Shaft Aligment Procedure
-
Upload
juan-camilo-cruz-rodriguez -
Category
Documents
-
view
1.146 -
download
7
Transcript of Shaft Aligment Procedure
Wärtsilä France
3 Bd de la loireB.P. 97511
44275 NANTES CEDEX 9France
Tel: +33 (0)2 40 41 16 02Fax: +33 (0)2 40 41 16 00E-mail: [email protected]
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B 27/08/09 R. Hoguin C. Binet
A 30/04/09 R. Hoguin
- 28/04/09 R. Hoguin Y. Tanguy
REVISION Date Written by Checked by Approved by
Project: 5038 Ref. document: B001980290
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 2
Wärtsilä France
CHANGES MADE TO DATE TO THE SPECIFICATION
Revision Changes made- 1st editionA Temporary support was down 0.5 mm down from Centre line. All change is
highlighted.B Modif. according. to “GL 09-066713/CGur” Notification; . § 3.8.2 / 4.3
revised, § 3.8.4 added, more check added. All change is highlighted.
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 3
Wärtsilä France
CONTENT
1. SUBJECT .............................................................................................................................42. REFERENCES .....................................................................................................................43. alignment data.....................................................................................................................4
3.1. Preliminary notes. ......................................................................................................................... 4
3.1.1. Introduction........................................................................................................................... 43.1.2. Geometrical consideration ..................................................................................................... 5
3.2. Thermal expansion influencing the alignment of the gearbox. ....................................................... 6
3.3. Aft bracket bearing........................................................................................................................ 6
3.4. Stern tube bearings........................................................................................................................ 6
3.5. Inboard bearing ............................................................................................................................. 7
3.6. Temporary supports ...................................................................................................................... 8
3.7. Embarking of the shafts................................................................................................................. 8
3.8. Assembling ................................................................................................................................... 8
3.8.1. First step assembling. ............................................................................................................ 93.8.2. Second step assembling. ........................................................................................................ 93.8.3. Third step assembling. ......................................................................................................... 133.8.4. Assembling data .................................................................................................................. 16
4. Checking of final alignment of the inboard shaftline bearing in afloat condition. ......184.1. Required equipment .................................................................................................................... 18
4.1.1. Special care to be taken ....................................................................................................... 184.1.2. Measurement ....................................................................................................................... 194.1.3. Alignment check ................................................................................................................. 20
4.2. Measurement JL1........................................................................................................................ 23
4.3. Measurement JL2........................................................................................................................ 26
........................................................................................................................................................... 27Appendix 1…………………………………………………………………………………………………..28
Appendix 2…………………………………………………………………………………………………..32
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 4
Wärtsilä France
1. SUBJECT
The purpose of this technical note is to give a procedure for the alignment of the shaft line
bearings of the Colombian Offshore Patrol Vessel, based on the shaft alignment calculations.
2. REFERENCES
Shafting arrangement drawing : DAAN000109 rev C.
Shaft alignment calculations : B001980285 rev 0.
3. ALIGNMENT DATA
Before any set up, the Bearings dimensions have to be checked. The Bearing
clearances have to be calculated from bearings and shaft dimensions.
3.1. Preliminary notes.
3.1.1. Introduction
The proposed alignment procedure is based on the assumption that the alignment is
done from aft to forward end of the shaft line. The alignment of the inboard shaft line
bearings and of the gearbox is assumed to be done with the ship in afloat condition.
This section describes the procedure for assembling the shaft in such way that the
correct alignment is achieved.
This procedure is intended as a general guidance for shipyards using Gap & Sag
method for shaft alignment. The shipyard however will always remain responsible for
the execution and final performance of the shafting system. This has to be done after as
much as possible of the ship’s structure is completed.
In alignment condition, open shaft, there will be no oil film between the shaft and the
Inboard bearing.
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 5
Wärtsilä France
3.1.2. Geometrical consideration
A reference Sight Line shall be used by the Yard, concentric with Stern tube (“SealPerpendicular to shaft” will be ensured). The Aft bracket, Aft and Fwd Stern Tubebearings should be aligned, by the yard, with offsets in relation to this Sight Line aspointed out on the sketch 1. This has to be done after the ship structure is completelyset up.
Fig1:
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 6
Wärtsilä France
The mounting surface for the PSE seal base shall be located according to requirements
of the drawing H78498-01 and the Technical manual for PSE.
3.2. Thermal expansion influencing the alignment of the gearbox.
The alignment procedure is assumed to be made in cold condition at 20° C. the thermal
offset of the gearbox is described in the alignment calculation note B001980285.
3.3. Aft bracket bearing
The Aft bracket bearing housing can be installed parallel to the shaft centre line in the
horizontal plane.
First adjust the bearing centreline exactly on the shaft line centreline. Using jack screws
at each end of the bearing, move the bearing up by half the bearing clearance to
compensate the bearing clearance.
The bearing housing shall be installed with a vertical slope of 0.15*10-3 rad. In this
condition, the relative vertical slope of the shaft in the bearing is in the limit of ±0.3*10-3
rad at all ship speeds.
Move the aft end of the bearing down by 0.04 mm
Move the forward end of the bearing up by 0.04 mm
For Portside & Starboard Aft Bracket bearings, this slope is shown on the Fig1.
The bearing has then the right vertical slope.
Pour the chockfast.
3.4. Stern tube bearings
The aft Stern tube Bearing Housing can be installed parallel to the shaft centre line in
the horizontal plane.
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 7
Wärtsilä France
First adjust the bearing centreline exactly on the shaft-line centreline.
Using jack screws at each end of the bearing, move the bearing up by half the bearing
clearance to compensate the bearing clearance.
The bearing housing shall be installed without a vertical slope.
Pour the chockfast.
For Portside & Starboard Stern tube bearings, this clearance is shown on the Fig1.
3.5. Inboard bearing
The complete Bearing, excepted for the upper housing can be installed parallel to the
shaft centre line in the horizontal plane (refer to Fig 2).
For detail of installation of the bearing see Bearing Supplier manual, reference TM-LSB
{issue C}.
As soon as Gap and Sag and Jack load measurements are achieved, pour the
Chockfast.
Fig: 2
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 8
Wärtsilä France
3.6. Temporary supports
A temporary support shall be installed at the forward end of the Propeller shaft, 840 mm
afterward of the Fwd end of the Propeller shaft. It is used for the connection of the Stern
tube shaft with the propeller shaft.
The second temporary support shall be installed at the forward end of the Intermediate
shaft, 765 mm afterward of the Fwd end of the intermediate shaft. It is used for the
connection of the Stern Tube shaft with the intermediate shaft and the intermediate
shaft with the Gear Box shaft.
The temporary support shall be equipped with a device to measure the load (Hydraulic
jack for instance).
3.7. Embarking of the shafts
Refer to instruction manual.
The Propeller shaft is supported by the aft bracket bearing and the first temporary
support close to the forward end.
The stern tube shaft is supported by the aft and Fwd stern tube bearings.
The intermediate shaft is supported the Inboard bearing and the second temporary
support close to the forward end.
3.8. Assembling
The Gap & Sag dimensions are to be measured very accurately by clock gauges in 0,01
mm. It is most advisable to mount one axial and one radial rotary dial gauges on a
rotating support, turning around the flange or shaft.
Rotate the support of the dial gauge slowly and record the deflection on top, bottom,
port and starboard. The location, where the dial gauge reading is taken must be clearly
marked so the measurement can be re-taken at exactly the same spot.
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 9
Wärtsilä France
The radial measured deflection (top and bottom) divided by two shows the radial offset
(Sag), whereas the recorded value on port and starboard must be equal.
The axial measured deflection (Difference between top and bottom) too can be carried
out by shims measurements that show the axial offset (Gap), whereas the recorded
value on port and starboard must be equal.
3.8.1. First step assembling.
The propeller shaft is set up in its final position, completely assembled. The Stern Tube
Shaft and the Aft sleeve coupling are in its parking position. Connect the oil pipes
Put the propeller shaft and the Stern tube shaft in their final axial position.
Connect the propeller shaft with the Stern Tube shaft by mounting the hydraulic sleeve
coupling. Refer to instruction manual.
Remove the first temporary support.
Insert the non split parts of the PSE seal on the shaft. Refer to instruction manual.
Achieve the final mounting of the PSE seal. Refer to the Technical manual for PSE.
The propeller shaft has to be axially secured in its position and then launch the ship.
Launch the ship.
3.8.2. Second step assembling.
At this stage the ship is afloat.
Put the sleeve coupling in the parking position on the aft end of the Intermediate shaft
which is 350 mm fwd of its final position and temporarily secured by achieving a push
up of approx 16 mm.
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 10
Wärtsilä France
The intermediate shaft is set up in its parking position, supported by the temporary
support and the Inboard bearing, allowing the connection of the oil pipes. Pull the
intermediate shaft in its final position toward the propeller shaft without wearing on the
inboard bearing. Refer to Instruction Manual (IPI: CPP-MP/01439).
Put the Hydraulic Flange coupling in its final position on the Fwd end of the intermediate
shaft.
The Sag dimension is to be measured very accurately by clock gauges in 0.01 mm. It is
most advisable to rigidly mount the radial rotary dial gauge to the end side of the shaft,
slowly rotate and record the deflection on top, bottom, port and starboard.
The location, where the dial gauge reading is taken must be clearly marked so the
measurement can be re-taken at exactly the same spot.
The radial measured deflection (top and bottom) divided by two shows the radial offset
(Sag), whereas the recorded value on port and starboard must be equal.
The axial measured deflection (Difference between top and bottom) can be carried out
by shims measurements that show the axial offset (Gap).
The axial measured deflection (Difference between top and bottom) shows the axial
offset ( Gap).
By adjusting the vertically the Inboard bearing and the Temporary support, the distance
between the shafts end has to be as stated in the following fig:
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 11
Wärtsilä France
Fig: 3
With Gap = 0.11 mm and Sag= 2.63 mm.
A pre-position of the Gear Box has to be achieved, With Gap = 0.15 mm and Sag= 1.39
mm between the hydraulic flange coupling and the GB flange.
The input files of the “Gap & Sag” calculation is carried forward in the appendix1.
The coordinates system which is used for all calculation is described the appendix 2.
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 12
Wärtsilä France
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 13
Wärtsilä France
Connect the Stern Tube shaft with the Intermediate shaft by mounting the hydraulic
sleeve coupling. Refer to instruction manual.
3.8.3. Third step assembling.
The propeller and intermediate shaft are set up in their final position, completely
assembled.
Check the load of the temporary support that should be ~ 8 kN.
Put the Hydraulic Flange coupling in the parking position on the Fwd end of the
intermediate shaft which is ~ {135 mm<L1< 185 mm} aft of its final position and
temporarily secured by achieving a push up of approx 8 mm (L1 is the measured
dimension as stated in drawing DAAN000166).
Fasten the oil pipes together. Refer to Instruction Manual (IPI: CPP-MP/01439).
Put the flange coupling in the final position -10 mm Afterward, on the Fwd end of the
Intermediate shaft.
The yard can now proceed to position and align the gearbox to the shaft line until the
calculated Gap and Sag values have been reached.
The Gap and Sag dimension are to be measured very accurately by clock gauges in
0.01 mm. It is most advisable to rigidly mount one radial and one axial rotary dial gauge
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 14
Wärtsilä France
to the flange of the gearbox output and rotate the gearbox output shaft slowly and
record the deflection on top, bottom, port and starboard. The location, where the dial
gauge reading is taken must be clearly marked so the measurement can be re-taken at
exactly the same spot.
The radial measured deflection (top and bottom) divided by two shows the radial offset
(Sag), whereas the recorded value on port and starboard must be equal.
The axial measured deflection (Difference between top and bottom) shows the axial
offset ( Gap).
By adjusting the vertically the Gearbox, the distance between the flange ends has to be
as stated in the following fig:
Fig: 4
With Gap = 10.02 mm and Sag= 1.66 mm.
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 15
Wärtsilä France
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 16
Wärtsilä France
As the dimension between the Fwd end of the intermediate shaft and the Gear Box
flange is able to vary from 135 to 185 mm, the Gap & Sag are calculated and the
tolerances are summarized in the following table:
TABLE 1
L1 (GB/ Shaft space) 135 mm 160 mm 185 mmGap (axial offset) 10.02 mm 10.02 mm 10.02 mmSag (radial offset) 1.67 mm 1.66 mm 1.65 mm
After measurement, the coupling has to be pulled along the shaft in its final position and
the flanges of the coupling and of the gear box have to be connected. Refer to
instruction manual.
Remove the temporary support then achieve the complete set up of the Inboard Bearing
according to the manual, reference TM-LSB. Adjusted by jack bolts, the bearing will be
set parallel to the centre line of the shaft thus resulting an absolute slope of -0.37 mrad
with the reference Sight Line described in § 3.1.2.
3.8.4. Assembling data
All the measurement achieved during the assembling steps is noted in the following
table:
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 17
Wärtsilä France
TABLE 2
Units mm; Prop/Inter shaft Inter/GB shaft FC spa. LoadkN Gap Sag Gap Sag L1 TS1
Measur. §3.8.2 /Measur. §3.8.3 / /
__________
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 18
Wärtsilä France
4. CHECKING OF FINAL ALIGNMENT OF THE INBOARD SHAFTLINE BEARING INAFLOAT CONDITION.
In order to check the alignment, the jack loads test close to the inboard shaft line’s
bearings and to the Aft Bearing of the Gear box can be performed.
4.1. Required equipment
2 Dial gauges with magnetic supports with an accuracy of 0.01mm and a total
capacity of 3 mm
The hydraulic or screw jacks with a capacity of 20000 N, a minimum stroke of 20
mm.
The pressure gauges with a capacity corresponding to the required pressure to
have a force of 20000 N in the jack
or the load cells with capacity of 20000 N in the jacks, the required accuracy for
these tools is 1% of the total range.
1 set of filler gauges 0.025 mm to 0.5 mm as long as possible
4.1.1. Special care to be taken
The measurement of the jack load will only be valid if the following preliminary checks have
been done:
The shaft line is laying on the bearings placed according to the drawing
The jack is positioned at the indicated position
During the lift of the shaft, it will not come in contact with the top part of one
bearing
During the lift of the shaft, it will not come in contact with any metallic part of a
shaft accessory as shaft seal, bulkhead seal, etc…
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 19
Wärtsilä France
4.1.2. Measurement
The jack is placed below the shaft
One dial gauge is placed above the shaft opposite to the jack (12 o’clock)
One dial gauge is placed at the same location at 3 o’clock position.
Fig: 5
It is wise to perform an initial lifting of the shaft in order to establish oil film between
shaft and bearing surface before recording the results.
Adjust the dial gauge to zero.
Jack up the shaft by steps of 0.01 up to 0.3 mm for JL1 and up to 0.1 mm for JL2.
At each step, record the lift and the load on the jack
Pull the shaft down by steps corresponding to the reverse direction of jacking up to
zero position
At each step, record the indication of the dial gauge and the load on the jack.
Plot the graph lift versus load in up and down directions
Compare the graphs (jacking up and jacking down) with the theoretical one.
The shape of the graph shall be similar to the shape of the theoretical one.
Jack Load MeasurementMeasurement
Load in N
Measurement in mm
Bearing
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 20
Wärtsilä France
The slope of the upper part of the graph (second segment) shall be the same as the
theoretical one with a tolerance of ± 10%
Draw a line between the upper parts of the jacking up and jacking down graphs.
The measured jack load can be read at the intersection of this line with the load axis.
4.1.3. Alignment check
The exact location of the first Jack-1’s load measurement shall be 320 mm Forwardof the centre line of the Inboard bearing.
Fig: 6
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 21
Wärtsilä France
The theoretical jack load value and the correction factor to get the actual bearing load
are given below:
Fig: 7
The exact location of the jack 2’s load measurement shall be 43 mm forward of the
forward side of the Gear box flange. The values are given as follow:
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 22
Wärtsilä France
Fig: 8
The following table can be used to record the results of the jack load test.
The following theoretical graph can be used to plot the measured values and have a
direct comparison of the slope of the graphs.
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 23
Wärtsilä France
4.2. Measurement JL1Jack load measurement 320 mm Fwd of the Inboard bearing – page 1/2.
Ambient temperature ----°C Sunshine on hull Yes / No
Vessel afloat Yes / No Propeller submerged Fully / ----%
Draft aft -------m Draft fwd -------m
Wanted lift Dial gauge readinglifting
Measuredlifting force
lifting
Dial gauge readinglowering
Measuredlifting force
lowering
1/100 mm Vertical1/100 mm
Horizontal1/100 mm N Vertical
1/100 mmHorizontal1/100 mm N
0123456789
1011121314151617181920
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 24
Wärtsilä France
Jack load measurement 320 mm Fwd of the Inboard bearing – page 2/2.
Ambient temperature ----°C Sunshine on hull Yes / No
Vessel afloat Yes / No Propeller submerged Fully / ----%
Draft aft -------m Draft fwd -------m
Wanted lift Dial gauge readinglifting
Measuredlifting force
lifting
Dial gauge readinglowering
Measuredlifting force
lowering
1/100 mm Vertical1/100 mm
Horizontal1/100 mm N Vertical
1/100 mmHorizontal1/100 mm N
21222324252627282930
TECHNICAL SPECIFICATIONSHAFT ALIGNMENT PROCEDURE
B001980290 / Rev.: B / Page 25
Wärtsilä Defence
0PV. Jack load Measurement 320 mm Forward ofthe Inboard bearing,
0
0,02
0,04
0,06
0,08
0,1
0,12
0,14
0,16
0,18
0,2
0 2000 4000 6000 8000 10000 12000
Jack Load (N)
Jack
offs
et (m
m) Load Transfer
Jack Influence Numberzero lift load
B001980290/ Rev.: B / Page 26
4.3. Measurement JL2Jack load measurement 43 mm Fwd of the forward side of GB flange/ page 1.
Ambient temperature ----°C Sunshine on hull Yes / No
Vessel afloat Yes / No Propeller submerged Fully / ----%
Draft aft -------m Draft fwd -------m
Wanted lift Dial gauge readinglifting
Measuredlifting force
lifting
Dial gauge readinglowering
Measuredlifting force
lowering
1/100 mm Vertical1/100 mm
Horizontal1/100 mm N Vertical
1/100 mmHorizontal1/100 mm N
0123456789
101112131415
After the Jack load measurement has been performed, a final report showing the
alignment data as per the Table 2 (§ 3.8.4) and Jack Load measurement has to be
drawn up. This document is submitted to Wärtsilä, when the results are accepted,
pour the chockfast and complete the final assembly of the Inboard bearing and Gear
box.
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 27
Wärtsilä Defence
0PV. Jack load Measurement 43 mm Fwdthe Fwd side of the GB flange,
0
0,01
0,02
0,03
0,04
0 2000 4000 6000 8000 10000
Jack Load (N)
Jack
off
set (
mm
) Load TransferJack Influence Numberzero lift load
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 28
Wärtsilä Defence
Appendix 1================================= INPUT =================================== 1 /analysis 2 /************General information****************/ 3 installation="5038" 4 engine_builder="Wärtsilä" 5 shipyard="COLOMBIA" 6 hullnr="59" 7 class="GL; Noations +100 N5 Aux NH 'Offshore Patrol Vessel' +MC AUT Aux NM." 8 calcnr="Proc-Alignt-water-2009-04-23" 9 shaft_drawing="DAAN000109" 10 name="Richard Hoguin" 11 12 /****************Gap & Sag Jack load ********/ 13 type=shafting 14 openshaft=(OKC2,FL2) 15 openshaft=(FL2) 16 jackplot=(Inb4,JL1) 17 jackplot=(gb_b5,JL2) 18 19 20 /***********Modelling of Shaft Line************/ 21 /node 22 od_b 23 sh_end 24 n14 25 gb_b6 y_clear=0.05e-3y_offset=(0.025e-3-1.7e-3) 26 ge_whe2 27 ge_whe 28 ge_whe1 29 gb_b5 y_clear=0.05e-3y_offset=(0.025e-3-1.7e-3) 30 n13 31 JL2 32 FL3 33 FL2 34 FL1 35 FC1_2 36 FC1_1 37 TS2 y_clear=0.1e-6 38 con10 39 n12 40 ND 41 ND_1 42 43 con9 44 n11 45 JL1 46 n10 47 con8 48 Inb4 y_clear=0.6e-3 y_offset=(0.3e-3) 49 Inb4_1 50 conB4 51 con7 52 n9
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 29
Wärtsilä Defence
53 OKC2 54 n8 55 con6 56 m_lin3 57 n7 58 PSE 59 fwd_b3 y_clear=0.8e-3 y_offset=(0.4e-3) 60 fwd5 61 con4 62 m_lin2 63 mid_b2 y_clear=0.8e-3 y_offset=(0.4e-3) 64 m_lin1 65 OKC1 66 li2 67 con2 68 n5 69 con1 70 n4 71 aft_b1_2 72 n3 73 aft_b1 74 b1_stat y_clear=0.85e-3 y_offset=(0.425e-3) 75 aft_b1_1 76 fl_cov 77 sha_flan 78 n2 79 prop 80 n1 81 82 83 /element 84 /***********Propeller Shaft***************************************************/ 85 shaft=(n1,prop) l=0.467 da=0.580 di=0.240 rho=1 86 shaft=(prop,n2) l=0.258 da=0.586 di=0.75*0.586 rho=1 87 shaft=(n2,sha_flan) l=0.075 da=0.561 di=0.104 rho=1 88 shaft=(sha_flan,fl_cov) l=0.039 da=0.230 di=0.100 rho=53320 89 shaft=(fl_cov,aft_b1_1) l=0.261 da=0.230 di=0.100 rho=9860 90 shaft=(aft_b1_1,b1_stat) l=0.138 da=0.230 di=0.065 rho=9510 91 shaft=(b1_stat,aft_b1) l=0.122 da=0.230 di=0.065 rho=9510 92 shaft=(aft_b1,n3) l=0.045 da=0.230 di=0.065 rho=9510 93 shaft=(n3,aft_b1_2) l=0.250 da=0.229 di=0.065 rho=9600 94 shaft=(aft_b1_2,n4) l=0.350 da=0.229 di=0.065 rho=9600 95 cone=(n4,con1) l=0.038 da_fwd=0.215 da_aft=0.229 di=0.065 rho=7100 96 shaft=(con1,n5) l=3.292 da=0.215 di=0.065 rho=7120 97 cone=(n5,con2) l=0.030 da_fwd=0.222 da_aft=0.215 di=0.065 rho=7110 98 shaft=(con2,li2) l=0.200 da=0.222 di=0.065 rho=9110 99 shaft=(li2,OKC1) l=0.600 da=0.220 di=0.065 rho=7110 100 /***************Stern tube Shaft************************************************/ 101 shaft=(OKC1,m_lin1) l=0.735 da=0.22 di=0.065 rho=7110 102 shaft=(m_lin1,mid_b2) l=0.402 da=0.221 di=0.065 rho=9200 103 shaft=(mid_b2,m_lin2) l=0.398 da=0.221 di=0.065 rho=9200 104 cone=(m_lin2,con4)l=0.029 da_fwd=0.215 da_aft=0.221 di=0.065rho=7110 105 shaft=(con4,fwd5) l=5.741 da=0.215 di=0.065 rho=7110 106 shaft=(fwd5,fwd_b3) l=0.369 da=0.215 di=0.065 rho=9770 107 shaft=(fwd_b3,PSE) l=0.427 da=0.215 di=0.065 rho=9770
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 30
Wärtsilä Defence
108 /******************** SW ===> Air ******************************/ 109 shaft=(PSE,n7) l=0.050 da=0.215 di=0.065 rho=16430 110 shaft=(n7,m_lin3) l=0.054 da=0.215 di=0.065 rho=11290 111 cone=(m_lin3,con6)l=0.039da_fwd=0.200 da_aft=0.215 di=0.065rho=8280 112 shaft=(con6,n8) l=0.179 da=0.200 di=0.065 rho=8320 113 shaft=(n8,OKC2) l=0.577 da=0.200 di=0.065 rho=8320 114 shaft=(OKC2,n9) l=0.600 da=0.200 di=0.065 rho=8320 115 cone=(n9,con7) l=0.024 da_fwd=0.19 da_aft=0.2 di=0.065 rho=8350 116 shaft=(con7,conB4) l=1.169 da=0.19 di=0.065 rho=8380 117 cone=(conB4,Inb4_1) l=0.016 da_fwd=0.195 da_aft=0.19 di=0.065rho=8360 118 shaft=(Inb4_1,Inb4) l=0.3 da=0.195 di=0.065 rho=8350 119 shaft=(Inb4,con8) l=0.3 da=0.195 di=0.065 rho=8350 120 cone=(con8,n10) l=0.017 da_fwd=0.19 da_aft=0.195 di=0.065 rho=8360 121 shaft=(n10,JL1) l=0.003 da=0.19 di=0.065 rho=8380 122 shaft=(JL1,n11) l=2.383 da=0.19 di=0.065 rho=8380 123 cone=(n11,con9) l=0.017 da_fwd=0.195 da_aft=0.190 di=0.065 rho=8360 124 shaft=(con9,ND_1) l=0.1975da=0.195 di=0.065 rho=8350 125 shaft=(ND_1,ND) l=0.05 da=0.195 di=0.065 rho=11800 126 shaft=(ND,n12) l=0.1535da=0.195 di=0.065 rho=8350 127 cone=(n12,con10) l=0.017da_fwd=0.2 da_aft=0.195 di=0.065 rho=8340 128 shaft=(con10,TS2) l=0.218 da=0.200 di=0.065 rho=8320 129 shaft=(TS2,FC1_1) l=0.219 da=0.200 di=0.065 rho=8320 130 shaft=(FC1_1,FC1_2) l=0.554 da=0.200 di=0.065 rho=21320 131 shaft=(FC1_2,FL1) l=0.112 da=0.315 di=0.287 rho=13020 132 flange=(FL1,FL2) l=0.04 da=0.46 di=0.287 rho=8520 133 /************************************G-Box****************************/ 134 flange=(FL2,FL3) l=0.05 da=0.46 di=0.065 rho=7930 135 shaft=(FL3,JL2) l=0.043 da=0.24 di=0.065 rho=8170 136 shaft=(JL2,n13) l=0.122 da=0.24 di=0.065 rho=8170 137 shaft=(n13,gb_b5) l=0.075 da=0.28 di=0.065 rho=8080 138 shaft=(gb_b5,ge_whe1) l=0.115 da=0.28 di=0.065 rho=8080 139 shaft=(ge_whe1,ge_whe) l=0.125 da=0.29 di=0.065 rho=8060 140 shaft=(ge_whe,ge_whe2) l=0.125 da=0.29 di=0.065 rho=8060 141 shaft=(ge_whe2,gb_b6) l=0.105 da=0.28 di=0.065 rho=8080 142 shaft=(gb_b6,n14) l=0.085 da=0.28 di=0.065 rho=8080 143 shaft=(n14,sh_end) l=0.314 da=0.14 di=0.065 rho=8950 144 shaft=(sh_end,od_b) l=0.3 da=0.148 di=0.07 rho=1 145 146 /***************************************mass************************/ 147 mass=(ge_whe) m=995 jx=106.3 148 mass=(od_b) m=44 jx=1.5 149 150 sleevecpl=(OKC1) m=265 jx=5.9 jz=2.95 e_mass=0.04dx_open=0.350 151 sleevecpl=(OKC2) m=205 jx=4.01 jz=2. e_mass=-0.043dx_open=0.35 152 153 /*************************bearing************************************/ 154 bearing=(b1_stat) c_stat=5.0e9 155 bearing=(mid_b2) c_stat=3.05e9 156 bearing=(fwd_b3) c_stat=1.83e9 157 bearing=(Inb4) c_stat=1e9 158 bearing=(gb_b5) c_stat=5e9 159 bearing=(gb_b6) c_stat=5e9 160 bearing=(TS2) c_support=1e9 161 162 /******************* Hub=4D650D ***************************************/
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 31
Wärtsilä Defence
163 164 propeller=(prop) blade=4 da=2.6 pdratio=1.288 aratio=0.76 165 m_hub=1262 e_hub=0.01421 m_blade=154 e_blade=0.051 166 buoyancy= 0.13jx=650 jx_air=426 qv=0.01
================================= OUTPUT ==================================
TECHNICAL SPECIFICATION
SHAFT ALIGNMENT PROCEDURE
B001980290/ Rev.: B / Page 32
Wärtsilä Defence
Appendix 2
Coordinates System.
____________