SH16 Lincoln to Westgate construction programme · 2016-08-29 · construction period: march 2017 -...
Transcript of SH16 Lincoln to Westgate construction programme · 2016-08-29 · construction period: march 2017 -...
SH16 LINCOLN TO WESTGATE PROJECT
CONSTRUCTION PERIOD: AUGUST 2016 - SEPTEMBER 2016 CONSTRUCTION PERIOD: OCTOBER 2016 - NOVEMBER 2016 CONSTRUCTION PERIOD: DECEMBER 2016 - MARCH 2017
CONSTRUCTION PERIOD: MARCH 2017 - JULY 2017 CONSTRUCTION PERIOD: AUGUST 2017 - OCTOBER 2017 CONSTRUCTION PERIOD: NOVEMBER 2017 - DECEMBER 2017
CONSTRUCTION PERIOD: JANUARY 2018 - APRIL 2018 CONSTRUCTION PERIOD: MAY 2018 - SEPTEMBER 2018 WHOLE WORK COMPLETION: FEBRUARY 2019
Royal Road Off-Ramp
Start:Mid August 2016
North Bound Shoulder Widening
Start: Early September
2016
Switch to New Ramp
Remove Existing - December 2016
Retaining WallStart - End
September 2016
Retaining Wall and Shared Used Path
Start: Early October 2016
Royal Road On-Ramp
Start: November 2016
Royal Road
Start: November 2016
Royal Road Off-Ramp
Finish:
End February 2017Lowtherhurst
Wetland
Start: Early February 2017
Huruhuru Road Bridge (South)
Start: March 2017
Retaining Wall and Culvert
Start: Early March 2017
Lowtherhurst Wetland
Finish: May 2017
Median
Start: April 2017
Royal Road Footpath &
Watermain Construction
Start: February 2017
Royal Road BridgeStart: February
2017
Switch to New Ramp
Remove Existing: May 2017
Finish: June 2017
Makora Road and Royal Road (South)
Start: August 2017
North Harbour Watermain Diversion
September 2017
Overlay Makora Road Existing
November 2017
Royal Road Bridge
Demolision Existing: November 2017
Lincoln Road On Ramp
January 2018
Lincoln Bridge No. 1
January 2018
Widening South Bound & Bus Lane
Start: December 2017
Lincoln Bridge
Demolition Existing:
May 2018
Lincoln Road On Ramp
Remove Existing
Switch to New Ramp
May 2018
Huruhuru Road
End: May 2018
Lincoln On Ramp and Bridge
End: October 2018
South Bound
Overlay Existing:
End: September 2018
North Bound
Overlay Existing: October 2018
North Bound widening and new
Bus Lane
Start: Early May 2018
Please note: timings may change due to construction conditions.
Huruhuru Road Bridge
Demoliton Existing: October 2017