolerance
of 12 mm for 75% of tests with a maximum tolerance of 25 mm for all tests.
3. Test specimens shall be formed in a mould 300 mm high, 100 mm diameter at the top
and 200 mm diameter at the bottom. The inside of the mould shall be cleaned before
each test and the mould placed on a hard flat impervious surface. The concrete mould
shall be formed in four layers with 25 strokes of a 16 mm diameter, 600 mm long rod.
After filling and tamping the surface of the concrete shall be struck off level with the
top of the mould, leakage cleaned from around the base of the mould, and the mould
then lifted vertically from the concrete.
26
4. The slump shall be measured as the difference between the height of the concrete
before and the greatest height after the removal of the mould. All tests to be carried
out within a period of two minutes of sampling.
c. Preliminary Cube Test Procedure:
1. Except where in controlled conditions it can be shown over a period of time that the
specified works cube strength of the concrete has been consistently attained,
preliminary strength cube tests shall be carried out at least four weeks before the
commencement of concreting on site.
2. Preliminary cubes shall be made for each mix from three samples of aggregate and
from each sample of aggregate six cubes shall be made, three for testing seven days
after casting and three for testing twenty-eight days after casting.
3. Each set of three cubes tested twenty-eight days after casting shall be accepted as
satisfactory if the average strength of the three cubes is not less than the preliminary
design strength and the difference between the greatest and the least strength is not
less than 20% of the average.
4. Results of all preliminary tested cubes shall be sent to the Engineer as soon as they are
available and before mixing concrete for placing on site or in moulds.
d. Work Cubes Test Procedure:
1. A sample of concrete shall be taken on two separate occasions during each of the
mixes is used on site. The Engineer/ his representative will direct to select the samples
at site. Subsequently, samples shall be taken for every 50 cu.m of concrete placed
with a minimum of one sample taken every second day on which the mix is used.
2. From each sample four cubes shall be made, one for testing seven days after casting,
two are for testing twenty-eight days after casting and one to be kept on site and only
disposed of on the Engineer's written instruction.
3. This procedure also applies to the manufacturer of precast concrete.
4. The results of the first forty cubes tested shall be analyzed as set in CP 114, Clause
209 C, an example of the method to be adopted being given CP 116, Appendix B. The
mix proportions shall be modified if any of the conditions set out in CP 114, Clause
209 C are not satisfied.
5. Subsequently, all cubes tested shall be analyzed as above and the standard deviation
calculated monthly for all results up to that date.
6. All cubes shall be clearly marked with the date of casting and accurate records shall
be supplied to the Engineer, stating the dates of taking and testing samples, together
with the results of tests and the exact position from which the samples were taken.
e. Cost of Tests:
1. The cost of taking and testing of concrete samples under this specification, including
transport to a testing station where required, shall be met by the Contractor, whether
the test results are satisfactory or not.
27
2. All preparation and testing of concrete samples shall be carried out in accordance with
BS 1881 at a testing station approved by the Engineer and under his direct technical
supervision, who shall receive certified copies of the results of all tests.
Part 3 - Execution
3.1 Workmanship
a. Transporting and Placing:
1. The concrete shall be handled and transported form the mixer to its final position in
the work as quickly as possible and in such a manner as to avoid segregation, loss of
any of the ingredients of evaporation of water.
2. All concrete shall be placed in a manner as to avoid segregation. The Contractor shall
submit details of his proposed method of placing for the Engineer's approval.
3. Concrete shall be deposited in layers not exceeding 300 mm compacted thickness and
no concrete shall be placed round any reinforcement until the latter has been approved
by the Engineer.
4. Where concrete is transported by non-agitating equipment, discharge shall be
completed within thirty minutes after mixing.
5. In no case shall more than thirty minutes elapse between the completion of discharge
final placing and after period the concrete shall not be further disturbed.
b. Compaction:
1. The concrete shall be thoroughly compacted by means of suitable tools approved by
the Engineer, both during and immediately after placing.
2. The concrete shall be worked round reinforcement and against the forms avoiding all
occurrences of voids or honeycombing.
3. Where compaction by mechanical vibration is used the formwork shall be suitably
strengthened and precautions taken to avoid leakage of grout through the joints.
4. Vibrating Methods: Vibration shall be carried out in accordance with the following:
- For the poker type of vibrator, move the poker frequently and avoid leaving the poker
in one place for any length of time.
- The vibrator must not be used to move concrete into place.
- The poker must be withdrawn slowly to avoid forming a hole in the concrete.
4. The poker must not be allowed to the sides of the formwork.
5. The poker must not be allowed to touch reinforcement which is already cast in
immature concrete (i.e. Concrete less than 48 hours old).
28
6. The poker should not be used to compact layers greater than 600 mm.
7. Formwork vibrators shall not be used unless expressly approved by the Engineer in
writing. External vibrators shall only be allowed. In no circumstances where the use
of a poker vibrator is not possible such as thin sections and where metal shutters are
used.
8. Surface vibrators may be used for thin slabs such as floors and roads. The surface
vibrator shall not be used for slabs exceeding 150 mm thickness.
9. Vibrators generally shall not be used after a decrease in volume of concrete is no
longer apparent and in no circumstances shall they be allowed to cause segregation.
10. At all times sufficient vibrators shall be used to adequately consolidate the concrete
whilst still fresh and a spare vibrator of the similar type to the ones being used shall
be immediately available in case of breakdown.
d. Curing:
1. All concrete during and after depositing is to be so protected that there will be no
avoidable loss of moisture from the surface for a minimum period of seven days.
Longer periods may be specified for special work. The Contractor shall submit for the
written approval of the Engineer the methods he proposes to use.
2. Approved methods of curing:
a. Spraying with an approved sealing compound.
b. Keeping constantly wet.
d. Covering with a waterproof membrane laid or wrapped around so as to be contact
with the surface. The membrane must not allow a free air flow over the surface of the
concrete.
3. Protection shall also be provided to prevent damage to freshly placed concrete due to
inclement weather, i.e. heavy rain or frost.
4. Before concreting commences the Engineer must be satisfied that the necessary
materials for curing and protection are immediately available close to the area of
concreting.
e. Concreting During Cold Weather:
1. Before the onset of cold weather Contractor shall inform the Engineer of the
precautions he proposes to take for concreting in cold weather. Below an air
temperature of 5C no concreting shall take place without prior approval by the
Engineer of the precautions to be taken.
2. The Contractor will inform the Engineer, in advance, of his proposals for concreting
in cold weather for precautions to be taken when the air temperature falls below 5C
within three days after placing the concrete. The concrete temperature should not fall
below 5C from the time of mixing until three days after placing.
f. Concreting During Hot Weather:
29
1. The Contractor shall take special measures in hot weather to ensure that the
temperature of the concrete when deposited does not exceed 32C. This also applies
to the manufacturer of precast concrete elements.
2. Such measures are to be approved by the Engineer and shall include some of, or if
necessary all of the following:
a. Aggregates:
1. Aggregates stock-piles sited in shade even if this has to be provided temporarily.
2. Aggregate regularly sprinkled with water to encourage cooling by evaporation.
Whenever possible successive layers watered during stock piling.
b. Water
1. Water for mixing obtained from the coolest possible economic source.
2. Water storage tanks sited in shade, permanent or temporary.
3. Water storage tanks insulated or buried below ground where site conditions permit.
4. All distribution pipes, or water trucks insulated or painted white.
5. Sufficient fog sprays shall be available at all times during concreting operations.
c. Cement: The cement store should preferably be sited in the shade.
d. Mixing and Placing Concrete:
1. The mixing plant and delivery equipment sited in shade wherever possible and
organized in such a way that the interval between mixing and placing is the absolute
minimum.
2. Where shade is impossible to provide, equipment painted white.
Immediately before concrete placing, formwork, reinforcement, cable ducts, etc.,
sprinkled with cool water.
Curing and Protection: Proper curing with adequate protection from sunlight
maintained without interruption. Windbreak shall also be provided.
Exposed surfaces always and, where practicable, shuttering protected from direct
sunlight.
e. Cutting Away: The Contractor shall not cut away any concrete work without the
written authority of the Engineer, and the Contractor will be held responsible for the
safety of any work damaged due to authorized cutting either by himself of his sub-
Contractors.
3.2 Ready Mixed Concrete
a. The Contractor shall be permitted to use "Ready Mixed Concrete" subject to the
following additional requirements, and only with the written agreement of the
Engineer.
b. The name and the address of the works of the supplier is to be submitted to the
Engineer, and his acceptance of the use of such supplier shall be obtained prior to
placing the order. Notwithstanding any such authorization by the Engineer, the
Contractor shall take full responsibility that the ready mixed concrete complies with
the requirements of the Specification.
c. The concreting materials shall comply with the requirements of the specification and
shall be tested in accordance with the Engineer's instructions. The cost of such testing
will be the responsibility of the Contractor. Works set cubes shall be taken on site be
30
the Contractor, in accordance with the Engineer's instruction and as described in this
Section of the specification.
d. The Contractor is to ensure that a record is at the supplier's works of the exact time
when the concreting materials are mixed.
e. In the case of plant mixed concrete, the concrete shall be carried in purpose made
agitators, operating continuously. When truck mixed concrete in used, water shall be
added under supervision either at the site or at the central batching plant as agreed by
the Engineer but in no circumstances shall water be added in transit. In no case shall
more than 45 minutes elapse between the addition of water to the mix and the placing
of the concrete.
f. Delivery notes shall record the following information. The Contractor shall keep all
such delivery notes for inspection by the Engineer :
1. Date and time of arrival of truck.
2. Time and Place of mixing of concreting materials.
3. Registration number of truck and name of depot.
4. Time and Place of adding water to material.
5. Time when concrete is placed in position and left undisturbed.
6. Mix type.
7. Position in the structure where the concrete is placed.
8. Whether test cubes were taken from this delivery.
9. Slump
10. Details of additives, where the use has been approved.
3.3 Bending And Fixing Of Reinforcement
a. Bar Bending Schedules: The Contractor shall prepare bar bending schedules for fixing
which show location, diameter, length, spacing, beds and laps for all reinforcement.
The schedules shall be approved by the Engineer before any concrete work is
commenced.
b. Bending and Cutting:
1. All dimensions on bending schedules are to be read in conjunction with BS 4466, ACI
Code (ACI-315) or any equally approved standards. Bars are to be bent to the shapes
and radius shown on the drawings and bar schedules and, except at bends and cranks,
shall be perfectly straight. Any bar showing signs of cracks, or brittleness shall be
rejected.
2. Bars are to be cropped to length and flame cutting will not be allowed.
31
3. Bending and re-bending bars on site as a temporary expedient will only be permitted
if the operation is carried out using the correct equipment. The latter must be
adequate to limit radius of the bend or re-bend at 12 times the bar diameter.
4. The use of heat to facilitate bending shall not be permitted with cold worked bars
without the approval of the Engineer.
c. Fixing:
1. The Contractor shall assemble all reinforcement in accordance with the drawings, by
wiring. Welding will be permitted only where shown on the drawings or with
approval of the Engineer. Cover shall be maintained by the proper use of chairs,
spacers or nonporous concrete blocks, sufficient to prevent displacement of the bars
during concreting. Plastic spacer blocks will not be permitted on any surfaces
exposed to weather or on other damp positions. No steel shall be fixed or covered by
concrete unless it is in the correct position and free from mud, oil, paint, retarders,
loose rust, millscale or other foreign matter.
2. A steel fixer shall be in attendance during concrete to rectify any unavoidable
displacement as the concrete is placed.
3. Unless otherwise shown on the drawings, concrete cover to reinforcement shall not be
less than the following:
a. Columns and beams with externally exposed faces 30 mm.
b. All other columns and beams 30 mm.
c. Suspended slabs with externally exposed faces 30mm.
d. All other suspended slabs -25mm.
e. Foundations - 70 mm
4. Columns starter bars shall be held accurately in position with suitable templates. No
bars must be placed by pushing into the wet concrete. Where welding is required
between bars or between bars and plates, it is to be carried out in accordance with BS
1856 and all welders employed on the work are to be approved by the Engineer. If
required by the Engineer, a welder may be required to carry out additional test pieces
and if there are not satisfactory the Engineer shall be entitled to ask for particular
welder to be replaced.
d. Site Provision: The Contractor shall provide on site bar cutting and bending facilities
to cater for minor variations without incurring avoidable delays.
3.4 Formwork
a. Materials:
1. Temporary formwork shall be constructed of timber, sheet metal, or other approved
material.
2. Unless otherwise specified, permanent formwork shall be constructed of slabs or
blocks of precast concrete, natural stone, brickwork, or other approved material. Slabs
or blocks shall have an exposed surface or the specified quality : they shall have
positive anchorage to the structure, and the joints between them shall be made tight
32
with mortar or by such other means as will prevent the leakage of grout from the
concrete.
b. Design:
Formwork shall be so designed and constructed that concrete can be properly placed
and thoroughly compacted.
Formwork shall be capable of adjustment to the lines and dimensions of the finished
concrete, and it shall be sufficiently strong to resist, without excessive distortion, the
pressure of concrete during its placing and compaction, and other loads to which it
may be subjected. It shall not be liable to suffer distortion under the influence of the
weather.
c. When concrete is to be vibrated, special care shall be taken to ensure that the
formwork will remain stable and the joints tight.
d. Deflection and Camber: The Contractor shall make allowance for any settlement or
deflection of formwork that is likely to arise during construction, so that the hardened
concrete conforms accurately to specified line and level. The Contractor shall also
make allowance on the formwork for any camber specified by the Engineer to allow
for the elastic deflection of structural members and deflection due to creep of the
concrete.
e. Supports:
1. Formwork shall be constructed so that formwork to the sides of members can be
removed without disturbing the soffit formwork or its supports. Props and supports
shall be designed to allow the formwork to be adjusted accurately to line and level
and to be erected and removed in an approved sequence without injury to the
concrete.
2. All floor slabs shall remain propped during the construction of the total concrete
frame. The weight of the floor slabs and other incidental loads shall be carried directly
through these props to suitable foundations at ground or basement level. All floor
slabs shall be struck at the highest level first and working progressively down the
frame to the lowest level.
3. Props and bracing shall be provided for the temporary support of composite
construction were separately specified.
f. Joints and Edges:
1. All joints in formwork shall be close fitting to prevent leakage of grout from the
concrete.
2. At construction joints formwork shall be tightly secured against previously cast or
hardened concrete to prevent the formation of stepping or ridges in the concrete.
3. Formwork shall be constructed to provide straight and through angles, arises, or
edges. were chamfers are shown on the drawings, the fillets shall be accurately cut to
size to provide a smooth and continuous chamfer.
33
g. Ties: The material and position of any ties passing through the concrete shall be to the
Engineer's approval. Except where corrosion of a metal type is important it shall be
possible to remove a tie so no part of it remaining imbedded in the concrete shall be
nearer to the finish surface of the concrete than the specified thickness of cover to the
reinforcement. Any holes left after the removal of ties shall be filled with concrete or
mortar of approved composition, unless specified otherwise.
h. Sundries:
1. Formwork shall be provided to the top surface of concrete where the slope or the
nature of the work requires it.
2. Provision shall be made for forming holes and chases for services and for building in
pipes, conduits, and all other fixings.
i. Cleaning and Treatment of Formwork: All rubbish, chipping, shavings, sawdust and
dirt shall be removed from the interior of the formwork before concrete is placed. The
formwork to be in contact with the concrete shall be cleaned and treated with a
suitable release agent in accordance with the manufacturer's instructions. Care shall
be taken that oil or dirt is kept from contact with the reinforcement or with concrete at
any construction joints. Retarding agents shall not be used except with the permission
of the Engineer. Formwork shall be thoroughly cleaned after each use. Damaged or
distorted formwork shall not be used.
j. Striking or Removal of Formwork:
1. All formwork shall be removed without shock or vibration that damage the concrete.
In no circumstances shall formwork be struck until the concrete reaches a cube
strength of at least twice the stress to which the concrete may be subjected at the time
of striking.
2. The formwork to vertical surfaces such as walls, columns and side of beams may be
removed after 12-14 hours in normal weather conditions although care must be taken
to avoid damage to the concrete, especially to arises and features.
3. Where the early concrete strengths are not accurately known, the following minimum
times shall elapse before removal of formwork.
Minimum Period Before Removing Formwork
Concrete Elements Effective Span
(m)
Average Temperature ( Degrees Centigrade)
21 and
Over
( 10 - 20 ) ( 5 - 10 ) 5 or Less
Concrete Age in Days
Non load bearing
columns and walls and
beam soffits.
-
2
3
5
7
Walls, Columns, and
vertically loaded
-
5
6
7
9
34
elements only.
Less than 3.0 7 10 14 21
Slabs 3.0 - 6.0 10 14 21 28
Greater than 6.0 14 21 28 28
Less than 3.0 10 14 21 28
Beams 3.0 - 6.0 14 21 28 28
Greater than 6.0 21 28 28 28
4. The times given for the removal of props are based on the assumption that the total
plus dead weight to be supported at the time of removal is not more than one half the
total design load. For horizontal members where the loading is a higher proportion of
the total design load these time may need to be increased.
5. The Contractor shall be responsible for any injury to the concrete formwork and for
any damage caused by, or arising from the removal and striking of the forms and
supports. Any advice, permission or approval given by the Engineer relative to the
removal and striking of forms and supports shall not relieve the Contractor of
responsibility.
k. Polystyrene at Expansion Joints: After striking formwork to sides of beams and faces
of walls where the drawings shown an expansion joint or separation between concrete
faces to be formed, fix polystyrene sheets of the appropriate sizes and thickness
before casting the adjacent beams and walls. Secure the polystyrene to cement faces
with an adhesive recommended by the manufacturer. After concrete is poured, rake
out polystyrene as necessary to receive expansion joint assemblies.
L. Formwork in Relation to the Surface Finish of Concrete:
1. Sawn Formwork: Sawn formwork is for covered concrete work and shall be
constructed of sawn boards, sheet metal panels or other material.
2. Wrought Formwork: Where formwork is described as "Wrought" the surface of the
concrete is to be exposed and shall be finished smooth and even, free from all board
marks, projections, pits, honey-combing and other defects and all arises shall be
straight and true. To obtain the finish, forms shall be lined with matt plastics, plywood
or other material to the satisfaction of the Engineer.
3. Smooth Finish Formwork:
a. Smooth finish formwork is to produce uniform smooth finish of high quality, with
even and true arises for exposed concrete. The finished concrete surface shall be non
staining have minor blemishes only and there shall be no staining or discoloration
from release agents, formwork materials or other sources. The forms shall be designed
to have as few joints as possible and shall be arranged in a uniform pattern as shown
on the drawings. Wherever possible joints between sheets shall be arranged to
coincide with architectural features such as opening or changes of plane.
b. The forming shall have an impermeable form face, using matt plastics, impregnated or
coated ply, or a form face with low and uniform permeability. Joints between
formwork sheets shall be rebated to maintain accurate alignment of the form faces.
35
c. Details of formwork design and materials to be used for form faces shall be submitted
to the Engineer for approval.
4. Bush Hammer Finish:
a. Concrete surfaces scheduled to have a bush hammer finish shall be cast against
wrought formwork as specified. Concrete surfaces shall be properly cured before bush
hammering is begun.
b. Bush hammer finish shall be executed by skilled craftsmen using air hammers and
bush tools as designed for work of this nature. Special care shall be taken to prevent
chipping out of pieces of concrete and leaving ragged, unsightly corners and
interstices.
m. Finishes:
1. All concrete surfaces which are not exposed are to be left as struck from the mould,
except that any surfaces which are found to be honeycombed shall be made good as
soon as they have been inspected by the Engineer. The making good shall be done
with a mixture of fine aggregate and cement in similar proportions to the concrete,
and as dry as possible.
2. All exposed concrete surface with sawn formwork are to be left as struck. The final
surface shall be free from all irregularities and discoloration, and shall be even level
surface. The final surface for all floor slabs is to be travel smooth.
3. If any honeycombing is found on exposed faces, the Engineer's decision as to whether
the concrete shall be cut out and replaced or made good shall be final.
n. Re - using Formwork: Care shall be taken when re-using formwork that its
surface is clean and smooth and that it is free from warping, twisting or other
deformities. Any formwork which has, in the Engineer's opinion, deteriorated
sufficiently to render it unsuitable for the work shall be rejected and must be broken
up at once, new formwork being provided at the Contractor's expense.
o. Control of Concrete Color:
1. It is imperative that where special concrete finishes, i.e., where smooth finish
formwork and bush hammer finish are required, the color of the concrete shall be
consistent. The following measures shall be taken to achieve this requirements.
Concrete mixes, once established, shall be kept constant within the limits imposed by
minor aggregate variations. Approved samples of special finishes shall also be used as
standards of color and shall be kept on site or at precast works close to the work in
hand.
2. Throughout the use of one particular finish the coarse and fine aggregate must each be
obtained from the same quarry or pit and the cement must be obtained from the same
manufacturer.
3. Before casting any concrete with special requirements or finishes, the Contractor shall
forward to the Engineer letter from his suppliers or aggregates and cement and/or
ready-mixed concrete agreeing to abide by this clause.
4. The same formwork lubricant shall be used for all concrete of the same surface finish.
36
5. Frequent inspection shall be made of the lining to formwork or moulds to ensure a
constant texture. The Engineer will order formwork to be relined or renewed if in his
opinion the surface has altered sufficiently to give a different texture or give rise to a
variation in the drying out time on the concrete. New and re-used boards shall not be
mixed on the same elevation of floor level. The specified curing procedure shall be
rigorously followed and the sticking and curing times kept effectively constant,
varying only to allow for differences of humidity and temperature.
6. If the Contractor requires to use rapid hardening cement or take other precautions for
concreting in cold weather which may affect the color of the concrete, then
precautions shall be taken throughout the concreting of each particular finish.
7. Any concrete showing an unacceptable variation in color as a result of the Contractor
not conforming with this clause shall be cut out and replaced at the Contractor's
expense.
p. Samples of Special Concrete Finishes:
1. The Contractor shall submit to the Engineer samples of the formwork materials to be
used for wrought and smooth finish formwork. After approval of the formwork
materials, the Contractor shall supply as many small samples (450 by 750 mm
minimum) as may be required by the Engineer to approve the finishes.
2. Similarly, samples shall be submitted showing bush hammer finish. Thereafter, the
Contractor shall supply one full size sample for each finish which shall be cast in the
same manner as on the job and contain the same reinforcement, etc.
3. On approval of the large samples, they shall be kept in a prominent position in the site
and used as standards against which the finished work is judged.
3.5 Construction Joints
a. Once concreting has started it must be carried on to its natural completion to properly
constructed day work joints. Vertical stop boards must be provided to form these
joints, with joggles wherever possible, provision shall be made for the reinforcement
to run continuously through the joint without being temporarily bent up or otherwise
displaced, and any concrete flowing past the joint to be hacked off as soon as it is set.
b. Before concreting is resumed, the surface of the concrete on the first side of the joint
shall be thoroughly cleaned, and the surface removed so as to expose the aggregate,
by light bush hammering, wire brushing or other approved method.
c. The new concrete shall be carefully worked up against the hardened surface of the
joint. Wherever possible, except in the case of exposed face work where color is
important, the proportions of cement and fine aggregate to coarse aggregate shall be
increased in the batches to be placed against the joint.
d. Unless otherwise shown on the drawings, the maximum distance between
construction joints shall be 10 meters in reinforced walls.
37
e. Concrete in walls shall be placed in lifts not deeper than 1.8 meters. Concrete in
columns shall be cast in one continuous operation between floors with no intermediate
constructions joint.
f. Floor slab shall be cast in bays which are approximately square and in no case the
longer dimension of the bay be greater than twice the shorter dimension.
g. The Contractor shall submit to the Engineer for discussion and approval a marked up
drawing of the construction showing proposed positions of construction joints at least
7 days before the relevant work commences.
3.6 Fixing Of Waterstop
Water-stops shall be carefully maintained and properly protected from damage and
the harmful effects of light, heat and frost during all stages of construction. Where
centrally placed water-stops are used the stop-boards on each side of the water-stop
shall be accurately brought to match the profile of the water-stop. The concrete shall
be carefully compacted under and around the water-stop so as to leave no activities
joints shall be welded in accordance with the manufacturer's printed instructions.
3.7 Joint Filler
The joint filler for slabs shall be export quality Flexcell or Bitucell manufactured by
Fosroc-Expandite,UK., or similar approved bituminous impregnated fiberboard
expansion joint filler. Where required the exposed edges shall be raked out for a depth
of 2.5 cm. Point with an approved two-part polysulphide-based elastomeric sealing
compound in accordance with BS 4254. Joint shall extend full depth of slab unless
otherwise shown on the drawings.
3.8 Tolerances
a. The following tolerances have been used when considering the fitting together of the
various components in the building, i.e. the assembly of precast units, fitting of
concrete cladding, window and door frames, etc., where they affect the final
appearance and functions of the structure. They will not be enforced in positions
where these factors are unimportant. Although all work shall be constructed
accurately to the dimensions shown to the satisfaction of the Engineer.
b. The tolerances on the elements of construction shall only be additive within the limit
allowed, i.e. errors in plumb of columns of wall, etc., shall be corrected on successive
lifts.
c. Levels of beams and slabs - Soffits levels to be within 3 mm of the true position,
taking the specified cambers into account.
d. Plumb of vertical members - 5 mm per storey.
e. Sections of in situ concrete members - = 3 mm.
38
f. Flatness of surfaces, other than those to be cambered, measured from a line stretched
between any two points of the surface:
up to 3 meters long + 1.5 mm.
up to 6 meters long + 3.0 mm.
up to 9 meters long + 4.5 mm.
up to 12 meters long + 6.0 mm.
above 12 meters long + 7.0 mm.
g. Clear distance between adjacent columns and walls at any level, where accuracy is
required for doors, windows, etc. : + 5 mm.
h. All precast units are to be fixed within a tolerance of a 3 mm per unit. This deviation
may consist of + 1.5 mm at one end and + 1.5 mm at the other end of the unit, or 0 at
one end and + 3 mm at the other, provided the step in surface of adjacent units does
not exceed 1.5 mm or such greater figure up to 3 mm where considered permissible
by the Engineer, without affecting the appearance of the work.
3.9 Fixture And Opening Within The Structure
a. Details of any fixtures to be cast into the concrete shall be to the approval of the
Engineer.
b. No fixtures shall be attached to the concrete by shot-firing without prior permission of
the Engineer. Notwithstanding any such authorization the Contractor shall take full
responsibility for any damage caused to the structure, and make good to the
satisfaction of the Engineer.
c. Details of any openings, holes, chases, etc., required to be formed, or cut in the
structure shall be approved by the Engineer prior to the work being carried out on site.
3.10 Temporary Loading During Construction
No temporary loading in excess of the loading shall be applied to any part of the
structure, without first submitting details of the temporary works, i.e. props or ties,
etc., necessary to protect the structure from damage, to the Engineer.
3.11 Precast Concrete For Lintels Over Openings
a. Generally: Unless otherwise specified precast concrete units shall be cast in concrete
nominal strength 25 N/mm2. All clauses in this section of the specification shall be
construed as applying to the manufacturer of precast concrete units unless specifically
excluded or amended by the following.
b. Casting:
1. Shall be performed either in an approved casting shop or on the site. If on the site the
casting area shall be adequately shaded to protect the members during curing. Precast
concrete units may be removed form their moulds as soon as the concrete has
achieved sufficient strength to resist the stresses due to demoulding and handling
without distortion.
39
2. Unless otherwise detailed on the drawings members shall be cast in convenient
lengths for handling. Any members not having reinforcement detailed for them shall
be reinforced sufficiently for handling.
c. Handling, Transportation and Erection:
1. Where applicable precast concrete units shall only be handled using the lifting
positions agreed with the Engineer. The Contractor shall ensure that at all times
during handling, transportation and erection the units are not subjected to overstress.
2. Bearing members such as lintels shall have the upper surface clearly marked to ensure
correct positioning in the work.
40
SECTION D: STONE WORKS
Part 1 - General
1.1 Description
a. Work Included:
1. Cut limestone cladding for exterior and interior walls.
2. Metal anchors, mortar, and joint pointing.
3. Joint sealant.
b. Related work:
1. Drawings and general provisions of Contract, including General and Supplementary
Conditions, Bills of Quantities and Specification sections, apply to work of this
section.
2. Related Sections:
a. Testing laboratory services.
b. Concrete supporting wall.
c. Bedding and pointing mortar.
d. Masonry supporting wall.
e. Masonry restoration and cleaning.
f. Masonry anchors from structural steel framing members.
g. Water repellent coating.
h. Sealant for joints.
c. Products furnished under this section: Placement of wall anchors and devices.
d. Products under this section: Metal fabricated items for building into cut stone.
1.2 Quality Assurance
a. Codes and standards:
1. ASTM A36 - Structural Steel.
2. ASTM A123- Zinc (Hot Galvanized) Coating on Products Fabricated from Rolled,
Pressed, and Forged Steel Shapes, Bars, and Strip.
3. ASTM A167- Stainless and Heat - Resisting Chromium - Nickel Steel Plate, Sheet,
and Strip.
4. ASTM C270 - Mortar for Unit Masonry.
5. ASTM C387 - Packages, Dry, Combined Materials for Mortar and Concrete.
6. ASTM C568 - Limestone Building Stone.
41
b. Quality Assurance: All stones for facing shall be selected well in advance of the time
required, samples of stone materials and dressing shall be submitted for the Engineer's
approval 30 days before delivery of any such material to site.
c. Qualifications:
1. Stone Suppliers: Company specializing in quarrying cut stone with minimum ten
years documented experience.
2. Installer: Company specializing in performing the work of this section with minimum
ten years documented experience.
3. Design anchors and supports subject to Engineer's approval.
d. Mockup:
1. Provide mockup of cut stone wall for Engineer's approval.
2. Construct stone wall mockup, 1.5 m long by 1.5 m wide, including stone anchor
accessories, sill and head details corner condition, and any necessary details
3. Locate where directed by Engineer on site.
1.3 Submittals
a. Shop Drawings: Indicate layout, pertinent dimensions, anchorages, reinforcement,
head, jamb, and sill opening details, control jointing methods. Include structural
calculations for the above for fixing details subject to the approval of the Engineer.
b. Product Data: Provide data on stone units, mortar products, and metal products,
including test reports and results.
c. Submit samples, illustrating minimum and maximum stone sizes, color range and
texture, markings, dressing, and surface finish.
d. Submit installation methods and field erection or setting drawings.
1.4 Product Handling
a. All stonework shall be carefully packed for transportation, exercising reasonable
precaution against damage in transit, and shall be delivered promptly as ordered and
in sequence in which it is to be erected.
b. Take all necessary precautions to prevent all stonework from chipping, cracking, or
other damage, during the unloading, and storage on the site. Damaged stonework will
not be allowed to be installed, and should any damage be found in erected work, such
work shall be removed immediately and replaced with new work and the Sub-
Contractor shall assume all expenses incurred there from.
c. The stone work shall be stored in the building site on planking set entirely clear of the
ground and shall be protected by proper means from damage to arise and from contact
with anything which would result in the accumulation of dirt, dust, grease or any other
42
staining, discoloring or disfiguring elements. During extended period of storage,
cover the cut stone with tarpaulins, non-staining building paper or boards.
d. During temporary storage on site, at the end of working day, or during rainy weather,
cover stone work exposed to weather with non-staining waterproof coverings,
securely anchored.
e. Cements and Limes: Shall be delivered in original sealed containers plainly marked
with name and brand of manufacture, and kept dry until use. Cements and limes
which are defective or show partial set or caking shall not be used and shall be
immediately removed from the premises.
f. Sand: Shall be stockpiled on platforms or otherwise protected from direct contact
with the ground and shall be so stockpiled and handled as to prevent the inclusion of
foreign deleterious substances.
1.5 Sequencing
a. Sequence work to coordinate the installation of stone work with installation of
adjacent construction.
1.6 Rates
a. The rates for stonework shall include the cost of supplying stone dressing, building
and all mortar used in the building of the stone and backing, etc. Stonework will be
measured by square meter for net area on one face, no extras will be paid for reveals,
corners, etc.
Part 2 - Products
2.1 Stone
a. Stone facing to walls shall be durable local stone, First Quality Whitish stone
Gamaian or Equivalent to be approved by the Engineer and of quality and standard
that meet the Jordanian specifications and standards set for stone.
b. Stone shall be even grained, free from cracks, seams, holes, shakes, objectionable
irregularities of colour, impurities, structural weaknesses and other defects that would
tend to increase unduly the deterioration from natural causes.
c. Stone Facing:
1. General:
a. Where Drawings indicate" stone work", it shall be of the thickness, sizes and profiles
as shown. All stonework shall be honed and/or polished finish where exposed,
unfilled and filled in areas specified hereinafter as selected by the Engineer.
Stonework shall be sound, dense and free from defects which may impair its strength
and durability. Care must be exercised in selecting panels for proper colour range
when matching, to produce an even overall colour range when panels are matched.
43
b. Thresholds shall be furnished the work herein and turned over to the tile setter for
installation. Edges shall be beveled to profiles shown with cut-out ends to engage
into door frame jambs. Coordinate trades for proper execution of work.
2. Thickness of Stone: For walls the minimum thickness of each stone shall be 5 cm at
ends and the greatest thickness of all stones to be 7cm.
3. Stone Dressing: Surface texture to be dressed Taltesh for all surfaces and Matabah for
window jambs, reveals and setbacks. Sample to be prepared by Contractor.
2.2 Mortar Materials
a. Cement :
1. Used for setting beds shall be Portland cement non-staining, conforming to current
ASTM C-91,Type I.
2. Cement Colouring: Cement used for exposed joints shall be mixed with approved
non-fading pigmented colour non-standing as approved by the Engineer.
b. Sand: Used in cement beds shall be clean, durable bank sand, free from silt, loam,
clay, soluble salts and/or vegetable matter, conforming to ASTM C-144 and graded
fine to coarse within the following limits 100% passing no. 8 sieve, 90% to 100%
passing no. 16 sieve, 60% to 90% passing no. 30 sieve, 25% to 55% passing no. 50
sieve and 0 to 15% passing no. 100 sieve.
c. Hydrated Lime : Shall be ASTM C-206, Type S or ASTM C-207, Type S.
d. Water: Shall be clear, clean, fresh and potable suitable for domestic consumption.
e. Mortar:
1. Shall consist of slaked lime putty or dry hydrated lime and cement and sand mixed
first and cement then added:
1 part cement.
2 parts lime or lime putty.
6 parts of fine crushed stone sand.
f. Admixtures: Plasticisers, subject to Engineer's approval.
g. Pointing Mortar Color: According to Local Standards. Color as selected and
approved by the Engineer.
h. Setting Mortar: According to Local Standards.
i. Add mortar color and admixtures in accordance with manufacturer's instructions.
Ensure uniformity of mix and coloration.
j. Do not use anti-freeze compounds to lower the freezing point of mortar.
k. If water is lost by evaporation, re-temper only within two hours of mixing.
44
l. Use mortar within two hours after mixing at temperatures of 26 C, or two and one
half hours at temperatures under 10 C.
2.3 Accessories
a. Anchors, Dowels, and Ties shall be steel, galvanized after fabrication to ASTM A
123, 380 g/m², of sizes and configurations required for support of stone and applicable
superimposed loads.
b. Bolts, Washers and Nuts: Galvanized steel.
c. Spacers: Inorganic.
d. Joint Filler: Closed cell foam.
e. Bond Breaker: Sheet 10 mil (0.25 mm) thick plastic.
F. Sealant: As specified, color to match stone color.
Part 3 - Execution
3.1 Requirements And Workmanship
a. All stone shall be installed, grouted, cleaned, protected and cured in accordance with
requirements as specified herein.
b. All materials shall conform to the requirements of applicable Specifications of the
American Society for testing Materials.
c. Work shall be commenced only after grounds, anchors, plugs, hangers and bucks
which are to be in or behind the stone work are installed. All surfaces shall be dry
and clean before setting beds are applied.
d. The stone setter shall co-operate fully with other trades to do all cutting, drilling and
fitting to accommodate work of others.
e. All cutting, drilling including cutouts to receive anchors, etc., shall be done accurately
on site.
f. Cutting at end conditions in the field regarding wall application of panels will be
permitted.
g. Stone Fabrication :
1. Fabrication Tolerances:
a. Maximum Variation from thickness : 3 mm.
b. Maximum Variation from face size : 2 mm.
c. Maximum Variation from flat : 2 mm/m².
45
2. Fabricate units for uniform coloration with adjacent units and over the full area of the
installation.
3. Veining pattern shall be in one direction (longest dimension of stone) except as
otherwise shown or directed. Stone shall be selected and cut with consideration to the
veining.
4. Form external corners to square joint profile.
5. Slope exposed top surfaces of stone and horizontal sill surfaces for natural wash.
6. Cut drip slot in work projecting more than 13mm over edges. Size slot not less than
10mm wide and 6mm deep, full width of projection.
3.2 Examination
a. Thoroughly examine all surfaces to receive work of this section, and notify Engineer
in writing of all conditions which would adversely affect this work. Do not
commence work in any area where such notice of adverse conditions has been sent to
the Engineer until corrective work has been completed or waived.
b. Starting of work in any area without issuance of such notice should constitute
acceptance of conditions in the area by this applicator who shall from that time be
responsible for the satisfactory results of his work and any defects occurring thereafter
shall be corrected without additional charge to the Owner.
c. Establish lines, levels, and coursing, protect from disturbance.
d. Verify that items built-in under other sections are properly located and sized.
e. Clean stone prior to erection. Do not use wire brushes or implements which will mark
or damage exposed surfaces.
3.3 Execution
a. Stone Facing to Wall:
1. General: Areas to receive stoneface shall be completed before commencement of any
stonework. Stonework for risers and all vertical application shall be same as
specified herein for walls.
2. Scratch Coat:
a. Apply one (1) part Portland cement, three (3) parts damp sand, 1/5 part lime by
volume. Prior to application saturate masonry evenly, do not leave surface
water. Apply to approximately 6 mm (1/4") thick, finish shall be cross scratched
ready to float coat.
b. Float Coat Mix: One (1) part Portland cement, three (3) parts damp sand, 1/5 part lime
by volume. Prior to applying the float coat the scratch coat shall be thoroughly cured.
Saturate the scratch coat evenly, do not leave surface water. Provided a plumb, true
mortar surface the proper thickness from finished wall line. Total thickness of float
46
coat shall be in accordance to details. Apply float coat over areas no greater than may
be covered with tile while the bed remains plastic. While bed is still plastic, set stone
as follows.
3. Setting : The float at walls and base shall be applied and rodded to a true and even
surface. Trowel or brush a thin layer, 2-3 mm in thickness, of neat Portland cement
paste over the back of stone. These areas (float coat and paste) shall be limited to
what can be covered with stone before the mortar sets. Stones that exhibit drying
along edges shall be soaked and drained. Allow no free moisture to remain on backs
of stone when being set.
4. Stone slabs shall be pressed firmly into the float coat bed, tamping with wood
blocks to obtain smooth surface. All tile shall be aligned properly with straight
closed joints .2 mm wide. All edges of stone shall be buttered with coloured
cement before closing joints, wipe off excess immediately with sponge and clear
water. Tamping shall be completed within one (1) hour after placing stone. Adjusting
stone out of line shall be done within the one (1) hour period.
b. Setting Standing Stonework:
1. Anchoring: Vertical stone facing shall be set with anchors attached to the stones by
being hooked and embedded in holes 1.9 cm (3/4") deep in the edges of the piece,
parallel to the face and equidistant from front and back faces. The hole shall be filled
with mortar mixed in proportions as specified herein before for wall installation.
Attachment to the back-up wall shall be done by inserting anchors into previously
drilled wedge-shaped holes and filled with same mortar mix.
2. Jointing:
a. All joints shall be closed joints, 6 mm (1/32") wide, edges of stone shall be scattered
with non-staining colored cement before closing joints, wipe off excess immediately
with sponge and clear water. (C. Arrange stone coursing to bond with a consistent
joint width of 6 mm.)
b. Arrange stone pattern to provide a consistent joint subject to Engineer's approval in
accordance to samples or mockups.
c. General:
1. After stonework has thoroughly set, sponge and wash thoroughly. Remove all surface
cement and take care not to damage stonework or adjacent materials. Do not use acid
or abrasive cleaners. Type of cleaner shall be approved by the Engineer prior to
application. Finally, clean all surfaces using soft, dry cloths. Cleaning shall be done
with cleaning solution as approved by the Engineer.
2. Protect work after final cleaning and approval of stonework with non-staining heavy
draft paper or other approved coverage until acceptance of the building. The
Contractor shall replace torn or worn papers after the stone setter has completed his
work.
3. Clean Up: Remove from the site and legally dispose of at the end of each day, all
cartons, rubbish and debris resulting from the work of this Section.
47
3.4 Final Acceptance Of Work
a. Upon completion of the work, the Engineer will inspect the work accompanied by the
stone setter and General Contractor to point out all stone work in the judgment of the
Engineer needing filler including other conditions which are not acceptable for final
approval. All such work shall be properly logged as to its location and shall be
replaced and/or corrected in satisfactory condition acceptable to the Engineer. All
work shall be completed prior to final approval without additional cost to the Owner.
48
SECTION “E” METALWORKS
Division Titles Page No.
E - 1 Scope 26
E - 2 Materials 26
E - 3 Manufacture 27
E - 4 Workmanship 28
E - 5 Balustrades and Railing 29
49
SECTION E
M E T A L W O R K
E –1 SCOPE
These Specifications cover ferrous and non-ferrous works intended to be used in the Project
all in accordance with the Drawings and as directed by the Engineer.
E –2 MATERIALS
E -2.01 Steel
Steel plates, and structural steel shaped sections shall conform to the requirements of B.S. 4
latest edition for structural sections, Part 1 Hot rolled sections and Part 2 Hot-rolled hollow
sections (Metric Series).
E -2.02 Bolts and Nuts
Bolts and nuts shall conform to the requirements of B.S. 4190: I.S.O. metric black hexagon
bolts, screws and nuts.
E -2.03 Washers
Plain washers shall be made of steel. Taper or other specially shaped washers shall be made
of steel or malleable cast iron and shall conform to the requirements of B.S. 4230 Metal
washers for general engineering purposes.
E -2.04 Galvanized Steel Pipes
Galvanized steel pipes shall conform to the requirements of B.S. 1387 – I.S.O. “Medium
Series”.
E -2.05 Paint
Paint for Metalworker shall comply with the applicable requirements as specified under “
PAINTING”.
E -4.03 Hollow Metal Door Frames
Hollow metal door frames shall be fixed and shown on the drawings all in accordance with
the manufacturer‟s printed instructions and flushed up solid with plain concrete or cement
mortar.
The rates for hollow metal door frames are to include for the supply and assembly of the
complete unit including all necessary holes for hinges and lock, cutting off torsion threshold
bar if necessary and fixing in walls in accord- ance with the manufacturer‟s printed
instructions and plain concrete or mortar filling as shown on the drawings.
E 5 BALUSTRADES AND RAILING
Balustrades and railings shall be of the materials and made to the sizes, dimensions and
designs shown on the drawings.
50
SECTION “F”
SANITARY WORKS
Division Titles Page No.
F - 1 General 31
F - 2 P.V.C. Pipes 31
F - 3 Domestic Water Piping 32
F - 4 Manholes 34
F - 5 Clean out Boxes 34
F - 6 Clean out Openings 34
F - 7 Floor Drain 34
F - 8 Roof Drain 35
F - 9 Water Tanks 35
F - 10 Fixtures 35
51
S E C T I O N F
SANITARY INSTALLATIONS
F– 1 GENERAL
a. Scope of work
The Contractor shall furnish all labour, materials equipments, tools, appurtenances, services
and tem- porary work to provide complete the several pl; umbing and drainage systems all in
perfect working order.
This work shall include but not be limited to the following:
Sanitary fixtures.
- Water supply systems including cold water services.
- Soil, waste and ventilating systems.
- Rain water services.
- External gravity sewer net work.
Testing of all piping systems and equipment and other devices to demonstrate that the entire
installations are in perfect working order.
All fixtuires and materials shall be brand new bearing stamped ratings as required and must
be approved by the engineer prior to their use.
b. General description of the work
The sanitary works shall consist of all water supply to and water discharge from all the
sanitary fixtures.
City water is stored in steel water tanks at the roof of the building. Water distribution to all
floors is by gravity from these roof tanks.
Drainage of all floors is discharged by gravity from individual points to risers which are inter
connected to a system of manholes which will be later discharged to a local sewage treatment
plant.
Rain water is collected from roof and discharged out of the building by means of risers.
c. Working drawings and ordering
Immediately the contract has been awarded, the Contractor shall prepare detailed working
drawings showing exact position of all sanitary fixtures and position and size of all water
pipe work and drainage, soil, waste and vent piping, clearly indicated fittings proposed.
These drawings, when approved by the engineer, shall be used for ordering purposes.
F - 2. P.V.C PIPES
a. Supply and installation of 2”, 4”, & 6” P.V.C. pipes as manufactured by “Psalm” as shown
in drawings either within slab and wall or exposed and hung under ceiling.
b. P.V.C. pipes and fittings such as elbow, T, Trap shall be spigot and socket, and jointed by
rubber seal ring.
c. Clean out opening must be provided where shown on drawings and where required.
d. All riser branches must be provided by elbow or nipple with gate and with T with opening
at point of conic-tin with branches.
52
e. P.V.C. pipes and fittings shall be fixed in shaft by means of approved galvanized, two
pieces, holderbates of pipe fixed vertically and at not more than 2m. centers on pipes fixed
horizontally. Horizontal 4” and 6” P.V.C. pipe in pipe turned must be approved clamp.
f. Slope of drain pipes to be 1cm/mr unless noted otherwise.
g. Vent for sewage pipes to be 1 meter above finished roof and including wire dome grating.
h. Where vent pipes penetrate roof slabs, sleeve must be provided above it, and roof finishes
and water proofing, must be carried up around the pipe and covered with sleeves to prevent
water penetration, all to the approval of the Engineer.
i. For testing soil and waste stack the system shall be subjected to water test prior to being
covered and also tested for water tightness after back filling. On any section of pipe under
test the head of water applied shall not be less than 3 meter and not more than 6 meter. Test
shall be rectified and the test re-applied to the complete satisfaction of the Engineer.
F- 3 DOMESTIC WATER PIPING
a. Pipe Installation All piping shall be properly supported or suspended on
stands, clamps, hangers, etc.. of approved design.
Supports shall be designated to permit free expansion and contraction while minimizing
vibration. Pipes shall be anchored as directed by means of steel clamps securely fastened to
the pipe and rigidly attached to the building structure. Screw threads shall be cut clean and
true and joints made tight without caulking. No bushing shall be used. Reducing fittings shall
be used to change pipe size, and reductions to be made with eccentric reducers short
radius fittings shall not be used. The drawings indicate generally the size and location of
piping as designed for space conditional ceiling heights and may not be changed until
coordinated with other contractors.
Pipe work shall confirm fully of the following requirements Piping shall be properly graded
to secure easy circulations and prevent noise and water hammer. As much pitch as space
conditions allow must be given. Capped dirt pockets to be installed at all riser heel, low
points, and other places where dirt may accumulate must be provided.
Allowance must be made for proper provision for expansion and contraction in all portions of
pipe work to prevent undue strain in piping. Expansion joints to be installed as directed by
the Engineer.
All fittings such as elbows, tees, bushes, etc. shall be of best quality, foreign made or local
made [Class A] according to local standard with smooth interior surfaces.
Approved screw unions with bronze or steel bodies and ground brass taper or spherical joints
shall be installed at trapes instruments, etc. and where else directed to permit easy connection
and disconnection. Final connection to all equipment and fixtures shall be made in a manner
that will permit the complete removal of any fixture or any piece of equipment without
cutting of pipeline. If after the plant is in operation any system do not circulate quickly and
noiselessly [due to trapped or airbound connections]. The Contractor shall make proper
alternations in these defective connections. If connections are concealed in furring floors or
ceilings, the contractor shall bear all expenses of tearing up and rebuilding construction and
finish.
All main shall have a slope of not less than 5mm in 3 meters in direction of flow. All
branches shall have a slope of not less than 1mm in 3 meters towards the main.
53
All branches from mains shall be connected at the angle of 45 if possible. Each piece of pipe
and each fitting shall be carefully inspected on the inside to see that there is not defective
workmanship on the pipe or obstructions in the pipes or fittings. Joints in all screwed piping
shall be made with red load and boiled in seed oil, completely covered the male threads.
Straight elbows, bushing, long screws or bull head tees shall not be installed, and all offsets
shall be made with fittings. Pipes shall not be bend at any time.
Pipe work shall be installed in manner to allow for ease of air escape and system draining. It
shall be endeavoured to obtain this naturally by gravity.
However, where conditions don‟t permit it an automatic air vent shall be installed at all air
pocket locations and drain gate valves shall be supplied and installed at all low points and
risers legs or as shown on drawing. Before turning the project over to owner, contractor shall
thoroughly disinfect the entire water system, include underground main. Systems shall be
thoroughly flushed of all dirt and foreign matter.
Pipes material is galvanized steel “blue sign” local made “class A”.
All pipe fittings such as elbow, tee, reducer, union, etc. shall be galvanized forged steel of the
same quality of the pipe. Pipes and fittings shall be suitable for threaded connections.
b) Hangers, supports, anchors, etc.
The Contractor shall provide suitable and substantial hangers and supports for all piping.
Piping shall be carried by pipe hangers supported from concrete insets. In general supports
for pipes shall be not more than 2.5m, apart for 2” and smaller pipes according to the
conditions of the job and directions of the engineer. Copper piping shall have hanger every
1.5 meter. All vertical piping be supported by heavy pipe clamps resting on the building
structure. No piping shall be hung from other piping and all hangers shall be of heavy
construction suitable for the size of pipes supported. All horizontal pipes shall be supported
by split ring hangers of malleable iron, with sockets for hangers of solid rod the length of
each shall be adjustable. All vertical pipe line passing up through the building shall be hung
from each floor of the building. Malleable iron clamps of sample size bolted around the
pipes, shall be used for these supports. These pipes shall be secured midway between the
floor and the ceiling of each story by means of malleable iron, solid hangers around the pipe
and fastened to adjacent walls by means of inverted bolts cast in concrete walls anchors shall
be separate and independent from all hangers and supports. All anchors shall be of heavy
angle iron construction and suitable in every way for the work, and shall be installed where
necessary or as directed by the architect.
c) Valves
Hand valves and check valves shall be of an approved quality “KIM” or equivalent and shall
be furnished and installed as shown on the drawings or as directed during construction.
The Contractor shall include for the finishing the required valve tag and a schedule of valves
with a schematic drawing showing position of each. The drawing shall be glazed, framed and
hung in the machine room.
d) Float Valves
Supply and install all float valves as shown on the drawings and wherever specified in this
book of specifications.
54
Float valves shall be all bronze, screwed ends, float operated. Float shall be all copper and
mounted at the end of a brass or copper rod, which actuates valve operation.
e) Cleaning of Pipe
During constructions, the contractor shall cap all lines so as to prevent the entrance of sand,
dirt, etc. All pipe, fittings, valve etc. shall be cleaned of grease, dirt, scale and foreign
material before installation.
Before turning the project over to the owner all piping system shall be thoroughly cleaned
following the hereinafter specified instructions:
Piping shall be cleaned by operating system at normal operating pressure approximately 48
hours, wasting the condensate. At the end of the 48 hours period, contractor shall clean all
strainers by removing baskets and flushing with clean water. Blowing down through strainer
blow down valve will not be acceptable.
f) Testing
The piping system shall be tested by accepted method and under 150 psi hydrostatic pressure.
Test shall be maintained under inspection by consulting engineer for period of not less than 8
hours. No part of piping system shall be repeated after leaks are corrected. No part of piping
system shall be covered or concealed until it has been tested, inspected and approved by
engineer.
F-4 M A N H O L E S
a. All manholes shall be built from concrete or solid brick laid on 10cm. Concrete base over a
15cm. Hard-core , dimensions and level of inverts of manhole are shown on drawings.
b. Work shall include excavation, back filling, concrete base, hard-core installation,
reinforced concrete cover slab, benching and rendering internally.
c. Benching of manholes to be semi circular of diameter equivalent to adjacent pipes and to
be rendered and plastered perfectly smooth, inclination in manhole to be 2cm minimum.
d. Manholes over 1 meter deep shall be supplied by Cast iron steps well anchored to the
concrete walls at a spacing of 30cms
e. Manholes exceeding 2 meters deep shall be reinforced concrete base and walls cast in place
as shown in drawings.
f. Drop manholes exceeding 2 meters to be also of reinforced concrete base above.
F-5 CLEAN - OUT BOXES
Clear – out boxes shall be approved quality P.V.C. 4”/2”. They shall be provided with air
tight, sealing cover of chrome plated bronze.
F-6 CLEAN - OUT OPENINGS
a. Clean out opening is exposed P.V.C. soil and waste pipes shall be provided where shown
on drawings and where required.
b. All elbows for under ceiling piping connection shall be provided with gates.
F-7 FLOOR DRAIN
Floor drain shall be obtained from an approved manufac- turer P.V.C. 4”/2” minimum water
seal complete with chrome plated duty strainer tightly sealed to drain body. All 2” P.V.C.
drain pipes are connected to floor trap by rubber sealed record fittings.
55
F-8 ROOF DRAIN
Each roof drain shall be of P.V.C. pipe constructed with no trap, having and integral flange
and wire Dome type strainer, fixed by screwing into the drain body. Rain drain shall be
installed as shown on drawings.
F-9 WATER TANKS
Tanks shall be constructed of anti-corrosive steel sheet of 0.08mm thickness. The work shall
include installation on steel bases and also connection of galvanized pipes from the main
public pipe with a water meter, valves and installation of diaphram ball valve. Also the
supply pipe from the tanks includes a vent pipe. A test will be made against any leakage or
defect and according to the approval of the Engineer.
F-10 PLUMBING FIXTURES
Contractor shall supply and install the plumbing fixtures. All fixtures shall be set true and
level. All necessary supports for fixtures shall be installed before plaster work. All exposed
connections and fittings shall be of chromium plated brass. All nipples through wall to fixture
connections shall be copper with compression connections.
F-10 PLUMBING FIXTURES [CONDT'D]
No water supply shall be less than 1/2”.
a. Supply and installation of wash basin, porcelain local made class “A” size 56x41, with
chrome plated cold water faucet, size ½” of approved manufacturer such as [Grohhe or
equivalent] including chrome P-trap same kind of faucet connected with over flow and with
the floor trap by plastic P.V.C. pipe 2” and with chain and rubber plug. Height of basin 80
cm. From floor.
b. Supply and install of porcelain W.C. bowel including internal SSiphon local made class
“A” or equivalent. The price includes plastic flushing tank, plastic W.C. seat cover of heavy
duty such as [Keter], chrome plated angle valve ½” chrome plated flexible hose ½” . The
W.C.‟s connected with the 4 inch P.V.C. main sewage pipes, connecting the flushing tank to
main cold water line by ½” galvanized pipe . W.C. bowels shall be fixed to floor-by cadmium
screws and tightly grouted.
c. Supply and installation of best quality class “A” Porcelain laundry sink of size
60x39x36cm with chrome plated cold water faucet size ½” of approved manufacture such as
[Grohhe or equivalent] including 2” plastic P-trap connected with the floor by P.V.C. pipe 2”,
and with chain and rubber plug. The price includes connection to cold water mainline by ½”
galvanized steel pipe. Height of sinks 60 cm from floor.
d. Supply and installation of stainless steel kitchen single sink size 100x56cm including the
supply of chrome plated cold water faucet of approved quality [Grohhe or equivalent]
connected to cold water mainline by ½” galvanized steel pipe and connected to floor drain
trap by 2” P.V.C. pipe.
56
SECTION F: PLASTER WORK
G 3.01 Mixing of Ingredients
Except where hand mixing of small batches is approved by the Engineer, mechanical mixers
of an approved type shall be used for the mixing of plaster.
Frozen, caked or lumped materials shall not be used.
Mechanical mixers, mixing boxes and tools shall be cleaned after the mixing of each batch
and kept free of plaster from previous mixes. Plaster shall be thoroughly mixed with the
proper amount of water until uniform in colour and consistency. Retempering will not be
permitted and all plaster which has begun to stiffen shall be discharged.
All plastering shall be executed in a neat wormanslike manner and internal and external
angles shall be true, straight and plumb. Plaster shall be made good adjacent to wood or metal
frames, skirting and around pipes or other fittings.
All tools, implements, vessels and surfaces shall at all times be kept scrupulously clean and
strict precautions shall be taken to avoid the plaster or other materials becoming
contaminated by pieces of partically set material which would tend to retard or accelerate the
setting time.
G 3.02 Preparation of Surfaces
All surfaces to be plastered shall be clean and free from dust, grease, loose or projecting
mortar and all traces of salts are to be thoroughly sprayed with water, but all free water shall
be allowed to dry and disappear from the surface before the plaster is applied.
Plastering shall not be commenced until the background has been suitably prepared.
Blockwork joints shall be deeply raked out, efflorescence brushed off and all dust and foreign
matter removed.
Before plastering is commenced all junctions between differing materials shall be reinforced.
This shall apply where wall join columns and beams, particularly where flush, and similar
situations where cracks are likely to develop and as directed by the Engineer. The
reinforcement shall consist of strip of galvanized wire mesh (10 to 15mm hexagonal mesh)
15cm wide which shall be plugged, nailed or stapled as required at intervals of not exceeding
45cm at both edges.
On all external surfaces and on all smooth internal surfaces spatter dash of cement and sand
which shall contain 500 kgs of cement per one meter cube of sand shall be applied and
allowed to dry before rendering is commenced. All surfaces of walls shall be wetted
immediately prior to applying the first coat of rendering and this shall be allowed to
thoroughly dry out before the next coat is applied.
The Contractor shall from vertical guide screeds 5cm wide. The spacing shall not exceed 1.50
meters.
The screeds shall be plumb and in the same plane with each other. The sides of the screed
shall be kept rough to bond with plaster, the surface shall be smooth.
The finished surface shall be true to shape and angle oven in all directions, with straight
arises free of cracks and trowel marks and to the entire satisfaction of the Engineer.
G 3.03 Application of Coats
a) Base-Coat (Rendering)
57
After the application of the spatterdash “rasheh” the base coat shall be applied after the
spatterdash coat has set but in no case earlier than 24 hours after the application of the
spatterdash coat.
When applied to masonry or to concrete surfaces the base coat shall be applied with sufficient
force to prevent air pockets and to secure a good bond.
The base coat shall be lightly scratched in both directions to provide a key for the finishing
coat and shall be kept moist with a fog spray for 2 days and then allowed to dry out.
b) Finishing Coat
Shall not be applied until the rendering or base coat has seasoned for seven days; just before
the appli- cation of the finish coat, the rendering or base coat shall be wetted evenly with a
fog spray. Where cement plaster with a smooth trowelled finish is specified or indicated on
the drawings, the finish coat shall be first floated to a true even surface, then trowelled in a
manner that will force the sand particles down into the plaster and with the final trowelling,
leave the surface finished smooth and free from rough areas, trowel marks, checks or other
blemishes.
G 3.04 Proportions for Internal and External Plaster
Internal and external plaster shall be composed of 400kg of cement per one cubic meter of
salt free sand.
Plastering shall be applied in two (2) coats unless otherwise specified or indicated on the
drawings.
Finishing coat shall have a resonably uniform thickness of approximately 5mm.
Screed shall be laid and ruled as necessary to allow for a total thickness of 15mm for external
and internal plaster and the rendering shall be applied to the required thickness.
The metal grid system shall be a patent system suitable for use with in-situ plaster and
expanded metal lathing and shall have, flat metal hangers to suit suspended ceilings depths as
shown on the drawings and described in the Bills of Quantities. The system shall include all
main and cross runners, necessary splicers, hangers, clips and wall mounting next to walls.
The system shall be installed complete in accordance with the manufacturer‟s instructions.
The metal grid suspension system shall be concealed and shall allow for the whole of the
ceiling to be demountable.
All concealed ferrous metal members such as channel runners, zbars, clips and splines shall
have an approved corrosive resistant finish.
G 3.05 Metal Lath
At all junctions of dissimilar materials (i.e. concrete and blockwork or steel elements) the
joint shall be covered by metal lath strips not less than 200mm in width securely fixed to the
surface.
G 4 WATERPROOFING PLASTER TO ALL EXTERNAL WALLS
Mixing of plaster ingredients and preparation of surfaces to be plastered with waterproofing
plaster shall be as specified above.
Rendering coat shall contain 450kg. Of Ordinary Portland Cement per cubic meter of clean
coarse salt free sand and with admixture of waterproofing compound as specified added in
accordance with the printed instructions of the manufacturer, shall be applied and the surfaces
shall be trowelled hard smooth and allowed to dry. All surfaces of plastered areas shall be
cured for a minimum of 7 days.
58
G 5 TYROLEAN PLASTER (FINE GRAIN)
G 5.01 General
The tyrolean plaster shall be executed to the extent shown on the Drawings and as directed by
the Engineer.
The contractor shall provide sample (s) of Tyrolean plaster for the approval of the Engineer
prior to commencement of Tyrolean work.
G 5.02 Mixing
Cement and aggregate for each batch shall be accurately measured and mixed dry until
evenly distributed and the mass is uniform in colour. All batches shall be of such size that
they can be entirely used within half an hour. Mechanical mixers of an approved type shall be
used for mixing tyrolean plaster, except when hand mixing of small batches is specifically
approved by the Engineer. Mechanical mixers, mixing boxes and tools shall be cleaned after
mixing each batch and kept free of tyrolean mortar from previous mixes. Water content shall
be maintained at a minimum. Mixing shall be continued until plasticity be maintained at a
minimum. Mixing shall be continued until plasticity is obtained.
G 5.03 Proportions
Proportions of materials for tyrolean, by volume shall be as follows:
a) Scratch Coat
1 part Ordinary Portland Cement
3 parts fine aggregate
b) Finish Coat
1 part of white Portland cement
3 parts fine selected aggregate
No lime shall be allowed in either scratch or finishing coat, scratch coat shall be set on
spatterdash.
G 5.04 Application of Tyrolean
a) Workmanship
Surfaces to receive tyrolean shall be clean, free from dust, dirt, oil, or other particles that
might interfere with a satisfactory bond. Surfaces to receive tyrolean shall be evenly
dampened (not soaked) with a fog spray before tyrolean is applied. If surfaces become dry in
spots, the dry areas shall be dampened again to restore uniform suction. Tyrolean coats shall
be applied continuously in one general di- rection without allowing mortar to dry at edges.
Edges to be jointed shall be dampened slightly to produce a smooth confluence. Tyrolean
unless otherwise shown or specified shall be two coats work not less than 20mm. thick (i.e.
spatterdash, crotch coat and one tyrolean coat).
All exterior corners of tyrolean shall be slightly rounded.
Tyrolean on soffit surfaces shall be pitched forward to form a drip.
b) Scratch Coat
Shall be approximately 14mm. thick and shall be applied under sufficient pressure to form
good keys and shall be brought to a plumb true even surface. The scratch coat shall be damp-
cured 48 hours before the finish coat is applied under sufficient pressure to form good keys
and shall be brought to a plumb, true even surface. The scratch coat shall be damp-cured 48
hours before the finish coat is applied.
59
c) Finish Coat
Shall be approximately 6mm, thick. Surfaces of the scratch coat shall be dampened several
hours before the finish coat is to be applied. Additional dampening at time of application
shall be by fogspraying. Dampening by brush will not be permitted. When measure with a
2meter long, straight- edge applied in all directions the finish surface shall not vary from a
true plane by more than 1.5mm. The finishing coat shall be applied by means of a proper
spraying machine and the degree of the finishing coat shall be determined by the Engineer.
G 6 BEDS AND BACKINGS
Cement and sand beds and bedding under floor finishings and backing behind wall and
column finishings shall be cement and sand (1:3) mix by volume unless otherwise specified.
G 7 CEMENT SCREED TO CHANNELS
Cement screed shall, unless otherwise ordered by the Engineer, consist of one part of
Ordinary Portland Cement to four parts of sand by volume. Ingredients shall be proportioned
and mixed specified under concrete work and laid to falls with smooth trowelled finish as
shown on the Drawings.
60
SECTION - J
ELECTRICAL WORKS
Division Titles Page No.
J – 1 General Requirements 60
J - 2 Miscellaneous Work 63
J – 3 General Condition of the Different
Parts of Installations 65
SECTION J
ELECTRICAL WORKS
Electrical contractors are invited to quote for the supply of all labour and materials required
for the completion of part of all the electrical installation.
J-1 GENERAL REQUIREMENT:-
1- Prerequisite Conditions:-
All applicable sections of the general Specifications are included by reference to the work
required by this division of the specifications.
2- Extend of Work:-
a- The work shall include all necessary labour, materials, plant services machinery and
appliances and at the Contractor‟s own risk and expense, to deliver construct and in- stall
complete in good working condition the electrical installation in accordance with the
drawings, specifications and bills of quantities. All materials and wormanship shall, except
where otherwise directed, comply with the requirements and regulations of the appropriate
local Electrical Authority, and I.E.E. and shall be subject to the approval of the Electrical
Engineer.
b- Work shall also include: -
1 The procurement of and payment for all permits and licenses required for the performance
of the work.
2 All hoits, scaffolds, staging, runways and equipment required for the performance of the
work.
3 All job measurements and shop layouts required for the proper installation of material and
equipment included in the work.
4 All lights, guards and signs as required by safety regulations applicable to the work.
5 The removal from the premises, as it accumulates, of all dirt and refuse resulting from the
performance of the work.
61
6 All equipment under this heading shall be installed under competent supervisory service
finished by this Contractor and where necessary this shall include the services of special
erection and operation engineers.
3 - Miscellaneous Conditions:-
a. All installed material and equipment shall be new, shall be of the best quality and design,
and shall be free from defects and imperfections.
b. All labour for the installation and adjustment of material and equipment shall be done by
experienced mechanics of the proper trade and all workmanship shall be first class.
c. Installed material and equipment included in the work shall be protected from dirt and
damage and maintained in a clean condition during the performance of the work.
d. Apparatus, equipment and material required for the performance of the work shall be
stored under requirements of applicable regulations and of direction from the Architect.
e. This Contractor shall cooperate with all other Contractors on the project, be responsible for
prompt delivery of all materials and equipments and for the installation of all works under
this division at a time and in a manner so that there will be no delay in the construction
schedule.
f. Acceptance of the work shall be subject to the condition that all installed systems,
equipment, apparatus and appliances included in the work shall operate and perform as
designed and as selected with respect to efficiency capacity and quietness and shall operate
and perform without producing objectionable noise within occupied areas of the building.
g. Acceptance of the work shall be subject to the conditions that any time within one year
after date of final approval, any defective part of the work resulting from the supply of faulty
workmanship or material shall be immediately amended, repaired or replaced as a part of the
contract work without cost to the owner.
4 - POWER SUPPLY: -
The system of distribution will be fed from a 230/400 volts 3- phase, 4 wire 50 Hz, system.
5 - SYSTEM OF DISTRIBUTION
The system of distribution to be used for lighting and power is to be the radial type, including
branch circuits and ring circuits system where shown in drawings.
6 - DRAWINGS AND SPECIFICATIONS
a All electrical drawings are intended to cover the layout and design of the work, but are not
to be scaled for exact measurements. Where special detail and dimensions are not shown on
the drawings, this Contractor shall take measurements and make electrical layouts as required
for the proper installation of electrical work so that interference with all other work will be
avoided.
b All drawings and specifications on the project are complementary, each set to all other sets,
and they shall be used in combination for the execution of this work.
Electrical work shown on any set drawings, including all architectural drawings for general
work and equipment, and electrical work called for under any section of the project
specifications, shall be considered as included in this work unless specifically excluded by
inclusion in some other branch of the work. This shall include roughing in for fixtures and
equipment as called for or inferred.
This Contractor shall check all drawings and specifications for the project and shall be
responsible for the installation of all electrical work.
62
7 - INSPECTION OF SITE
Contractor of this work shall inspect the Site, study existing conditions, check with the
drawings and specification and be fully informed as to the work required the Contract.
8 - OPERATION AND MAINTENANCE INSTRUCTIONS: -
a This Contractor shall furnish all services as required for adequate verbal and printed
instructions to the Owner‟s operating and maintenance personnel for operation and
maintenance of all equipment and systems installed under this heading. Two complete copies
of a service manual in hard back binders shall be furnished at the end of the project and shall
include printed operating and maintenance instructions for systems specified under this
heading, all approved shop drawings and all manufacturer‟s printed instructions for
equipment operation and maintenance.
b- When the work is complete and at a time designed by the Owner, the Contractor shall
furnish the services of a qualified instructor to instruct the Owner‟s personnel in the operation
and maintenance the systems and equipment.
9 - RECORD DRAWINGS: -
a Contractor shall be required to keep a day to day record of changes in location of all
equipment, conduit, and devices on one or more sets of contract drawings, underground
utilities, use to be dimensioned from building walls, foundations or other readily indentifiable
feature.
b The Contractor shall record such changes in red ink on black line prints, the record prints
shall be submitted to the Architect for approval prior to final payment.
10- CUTTING AND PATCHING: -
Any cutting of new construction which is required for the installation of electrical work after
the construction of walls and floor slabs, shall be done by this Contractor. Cutting shall be
done with extreme care so that the strength of the structure will not be endangered. Adequate
protection shall be provided to prevent damage to adjacent areas. Patching and finishing of
opening shall be the responsibility of the Electrical Contractor.
11- EXISTING EQUIPMENT: -
a All existing equipment that indicated to be removed shall remain the property of the Owner
if he so desires. Such equipment shall be removed by the Contractor and delivered to a point
on the project site as designated by the Owner.
Any equipment that the Owner does not desire to retain shall be promptly removed from the
Site by this Contractor.
b Any existing equipment or material that is to remain in service and is damaged by the
Contractor during the course of the Contract, shall be repaired and refinished or replaced to
the satisfaction of the Owner, at his discretion.
12- CONDUCT OF WORK: -
All work under this Contract which may interference with the Owner‟s Operation shall be
done in such a manner and at such time as may be satisfactory to the Owner. Make temporary
alternations and connections as required to execute work so that all services in the building
are maintained with the minimum possible interruption. Temporary shutdowns shall be
segregated and shall be of the shortest possible duration. All services shall be kept on
63
continuous operation unless permissions are otherwise granted by the Owner. All temporary
wiring shall be the responsibility of the Contractor at no additional cost of the Owner.
13- OMISSIONS
If anything necessary to the proper installation or operation of the electric system is omitted
from the drawings or specifications, or bill of quantities, or indicated incorrectly, the
Contractor shall call the attention of the electrical Engineer to these omissions or inaccuracy
immediately before work proceeds. Should the Contractor shall fall to do so, he shall be
helder responsible and shall make good at his own expense such errors or any damage
caused.
14- SAMPLES:-
Single samples of the following shall be submitted to Electrical Engineer by the Contractor
before the work commences. Section of conduit, section of wire and cable, junction boxes,
switches and plates, outlet box isolating switches, lamp holders, ceiling roses distribution
boxes, circuits breakers, earth leakage relay and any fixtures supplied by the Contractor and
other materials to be incorporated in the installation, the work done by the Contractor shall
not vary in any manner from the samples submitted and approved without written permission
from the electrical engineer.
` 15- LAYOUT: -
Before the Contractor commences the installation he shall discuss the exact timing and the
whole layout in detail with the Engineer, in order to determinate the exact position of
distribution boards, fittings and accessories, and the runs of cable and conduits unless
instructions are given after the relevant section of the work is completed.
16- DRAWINGS: -
The design of the accompanied drawings and the quantities in the attached schedules are not
definite and are subject to any variations made by the Electrical Engineer during
constructions.
No variations or amendments in the drawings and the specifications shall be made to the
Contractor except as directed in writing by the Electrical Engineer who has the right to refuse
all the materials and works which are not, in line with the drawings and specifications.
17- TESTING:-
The Contractor shall make or cause to be made at his own expense and in the presence of the
electrical engineer tests for perfect operation for installation ,insulation resis- tance and earth
continuity,
18- Tenderers:-
for this work have the previous experience in this field of work and an official license of
three phase installation from the Electric Company–Jerusalem District.
19 - The Contractor should provide on his own expense and all risks insurance policy for his
workers during all the period of his work.
20- The Contractor or his representatives should be on the Site or work daily for taking any
instructions from the director of works.
64
21- The Owner reserves, the right to accept any tender, either as regards the whole of the
work indicated therein, or as regards any one or, more parts so included. The Owner does not
bind himself to accept the lowest of any Tender.
J – 2 MISCELLANEOUS WORK:
1 - EQUIPMENT INDETIFICATION AND LABELS
a All electrical equipment, such as disconnect switches, motor starters, controls, pushbuttons,
panelboards, and other similar items shall be adequately identified with labels. Labels shall
clearly designate name and use of equipment. Labels shall be made with embossed plastic
tape except where engraved plates are called for elsewhere in the specification or on the
drawings.
2 - GROUNDING: -
a- Grounding shall be in accordance with the local Electrical Authority requirements and
regulations, and with the I.E.E. regulations.
b- All branch circuit conduit wiring shall include an insulated copper wire for grounding of
all non-current carrying conductive surfaces of electrical equipment subject to person contact,
and for every electrical outlet.
c- Earth Electrode must be provided. This to consist of 3 driven copper rods 1,5 meter long of
standard type, and must be installed as near as possible to the main board.
The earth wire has to be copper conductor as specified making loop connection between the
rods and the earth (ground) bus bar, the distance between each rod and the other have to be at
least 7 meters with a checking man hall at least 60cm depth.
d- Other similar P.V.C. copper conductor has to be bonded to the main water supply pipe
from the earth bus bar.
The impedance shall be less than 5 Ohm
3 - ADJUSTING, ALIGNING AND TESTING:-
a - All-electrical equipment furnished under this heading and all electrical equipment
furnished by others shall be adjusted and tested by this Contractor.
b Mechanism of all electrical equipment shall be checked for alignment with drive and
adjusted as required. Protective devices and parts shall be checked and tested for specified
and required application and adjusted as required. Adjustable parts of all lighting fixtures and
electrical equipment shall be checked, tested and adjusted as required to produce the intended
performance.
c Complete wiring system shall be free from short circuits and after completion the
Contractor shall perform tests for insulation resistance in accordance with the requirements of
the I.E.E.
d The Contractor shall be held responsible for the operation, service and maintenance of all
new electrical equipment, furnished by him, during construction and prior to acceptance by
the Owner of the complete project under this Contract. All electrical equipment shall be
maintained in the best operating condition including proper Lubrication. Operational failure
caused by defective material and/or labour covered under other headings or furnished by
others.
65
4 - MOTOR AND OTHER CONTROL EQUIPMENT
a This Contract shall install and mount miscellaneous disconnect switches and motor controls
furnished by other Contractors in accordance with their instructions, wiring diagrams and
approved shop drawings, but he shall be responsible for the operation of such devices only to
the extend of proper mounting and wiring. Work shall include mountings and supports as
required for all equipments including angle frames, steel plates, bars, bolts, etc.
This Contract shall furnish and install all conduit, wire, etc., as required to connect all
equipment furnished by him and other Contractors including motors, dis-connect switches,
starters, controls, pushbuttons, etc.
b This Contractor shall perform all work required to rough in and connect to all equipment
required electrical connections, except equipment that is furnished by the Owner which shall
be roughed in only. This work shall be as indicated on drawings, by approved equipment
shop drawings and by direction on the job.
c The Electrical Contractor shall run feeders to control and motors as shown on drawings,
make connections and install and wire all mechanical components, except temperature
control, in accordance with wiring diagrams furnished by Mechanical Contractor. The
Electrical Contractor shall coordinate with other traders involved for the proper coil voltages
for control of magnetic starters and contractors.
5 - OPENING AND SETTING OF CONDUIT:-
a Work shall include the direction for other work as required to provide openings for the
admittance into the building of material and equipment included in the work.
Work shall include all cutting required for the installation of material and equipment included
in the work.
b Any cutting and/or patching of new construction which is required for the installation of
Electrical work after new walls and floors have been constructed shall be the responsibility of
the Electrical Contractor if the cutting and patching is due to errors or omissions on the part
of the Electrical Contractors.
6 - EXCAVATION AND BACKFILLING:
a This Contractor shall excavate as required for the installation of all underground work
under this heading. Surplus material not needed for backfilling shall be deposited or
distributed on the premises as directed.
Trenches shall be of sufficient width and shall be cribbed or braced to prevent cave-in or
settlement. Trenches close to walls and columns shall not be excavated without prior
consultation with the Architect or his representative.
Pumping equipment shall be furnished to keep trenches free of water. Dry earth shall be
rammed into place at sides of conduits, leaving joints and top of conduits exposed until
approved. After approval, all trenches for work installed by the Contractor shall be backfilled
by him in 15cm layers of well-tamped dry earth in a manner to prevent future settlement.
Rocks debris, bricks, and like material shall not be used for backfill. Where direct burial
cable is installed the trenches shall have 5cm of medium sand installed in bottom of trench
and put over the sand.
66
b Any trenches improperly backfilled or where settlement occurs, shall be reopened to a
depth required for the proper compaction, then refilled and compacted with the surface
restored to the required grade.
c As a part of this Contract, all roads, streets, and sidewalks damaged by the installation of
building services or other work under this heading shall be repaired to the satisfaction of the
authorities and regulations having jurisdiction.
J - 3 GENERAL CONDITION OF THE DIFFERENT PARTS OF INSTALLATIONS
1 - CONDUITS
a Conduit shall be installed for all wires and cables except where otherwise stated or directed
. The conduits shall be P.V.C. pipe of the thinner type (Merikaf) or similar under plaster.
b of a fireproof plastic type should be used whenever exposed installations are used. And it
shall Conduits be securely fastened in place with approved straps.
c Steel conduit should be used in the boiler, and wherelse directed by the Electrical Engineer.
d No conduits used should have an internal diameter less that 13mm. The Conductors area
within the conduit should not exceed 50% of the area of the conduit. .
e The conduit has to be away from heat mechanical pressure.
f The contractor shall be responsible for ensuring that the conduits are so laid that water
cannot infiltrate or accumulate at any point.
g The Contractor shall be responsible to ensure that placing of the conduit is done prior to
pouring of concrete without delaying the concrete work.
h In conduit installation the Contractor should make all his effort to run all the pipes in
horizontal or vertical lines and not inclined and to be at the same level from the floor in all
rooms.
i The conduits should have at least cover of 2cm of plaster or concrete.
j Separateconduits have to be used for separate sys-tems of different voltage.
k Conduits between any two connection boxes have to be of one piece with no connection in
the pipes.
l Where finish wall surfaces are to be plastered, the Electrical Contractor shall cooperate with
the General Contractor during construction of these walls and use care in the installation of
all conduits and boxes so that wall surfaces will have a finished appearance
m Conduit shall be installed to requirements of structure and to requirements of all other
work on the project.
67
Conduit shall be installed to clear all openings, depressions, pipes, ducts, reinforcing steel,
etc., and conduit set in forms for concrete structure shall be installed in a manner that
installation will not affect the strength of the structure.
n All electrical work shall be protected against damage during construction and any work
damaged or moved out of line after roughing-in shall be repaired and reset to the approval of
the Electrical Engineer, without additional cost to the owner.
o - All conduits have to be approved by local standard.
2 - PULL BOXES AND CONNECTION BOXES
a The contractor has to make his best to use the minimum number of these boxes.
b All boxes should be of the same material as that of the conduits.
c Boxes should be wide enough to contain easily all connections of cables.
d Pull boxes and connection boxes should be installed all at the same level from ceiling.
e - All boxes should be covered.
f Installed connectors should be used in all the connections inside the boxes.
g Cables of different voltage should not be drawn or connected in the same connection box.
3 - OUTLET BOXES
a Suitable outlet boxes shall be installed for all electrical service outlets, including plug
receptacles. Lighting fixtures, switches.
b Location of outlets on drawings is approximate and, except where dimensions are shown,
exact location of outlets shall be taken from plans and details on general drawings or as
directed by the Architect. Outlets shall be located generally from column centers and finished
wall lin4s or to center of acoustical and decorative ceiling panels and to centers or joints of
wall panels.
c Outlets shall be installed in an accessible location.
4 - SWITCHES
a Outlet boxes for switches are to be fixed 140cm above finished floor level and 12cm
horizontally from the outside edge of the nearest door.
b Switches should be of 10 amp. With different signs for emergency switches if used.
c Switches should be of waterproof type DIG or equivalent for the bathrooms and where
otherelse shown.
d All switches should be all-installed rockers flush of Tadiran kind or equivalent.
e - Switches shall be wired in the phase lines only.
f - The neutral conductors shall not be broken.
g Switches panels shall have a similar assembly to switches and it should be group-mounted
in a common box if possible, and if it is without pilot tamp. Otherwise it has to be group
mounted in aluminium or stainless steel cover to the approval of the Engineer.
5 - SOCKETS
a Boxes for sockets outlets are to be installed 60cm or, as shown in the drawings above
finished floor level.
b Socket should be of 13 amp. For the power socket with different color for socket and non-
emergency.
68
c - Sockets should be of Tadiran kind or equivalent type.
d Sockets in the boiler room should be industrial heavy duty.
e Sockets in the bathrooms and where Therese shown shall be waterproof type DIG or
equivalent.
f All sockets shall be wired in the same manner with the phase always connected to the same
pole [rightpole].
6 - WIRES, WIRING
a All wires and cables, except where otherwise stated are to have a soft copper core, refined
and tinned, with an electric conductivity of not less than 98% the core shall be insulated with
rubber with braid for 600 volley service.
b Samples, of cabling and wiring proposed the contractor, are to be submitted prior to
commencement of the work.
These must comply with the requirements of the I.E.E., and local standard to ensure a
constant voltage in every part of the building.
c All wires are to be standard. [for lighting and power, the neutral wire shall be different in
color from the phase wires].
d All wires shall be run on conduit and shall be continuous between outlets and boxes. At
least 20cm of wire be left at outlets for fixture connections.
e Where wire size is shown on drawings, or specified, it shall be the same size throughout the
circuit.
f Wiring inside panel boards shall be neat and well arranged, using appropriate lugs for
termination and connection of conductors.
g Joints in the cables or wires are not allowed to be made inside conduits.
h Wires are to be fixed to boards with an appliance ensuring perfect electrical contact, to the
approval of the Electrical Engineer.
i In drawing wires through conduits, no lubricant is permitted.
j Cable shoes have to be used for wires of 6 sq. mm. or above.
k All boxes and distribution boards have to be carefully cleaned from plaster and other
foreign material before drawing any electric wires or cables.
l - Colours of the cables should be as follows:
a. Single phase circuits :
Brown for the phase
Black for the neutral
Green & Yellow or White for the earth
Blue for direct [switch
Wires].
b. 3 Phase circuits :
Brown, Yellow & Blue for the threephase.
Black for the neutral
Green & Yellow or white for the earth
m - Cables
a All the cables should be of the following type N.Y.Y. 5 or 4 cores, 11000 volt, plain
annealed high conductivity copper wire conductors P.V.C. sheathed.
69
Under Ground cables should be of type NYBY.
b Colours of cores in the cable should be red, yellow, blue & black. Colours of the sheathes
shall be black.
c Cables terminations should be through brass cable glands. Glands should be complete with
brass earth tags and steel locknuts.
d Cable connection at both ends should be through cable shoes.
e Cables should be covered with soft sand, concrete slabs and special warning in 3 languages.
n - Wire Size
a - Sizes of wires are shown in the drawings
b The size of the earth cable for any circuit should be the same size as that of the phase or as
shown on the drawings.
c The size of the wire for the bells, loud speakers and sound outlets should not be less than
0.6sq.mm.
d - Size of wire for Fir Alarm should be at least 1.5 sq. mm.
7 - ELECTRICAL BOARDS
1 a- All boards should be manufactured by a qualified factory who has a wide experience in
this field.
b The tenderer should supply with his tender complete drawings for each board which shows
the electrical and mechanical design of the boards with dimensions.
c Therefore, the contractor gets the approval of the engineer before he commences with the
manu-facturing of these boards.
d Electrical boards should be erected complete with all conduits terminated to it before
installation of any cable in the conduit.
2 - B O D Y
a Electrical boards and panels shall be ready made otherwise it should be manufactured from
2mm steel sheet with all angles and channels needed for supporting and mounting the
equipment, and it should be full finished steel with electrostatic painting. Colour should be
beige.
b All screws. Nuts and washers should be galvanized.
c Boards to be designed with removable front plates for easy access to the interior for cabling
up and maintenance.
d A special compartment with separate cover shall be made for terminals, neutral and earth
bars.
e - All panel boards shall be with doors.
f All doors which have equipment mounted on them shall be shielded from inside with
isolation sheets.
g Distribution Boards in wet areas should be of waterproof type.
h All electrical boards shall have spare space of at least 25% of their area.
3 - BUS - BARS
â All bus bars shall be of hard drawn electrolytic copper.
b Bus bars shall be supported by suitable bus bar insulator to protect the bars from any
electrical, mechanical and dynamic stresses.
c - Bus bars shall be rated at a max. of 2 amps/sq. mm.
4 - NEUTRAL AND EARTH BARS
Suitable bars for neutral and earth shall be mounted on the top compartment of each board,
for terminating the outgoing circuits on them.
70
A bolt with suitable size shall be welded on the body of each board for earthing.
5 - L A B E L S
All circuits shall be labelled in English language. Labels shall be of the black sandwich type
and engraved.
6- MAIN C.B.S
These C.Bs shall be air insulated, adjustable, with magnetic and thermal protection, and have
a min. rupturing capacity of 25 K.A.
These C.Bs shall be of the best quality and preferably of the Simmons or NZM-type made
K.L.M. in Germany or equivalent.
7 - MINIATURE C.BS, AUTOMATIC CHANGE OVER SWITCH,[MECHANICAL
INTERLOCK] AND E.L.Rs.
These M.C.Bs shall be of the air insulated type with magnetic and thermal protection and
fixed adjustment, the main rupturing capacity if these M.C.Bs, shall not be less than /5 K.A.
The M.C.Bsm type N and E.L.R. shall be of the best quality and preferably Simmons or
K.L.M. made or equivalent. All E.L.R. shall be 4-pole with 0,03 amp. Sensitivity.
8 - ON - OFF SWITCHES
All these switches shall be hand operated, air insulated and able to withstand any load and
fault conditions. These switches shall be Siemens type N. or K.L.M. made or equivalent.
9 - INSTRUMENTS
All the measuring shall be very accurate which have dimensions of 120x100 mm. and
mounted on the boards.
All amperemeters shall be with selector switches to measure the voltage between phases and
between phases and the neutral.
10- CONNECTORS
All outgoing shall be terminated on connectors mounted on the compartment of the boards.
Connectors must have a copper strip between the wire and the screws. All connectors shall
have special paper fixed on them for writing the names of the circuits.
Connectors shall be of or best quality.
11 - T E L E P H O N E S
a 1” conduit should be installed from each telephone box to the telephone box in the floor
where shown in drawing with galvanized wire installed within for the telephone company.
b The telephone box should be 1 meter high from floor level.
c Main conduits from the floor boxes and the operator have to be shown in drawings with a
galvanized wire.
d Telephones cables for the main boxes and the telephone outlet should be drawn with the
presence of the telephone department.