SH16 Lincoln to Westgate construction programme · 2016-08-29 · construction period: march 2017 -...

1
SH16 LINCOLN TO WESTGATE PROJECT CONSTRUCTION PERIOD: AUGUST 2016 - SEPTEMBER 2016 CONSTRUCTION PERIOD: OCTOBER 2016 - NOVEMBER 2016 CONSTRUCTION PERIOD: DECEMBER 2016 - MARCH 2017 CONSTRUCTION PERIOD: MARCH 2017 - JULY 2017 CONSTRUCTION PERIOD: AUGUST 2017 - OCTOBER 2017 CONSTRUCTION PERIOD: NOVEMBER 2017 - DECEMBER 2017 CONSTRUCTION PERIOD: JANUARY 2018 - APRIL 2018 CONSTRUCTION PERIOD: MAY 2018 - SEPTEMBER 2018 WHOLE WORK COMPLETION: FEBRUARY 2019 Royal Road Off-Ramp Start: Mid August 2016 North Bound Shoulder Widening Start: Early September 2016 Switch to New Ramp Remove Existing - December 2016 Retaining Wall Start - End September 2016 Retaining Wall and Shared Used Path Start: Early October 2016 Royal Road On-Ramp Start: November 2016 Royal Road Start: November 2016 Royal Road Off-Ramp Finish: End February 2017 Lowtherhurst Wetland Start: Early February 2017 Huruhuru Road Bridge (South) Start: March 2017 Retaining Wall and Culvert Start: Early March 2017 Lowtherhurst Wetland Finish: May 2017 Median Start: April 2017 Royal Road Footpath & Watermain Construction Start: February 2017 Royal Road Bridge Start: February 2017 Switch to New Ramp Remove Existing: May 2017 Finish: June 2017 Makora Road and Royal Road (South) Start: August 2017 North Harbour Watermain Diversion September 2017 Overlay Makora Road Existing November 2017 Royal Road Bridge Demolision Existing: November 2017 Lincoln Road On Ramp January 2018 Lincoln Bridge No. 1 January 2018 Widening South Bound & Bus Lane Start: December 2017 Lincoln Bridge Demolition Existing: May 2018 Lincoln Road On Ramp Remove Existing Switch to New Ramp May 2018 Huruhuru Road End: May 2018 Lincoln On Ramp and Bridge End: October 2018 South Bound Overlay Existing: End: September 2018 North Bound Overlay Existing: October 2018 North Bound widening and new Bus Lane Start: Early May 2018 Please note: timings may change due to construction conditions. Huruhuru Road Bridge Demoliton Existing: October 2017

Transcript of SH16 Lincoln to Westgate construction programme · 2016-08-29 · construction period: march 2017 -...

Page 1: SH16 Lincoln to Westgate construction programme · 2016-08-29 · construction period: march 2017 - july 2017 construction period: august 2017 - october 2017 construction period:

SH16 LINCOLN TO WESTGATE PROJECT

CONSTRUCTION PERIOD: AUGUST 2016 - SEPTEMBER 2016 CONSTRUCTION PERIOD: OCTOBER 2016 - NOVEMBER 2016 CONSTRUCTION PERIOD: DECEMBER 2016 - MARCH 2017

CONSTRUCTION PERIOD: MARCH 2017 - JULY 2017 CONSTRUCTION PERIOD: AUGUST 2017 - OCTOBER 2017 CONSTRUCTION PERIOD: NOVEMBER 2017 - DECEMBER 2017

CONSTRUCTION PERIOD: JANUARY 2018 - APRIL 2018 CONSTRUCTION PERIOD: MAY 2018 - SEPTEMBER 2018 WHOLE WORK COMPLETION: FEBRUARY 2019

Royal Road Off-Ramp

Start:Mid August 2016

North Bound Shoulder Widening

Start: Early September

2016

Switch to New Ramp

Remove Existing - December 2016

Retaining WallStart - End

September 2016

Retaining Wall and Shared Used Path

Start: Early October 2016

Royal Road On-Ramp

Start: November 2016

Royal Road

Start: November 2016

Royal Road Off-Ramp

Finish:

End February 2017Lowtherhurst

Wetland

Start: Early February 2017

Huruhuru Road Bridge (South)

Start: March 2017

Retaining Wall and Culvert

Start: Early March 2017

Lowtherhurst Wetland

Finish: May 2017

Median

Start: April 2017

Royal Road Footpath &

Watermain Construction

Start: February 2017

Royal Road BridgeStart: February

2017

Switch to New Ramp

Remove Existing: May 2017

Finish: June 2017

Makora Road and Royal Road (South)

Start: August 2017

North Harbour Watermain Diversion

September 2017

Overlay Makora Road Existing

November 2017

Royal Road Bridge

Demolision Existing: November 2017

Lincoln Road On Ramp

January 2018

Lincoln Bridge No. 1

January 2018

Widening South Bound & Bus Lane

Start: December 2017

Lincoln Bridge

Demolition Existing:

May 2018

Lincoln Road On Ramp

Remove Existing

Switch to New Ramp

May 2018

Huruhuru Road

End: May 2018

Lincoln On Ramp and Bridge

End: October 2018

South Bound

Overlay Existing:

End: September 2018

North Bound

Overlay Existing: October 2018

North Bound widening and new

Bus Lane

Start: Early May 2018

Please note: timings may change due to construction conditions.

Huruhuru Road Bridge

Demoliton Existing: October 2017