Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also...

113
Sewer Division of Public Works Sewer Improvement Program October 2016 Pierce County Public Works Sewer Improvement Program 20172037 ____________________________ Chambers Creek Regional Wastewater Treatment Plant Expansion Project

Transcript of Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also...

Page 1: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program October 2016

Pierce County Public Works Sewer Improvement Program 

2017‐2037 

____________________________ 

Chambers Creek Regional Wastewater Treatment Plant Expansion Project 

 

 

 

Page 2: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program i October 2016

   

Page 3: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program ii October 2016

Executive Summary The Sewer Division  for Pierce County Public Works Department manages all activities  involved with  the collection, transmission, and treatment of wastewater produced within unincorporated Pierce County and several cities under interlocal agreements.  The sewer service area consists of 117 square miles serving the cities of Lakewood, University Place, DuPont, Milton, and the unincorporated areas of Parkland, Spanaway, Midland, South Hill, Graham, Frederickson, Fife Heights, Brown’s and Dash Points, and the master planned communities of Sunrise and Tehaleh (Cascadia).  The Sewer Division also provides contract services to the Town of Steilacoom and portions of the cities of Tacoma, Fife, and Edgewood. Since the founding of the original sewer service area in the 1970s, the Sewer Division has continued to protect water quality and public health, while facilitating significant growth and shaping economic vitality.    The Sewer Improvement Program (Program) provides direction for the Sewer Utility including the Chambers Creek Regional Wastewater Treatment Plant and Collection System, a $1.8 billion dollar  investment  for Pierce County, and helps to ensure a reliable and seismically safe sewer system now and for generations to come. The Program also lays the groundwork for continued sewer system improvement projects to meet the changing demands of regulatory impacts, population growth and development, and infrastructure repair and  replacement  over  a  20‐year  planning  horizon  in  accordance  with  the Washington  State  Growth Management Act (GMA).  Population and employment projections are used to evaluate the system’s ability to meet future needs, and form the basis of recommendations for capacity expansion projects.  The  Program  also  addresses  aging  of  infrastructure,  system  expansion,  newly  available  analytical  data, finances,  revised  forecasting of  growth,  and  recommended  improvements,  serves  as  a basis  for  capital improvement planning for the next 20 years, and forecasts anticipated system build‐out needs based on land use zoning through 2037.  The Program also identifies the costs of the improvement projects and provides a financial plan for funding the projects in coordination with the Capital Facilities Six‐Year Financing Plan.    

Page 4: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program iii October 2016

Contents 

Chapter 1: Introduction 

Mission Statement ..........................................................................................     1‐1 Purpose ............................................................................................................     1‐1 Organizational Structure .................................................................................     1‐2 

Engineering 

Maintenance and Operations 

Organizational Services 

Planning and Programming 

Sewer Service Framework ...............................................................................     1‐3 

Chapter 2: System Planning Considerations 

Land Use ..........................................................................................................     2‐5 Sole Source Aquifer and Comprehensive Plan Requirements ........................     2‐5 Level of Service (LOS) ......................................................................................     2‐6 Flow Projections ..............................................................................................     2‐7 Conveyance and Treatment ............................................................................     2‐7 

Chapter 3: Six‐year Capital Facilities Plan Projects 

Sewer Improvement Categories ......................................................................     3‐9 Project Coordination .......................................................................................     3‐9 Basis for Cost Estimates ..................................................................................     3‐10 Project Funding ...............................................................................................     3‐10 Recommended 2017 ‐ 2022 Sewer Projects ...................................................     3‐12 

Chambers Creek Regional Wastewater Treatment Plant ...................     3‐12 

Collections Improvement Projects ......................................................     3‐24 

Collections Renovation and Rehabilitation Projects ...........................     3‐38 

Miscellaneous Scoping and Feasibility Studies ...................................     3‐52 

WWTP and Collections Systems Repairs and Replacement Projects ..     3‐54 

Operations and Maintenance Projects ...............................................     3‐56 

Chambers Creek Properties Projects  ..................................................     3‐58 

Environmental Services Building Projects ...........................................     3‐62 

Chapter 4: Future Projects ‐ Sewer Improvement Program 

2023 ‐ 2037 Project Descriptions  ...................................................................     4‐67 Lakewood East and West Sub‐basins including Town of Steilacoom .............     4‐67 Parkland Sub‐basin ..........................................................................................     4‐69 Brookdale/Golden Given Sub‐basin ................................................................     4‐70 Spanaway Sub‐basin ........................................................................................     4‐72 Spanaway Sub‐basin ‐ City of Roy ...................................................................     4‐74 Hylebos Sub‐basin ...........................................................................................     4‐75 

Page 5: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program iv October 2016

 Chambers Creek Properties Sub‐basin ............................................................     4‐76 

Chapter 5: Developer Built Infrastructure Projects 

2013‐2037 Project Descriptions ......................................................................     5‐77 City of DuPont including Northwest Landing Sub‐basin .................................     5‐77 Cascadia (Tehaleh) Sub‐basin ..........................................................................     5‐78 

Chapter 6: Chambers Creek Regional Wastewater Treatment Plant 

Treatment Type ...............................................................................................     6‐79 Expansion Phase 1 ...........................................................................................     6‐79 Expansion Phases 2‐5 ......................................................................................     6‐79 

Chapter 7: Financial Information 

Financial Methodology  ...................................................................................     7‐81 Credit Worthiness ...........................................................................................     7‐82 Current Financial Status ..................................................................................     7‐82 Financial Outlook .............................................................................................     7‐84 Funding Sources ..............................................................................................     7‐85 

Chapter 8: Sewer Division Public Programs 

Sewer Connection Program ............................................................................     8‐87 Sewer Commercial Conservation Program .....................................................     8‐87 Sewer Residential Conservation Program .......................................................     8‐87 Impact Fee and Connection Charge Deferral Program ...................................     8‐88 

Appendices 

Appendix A ‐ Staff Recommendation to the Planning Commission ................     9‐89 Appendix B ‐ 2017‐2037 Detailed Project Spreadsheets ................................     9‐90 Appendix C ‐ Adopting Ordinance 2016‐xx .....................................................             9‐105 

List of Tables 

Table 2‐1 Facilities, Capacities, and Locations ................................................     2‐6 Table 2‐2 Summary of Flow Projections .........................................................     2‐7 Table 2‐3 Service Area for Chambers Creek Regional Wastewater Treatment Plant 2‐8  Table 4‐1 Lakewood East and West Sub‐basins ..............................................     4‐67 Table 4‐2 Parkland Sub‐basin ..........................................................................     4‐69 Table 4‐3 Brookdale/Golden Given Sub‐basins...............................................     4‐70 Table 4‐4 Spanaway Sub‐basin ........................................................................     4‐72 Table 4‐4a Spanaway Sub‐basin ‐ City of Roy .................................................     4‐74 Table 4‐5 Hylebos Sub‐basin ...........................................................................     4‐75 Table 4‐6 Chambers Creek Properties Sub‐basin ............................................     4‐76 

Page 6: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program v October 2016

List of Tables ‐ Continued 

Table 5‐1 DuPont Sub‐basin ............................................................................     5‐77 Table 5‐2 Cascadia (Tehaleh) Sub‐basin ..........................................................     5‐78 Table 7‐1 Revenues, Expenses, and Reserve Balances by Year ......................     7‐83 Table 7‐2 Forecasted Expenses, and Reserve Balances by Year .....................     7‐84 Table 7‐3 Project Expenditures by Fund for 2017 ...........................................     7‐86  

Page 7: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 1 October 2016

      Chapter 1 Introduction 

Mission Statement The mission of the Sewer Division is to provide customers with high quality, cost effective sanitary sewer services by collecting and treating all wastewater generated from County service areas in accordance with applicable Local, State, and Federal permit requirements. 

Purpose  With  the passage of Ordinance No. 2006‐115s  the Pierce County Council  required  the Sewer Division of Public Works to combine the information found in the annual Pierce County Budget and the Capital Facilities Plan  to  produce  an  annual  Sewer Improvement Program or SIP.  

 The  SIP  would  then  serve  as  a  20‐year central  review  document  for  the  Sewer Division,  County  Council,  their  staff members,  and  the  public  to  review  the scope, cost, funding, and status of planned sewer  improvement  projects  proposed  to be undertaken by the Division.   The  SIP  is  a  companion  reference  to  the Capital  Facilities  Six‐Year  Financing  Plan. Budget proposals will continue to be part of the overall financial process, and the Capital Facilities Plan (CFP) will continue to be a part of the overall County six‐year projection as compiled by the Office of Budget and Finance under the Capital Facilities Six‐Year Financing Plan.  The Sewer Division employs an asset management approach of “lowest  life cycle cost” and “just  in time” forecasting to identify needs and costs for collection and treatment improvements. Projects in the capital program are prioritized based upon commitment and need. Projects that are under contract have highest priority, followed by system needs and other opportunities.  The SIP is utilized for long‐range planning and engineering of the county sewer system and of the Chambers Creek Regional Wastewater Treatment Plant. The Program is instrumental in securing long‐term funding and providing  a  dynamic  platform  for  adjustment  and  revision  to  the  CFP  to  best  take  advantage  of  new technologies and favorable construction opportunities.  Together the CFP and SIP will continue to provide the direction for ongoing sewer system expansion and preservation.   

Chambers Creek Regional Wastewater Treatment Plant Expansion Mid 2016

Page 8: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 2 October 2016

Projects presented in this document are based upon the following Public Works Core Values:   

Teamwork ‐ work together as a team with each other and our partners in other agencies and groups; 

Integrity ‐ always be dependable, open, honest, and fair in all we do; 

Quality  ‐ strive  for excellence to provide quality systems and services that are the best value  for those we serve; 

Innovation ‐ strive to improve our systems and services with proven innovations; 

Safety ‐ work for the safety of each other and those using our systems and services in everything we do; 

Public Service ‐ strive for the best service for our customers, both internal and for the public using our systems and services;  

Stewardship  ‐ be  responsible stewards of  the assets and  resources entrusted with us and of  the environment we live and work within; 

Organizational Structure The organizational structure of the Sewer Division is described below as it pertains to the administration, operation, and maintenance of the County’s sewer system.   The sewer system is administered by the Sewer Division of Pierce County Public Works Department, whose overall management is provided by the Director and Deputy Director. In addition to general management duties, the director is responsible for reviewing regional and state legislative issues and for implementing policy. The director’s office is the primary point of contact for the County Executive and County Council. The County Council  is  the policy‐making body of Pierce County and consists of seven elected members. The County Executive, who is also elected, serves as chief executive officer.    The Sewer Division is separated into four major sections:  

Engineering The section manager for Engineering is responsible for management of project design, construction services and development review functions. The section oversees capital project design and management, conducts permit reviews, administers development processes requiring coordination with other County departments, and  provides  regulatory  compliance  and  code  enforcement.    The  section  oversees  staff  at  the  Permit Counter, which  is  the  first  contact  for  customer  service  and  information on development  requests  and approvals, and also conducts construction inspections to assure timely and efficient completion of projects, and ensure projects are  installed and constructed according to approved design plans and specifications.  Unless a specialized process requires the use of a consultant, design of projects  is done primarily by the internal engineering section.  

Maintenance and Operations The section manager for Maintenance and Operations manages the day‐to‐day operations and maintenance of  the  sewer  system,  including  supervision  of  field  crews, monitoring  and  assessing  the  condition  of infrastructure  to minimize  system  failures  and maximize  the  life  of  system  components,  wastewater treatment plant operations, laboratory testing, and environmental compliance and reporting.  

Page 9: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 3 October 2016

Organizational Services The  section manager  for Organizational  Services  is  responsible  for management  of  the  sewer  division administrative support functions, internal and external communication and outreach, business development and  legislative efforts, emergency  response and  safety planning, water  resources analysis, and biosolids coordination and management.  

Planning and Programming The  section manager  for Planning and Programming manages  the division’s  financial portfolio  including annual budget development and monitoring, rate forecasting, interlocal agreements and service contracts, grant and loan programs, and billing program support functions.  This section oversees sewer systems long‐range plans, including the Unified Sewer Plan, Capital Facilities Plan, Sewer Improvement Program, sewer code regulations, and reviews and evaluates developer requests to determine long‐term effect on system operation.    This  section  also  coordinates  capital  project  permitting,  asset  detail,  hydraulic  modeling, mapping, and property data management.   

Sewer Service Framework 

Improvement Types The Sewer Division strives to make every effort to  improve services through five classes of  improvement types:  Maintenance: A project considered a routine activity associated with repairing a physical asset or keeping the physical asset functional during the asset's useful life. Maintenance of the wastewater treatment plant, collection system, pumps, and generators are examples of maintenance activities.  Operations: Projects that include the costs and activities associated with the continued, highest, and best use of an asset. Public Works operations consist of all plant operations including collections, treatment, and fertilizer manufacturing. Providing public education on how to best use a system, responding to constituent requests  and  questions,  and  sewer  billing  are  also  regarded  as  activities  associated with  the  efficient operations of a system.  Preservation: Preservation is actually the replacement, or rehabilitation, of an asset after it has reached its useful  life  to  accomplish  the  same  overall  function.  These  projects  can  be  confused  with  the  capital improvement of a system. Types of preservation projects for the Sewer Division can be: replacing a pump at a pump station, or replacing a failed pipe in a collections system.  Improvement: This is a project that primarily improves the capacity or function of an asset. Any activity in the Capital Improvement Plan is considered an improvement activity.  In Public Works the actions associated with the identification or development of the Capital Facilities Plan is considered an improvement activity.  Administrative: These programs involve the management, planning, and coordination of the overall asset or asset group. Examples of administration activities  include  the management of boards or committees, planning activities such as basin planning or work on Environmental Impact Statements. Maintaining records and participation in department‐wide programs is also considered an administration activity.   

Page 10: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 4 October 2016

Service Types The Sewer Division has two types of service areas: Urban and Rural.   The Urban Service Area is the Sewer Division’s primary service area consisting of a 117 square mile sewer service basin consisting of 19 individual sub‐basins corresponding with the core of urban growth that has occurred around the City of Tacoma,  in and around the Town of Steilacoom, and the cities of Lakewood, Fife, Milton, DuPont,  and  Puyallup.  The  service  area  also  includes  unincorporated  areas  of  the  County including Frederickson, Parkland, Spanaway, South Hill, Graham, Brown’s and Dash Points, Fife Heights, the planned community of Tehaleh (Cascadia), and a small area in the City of Edgewood. Covering 35 percent of urban Pierce County, this comprises the bulk of Pierce County’s sewer service area.  The Rural Service Area was established prior to the adoption of the State Growth Management Act in 1994 and  the  Pierce  County  Comprehensive  Plan  in  1995.  These  areas were  once  under  the  designation  of predominately General (G) or Suburban Residential (SR) and other less restrictive zoning designations that, prior to 1994/1995, allowed sewer connection. Once the Pierce County Comprehensive Plan was adopted in 1995 and re‐adopted and approved by Council  in 2016, the Rural Service Area was and has remained restricted to parcels already served, and those parcels and projects that have vested connection rights.   The Tacoma‐Pierce County Health Department also has the authority to require parcels in the rural zones and rural service area to connect to the public sewer system  in the case of public health and welfare or environmental concerns.   New connections not expressly vested  through past  land use decisions or Tacoma‐Pierce County Health Department connection requirements, are prohibited in any rural area.  

Customers The Sewer Division’s customers or ratepayers are located in areas of unincorporated Pierce County within designated Urban Growth Areas, including Parkland, Spanaway, Midland, Frederickson, Graham, South Hill, Brown’s and Dash Points, Fife Heights, Tehaleh (Cascadia) and all or portions of the following towns and cities: 

Town of Steilacoom 

City of DuPont including the Historic Village and Northwest Landing  City of University Place  City of Lakewood including Tillicum and American Lake Gardens. 

City of Tacoma (Western Slopes Service Area) 

City of Milton (flows to the City of Tacoma's Central Wastewater Treatment Plant) 

City of Fife (flows to the City of Tacoma's Central Wastewater Treatment Plant) 

City of Edgewood (flows to the City of Tacoma’s Central Wastewater Treatment Plant)  

Page 11: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 5 October 2016

CHAPTER 2 

Systems Planning Considerations  

Chapter 2 identifies physical features and sewer system facilities within Pierce County, and discusses their correlation and operation. Pierce County sewer system is entirely separate from the storm and surface water collection system. The wastewater system is well mapped, inspected, and maintained. There are no known connections between or conflicts with sources of water supply or storm water conveyance. 

Land Use Land use within sewer service area is governed by the Pierce County Comprehensive Plan and various city comprehensive plans within the service area. The plan addresses current  land use within the county and future land use direction. Land uses for future development of the service area were used in preparation of this plan. The density of development permitted in each land use designation throughout the entire sewer service area  is specified  in the zoning ordinances of the County and of other municipalities  in the service area.  

Sole Source Aquifer and Comprehensive Plan Requirements Much of Pierce County’s Urban Growth Area is located above a sole source aquifer. The installation of sewers and the continued decommissioning of individual septic systems in the urban zoned areas of the County aid in protecting this valuable resource.   The 2015 Pierce County Comprehensive Plan Section 13 ‐ Utilities Element states goals to provide for the location of utility facilities and to insure adequate utility capacity for future growth. Further goals for sewer utilities are to provide sanitary sewers within the Urban Area and to utilize best construction methods and practices and innovative techniques in the design and construction of sewer utilities.  

  

Pierce County requires the use of sewers in the County’s urban growth and urban zoned areas. To this end, collection system expansion is primarily accomplished by new development paying for the construction of new  lines and connections  to carry wastewater  to  the Chambers Creek Regional Wastewater Treatment Plant, Tacoma Central Wastewater Treatment Plant, and the Cascadia (Tehaleh) Large Onsite Septic System.  The Sewer Improvement Program is utilized for a 20‐year planning cycle and is instrumental in securing long‐term funding and providing a dynamic platform for adjustment and revision to the Capital Facilities Plan to best take advantage of new technologies and favorable construction opportunities.   The 2017‐2022 Capital Facilities Plan together with the 2017‐2037 Sewer Improvement Program will provide direction for the Sewer Division of Pierce County’s Public Works Department.   

Page 12: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 6 October 2016

Level of Service The  current  Level of  Service  (LOS) of 220  gallons per day per  residential equivalent meets  current  LOS requirements. This includes Chambers Creek Regional Wastewater Treatment Plant average daily treatment demand in 2014/2015 of 20.1MGD from an available operational capacity of 24.4MGD. Growth‐related and permit required reserves of 4.3MGD provide a total Plant capacity of 28.7MGD as shown in Table 2‐1.    With  substantial  completion  of  Phase  1  of  the  Chambers  Creek  Regional Wastewater  Treatment  Plant Expansion project in December 2016, a re‐rating of the treatment capacities will be done in early to mid‐2017. At that time the maximum operational capacity and the capacity held  in reserve will be revised to reflect these improvements. The new capacity rating will be approximately 43‐45MGD.  The  Sewer Division  also  owns  2.56MGD  of  capacity  and  treatment  at  the  Tacoma  Central Wastewater Treatment Plant located in the City of Tacoma at the Port of Tacoma. Flows from the cities of Milton and Edgewood and unincorporated Brown’s Point and Fife Heights areas are sent to this facility. Total available capacity  from all  locations  including reserves within the Pierce County Sewer Service Area  is 31.34MGD.  Table 2‐1 summarizes the current capacities for all Sewer Division treatment facility locations.  The two large on‐site septic or “LOSS” systems, listed in Table 2‐1 below, are stand‐alone installations for a specific single or multi‐customer use. These systems are the Cascadia LOSS at the Tehaleh Master Planned Development and the Etloh LOSS located on Fox Island.  

The Cascadia LOSS (WWTP) system is currently rated at .1MGD. An interim WWTP is under review that will expand over time to become the Cascadia WWTP at Tehaleh, a 4.3MGD rated facility that will meet the wastewater treatment demands of the Tehaleh Master Planned Development through project build‐out.  

The Etloh LOSS is a closed system that serves a small planned development on the south end of Fox Island.  No  new  connections  are  anticipated  to  this  system.  Should  additional  connections  be proposed, additional capacity would be required, and constructed, prior to any new connections. 

 Table 2‐1 

 Facilities, Capacities, and Locations 

Facility  Capacity  Location 

Chambers Creek Regional Wastewater Treatment Plant 28.70 MGD* City of University Place

Tacoma Central Wastewater Treatment Plant 2.54 MGD** City of Tacoma

Sub Total 31.24 MGD  

Large On‐Site Systems (LOSS)   

Cascadia Wastewater Treatment Plant at Tehaleh .1 MGD East Pierce County

Etloh LOSS  .001 MGD Fox Island, Pierce County

Sub Total .1 MGD  

Total Capacity (all facilities) 31.34 MGD  

*Millions of Gallons per Day, **Owned Treatment and Capacity 

Page 13: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 7 October 2016

Flow Projections Flow projections are generated using the Division’s flow modeling software and land use designations from the Pierce County Geographic Information System (GIS) using point flows for the service areas integrated into the flow projection model. The model then simulates the volume of wastewater that would be conveyed through the transmission pipelines to the treatment plant.  Table 2‐2 presents a summary of the flow projections for the WWTP and conveyance system.  

Table 2‐2  

Summary of Flow Projections 

Condition  1999 Actual  2010 Actual  2017 Projected 

Average Dry Weather Flow  14MGD  18.9MGD  21MGD 

Maximum Monthly Flow  22MGD  21MGD  23MGD 

Peak Wet Weather Flow  44MGD  43MGD  43MGD Data derived from 2010/2012 Unified Sewer Plan 

 The model results suggest that the volume of wastewater flow at future service levels may be approximately two times greater than the volume of wastewater treated in 2010. The increase stems not only from the addition of new services, but also from development within the existing service area. Sewer service sub‐basins east of Interstate 5 have a number of medium sized undeveloped tracts for future development and also have large areas developed with on‐site septic drain field systems.  Connection of existing development on on‐site septic drain field systems and future development will result in an increase in the volume of wastewater transmitted through the major conveyance facilities and treated at the Chambers Creek Facility.  The projected average dry weather flow (ADWF) for 2016 is the same as was projected in the 2010/2012 Unified Sewer Plan Update. Future projected peak flows for 2037 of 109MGD are expected to exceed the capacity of the influent sewer pipeline to the WWTP of 104MGD and the capacity of the existing effluent outfall of 100MGD. However, improvements to these treatment plant related facilities will not be needed until the sewer service basin nears full development. 

Conveyance and Treatment Wastewater conveyance and treatment services will continue for all basins in the existing sewer service area. The potential for new service for the Cities of Fircrest, Roy, and areas within DuPont, will be as requested by the individual cities.  Table 2‐3 outlines a summary of the existing and possible service area components for the Chambers Creek facility.    

Page 14: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 8 October 2016

Table 2‐3 

 Service Area for Chambers Creek Regional Wastewater Treatment Plant 

Service Area  Area in Acres  

Existing Chambers Creek Regional WWTP Sewer Service Area 

       All Basins (117 square miles)  74,880 

   

City of Fircrest   

       Flows sent to the Tacoma Central WWTP   1,071 

   

City of DuPont  

       Sequalichew Village (gravel pit)  826 

       First Park Development  260 

       El Rancho Madrona Subdivision  18 

   

South Hill 

       Zone 3 ‐ Potential Service Area  818 

       CUGA pockets ‐ including Rodgers Ridge  711 

   

City of Roy 

       Assumes independent financing obtained, project‐specific environmental review    completed, and local collection facilities constructed, by the City.  164 

Total Acres 78,748           Source: 2010/2012 Unified Sewer Plan 

 In the event that the City of Fircrest chooses to transfer their wastewater flows from the Tacoma Central WWTP  to  the  Chambers  Creek  Facility,  infrastructure  improvements must  be made  by  the  City  to  its collection system before these flows could be redirected.   The  City  of  DuPont  including  Northwest  Landing  continues  to  be  provided  the  opportunity  to  send wastewater flows from the El Rancho Madrona and First Park sub‐divisions and from currently undeveloped property in the central and northwest areas of DuPont.  Sewer service for the City of Roy can be accommodated within the existing collection system. The City would be  required  to  secure  funding  for  connection  charges  for  the  capital  improvements  to  convey  the wastewater to the Pierce County collection system. This would also require the City to complete, and have approved, a facility plan and project‐specific environmental review.  

   

Page 15: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 9 October 2016

Chapter 3 CFP Projects 2017‐2022 

 Chapter 3 references and includes the projects for the current Capital Facilities Plan (CFP) as a part of the 2017‐2037 Sewer Improvement Program. Projects from the CFP have individual spreadsheets and location maps  included  to easily  spot  the project’s  location within  the  sewer  service basin.  Information  in  these individual  project  breakdowns  detail  projected  costs  for  Preliminary  Engineering,  Final  Engineering, Permitting, Construction, Construction Engineering, and Miscellaneous or Other. Dollar estimates include a 4% annual inflation factor compounding over the six‐year cycle. 

Sewer Improvement Categories Recommended sewer system improvements fall into eight general categories:  

 

Chambers Creek Regional Wastewater Treatment Plant: These projects address known or potential system capacity expansion or reliability problems at the existing treatment plant. 

Collections Improvement Projects: These projects address projected system capacity problems due to  forecasted  future  development,  and  potential  system  capacity  or  reliability  problems  at  the existing. 

Collections  Renovation  and  Rehabilitation  Projects:  These  projects  are  intended  to  reduce  the number and severity of system failures due to age in the collections system.  

Miscellaneous  Scoping  and  Feasibility  Studies:  Annual  improvements  that  recommend improvement opportunities or feasibility studies to maintain, rehabilitate, and upgrade the Sewer Division assets. 

WWTP and Collections Systems Repair and Replacement Projects: These projects and programs are intended to reduce the number and severity of system failures in the due to age at the WWTP. 

Operations and Maintenance Projects: Projects recommended to maintain and increase efficiencies for operation of the Chambers Creek Regional Wastewater Treatment Plants existing infrastructure. 

Chambers Creek Properties Projects: These projects are intended to improve the Chambers Creek Properties in conformance with the Chambers Creek Properties Master Site Plan, provide mitigation for current and future Chambers Creek Regional Wastewater Treatment Plant expansions, and to meet the requirements from the State of Washington, Department of Natural Resources, to reclaim the site from previous mining activities. 

Environmental Services Building Projects:   Projects  recommended  to maintain,  rehabilitate, and upgrade the Sewer Division’s Environmental Services Building’s existing infrastructure. 

Project Coordination The Sewer Division coordinates with the Transportation Division of Public Works for proposed infrastructure and maintenance projects each year. Projects are reviewed and coordinated with Transportation  for the location of, or  improvement to, new or existing sewer  infrastructure. The Sewer Division’s Development Engineering Section will send copies of all proposed developer driven extensions after first review to the 

Page 16: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 10 October 2016

Road Operations and Design sections to alert Transportation to upcoming developer sewer line extensions in the sewer service basin not associated with an adopted roads project.  

Basis for Cost Estimates Cost estimates  in  this Program  are planning  level estimates  and,  as  such, have been prepared without detailed  engineering  data.  The  cost  estimates  presented  reflect  the most  probable  capital  cost. Actual project costs can be expected to vary in the future. Project cost estimates vary due to design changes made during preparation of final engineering plans and specifications, and as a result of changes  in the cost of materials, labor, and equipment.   Costs cited in this report are based on preliminary layouts of the proposed projects.  The capital cost includes the estimated construction cost, state and local sales tax, and costs for administrative, engineering, financial and legal services and contingencies. Costs for land and easements are also included in this analysis.  These costs are used in the Sewer Division’s financial model to generate long‐term financial forecasts and capital programming for the Sewer Utility. 

Project Funding 2017‐2022 The County updates the 6‐year Capital Facilities Plan (CFP) and 20‐year Sewer Improvement Program (SIP) with detailed funding sources and project scheduling, every year. During each update, all proposed capital projects are evaluated against specific criteria and available resources, they are then prioritized, funded, and scheduled accordingly. Currently  funded capital projects are presented  in detailed project sheets below.  Information, such as Project Fund and Identification, Scope, Purpose, Council District and Service Basin, can be found on theses individual project sheets.  The project funding levels are consistent with those produced by the Pierce County Office of Budget and Finance.  This information, in a less detailed format, is also found in the adopted 2017‐2022 CFP.  Of the twenty‐seven (27) funded projects  in the current Sewer Improvement Program, twenty‐three (23) are Sewer Division projects, two (2) are improvement projects for the Environmental Services Building, and two (2) are Chambers Creek Properties projects. Some projects do not have an individual project map due to their stature as system‐wide projects or an association with an existing Utility Local Improvement District. These projects include minor sewer line extensions, flow meter installations, and/or emergency generator replacements.  Chart 3‐1 summarizes the six‐year capital project funding priorities by improvement category.  The majority of capital spending is for Chambers Creek Regional Wastewater Treatment Plant (WWTP) projects through 2022, with a total of $38,434,100 budgeted for 2017 and 2022.  With the completion of the WWTP Expansion Project scheduled for 2020, funding priorities begin to shift to Collections Improvement projects, Collection Renovation  and  Rehabilitation  projects,  and WWTP  and  Collections  Systems  Repair  and  Replacement projects.    

Page 17: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 11 October 2016

 Chart 3‐1 

 Six‐Year Capital Project Funding Totals by Sewer Improvement Category 

 

    

2017 2018 2019 2020 2021 2022

CCRWWTP Projects $6,407,300 $3,856,200 $13,559,800 $14,610,800 $296,000 $297,400

Collections Improvements $155,000 $375,000 $901,700 $14,083,400 $8,419,000 $3,331,800

Collections R & R $2,721,500 $775,500 $785,800 $1,377,600 $2,149,900 $13,205,400

Scoping & Feasibiity $50,000 $50,000 $50,000 $50,000 $50,000 $50,000

WWTP & Collection Projects $0 $400,000 $3,977,500 $5,141,600 $8,123,000 $8,571,500

O & M Projects $0 $200,000 $200,000 $200,000 $200,000 $200,000

Chambers Creek Properties $1,445,000 $567,000 $5,000 $0 $0 $0

Environmental Services Building $870,000 $5,000 $0 $0 $0 $0

$0

$1,000,000

$2,000,000

$3,000,000

$4,000,000

$5,000,000

$6,000,000

$7,000,000

$8,000,000

$9,000,000

$10,000,000

$11,000,000

$12,000,000

$13,000,000

$14,000,000

Page 18: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 12 October 2016

Chambers Creek Regional WWTP Expansion Phase 1 2017‐2018 

Project Number ‐ 1 

Project  Description:  This  is  an  improvement  project  to  expand  the  treatment  capacity  of  the  Plant, modernize the treatment process, and rehabilitate existing systems. It is the first of five phases approved by the City of University Place  in  February 2010  through Conditional Use Permit CUP09‐0001.  This permit consolidated all previous  land use approvals for the WWTP  into one new Conditional Use Permit using a Chambers Creek WWTP Overlay in what is now zoned as Residential 2 or R2 zoning classification. Completion of all five phases is not anticipated until 2040. 

Sewer Service Basin: Chambers Creek Properties Sub‐basin 

Council District: 4 

Project Priority: High 

Project Status: The Phase 1 expansion project is estimated for completion in year 2018 

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402  $313,157,000  $5,452,000  $5,000          $318,609,000

Fund 403          Fund 404         

Totals  $313,157,000  $5,452,000  $5,000          $318,609,000 

   

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

               

Final Engineering 

               

Permitting                 

Construction    $5,070,000            $5,070,000 

Construction Engineering 

  $382,000            $382,000 

Other      $5,000          $5,000 

Totals  $313,157,000  $5,452,000  $5,000          $318,609,000 

Page 19: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 13 October 2016

 

Project Location 

Page 20: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 14 October 2016

Chambers Creek Regional WWTP Expansion Phase 1: Reclaimed Water PS 2018‐2021 

 

Project Number ‐ 2 

Project Description: This is an improvement project consisting of building a pump station, storage pond, and constructing piping to distribute reclaimed water to the irrigation system of the Chambers Creek Properties to irrigate the park features of the Chambers Creek Regional Park with the future intention of also irrigating the Chambers Bay Golf Course. Peak demands of up to 1‐2MGD in potable water savings may be realized with the availability of reclaimed water. 

Sewer Service Basin: Chambers Creek Properties Sub‐basin 

Council District: 4 

Project Priority: Low 

Project Status: The project is estimated for completion in year 2021 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402      $307,700  $1,435,300  $2,619,300  $2,500    $4,364,800 

Fund 403      $158,500  $739,700  $1,349,300  $2,500    $2,250,000 

Fund 404                 

Totals  $137,600    $466,200  $2,175,000  $3,968,600  $5,000    $6,725,400 

   

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

               

Final Engineering 

    $466,200          $466,200 

Permitting                 

Construction        $1,958,000  $3,571,700      $5,529,700 

Construction Engineering 

      $217,000  $369,900      $586,900 

Other            $5,000    $5,000 

Totals  $137,600    $466,200  $2,175,000  $3,941,600  $5,000    $6,725,400 

Page 21: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 15 October 2016

 

Project Location 

Page 22: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 16 October 2016

Chambers Creek Regional WWTP: Solids Handling Expansion 2017‐2021 

 

Project Number ‐ 3 

Project Description: The solids handling system will have insufficient capacity by 2020. This planning project will begin looking at options for the next phase of the solids handling process.   Sewer Service Basin: Chambers Creek Properties Sub‐basin  Council District: 4 

Project Priority: High 

Project Status: The project is estimated for completion in year 2021 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402  $22,500  $112,500  $1,560,000  $5,586,650  $5,186,150  $2,500    $12,470,300 

Fund 403  $22,500  $112,500  $1,560,000  $5,586,650  $5,186,150  $2,500    $12,470,300 

Fund 404                 

Totals  $45,000  $225,000  $3,120,000  $11,173,300  $10,372,300  $5,000    $24,940,600 

  

    

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

               

Final Engineering 

  $225,000  $3,120,000          $3,345,000 

Permitting        $600,000        $600,000 

Construction        $9,082,400  $8,980,400      $18,062,800 

Construction Engineering 

      $1,009,200  $997,800      $2,007,000 

Other        $481,700  $394,100  $5,000    $880,800 

Totals  $45,000  $225,000  $3,120,000  $11,173,300  $10,372,300  $5,000    $24,940,600 

Page 23: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 17 October 2016

Project Location 

Page 24: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 18 October 2016

Chambers Creek Regional WWTP: Digester Rehabilitation 2017‐ 

Project Number ‐ 4 

Project Description: With the completion of Phase 1 of the WWTP Expansion Project, two new digesters will come on‐line. Once the new digesters are fully operational the three existing units will be put on a regular maintenance schedule, with the all units on a five‐year rotation to undertake cleaning, inspection, and spot repairs. The three existing units will be used as storage for treated wastewater when not in use as digesters.   

Sewer Service Basin: Chambers Creek Properties Sub‐basin 

Council District: 4 

Project Priority: Medium 

Project Status: The project is forecasted through the year 2037 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Fund 402                 

Fund 403                 

Fund 404    $350,000  $255,000  $256,000  $275,000  $286,000  $297,400  $1,728,400

Totals    $350,000  $255,000  $256,000  $275,000  $286,000  $297,400  $1,728,400

 

   

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Cumulative Project Cost 

Preliminary Engineering 

               

Final Engineering 

               

Permitting                 

Construction                 

Construction Engineering 

               

Other    $350,000  $255,000  $256,000  $275,000  $286,000  $297,400  $1,728,400 

Totals    $350,000  $255,000  $256,000  $275,000  $286,000  $297,400  $1,728,400 

Page 25: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 19 October 2016

 

Project Location 

Page 26: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 20 October 2016

Chambers Creek Regional WWTP: FMF Furnace Replacement 2017‐2018 

Project Number ‐ 5 

Project Description: The furnace is an essential component in the Fertilizer Manufacturing Facility, without which it cannot operate.  If inoperable, the Division is unable to produce Class A Exceptional Quality biosolids and would  be  required  to  haul  and  then  land  apply  Class  B  biosolids  using  a  contracted  vendor, with anticipated  costs of $20,000‐$25,000 per week  in 2016 dollars.  The  recommended  scope of work  is  to replace the furnace with a new, stainless steel furnace which will be less susceptible to corrosion than the existing steel unit. The balance of the work, estimated at $347,000, would be completed in 2017‐2018. 

Sewer Service Basin: Chambers Creek Properties Sub‐basin 

Council District: 4 

Project Priority: High 

Project Status: The project is estimated for completion in year 2018 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402  $125,000  $217,000  $5,000          $347,000 

Fund 403                 

Fund 404                 

Totals  $125,000  $217,000  $5,000          $347,000 

    

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

               

Final Engineering 

$25,000              $25,000 

Permitting                 

Construction    $35,000            $35,000 

Construction Engineering 

  $20,000            $20,000 

Equipment/ Hauling 

$100,000  $162,000  $5,000          $267,000 

Totals  $125,000  $217,000  $5,000          $347,000 

Page 27: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 21 October 2016

  

Project Location 

Page 28: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 22 October 2016

Chambers Creek Regional WWTP: FMF Digester Gas Delivery 2017‐2018 

Project Number ‐ 6 

Project Description: The Fertilizer Manufacturing Facility was designed to utilize up to 60% digester gas that is readily available onsite through the digestion process. Utilizing this energy source has been hampered by inadequate system pressure, piping, and condensate removal, to allow the gas from the digestion system to be delivered properly. This project will  install a new pressure boosting blower,  install a new condensate removal system, and provide adjustments  from  the digesters  to  the FMF  to allow digester gas use. This project is anticipated to save an estimated $100,000 annually on natural gas usage. 

Sewer Service Basin: Chambers Creek Properties Sub‐basin 

Council District: 4 

Project Priority: High 

Project Status: The project is forecasted through the year 2018 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402    $173,300  $5,000          $178,300 

Fund 403                 

Fund 404                 

Totals    $173,300  $5,000          $178,300 

 

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

  $5,000            $5,000 

Final Engineering 

  $15,000            $15,000 

Permitting                 

Construction    $115,000            $115,000 

Construction Engineering 

  $20,000            $20,000 

Other    $18,300  $5,000          $23,300 

Totals    $173,300  $5,000          $178,300 

Page 29: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 23 October 2016

 

Project Location 

Page 30: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 24 October 2016

Collections Improvement: B Street Interceptor Phase 3 2018‐2022  

Project Number ‐ 7 

Project Description: This project was created by  the split of  the B Street  Interceptor Phase 2 project as identified in the 2011 Capital Facilities Plan and budget into two phases. This improvement project includes the installation of approximately 5,900 lineal feet of 30” diameter gravity pipeline along “B” Street East and Mountain Highway from 192nd Street East to 204th Street East. 

Sewer Service Basin: Parkland/Spanaway 

Council District: 3 

Project Priority: Medium 

Project Status: The project is estimated for completion in year 2022 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402                 

Fund 403  $517,600    $225,000  $225,000  $9,695,600  $4,083,800  $5,000  $14,752,000 

Fund 404                 

Totals  $517,600    $225,000  $225,000  $9,695,600  $4,083,800  $5,000  $14,752,000 

    

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

               

Final Engineering 

    $225,000  $225,000        $450,000 

Permitting                 

Construction          $8,726,000  $3,675,400    $12,401,400 

Construction Engineering 

        $969,600  $408,400    $1,378,000 

Other              $5,000  $5,000 

Totals  $517,600    $225,000  $225,000  $9,695,600  $4,083,800  $5,000  $14,752,000 

Page 31: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 25 October 2016

 

Project Location 

Page 32: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 26 October 2016

Collections Improvement: Miscellaneous Sewer Line Connections 2017‐ 

Project Number ‐ 8 

Project Description: This operations and  improvement project will construct gravity collector sewer  line extensions. This  includes sewer  improvements  in conjunction with other  jurisdiction’s road  improvement projects. This also includes the cost of raising existing manhole rims located in road improvement projects. 

Sewer Service Basin: Various Sub‐Basins 

Council District: Various 

Project Priority: Medium 

Project Status: The project is forecasted through the year 2037 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Fund 402                 

Fund 403  $1,034,600  $150,000  $150,000  $150,000  $150,000  $150,000  $150,000  $1,934,600 

Fund 404                 

Totals  $1,034,600  $150,000  $150,000  $150,000  $150,000  $150,000  $150,000  $1,934,600 

 

   

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Preliminary Engineering 

               

Final Engineering 

               

Permitting                 

Construction  $1,034,600  $150,000  $150,000  $150,000  $150,000  $150,000  $150,000  $900,000 

Construction Engineering 

               

Other                 

Totals  $1,034,600  $150,000  $150,000  $150,000  $150,000  $150,000  $150,000  $1,934,600 

Page 33: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 27 October 2016

 

  

 

 

 

 

 

 

 

 

 

 

These projects are system wide and have no associated map for individual project locations. 

        

 

Page 34: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 28 October 2016

Collections Improvement: Upper Leach Creek Interceptor 2018‐2022 

Project Number ‐ 9 

Project Description: This project will install 2,400 lineal feet of 30‐inch interceptor line in Upper Leach Creek. The interceptor will serve areas of University Place and provide sewer access to the City of Fircrest should they wish to contribute to the project. 

Sewer Service Basin: University Place East 

Council District: 4 

Project Priority: Low 

Project Status: The project is estimated for completion in year 2022 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402                 

Fund 403        $526,700  $3,927,000  $2,766,000  $5,000  $7,238,700 

Fund 404                 

Totals        $526,700  $3,927,000  $2,766,000  $5,000  $7,238,700 

    

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

      $156,000        $156,000 

Final Engineering 

      $312,000        $321,000 

Permitting        $58,700        $58,700 

Construction          $3,534,400  $2,494,000    $6,028,400 

Construction Engineering 

        $392,600  $272,000    $664,600 

Other              $5,000  $5,000 

Totals        $526,700  $3,927,000  $2,766,000  $5,000  $7,238,700 

Page 35: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 29 October 2016

 

Project Location 

Page 36: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 30 October 2016

Collections Improvement: Woodland Pump Station and Temporary Force Main 2020 ‐2023 

Project Number ‐ 10 

Project Description: This project will construction a new regional pump station and temporary force main connecting  into the 112th Street East sewer  line extension. The temporary force main will be replaced  in 2030, when the Brookdale Interceptor is installed from Woodland Avenue to Waller Road. 

Sewer Service Basin: East Sub‐Basin 

Council District: 2 

Project Priority: Low 

Project Status: The project is estimated for completion in year 2023 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Fund 402                 

Fund 403            $354,100  $2,833,800  $3,187,900 

Fund 404                 

Totals            $354,100  $2,833,800  $3,187,900 

   

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Preliminary Engineering 

          $104,000    $104,000 

Final Engineering 

          $208,000    $208,000 

Permitting            $42,100    $42,100 

Construction              $2,452,400  $2,452,400 

Construction Engineering 

            $381,400  $381,400 

Other                 

Totals            $354,100  $2,833,800  $3,187,900 

Page 37: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 31 October 2016

 

Project Location 

Page 38: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 32 October 2016

Collections Improvement: 122nd Avenue East Interceptor 2019‐2022 

Project Number ‐ 11 

Project Description: This project will install 3,000 lineal feet of 15‐inch sanitary sewer mainline east on 136th Street East to the intersection of 136th Street East and 122nd Avenue East and then south along 122nd Avenue East to the intersection of 122nd Avenue East and 144th Street East.  Sewer Service Basin: East Sub‐Basin 

Council District: 1 

Project Priority: Low 

Project Status: The project is estimated for completion in year 2022 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402                 

Fund 403          $310,800  $1,065,100  $5,000  $1,380,900 

Fund 404                 

Totals          $310,800  $1,065,100  $5,000  $1,380,900 

    

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

        $104,000      $104,000 

Final Engineering 

        $156,000      $156,000 

Permitting          $50,800      $50,800 

Construction            $963,100    $963,100 

Construction Engineering 

          $102,000    $102,000 

Other              $5,000  $5,000 

Totals          $310,800  $1,065,100  $5,000  $1,380,900 

Page 39: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 33 October 2016

 

Project Location 

Page 40: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 34 October 2016

Collections Improvement: Thun Field EC Sewer Line Extension 2015‐2017  

Project Number ‐ 12 

Project Description: This project will install 1,925 lineal feet of 8‐inch sanitary sewer mainline southerly from the  intersection  of  158th  Street  East on  110th Avenue  East  to provide  sewer  collection  services  for  the approximately 914 acres of underdeveloped Employment Center parcels along  the eastern side of Thun Field. These are  the  last EC zoned parcels available  for development  in Pierce County. Existing and new residential and commercial developments can also be accommodated should they wish to connect. 

Sewer Service Basin: Rainier Terrace Sub‐Basin 

Council District: 1 

Project Priority: Medium 

Project Status: The project is estimated for completion in year 2017 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402  $976,000  $5,000            $981,000 

Fund 403                 

Fund 404                 

Totals  $976,000  $5,000            $981,000 

 

   

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

               

Final Engineering 

               

Permitting                 

Construction                 

Construction Engineering 

               

Other    $5,000            $5,000 

Totals  $976,000  $5,000            $981,000 

Page 41: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 35 October 2016

 

Project Location 

Page 42: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 36 October 2016

Collections Improvement: Fife Heights Trunk 2022‐2025 

Project Number 13 

Project Description: The project, a 7,255 lineal foot 12” diameter line, starts at Pacific Highway at Porter Way, easterly to 70th Avenue East, then southerly along 70th Avenue East to 10th Street East, then westerly along 10th Street East to 66th Avenue East to the  intersection of 66th Avenue East and 4th Street East. The  line provides sewer service to the urban area of Fife Heights and will discharge to the existing  interceptor  in Pacific Highway.   

Sewer Service Basin: Hylebos Sub‐Basin 

Council District: 2 

Project Priority: Low 

Project Status: The project is estimated for completion in year 2025 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Fund 402                 

Fund 403              $333,000  $333,000 

Fund 404                 

Totals              $333,000  $333,000 

 

   

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Preliminary Engineering 

            $149,000  $149,000 

Final Engineering 

            $166,500 $166,500

Permitting              $16,700 $16,700

Construction               

Construction Engineering 

             

Other               

Totals              $333,000  $333,000 

Page 43: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 37 October 2016

 

Project Location 

Page 44: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 38 October 2016

Collections Renovation and Rehabilitation: Manhole Rehabilitation 2017‐ 

Project Number ‐ 14 

Project Description:  This  is  a  preservation  project  to  continue  the  repair  and  rehabilitation  of  existing manhole installations throughout the County’s sewer service area due to changing road and field conditions such as repaving, and normal wear and tear.  

Sewer Service Basin: Various Basins 

Council District: Various Districts 

Project Priority: Low 

Project Status: The project is forecasted through the year 2037 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Fund 402               

Fund 403               

Fund 404  $807,500  $234,000  $243,200  $253,000  $263,100  $273,600  $284,500  $2,358,900 

Totals  $807,500  $234,000  $243,200  $253,000  $263,100  $273,600  $284,500  $2,358,900 

    

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Preliminary Engineering 

  $6,800  $7,000  $7,300  $7,700  $8,000  $8,300  $45,100 

Final Engineering 

  $13,700  $14,200  $14,800  $15,400  $16,000  $16,600  $90,700 

Permitting    $6,800  $7,100  $7,400  $7,700  $8,000  $8,300  $45,300 

Construction    $193,000  $200,700  $208,700  $217,100  $225,700  $234,600  $1,279,800 

Construction Engineering 

    $14,200  $14,800  $15,400  $16,000  $16,700  $77,100 

Other                 

Totals  $807,500  $234,000  $243,200  $253,000  $263,100  $273,600  $284,500  $2,358,900 

Page 45: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 39 October 2016

  

            

These projects are system wide and have no associated map for individual project locations. 

        

 

 

 

Page 46: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 40 October 2016

Collections Renovation and Rehabilitation: Parkland/Brookdale Interceptor Ph 3 2020‐2025 

Project Number ‐ 15 

Project Description: The project, a 72” diameter 12,121  lineal foot  interceptor, will provide future capacity relief  for  the  interceptor  located  between  the  Brookdale  Interceptor  (Brookdale  Sub‐basin)  and  the Spanaway Loop Bypass and will follow the existing interceptor in most places but will also utilize other right‐of‐way  corridors.  The  improvement  will  serve  the  East  Basin,  Rainier  Terrace,  Frederickson, Brookdale/Golden Given Sub‐basins, as well as the Parkland Sub‐basin. 

Sewer Service Basin: Parkland/Spanaway 

Council District: 5 

Project Priority: Low 

Project Status: The project is estimated for completion in year 2025 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Fund 402                 

Fund 403          $280,200  $650,000  $6,160,750  $7,090,750 

Fund 404          $280,200  $650,000  $6,160,750  $7,090,750 

Totals          $560,000  $1,300,000  $12,321,500  $14,181,500 

    

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Preliminary Engineering 

        $560,400      $560,400 

Final Engineering 

          $1,200,000    $1,200,000 

Permitting            $100,000    $100,000 

Construction              $9,784,300  $9,784,300 

Construction Engineering 

            $2,537,200  $2,537,200 

Other                 

Totals          $560,000  $1,300,000  $12,321,500  $14,181,500 

Page 47: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 41 October 2016

 

Project Location 

Page 48: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 42 October 2016

Collections Renovation and Rehabilitation: Brown’s Point Generator Replacement 2010‐2018 

Project Number ‐ 16 

Project Description: This is a preservation project that will replace emergency generators that have come to the end of their useful life at two pump station sites in Brown’s Point.   

Sewer Service Basin: Brown’s Point Sub‐Basin 

Council District: 2 

Project Priority: Medium 

Project Status: The project is estimated for completion in year 2018 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402                 

Fund 403                 

Fund 404  $70,000  $130,000  $5,000          $205,000 

Totals  $70,000  $130,000  $5,000          $205,000 

    

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

              $25,000 

Final Engineering 

  $15,000            $15,000 

Permitting                 

Construction    $90,000            $90,000 

Construction Engineering 

  $30,000            $30,000 

Other      $5,000          $5,000 

Totals  $70,000  $130,000  $5,000          $205,000 

Page 49: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 43 October 2016

Project Location 

Project Location 

Page 50: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 44 October 2016

Collections Renovation and Rehabilitation: Sewer Line Rehabilitation 2017‐ 

Project Number ‐ 17 

Project Description: This is a preservation project to rehabilitate/repair and replace existing pipe throughout the County’s service area damaged by hydrogen sulfide gases or other factors within the collection system. 

Sewer Service Basin: Various Basins 

Council District: Various Districts 

Project Priority: Medium 

Project Status: The project is forecasted through the year 2037 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Fund 402                 

Fund 403                 

Fund 404  $807,400  $492,500  $512,300  $532,800  $554,100  $576,300  $599,400  $4,074,800 

Totals  $807,400  $492,500  $512,300  $532,800  $554,100  $576,300  $599,400  $4,074,800 

    

   

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Cumulative Project Cost 

Preliminary Engineering 

  $13,600  $14,200  $14,700  $15,400  $16,000  $16,700  $90,600 

Final Engineering 

  $20,500  $21,300  $21,300  $23,100  $24,000  $24,900  $135,000 

Permitting    $6,800  $7,100  $7,100  $7,700  $8,000  $8,600  $45,300 

Construction    $437,900  $455,500  $473,700  $492,600  $512,300  $532,500  $2,904,500 

Construction Engineering 

  $13,700  $14,200  $14,800  $15,300  $16,000  $16,700  $90,500 

Other                 

Totals  $807,400  $492,500  $512,300  $532,800  $554,100  $576,300  $599,400  $4,074,800 

Page 51: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 45 October 2016

 

 

 

 

 

 

 

 

 

 

 

These projects are system wide and have no associated 

map for individual project locations. 

 

 

 

 

 

 

 

 

Page 52: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 46 October 2016

Collections Renovation and Rehabilitation: Hidden Hills PS Rehabilitation 2015‐2018 

Project Number ‐ 18 

Project Description: This  is a preservation project  to  rehabilitate an existing pump station  in  the City of University Place within the County’s service area. 

Sewer Service Basin: University Place East Sub‐Basin 

Council District: 4 

Project Priority: High 

Project Status: The project is estimated for completion in year 2018 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402                 

Fund 403                 

Fund 404  $150,000  $1,035,000  $5,000          $1,190,000 

Totals  $150,000  $1,035,000  $5,000          $1,190,000 

      

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

$150,000              $150,000 

Final Engineering 

               

Permitting                 

Construction    $1,000,000            $1,000,000 

Construction Engineering 

  $35,000            $35,000 

Other      $5,000          $5,000 

Totals  $150,000  $1,035,000  $5,000          $1,190,000 

Page 53: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 47 October 2016

Project Location 

Page 54: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 48 October 2016

Collections Renovation and Rehabilitation: Lakewood Generator Replacement 2010‐2018 

Project Number ‐ 19 

Project  Description:  This  is  the  final  year  of  a  eight  year  preservation  project  to  replace  emergency generators at 28 pump station sites in the City of Lakewood within Utility Local Improvement District 73‐1 service area that have come to the end of their useful life.  Sewer Service Basin: Lakewood Sub‐Basin 

Council District: 3 

Project Priority: Medium 

Project Status: The project is estimated for completion in year 2018 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402                 

Fund 403                 

Fund 404  $4,501,100  $525,000  $5,000          $5,031,100 

Totals  $4,501,100  $525,000  $5,000          $5,031,100 

    

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

               

Final Engineering 

               

Permitting                 

Construction    $500,000            $500,000 

Construction Engineering 

  $25,000            $25,000 

Other  $4,501,100    $5,000          $4,506,100 

Totals  $4,501,100  $525,000  $5,000          $5,031,100 

Page 55: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 49 October 2016

Project Location 

Page 56: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 50 October 2016

Collections Renovation and Rehabilitation: Philips/Allard Pump Station 2016‐2018 

Project Number ‐ 20 

Project Description: This  is a preservation project  to  rehabilitate an existing pump station  in  the City of Lakewood within the County’s service area. 

Sewer Service Basin: Lakewood East 

Council District: 6 

Project Priority: Medium 

Project Status: The project is estimated to continue into year 2018 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402                 

Fund 403                 

Fund 404  $40,000  $305,000  $5,000          $350,000 

Totals  $40,000  $305,000  $5,000          $350,000 

     

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

               

Final Engineering 

               

Permitting                 

Construction    $280,000            $280,000 

Construction Engineering 

  $25,000            $25,000 

Other  $40,000    $5,000          $45,000 

Totals  $40,000  $305,000  $5,000          $350,000 

Page 57: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 51 October 2016

Project Location 

Page 58: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 52 October 2016

Miscellaneous Scoping and Feasibility Studies 2017‐ 

Project Number ‐ 21 

Project Description:  This  funds miscellaneous  studies  to determine  scope  and budget  for  future  Sewer Division projects. These are separate from Major Studies as were completed for the JBLM Proposal. 

Sewer Service Basin: Various Sub‐Basins 

Council District: Various Districts 

Project Priority: Low 

Project Status: The project is forecasted through the year 2037 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Fund 402  $158,100  $50,000  $50,000  $50,000  $50,000  $50,000  $50,000  $458,100 

Fund 403                 

Fund 404                 

Totals  $158,100  $50,000  $50,000  $50,000  $50,000  $50,000  $50,000  $458,100 

      

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Preliminary Engineering 

$158,100  $50,000  $50,000  $50,000  $50,000  $50,000  $50,000  $458,100

Final Engineering 

               

Permitting                 

Construction                 

Construction Engineering 

               

Other                 

Totals  $158,100  $50,000  $50,000  $50,000  $50,000  $50,000  $50,000  $458,100 

Page 59: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 53 October 2016

 

 

 

 

 

 

 

 

 

 

These are studies for future projects and have no specific area locations. 

 

 

 

 

 

 

 

 

 

 

Page 60: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 54 October 2016

WWTP and Collection System Rehabilitation and Replacement 2018‐   Project Number ‐ 22 

 Project Description:  This  funds miscellaneous  rehabilitation  and  replacement  projects  in  the Collection System. As projects are identified, monies will be reallocated from this project to fund identified projects. 

Sewer Service Basin: Chambers Creek Properties Sub‐Basin 

Council District: 4 

Project Priority: Low 

Project Status: The project is forecasted through the year 2037 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Fund 402                 

Fund 403                 

Fund 404      $200,000  $3,777,600  $4,941,600  $7,923,000  $8,371,500  $25,213,700 

Totals      $200,000  $3,777,600  $4,941,600  $7,923,000  $8,371,500  $25,213,700 

   

 

 

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Preliminary Engineering 

    $50,000  $188,900  $247,100  $396,200  $419,000  $1,301,200 

Final Engineering 

    $150,000  $377,800  $494,200  $792,300  $837,000  $2,651,300 

Permitting                 

Construction        $2,833,100  $3,706,200  $5,942,300  $6,278,500  $18,760,100 

Construction Engineering 

      $377,800  $494,100  $792,200  $837,000  $2,501,100 

Other                 

Totals      $200,000  $3,777,600  $4,941,600  $7,923,000  $8,371,500  $25,213,700 

Page 61: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 55 October 2016

            

 These projects are system wide and have no associated 

map for individual project locations.  

                

Page 62: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 56 October 2016

Operations and Maintenance Projects 2018‐2022 

Project Number ‐ 23 

Project Description: This funds miscellaneous operations, maintenance, and efficiency/optimization projects throughout the Chambers Creek Regional Wastewater Treatment Plant.

Sewer Service Basin: Chambers Creek Properties Sub‐Basin 

Council District: 4 

Project Priority: Low 

Project Status: The project is forecasted through the year 2037 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

CumulativeProject Cost 

Fund 402  $200,000    $200,000  $200,000  $200,000  $200,000  $200,000  $1,200,000 

Fund 403                 

Fund 404                 

Totals  $200,000    $200,000  $200,000  $200,000  $200,000  $200,000  $1,200,000 

    

   

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Cumulative Project Cost 

Preliminary Engineering 

               

Final Engineering 

               

Permitting                 

Construction  $200,000    $200,000  $200,000  $200,000  $200,000  $200,000  $1,200,000 

Construction Engineering 

               

Other                 

Totals  $200,000    $200,000  $200,000  $200,000  $200,000  $200,000  $1,200,000 

Page 63: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 57 October 2016

            

     

These projects are plant wide and have no associated map for individual project locations. 

               

Page 64: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 58 October 2016

Chambers Creek Properties: Pier and Moorage 2015‐2018 

Project Number ‐ 24 

Project Description: An improvement project to continue the construction of Phase 3 of the Pier Extension and Moorage project on the Chambers Creek Properties. The project  is currently funded through a 2015 State  budget  appropriation  of  $1.7  million  that  will  complete  Phase  2.  Additional  grant  and  loan opportunities are currently being investigated to secure funding for the final phase of construction. 

Sewer Service Basin: Chambers Creek Properties Sub‐Basin 

Council District: 4 

Project Priority: Low 

Project Status: The project is estimated for completion in year 2018 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402  $250,000  $1,445,000  $5,000          $1,700,000 

Fund 403                 

Fund 404                 

Totals  $250,000  $1,445,000  $5,000          $1,700,000 

 

    

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

$100,000              $100,000 

Final Engineering 

$150,000              $150,000 

Permitting                 

Construction    $1,100,000            $1,100,000 

Construction Engineering 

  $150,000            $150,000 

Other    $195,000  $5,000          $200,000 

Totals  $250,000  $1,445,000  $5,000          $1,700,000 

Page 65: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 59 October 2016

 

Project Location 

Page 66: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 60 October 2016

Chambers Creek Properties: Remedial Beach Clean‐up 2018‐2019 

Project Number ‐ 25 

Project Description: This is a maintenance project to continue the ongoing clean‐up of the Chambers Creek Properties shoreline, or to pursue additional toxics removals from the Chambers Creek Properties Regional Wastewater Treatment Plant. At this time this project is funded through the remaining $567,000 of a 2015 State budget appropriation of $2.5 million used for the removal of derelict structures including two docks, a concrete pump house and boat ramp, and an operator’s shack on the Properties shoreline. The funds are currently on hold in the state legislature. 

Sewer Service Basin: Chambers Creek Properties Sub‐Basin 

Council District: 4 

Project Priority: Low 

Project Status: The project is estimated for completion in year 2019 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402      $562,000  $5,000        $567,000 

Fund 403                 

Fund 404                 

Totals      $562,000  $5,000        $567,000 

   

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

               

Final Engineering 

               

Permitting                 

Construction                 

Construction Engineering 

               

Other      $562,000  $5,000        $567,000 

Totals      $562,000  $5,000        $567,000 

Page 67: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 61 October 2016

 

Project Location 

Page 68: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 62 October 2016

Environmental Services Building: Roof Rehabilitation 2016‐2017 

Project Number ‐ 26 

Project Description: An  improvement project  that will provide  for  the  rehabilitation of  the  roof of  the Environmental Services Building. 

Sewer Service Basin: Chambers Creek Properties 

Council District: 4 

Project Priority: High 

Project Status: The project is estimated for completion in year 2018 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402                 

Fund 403                 

Fund 404  $200,000  $870,000  $5,000          $1,075,000 

Totals  $200,000  $870,000  $5,000          $1,075,000 

    

   

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

               

Final Engineering 

               

Permitting                 

Construction    $850,000            $850,000 

Construction Engineering 

  $20,000            $20,000 

Other  $200,000    $5,000          $205,000 

Totals  $200,000  $870,000  $5,000          $1,075,000 

Page 69: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 63 October 2016

 

Project Location 

Page 70: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 64 October 2016

Environmental Services Building: Boiler Replacement 2016‐2017 

Project Number ‐ 27 

Project Description: An improvement project that will provide for the replacement of the main boilers in the Environmental Services Building. 

Sewer Service Basin: Chambers Creek Properties 

Council District: 4 

Project Priority: High 

Project Status: The project is estimated for completion in year 2017 

  

Funding Source 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Fund 402  $155,000  $5,000            $160,000 

Fund 403                 

Fund 404                 

Totals  $155,000  $5,000            $160,000 

      

Project Phase 

Prior Expenditure 

Adopted 2017 

Projected 2018 

Projected 2019 

Projected 2020 

Projected 2021 

Projected 2022 

Total Project Cost 

Preliminary Engineering 

               

Final Engineering 

               

Permitting                 

Construction                 

Construction Engineering 

$10,000              $10,000 

Other  $145,000  $5,000            $150,000 

Totals  $155,000  $5,000            $160,000 

Page 71: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 65 October 2016

 

Project Location 

Page 72: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 66 October 2016

              

                      

Page 73: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 67 October 2016

Chapter 4 

Future Projects 2023‐2037  The projects not included within the six‐year Capital Facilities portion of the Sewer Improvement Program are listed here as projects projected for the years 2023‐2037. Basic information is provided in the form of a Project Number, Name, Type, Size and Length/Size of the improvement (if applicable) and estimated Cost. These projects are also included in Section 7 ‐ Future Expansion and Improvements ‐ of the Unified Sewer Plan.  Dollar estimates are inflated for the proposed years of construction. 

Sewer Sub‐Basin: Lakewood East and West including the Town of Steilacoom 2025‐2030 The City of Lakewood, excluding the areas known as American Lake Gardens and Tillicum, is located within Utility Local Improvement District (ULID) 73‐1.  The City of  Lakewood  completed  a  sewer extension  that has  allowed both  Tillicum  and American  Lake Gardens properties to connect to the sewer system. These two areas of Lakewood contain 968 single family and  1,124 multi‐family  homes  that  in  some  cases  will  continue  to  be  served  by  both  individual  and community on‐site  sewer  systems. With  the  sewer  line extension,  these  flows began  to be  sent  to  the Chambers Creek Regional Wastewater Plant in late 2011. The total system service area is 11,041.  The Lakewood West sub‐basin includes regional facilities serving both construction infill of the Lakewood West sub‐basin as well as  facilities serving the DuPont Sub‐basin. No  improvements are proposed  in the Lakewood West sub‐basin.   

Table 4‐1  Lakewood East and West Sub Basins 

 Interceptor Pipeline 

Project #  Project Name  Type  Size  Length  Cost* 

IS99‐54  Bypass Interceptor  New Project  84”  19,000 lf  $39,657,000

IS99‐58  Tunnel Expansion Phase 1  Expansion  72”  2,532 lf  $5,289,000

Total*  $44,946,000                                                                                                                                                                                                  *Funds calculated in 2017 Dollars 

Bypass Interceptor ‐ Proposed Construction Years 2025‐2030 This project will provide relief to the southern section of the Bridgeport Interceptor as well as the Steilacoom Boulevard Interceptor and will consist of an expansion of several existing interceptors coupled with new interceptor segments. The 72” 19,000 lineal foot gravity pipeline will serve the sewer service sub‐basins to the east of Interstate‐5 as well as the existing portion of the Lakewood East Sub‐basin. The alignment will generally run from the Chambers Creek Tunnel at Bridgeport Way and 75th Street West in a southeasterly direction in 75th Street, Lakewood Drive, Steilacoom Boulevard, and Lakeview Drive to the existing Spanaway Bypass Interceptor at 111th Street SW and Lakeview Drive.  

Page 74: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 68 October 2016

Chambers Creek RWWTP Tunnel Expansion Ph1 ‐ Proposed Construction Years 2028‐2030 

The project will replace or parallel the existing WWTP tunnel’s 54” lines to provide adequate capacity for build out and will consist of an expansion of 2,532 lineal feet of existing 54” pipeline with 72” pipeline (or the equivalent parallel system to give the combined system the same hydraulic capacity as a 72”). The new line will serve the entire sewer service basin, minus the City of University Place and the City of Tacoma’s Western Slope area. The alignment will generally run from the start of the Chambers Creek Tunnel at Bridgeport Way and Meadow  Park  Road,  in  a  southeasterly  direction  in  Bridgeport  Avenue,  to  the  end  of  the  bypass interceptor at Bridgeport Avenue and 75th Street West.  

   

Page 75: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 69 October 2016

Sewer Sub‐Basin: Parkland 2027‐2034 The Parkland Sub‐basin is located in unincorporated Pierce County and consists of approximately 4,197 acres of which 67 acres is designated Rural Service Area. The Parkland Sub‐basin has four (4) proposed interceptor pipeline projects proposed for completion in years 2027 through 2034. No new services are planned within the Rural Service Area. 

Table 4‐2 Parkland Sub Basin 

 Interceptor Pipeline 

Project #  Project Name  Type  Size  Length  Cost* 

IS99‐52  West Lake Spanaway Interceptor  New  12”‐18”  12,274 lf  $4,104,000

IS10‐03  Parkland Interceptor Bypass  Bypass  42”  2,600 lf  $2,060,000

Total*  $6,164,000                                                                                                                                                                                                *Funds calculated in 2017 Dollars 

 

West Lake Spanaway Interceptor ‐ Proposed Construction Years 2027‐2030 

The project, a 12”‐ 18” diameter 12,274 lineal foot interceptor, will extend sanitary sewer service to the west side of Lake Spanaway. It will generally follow along Spanaway Loop Road from Tule Lake Road to the south end of Lake Spanaway. 

Parkland Interceptor Bypass ‐ Proposed Construction Years 2033‐2034 

The project, a 42” diameter 2,600  lineal foot  interceptor bypass, will provide future capacity relief for the existing interceptor. The bypass will extend from 141st Street and C Street to 133rd Street and serve parts of the Parkland and Spanaway basins. 

   

Page 76: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 70 October 2016

Sewer Sub‐Basin: Brookdale/Golden Given 2023‐2035 The  Brookdale/Golden  Given  Sub‐basin  is  located  in  unincorporated  Pierce  County  and  consists  of approximately 9,302 acres, of which 3,200 acres are designated as Rural Service Area. The Brookdale/Golden Given Sub‐basin has five (5) proposed interceptor pipeline projects proposed for completion in years 2023 through 2035 and one (1) pump station project proposed for year 2030. No new services are planned within the Rural Service Area. 

 Table 4‐3 

Brookdale/Golden Given Sub Basin 

Interceptor Pipeline 

Project #  Project Name  Type  Size  Length  Cost* 

IS99‐46  North Fork Trunk   New  12”‐18”  9,920 lf  $3,016,000

IS99‐56  Brookdale Trunk  New  30”  10,600 lf  $5,910,000

IS99‐62  Brookdale Interceptor   Expansion   72”  17,730 lf  $35,930,000

IS10‐04  Military Road Interceptor  New  15”‐18”  3,750 lf  $1,275,000

Total*  $46,131,000 

Force Main 

Project #  Project Name  Type  Size  Length  Cost* 

FM10‐01  Woodland PS Force Main  New  12”  16,000 lf  $3,567,000

Total*  $3,567,000                                                                                                                                                                                               *Funds calculated in 2017 Dollars 

 

North Fork Trunk ‐ Proposed Construction Years 2027‐2030 The project will provide services to a portion of the Parkland service area and will relieve future capacity restrictions  in  the Midland Trunk. The 12”‐18” diameter 9,920  lineal  foot  trunk will  run north and  south between Brookdale Road and 112th Street East generally  following 30thAvenue East  to Shady  Lane, 14th Avenue East to 120th Street East and then along Aqueduct Drive East to 112th.   The North Fork Trunk extends through a part of the Brookdale/Golden Given Sub‐Basin designated rural by the Pierce County Comprehensive Plan and connects urban growth area in the north part of the sub‐basin to the Brookdale Interceptor. New connections from rural zoned properties would not be permitted except in conformance with the policies of the Pierce County Comprehensive Plan or by direction of the Tacoma‐Pierce County Health Department.   

Brookdale Trunk Proposed Construction Years 2027‐2030 This project, a 30” diameter 10,670 lineal foot line, will provide service to the eastern part of the Parkland area and  the Woodland area of  the East Basin. The pipeline will generally  follow Waller Road between Brookdale Road and 112th Street East and will extend through a service area that is designated rural by the Pierce County Comprehensive Plan. The trunk will connect the urban growth area along SR‐512 to urban growth area on the south side of Brookdale Road. Connections of areas designated rural to the Brookdale Trunk will not be permitted except in conformance with Comprehensive Plan policies or by direction of the Tacoma‐Pierce County Health Department. 

Page 77: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 71 October 2016

Brookdale Interceptor Expansion ‐ Proposed Construction Years 2031‐2035 The project, a 72” diameter expansion of the Brookdale Interceptor, will relieve future capacity constraints in the existing 54” Brookdale Interceptor. The expansion, a parallel pipeline or replacement/ enlargement, will extend approximately 16,003 lineal feet along the same corridor as the existing Brookdale Interceptor. It will connect the East Basin Interceptor in the East Basin Sub‐basin to the Parkland/Brookdale Interceptor in the Parkland Sub‐basin. The Brookdale Interceptor expansion will serve all sub‐basins upstream, including the East Basin, Rainier Terrace, and Frederickson Sub‐basins.   

Military Road Interceptor ‐ Proposed Construction Years 2023‐2025 The project, a 15 to 18‐inch diameter, 3,750 lineal foot interceptor, follows Military Road from 32nd Avenue East to 22nd Avenue East. This project will provide sanitary sewer service between Military Road and 176th Street East.  

 Woodland Pump Station Permanent Force Main ‐ Proposed Construction Years 2029‐2031 The project, a 12” diameter 16,000 lineal foot force main, follows Woodland Avenue East north to SR‐512, then west along the southern edge of SR‐512’s right‐of‐way to Waller Road, then south on Waller Road to 112th Avenue East and then west to the future Brookdale Trunk. This project will connect the Woodland Pump Station to its permanent discharge point.    

Page 78: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 72 October 2016

Sewer Sub‐Basin: Spanaway including the City of Roy 2027‐2035 The Spanaway Sub‐basin consists of approximately 4,859 acres, of which 1,767 acres is designated as Rural Service Area and is located in unincorporated Pierce County. The Spanaway Sub‐basin has six (6) proposed trunk and  interceptor pipeline projects proposed for completion  in years 2027 through 2035 and one (1) Pump Station project proposed for years 2033‐2035. No new services are planned within the Rural Service Area.  

Table 4‐4 Spanaway Sub Basin 

 Interceptor Pipeline ‐ Spanaway Sub Basin 

Project #  Project Name  Type  Size  Length  Cost* 

IS10‐06  Spanaway Interceptor Phase 2  New  18”‐24”  11,714 lf  $10,400,000 

IS99‐48  Muck‐Kapowsin Trunk  New  15”  2,115 lf  $635,000 

IS99‐49  Elk Plain Trunk  New  12”  3,877 lf  $1,215,000 

IS99‐49  Elk Plain Force Main  New  8”  1,800 lf  $365,000 

IS99‐48  Muck‐Kapowsin Trunk  New  15”  2,115 lf  $635,000 

  Total*  $13,250,000                                                                                                                                                         

Pump Station 

Number  Pump Station Name  Type  Peak Capacity  Cost* 

FM99‐49  Elk Plain Pump Station  New  1.0MGD  $1,025,000 

Total*  $1,025,000                                                                                                                                                                                                 *Funds calculated in 2017 Dollars 

 

Spanaway Interceptor Phase 2 ‐ Proposed Construction Years 2027‐2030 The project will collect wastewater from the most southerly part of the Spanaway Sub‐basin and convey it to  the B  Street  Interceptor  via  Spanaway  Interceptor  Phase  1.  This  18”‐24”  diameter  11,714  lineal  foot interceptor  will  extend  southwest  down  the  Mountain  Highway  to  approximately  224th  Street  East.  

Muck ‐ Kapowsin Trunk ‐ Proposed Construction Years 2033‐2035 The project, a 15” diameter 2,115 lineal foot line, will provide service to a part of the Spanaway Sub‐basin that was designated rural by the Pierce County Comprehensive Plan.   This  line would not be constructed until either a sizeable number of on‐site sewer system failures occur that threaten water quality (pursuant to policies in the County Comprehensive Plan) or the area is incorporated into the County’s Urban Growth Area. The trunk will branch from the Spanaway Interceptor at 224th Street East and Mountain Highway and follow 224th Street East to approximately 35th Avenue Court East.  

Elk Plain Force Main ‐ Proposed Construction Years 2033‐2035 The project, an 8” diameter, 1,800 lineal foot force main, will provide service to the Elk Plain Trunk line and will discharge into the Muck‐Kapowsin Trunk. The force main will be constructed at the same time as the Elk Plain Trunk line. The Elk Plain Force Main is a modification of the Elk Plain Trunk project.    

Page 79: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 73 October 2016

Elk Plain Pump Station ‐ Proposed Construction Years 2033‐2035 This project  is a modification of the Elk Plain Trunk project and when completed  is expected to receive a peak flows of 1.0MGD transferring flows from the Elk Plain area through the Elk Plain Force Main to the Muck‐Kapowsin Trunk.  

Elk Plain Trunk ‐ Proposed Construction Years 2033‐2035 The  project,  a  12”  diameter,  3,877  lineal  foot  line, will  provide  service  to  the  southern  portion  of  the Chambers Creek Regional WWTP service area in the Spanaway Sub‐basin that was designated rural by the Pierce County Comprehensive Plan. The Elk Plain Trunk will drain into the Elk Plain Pump Station. Like the Muck ‐ Kapowsin Trunk, the Elk Plain Trunk would not be constructed until either a sizeable number of on‐site sewer system failures occur that threaten water quality (pursuant to policies in the County Comprehensive Plan) or when the area is incorporated into the County’s Urban Growth Area.    

Page 80: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 74 October 2016

Sewer Sub‐Basin: Spanaway ‐ City of Roy ‐ 3rd Party Funding Sewer service for the City of Roy can be accommodated within the existing collection system should the City secure funding for connection charges for the capital improvements to convey the wastewater to the Pierce County collection system. This would also require the City to complete, and have approved, a facility plan and project‐specific environmental review. The City has three proposed infrastructure projects in addition to additional planning and environmental work that must be completed prior to connection to the Pierce County sewer system.  

Table 4‐4a Spanaway Sub Basin ‐ City of Roy 

 Interceptor Pipeline 

Project #  Project Name  Type  Size  Length  Cost* 

IS99‐07  Roy Interceptor  New  15”‐36”  2,331 lf  $1,320,000 

FM99‐01  Roy Force Main  New  12”       42,663 lf  $13,590,000 

Total*  $14,910,000                                                                                                                                                        

Pump Station 

Number  Pump Station Name  Type  Peak Capacity  Cost* 

PS99‐02  Roy Pump Station  New  0.4MGD  $685,000 

Total*  $685,000                                                                                                                                                                                                   *Funds calculated in 2017 Dollars 

 

Roy Interceptor ‐ Project dependent on City of Roy Environmental Review and Funding  The proposed Roy Interceptor is estimated to be 15”‐ 36” diameter line and have a length of approximately 2,454 feet. The  interceptor will connect to the Roy Force Main to convey wastewater by gravity  into the Spanaway  Interceptor.  It would convey wastewater between  local collection  facilities and the Roy pump station. Preliminary costs for the interceptor assume 36” piping for the entire length.  

Roy Force Main ‐ Project dependent on City of Roy Environmental Review and Funding  The proposed Roy Force Main will be a 12” diameter line and extend 42,663 lineal feet and will be located generally along SR‐507, the Spanaway‐McKenna Highway. The force main will discharge into the County’s Wastewater Utility conveyance system in the Spanaway sub‐basin.  

Roy Pump Station ‐ Project dependent on City of Roy Environmental Review and Funding The proposed Roy Pump Station is expected to receive a peak flow of 0.4MGD. This station will pump flow from the City of Roy through the Roy Force Main to Pierce County Wastewater Utility conveyance system facilities in the Spanaway Sub‐basin.   

 

 

Page 81: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 75 October 2016

Sewer Sub‐Basin: Hylebos 2027‐2030 The Hylebos  Sub‐basin  is  located within  the City of  Fife,  the City of Milton,  and unincorporated Pierce County. Seven parcels of the City of Edgewood are also included in this sub‐basin. This sub‐basin consists of approximately  4,824  acres.  The  Lakehaven  Utility  District  connects  to  the  Pierce  County’s  conveyance system at Porter Way within  the City of Milton, where  it  is conveyed  to  the Tacoma Central WWTP  for treatment. The Hylebos Sub‐basin has one  (1) proposed  trunk pipeline project,  two  (2) proposed pump station projects, and one (1) force main project proposed for completion in years 2027 through 2030.  

Table 4‐5 Hylebos Sub Basin 

 Pump Stations 

Number  Pump Station Name  Type  Peak Capacity  Cost* 

PS99‐04  Hylebos 5 Pump Station  Replacement  4.5  $2,600,000 

Total*                 $2,600,000 

 

Force Main 

Project #  Project Name  Type  Size  Length  Cost* 

FM99‐03  Hylebos 5  New  18”  17,394 lf      $5,300,000    

Total*  $5,300,000                                                                                                                                                                *Funds calculated in 2017 Dollars 

 

Hylebos 5 Force Main ‐ Proposed Construction Years 2027‐2030 The project, an 18” diameter  force main, will  transmit wastewater  to Tacoma Central WWTP  from Fife Heights, Lakehaven’s East Hylebos Basin, and the City of Milton. The pressure line is estimated to extend a distance of 17,394 lineal feet from the Hylebos 5 Pump Station to Tacoma Central WWTP.  

Hylebos 5 Pump Station ‐ Proposed Construction Years 2027‐2030 This new pump station is estimated to receive future peak flows of 4.5MGD. The pump station will convey wastewater from the Fife Heights Trunk and Milton ‐ Hylebos Interceptors to the new Hylebos 5 Force Main to the Tacoma Central WWTP. This improvement coupled with the Hylebos 5 Force Main will relieve capacity in Tacoma’s Lincoln Avenue pump station and force main and provide additional conveyance capacity for future development of the service area.    

Page 82: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 76 October 2016

Sewer Sub‐Basin: Chambers Creek Properties 2033‐2035 The  Chambers  Creek  Properties  Sub‐basin  is  a  630  acre  basin  that  is  known  as  the  Chambers  Creek Properties. Within the Properties are the Chambers Bay Golf Course, Chambers Creek Regional Park, and the Chambers Creek Regional Wastewater Treatment Plant. The Sub‐Basin has four (4) proposed pipeline projects, and one (1) proposed pump station project, scheduled for completion in years 2033 through 2035.  

Table 4‐6 Chambers Creek Properties Sub Basin 

 Interceptor Pipelines 

Project #  Project Name  Type  Size  Length  Cost* 

IS99‐43  DuPont‐Lakewood Bypass  New  42”  4,800 lf  $3,796,000

IS99‐43  DuPont‐Lakewood Bypass FM  New  36”  3,000 lf  $1,825,000

Total  $5,621,000

 

Pump Station 

Number  Pump Station Name  Type  Peak Capacity  Cost* 

PS99‐13  DuPont‐Lakewood Bypass PS  New  7.0MGD  $3,100,000

Total*  $3,100,000                                                                                                                                                                       *Funds calculated in 2017 Dollars  DuPont‐Lakewood Bypass Interceptor ‐ Proposed Construction Years 2033‐2035 The project will be a 42” gravity pipeline extending 4,800 lineal feet from the corner of Steilacoom Boulevard and Farwest Road to the north edge of the Abitibi property. The Steilacoom force main will discharge into this new Interceptor at Chambers Creek Road. At its terminus, the wastewater will flow into the DuPont‐Lakewood Bypass Pump Station.  

DuPont‐Lakewood Bypass Force Main Proposed Construction Years 2033‐2035 The project will convey flows from the DuPont‐Lakewood Bypass Pump Station to its discharge point in the Chambers Creek Regional WWTP energy dissipater. The alignment will approximately  follow the existing alignment for the Town of Steilacoom’s force main.   

DuPont‐Lakewood Bypass Pump Station ‐ Proposed Construction Years 2033‐2035 This bypass pump station will be a 7.0MGD pump station located to the north of the Abitibi property. 

 

 

 

Page 83: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 77 October 2016

Chapter 5  Developer Built Infrastructure Projects 

Sewer Sub‐Basin: DuPont including Northwest Landing The City  of DuPont  is  located  in  the  southwest  corner  of  the Basin.  The Historic Village  of DuPont was connected, and flows began to be sent to the WWTP, in 2008. The City has also contracted with Pierce County to provide sewer service  to  the Northwest Landing development  (ULID 90‐4) and  in October of 2000,  the Northwest Landing Offsite Wastewater Facilities Project was completed and wastewater is now conveyed to the Chambers Creek Facility.  Pierce  County  now  provides  for  collection,  transmission,  and  treatment  for  flows  from  the Northwest Landing Development (Villages I, II, III, IV, and V), Industry, Town Center, and the Historic Village of DuPont. The system service area is 3,727 acres in total area. The DuPont Sub‐basin has four (4) developer constructed projects proposed for completion as future development requires additional infrastructure.  Developer built projects require review, construction, approval and acceptance by the Sewer Division prior to final connection to the sanitary sewer collection system.   

Table 5‐1 DuPont Sub Basin 

 Interceptor Pipeline 

Project #  Project Name  Type  Size  Length  Cost 

‐  First Park NWL Trunk  New 10”‐12”  3,440 lf  Developer Built 

‐  First Park NWL Trunk  New 4”  1,690 lf  Developer Built 

Pump Station 

Number  Pump Station Name  Type  Peak Capacity  Cost 

  First Park NWL Pump Station  New  .05MGD  Developer Built 

Total  ‐ 

 

First Park Northwest Landing Trunk ‐ Project to be completed by Developer The First Park Trunk will be a new 10”‐12” trunk line serving a commercial development. It will be constructed by a developer as development occurs in this area.   First Park Northwest Landing Force Main ‐ Project to be completed by Developer The First Park Main will be a new 4” force main connecting the First Park Pump Station to the First Park NWL Trunk line. It will be constructed by a developer as part of the pump station project.   First Park Northwest Landing Pump Station ‐ Project to be completed by Developer The First Park Pump Station will be a new 0.5MGD pump station serving a commercial development. It will be constructed by a developer before the area it serves is developed.     

Page 84: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 78 October 2016

Sewer Sub‐Basin: Cascadia (Tehaleh) All projects  in the Cascadia Sub‐basin are to serve new development within the Tehaleh Master Planned Community. As new development follows the approved master site plan Newland Communities, Tehaleh’s prime developer, will be responsible to build all sewer collection and treatment improvements.   Developer built projects require review, construction, approval, and acceptance by the Sewer Division prior to final connection to the sanitary sewer collection system.  

Table 5‐2 Cascadia (Tehaleh) Sub Basin 

 Interceptor Pipelines 

Project #  Project Name  Type  Size  Length  Cost 

‐‐  Cascadia Interceptor Extension  New  21”‐24”  6,020 lf  Developer built 

‐‐  Canyon Falls Creek Force Main  New  8”  1,470 lf  Developer built 

‐‐  Canyon Falls Creek Trunk  New  10”  2,100 lf  Developer built 

‐‐  North Cascadia Force Main  New  4”  1,400 lf  Developer built 

‐‐  North Cascadia Trunk  New  8”  1,400 lf  Developer built 

‐‐  Cascadia Golf course Force Main  New  4”  6,440 lf  Developer built 

‐‐  Cascadia Exemption Area FM  New  4”  4,270 lf  Developer built 

‐‐  Cascadia Phase 3 Force Main  New  8”  4,620 lf  Developer built 

‐‐  Cascadia Phase 3 Interceptor   New  21”‐24”  8,610 lf  Developer built 

‐‐  Cascadia Phase 2 Force Main  New  4”  980 lf  Developer built 

‐‐  Cascadia Phase 2 Interceptor  New  24”  7,000 lf  Developer built 

 

 

Pump Stations 

Number  Pump Station Name  Type  Peak Capacity  Cost 

‐‐  Cascadia Pump Station 1  New  1.4MGD  Developer built 

‐‐  Cascadia Pump Station 2  New  0.6MGD  Developer built 

‐‐  Cascadia Pump Station 3  New  0.7MGD  Developer built 

‐‐  Cascadia Pump Station 4  New  0.4MGD  Developer built 

‐‐  Cascadia Pump Station 5  New  0.5MGD  Developer built 

‐‐  Cascadia Pump Station 7  New  3.4MGD  Developer built 

 

 

Treatment Facilities 

Number  Pump Station Name  Type  Peak Capacity  Cost 

‐‐  Cascadia (Tehaleh) WWTP  New  4.3MGD  Developer built 

 

 

 

Page 85: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 79 October 2016

Chapter 6 Chambers Creek Regional Wastewater Treatment Plant 

Treatment Type The Chambers Creek Regional Wastewater Treatment Plant is an anoxic selector‐assisted activated sludge secondary  treatment  facility with primary sedimentation and anaerobic sludge digestion. The  treatment plant is rated to treat 28.7 (24.4 at 85% capacity) million gallons per day (MGD) Average Dry Weather Flow (ADWF) with discharge to the Gordon Point zone of South Puget Sound. Completion of the first phase of the WWTP Expansion Project is expected to see a plant re‐rating of 43‐45MGD.  

Expansion ‐ Phase 1 The expansion project was broken down  into  five phases with Phase 1 beginning  in 2010 with a  stated completion date of Quarter 4, 2016.  Phase 1 was further broken down  into four Construction Packages or CP. Each CP has a sub‐list of major projects within each package that was delineated in the approved Conditional Use Permit.   Construction Package Recap as of Quarter 3, 2016: 

1. Construction Package 1 ‐ Substantially complete. 2. Construction Package 2 ‐ Substantially complete. 3. Construction Package 3 ‐ On track for substantial completion by December 2016. 4. Construction Package 4 ‐ On track for substantial completion by December 2016. 

 Full completion of the Phase 1 Construction Packages are also dependent upon final plant ratings that will be undertaken in 2017.  

Expansion ‐ Phases 2‐5  All planned improvements for the WWTP Expansion Project will be undertaken and completed within the Chambers Creek Properties Sub‐basin over the approved 30 year planning and construction cycle. Phase 1 will be completed with final plant ratings and systems shakedowns scheduled for completion in first Quarter 2017. Phases 2 through 5 are as outlined in the following list of additions and modifications for the WWTP.   Total number of proposed major projects is 16, with many projects having smaller sub‐projects associated with them, these sub‐projects are not listed separately. All costs are in 2017 dollars. Following is a list of all planned and approved projects as  included  in  the 2010 Conditional Use Permit  for  the Chambers Creek Regional Wastewater Treatment Plant.  

Page 86: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 80 October 2016

WWTP Expansion Phase 2: Projected Construction Years 2023‐2027  Biological Process Phase 2 

Fermenter 

Centrate Treatment 

Utilidor Development Phase 2 

Electrical Systems Upgrades  

Reclaimed Water Facility Expansion: Projected Construction Years 2023‐2027  18MGD Reclaimed Water Production 

Groundwater Recharge Basins  

WWTP Expansion Phase 3: Projected Construction Years 2026‐2031  Primary Sedimentation Expansion 

Solids Thickening Expansion Phase 2 

Disinfection System Expansion Phase 3  

WWTP Expansion Phase 4: Projected Construction Years 2031‐2046  Digester Expansion Phase 2 

Biological Process Phase 3 

Utilidor Development Phase 3  

WWTP Expansion Phase 5: 2036‐2045  Electrical Systems Upgrades 

Fertilizer Manufacturing Facility Expansion Phase 2 

Advanced Treatment Implementation    

Page 87: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 81 October 2016

Chapter 7 Financial 

Financial Methodology The Sewer Division of Pierce County Public Works operates as an enterprise, essentially a business subsidiary of the County.  As such, the Utility must operate within a budget constrained by rate revenues, connection charges for services, and maintain adequate reserves for contingencies.    The Sewer Division uses a financial model to establish rates and connection charges to recover utility costs related  to operational  services  and  capital  facilities  that provide  sewer  service. Rates  are  set at  a  level sufficient  to  cover  current  and  future  expenses,  and  maintain  reserves  consistent  with  debt  service requirements and long‐term financial forecasts.  The model attempts to minimize the fiscal impact on the customer by assuming only enough debt to meet capital needs.  The Sewer Division attempts to change rate levels gradually and uniformly to the extent that costs (including CIP transfers) can be forecast. Local and/or national  inflation  indices, such as the Consumer Price  Index (CPI), are used as a basis for evaluating rate increases.  Costs for services are passed directly through to Pierce County sewer customers.  Each  connected property bears  an equitable  share of  the  cost of  the public  sewer  system  through  the collection of connection charges and rates for sewer service.  Connection charges are paid before a property is allowed to connect to the public sewer system, or through a Utility Local  Improvement District (ULID).  Sewer  rates  are  set  by  the  County  Council,  and  are  in  addition  to  connection  charges.  The Utility  has established classifications of customers using rate charging methods authorized by State law in the Revised Code of Washington (RCW).    Sewer rates are based on revenue requirements necessary to cover costs of the utility and are evaluated and authorized each year as part of  the adoption of  the annual budget.   The Sewer Division’s  financial strategy  for  developing  the  annual  operating  budget,  forecasting  capital  investment,  and  determining revenue projections includes a detailed analysis of the following factors:  

Utility objectives, policies, and  standards  for  level of  service, growth management, and  land use constraints. 

Debt service payments and debt service coverage/reserve requirements. 

Capital assets including infrastructure, capital equipment, resources, and water rights. 

Operations including labor and services, facilities, utilities, and supplies. 

 To ensure the Sewer Division continues to maintain a stable financial position, the capital and operating costs of the Utility are forecasted in the model through 2035.     

Page 88: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 82 October 2016

Credit Worthiness Bond ratings from Moody’s Investors Service and Standard and Poor’s indicate a high level of confidence in the ability of the Utility to repay debt obligations. While the Sewer Division functions as a part of the overall County organization within the Public Works Department, the Utility operates independently for financial reporting purposes. This enables the Utility to issue bonds at more favorable interest rates by presenting its financial resources and revenue‐generating capability as related debt security.  Bonds issued by the Utility have earned very positive evaluation of credit worthiness based on factors that include financial position, reserve levels, and debt service coverage. The Utility currently has a high grade bond rating of “Aa3” from Moody’s Investors Service and “AA” from Standard & Poor’s. Ratings at this level indicate a strong degree of confidence by the rating agency in the ability of the Sewer Division to repay related debt obligations. The Sewer Division has no immediate plans to issue additional debt. However, if this action becomes necessary, the Utility can expect a proposed bond issue to receive a similarly favorable credit rating and, therefore, to sell at lower interest rates than would otherwise be possible. 

Current Financial Status The  Sewer  Division  for  Pierce  County  Public Works  has  a  sound  financial  base  that  can  finance  the recommended  capital  improvements.  The  Sewer Division  has  adopted  financial  policies  that  guide  the stewardship  and  investment  of  funds,  use  of  debt,  system  expansion,  connection  and  cost  recovery, customer rates, and reserves for repair and rehabilitation.    Table 7‐1 summarizes actual cash‐basis revenues, expenses, and fund balances for the sewer utility for the most  recent  five‐year period.   Over  the past  five years,  the  sewer  fund balance, which  represents  total unexpended resources carried forward to future years, increased from $91 million at the beginning of 2011 to a current balance of $101 million at the end of 2015 (See Chart 7‐1).  During 2011 through 2015, a total of $534 million was spent on capital projects and service operations, including $52 million of debt service payments.  The Utility plans for, and secures a reserve balance that covers 1.25 of debt service, and which includes 90‐days of annual operating budget.     

Page 89: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 83 October 2016

Table 7‐1 Sewer Utility Fund 

Revenues, Expenses & Reserve Balances by Year 

 

Chart 7‐1 Reserve Balances by Year 

 

  

$0

$50,000,000

$100,000,000

$150,000,000

$200,000,000

$250,000,000

$300,000,000

  2011  2012  2013  2014  2015 

Beginning Reserve Balance  $ 112,148,049   $   91,122,011  $ 273,521,388  $212,558,160   $113,725,966  

Annual Revenues:           

   Sewer Charge  $  40,185,659 $   44,407,639 $  50,031,718 $  52,585,680  $  54,364,780

   Other Operating Revenue  $    5,034,157  $     7,108,676  $     4,286,121  $    3,609,212  $    3,748,920 

   Bonds Proceeds  $  $ 196,090,000 $ $  32,525,000  $  21,440,000

   Grants and Loans  $  $  $  $  $  60,000,000 

            Sub‐Total  $   45,219,816   $ 247,606,315  $   54,317,839  $  88,719,892   $139,553,700  

Annual Expenditures:           

   Capital Improvements  $   31,756,630  $   30,272,004  $   67,589,385  $ 136,337,107   $   94,212,366    Utility Internal Services  $     5,480,669 $     3,016,426 $     3,094,603 $     3,278,224  $     3,659,970   Admin. & Engineering  $   10,006,327  $   11,438,640 $   12,207,833 $   13,690,837  $   16,708,420   Maintenance & Operations 

$   16,558,928  $   17,329,868  $   18,085,646  $   18,897,918  $   20,631,910 

            Sub‐Total  $   63,802,554  $   62,056,938  $ 100,977,467  $ 172,204,086   $ 135,212,666 

Debt Service Payment  $     2,443,300   $     3,150,000   $   14,303,600  $   15,348,000   $   16,895,000  

Ending Reserve Balance  $   91,122,011   $ 273,521,388  $ 212,558,160  $ 113,725,966   $ 101,172,000 

Page 90: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 84 October 2016

Financial Outlook Table 7‐2 presents a projection of annual utility revenues, expenses, and fund balances through 2022, based on the 2016 Preliminary Forecast amounts and changes expected to occur  in various categories over the subsequent four‐year period as a result of new customers, general inflation, and other related factors. This type of  forecast  is  routinely used by utilities  in developing  rate adjustment proposals and assessing  the impact of changing budget assumptions on future rate requirements.  

Table 7‐2 Sewer Utility Fund 

Forecasted Revenues, Expenses & Reserve Balances by Year  

  2016  2017  2018  2019  2020  2021  2022 

Beginning Reserve Balance 

$101,172,000  $ 57,875,671  $ 58,535,507  $ 61,928,596  $ 55,254,092  $ 36,607,582  $ 38,219,966 

 Annual Revenues: 

             

Sewer Charges  $ 62,435,769 $ 66,299,348 $ 70,436,806 $ 74,775,017 $ 79,590,221  $ 84,471,923 $ 89,644,303 Other Operating Revenues 

$   8,740,472  $   9,809,413  $ 10,050,318  $ 10,836,652  $ 11,514,239  $ 1,179,899  $ 12,183,904 

       Grants and Loans 

$      250,000  $   1,450,000           

            Sub‐Total  $   71,426,41  $ 77,558,762  $ 80,487,124  $ 85,611,669  $ 91,104,960  $ 96,270,812  $ 101,828,207 

 Annual Expenditures: 

             

Capital Improvements 

$ 54,029,400  $ 12,315,300  $   6,038,200  $ 19,891,200  $ 35,889,800  $ 19,368,200  $ 26,057,600 

       Administration and Engineering  

$ 17,502,073  $ 20,512,340  $ 21,300,546  $ 21,862,797  $ 22,384,900  $ 22,941,600  $ 23,512,300 

Maintenance and Operations 

$ 24,982,297      $ 25,656,986  $ 27,501,688  $ 28,331,176  $ 29,159,170  $ 30,058,358  $ 30,993,839 

            Sub‐Total  $ 96,513,770  $ 58,484,626  $ 54,849,435  $ 70,085,173  $ 87,433,870  $ 72,368,128  $ 80,563,739 

Debt Service Payments 

$ 18,208,800  $ 18,414,300  $ 22,244,600  $ 22,201,000  $ 22,254,600  $ 22,290,300  $ 21,337,100 

Ending Reserve Balances 

$ 57,875,671  $ 58,535,507  $ 61,928,596  $ 55,254,092  $ 36,670,582  

$ 38,219,966  $ 38,147,334 

 

Key assumptions that were used in forecasting the future annual revenues and expenses are:  A 3.3 percent rate increase in 2017; 

System growth to increase at a rate of 2.5 percent annually; 

Connection charges to increase at a rate of 2.4 percent annually; 

Page 91: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 85 October 2016

Annual debt service costs matching bond payment tables; and 

The capital plan being consistent with the Pierce County Capital Facilities Plan (CFP). 

Funding Sources The Sewer Division receives income from a variety of sources including bi‐monthly billing from all residential, commercial, and industrial customer accounts, and connection, treatment and other fee‐based operations. The Sewer Division operates under an Enterprise Fund that is wholly based upon the rates, fees, and permit generated  income charged for the collection and treatment of wastewater throughout the Pierce County Sewer Service Area.  

Sewer Operating Fund 402 This fund is used to pay for ongoing Maintenance, Operations, and Administration of the Sewer Division. This account is the Sewer utility operating and debt reserve.  

Sewer Facility Restricted Reserve Fund 403 The fund finances construction projects that benefit its current and future customers deriving revenues from connection, area, and facility charges. Reserves in this account are for capital expansion. 

Sewer Rehabilitation and Replacement Fund 404 The Sewer Division’s Construction Fund is financed through Fund 402, and is used to account for all rehabilitation and replacement work for projects at the Chambers Creek Regional Wastewater Treatment Plant and County‐wide Collection system. The fund is financed through collected rates. 

Sewer Division Construction Fund 425 The  Sewer  Division’s  Construction  Fund  is  used  to  account  for  all  non‐Local  Improvement  District construction work and  is  financed  through  the Sewer Utility Operating Fund 402,  the Facility Restricted Reserve Fund 403, and the Sewer Rehabilitation and Replacement Fund 404. Table 7‐4 details the Project, Prior Expenditures, and which fund was charged for the work Refer to the table on the following page.

Page 92: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 86 October 2016

Proposed Fund 402 Expenditures for 2017 This Sewer Improvement Program includes expenditures for the Pierce County Sewer System and Facilities and the Chambers Creek Properties. 

Table 7‐3  Project Expenditures by Fund for 2017 

 

*Funded through a 2013 State Budget Appropriation ** Funded through a 2015 State Budget Appropriation         

  

Project Number/Description 

 Prior 

Expenditures  Proposed 

Expenditures Fund 402  Fund 403  Fund 404 

1  WWTP Expansion Phase 1  $313,157,000  $5,447,000  $5,452,000     

2  WWTP Reclaimed Water PS  $137,600         

3  WWTP Solids Handling  $45,000  $225,000  $112,500  $112,500   

4  WWTP Digester Rehab    $350,000      $350,000 

5  FMF Furnace Replacement  $125,000  $212,000  $212,000     

6  FMF Digester Gas Delivery    $173,300  $173,300     

7  B Street Interceptor Phase 3  $517,600         

8  Misc. Sewer Line Connects  $1,034,600 $150,000 $150,000

9  Upper Leach Creek Intercept          

10  Woodland PS and FM           

11  122nd Street East Interceptor          

12  Thun Field Extension  $976,000  $5,000  $5,000     

13  Fife Heights Trunk           

14  Collections Manhole Rehab  $807,500  $234,000      $234,000 

15  Parkland/Brookdale Phase 3           

16  Brown’s Point Generators  $70,000  $130,000      $130,000 

17  Sewer Line Rehabilitation  $807,500  $492,500      $492,500 

18  Hidden Hills PS Rehabilitation  $150,000  $1,035,000      $1,035,000 

19  Lakewood Generators  $4,501,100  $525,000      $525,000 

20  Philips/Allard Pump Station  $40,000  $305,000      $305,000 

21  Scoping/Feasibility Study  $158,100  $50,000  $50,000     

22  WWTP and Collection Rehab          

23  O/M Projects WWTP  $200,000    $200,000     

24  CCP Pier and Moorage**  $250,000  $1,445,000  $1,445,000     

25  CCP Beach Debris Removal*           

26  ESB Roof Rehabilitation  $200,000  $865,000      $865,000 

27  ESB Boiler Replacement  $155,000  $5,000  $5,000    $120,000 

Totals  $323,332,000  $11,648,800  $7,654,800  $262,500  $4,056,500 

Page 93: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 87 October 2016

Chapter 8 Sewer Division Public Programs 

  Over the past few years the Pierce County Council has requested that the Sewer Division  investigate and produce  various  programs with  the  goals  to  assist  both  economic  development  and  assistance  to  the individual  ratepayers  to  expand  and  improve  the  sanitary  sewer  collection  system.  The  following  four programs either have been  implemented, or  are  in  final development, with  the  guidance of  the Pierce County Council to achieve these goals.   Of  the  four  programs  three,  the  Sewer  Connection  Program,  the  Sewer  Commercial  Conservation  Loan Program, and the Impact Fee and Connection Charges Deferral Program, are active and available for use by the public. The fourth, the Sewer Residential Conservation Loan Program will undergo final program review by Council later in Quarter 4 of 2016 and, if approved by Council, will become available to the public in mid to late 2017.  

Sewer Connection Program This program was established by Council  in 2007, and has been utilized for a variety of projects both public and private. Program  funds have been distributed along a value  rating system acknowledging everything  from  acres  served  and  jobs  created,  to  economic  development  and  health  and  safety improvements. The Program has funded various large sewer line extension projects sharing installation costs with local jurisdictions. Additional information pertaining to this program is available in the 2016‐2021 Sewer Improvement Program and on the Sewer Division’s website www.co.pierce.wa.us/sewer ‐ Plans, Reports, and Publications.  

Sewer Commercial Conservation Loan Program This program has been established  to provide  loans of up  to 90% of  the estimated  total cost  for  the installation of required sewer pretreatment facilities. Funding for these projects is available up to $50,000 for a term of up to 10 years. All loans are secured by a lien against the title of the commercial real property where  the  improvement  exists  and  are  subject  to  the  Division's  terms  and  conditions.  Additional information  pertaining  to  this  program  is  available  on  the  Sewer  Division’s  website www.co.pierce.wa.us/sewer ‐ Plans, Reports, and Publications.   

Impact Fee and Connection Charges Deferral Program This program  is designed  to assist development and provide a mechanism  that defers, but does not eliminate,  fees paid  for  connection  to  the County’s  sewer  collection  system. Additional  information pertaining to this program  is available on the Sewer Division’s website www.co.pierce.wa.us/sewer  ‐ Plans, Reports, and Publications.   

Page 94: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 88 October 2016

Sewer Residential Conservation Loan Program This program, requested by the Pierce County Council, is under review as a means to assist financially burdened  rate payers with costly side sewer  repairs, and prevention of side sewer breakdowns. The program would establish requirements and financing options for property owners to inspect, maintain, repair and/or replace sewer laterals, sewer relief valves, and sewer backwater valves as necessary on properties connected to the County’s sewer system. A residential program to keep side sewers in good repair is in the best interests of the health and welfare of the citizens of Pierce County. The Division looks forward to final program approvals in Quarter 4, 2016 and enactment of the program in 2017.      

Page 95: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 89 October 2016

Appendix A ‐ Planning Commission Staff Report  Planning Commission Hearing: August 23, 2016  TO:   Pierce County Planning Commission SUBJECT:    2017‐2037 Sewer Improvement Program CONTACT:   Stefan Kamieniecki, Dana Larsen Sewer Division Senior Planners 

Pierce County Public Works ‐ Sewer Division  PROPOSAL: The 2017‐2037 Sewer  Improvement Program  is  intended  to  identify  the  scope,  timing, and funding  for  maintenance,  operation,  preservation,  improvement,  and  administrative  projects  for  the Chambers Creek Regional Wastewater Treatment Plant and Collection System throughout the 117 square mile Pierce County Sewer Service Basin over a twenty (20) year time frame.   EXHIBIT: 2017‐2037 Sewer Improvement Program.  NOTICE: Notice of this request and date of this hearing were advertised in accordance with Pierce County Code and notice of the date and time of today’s hearing was published two (2) weeks prior to the hearing in the official County newspaper.  REQUEST:  Staff  will  not  present  a  formal  staff  report  to  the  Commission  at  this  hearing,  but  a recommendation  to  the Commission  for  transmittal  to  the Pierce County Council  to approve  the Sewer Improvement Program as presented today.  BACKGROUND: The Sewer Division prepares both a six‐year Capital Facilities Plan and a fourteen‐year Sewer Improvement Program, for use by both the County Council and public‐at‐large to understand the direction for maintenance, operations, preservation,  improvement and administrative projects undertaken by  the Division over a 20‐year time frame. The Capital Facilities Plan is part of the Budget and Finance Department annual budget process.  

 With  the passage of Ordinance No. 2006‐115s  the Pierce County Council  required  the Sewer Division  to combine  the  information  found  in  the Capital Facilities Plan and a  fourteen year  forecast  to produce an annual 20‐year Sewer  Improvement Program. This program serves as a review document for the County Council, their staff members, and the public to review the scope, cost, funding, and status of near term and future planned sewer improvement projects.  STAFF RECOMMENDATION: Staff  requests  that  the Planning Commission  forward a  recommendation of approval to the Pierce County Council for the 2017‐2037 Sewer  Improvement Program as presented this day. 

    

Page 96: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Improvement Program 90 October 2016

Appendix B ‐ CFP Project Expenditures and Funding Source Each project  in the six‐year 2017‐2022 Capital Facilities Plan  is now  included as a single sheet project  in Section 3 and is also included in a spreadsheet format here in Appendix B. This format details:  

Project Name 

Project Number 

Project Description 

Sewer Service Basin 

Council District 

Project Priority 

Project Status 

Sewer Division Section   

Project Specific Spreadsheet 

New for 2017‐2037 are individual project maps for each project in the 2017‐2022 cycle reflected in Chapter 3 ‐ CFP Projects. This will provide Council, staff, and the public an easier document to review without going back and forth through the document to find information about single or multiple projects and then find a location map  to  identify where  a  specific  project  is  in  the  sewer  service  basin. While  this  information duplicates  that  found  in  the Budget and Finance  “Budget Book”  the Sewer  Improvement Program goes further to provide more detailed information pertaining to each project. 

Appendix B provides an additional tool that brings all of the materials in Section 3 together in a shortened spreadsheet format for easy reference.

Page 97: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 91 October 2016

Appendix B ‐ 2017‐2022 CFP ‐ Project Expenditures and Funding Sources Project 1 ‐ Wastewater Treatment Plant Expansion Phase 1 ‐ Expansion Project An improvement project to expand the treatment capacity of the Plant, modernize the treatment process, and rehabilitate existing systems. It is the first of five phases approved by the City of University Place in February 2010 through Conditional Use Permit CUP09‐0001. The CUP consolidated all previous land use approvals for the WWTP into one new Conditional Use Permit using a Chambers Creek WWTP Overlay in what is now zoned as residential two or R2 zone classification. Completion of all five phases is not anticipated until 2040.  Project 2 ‐ Wastewater Treatment Plant ‐ Reclaimed Water Pump Station An improvement project consisting of building a pump station, storage pond, and constructing piping to distribute reclaimed water to the irrigation system of the Chambers Creek Properties to irrigate the park features of the Chambers Creek Regional Park with the future intention of also irrigating the Chambers Bay Golf Course. Peak demands of up to 1‐2MGD in potable water savings may be realized with the availability of reclaimed water. 

 Capital Facilities Planning ‐ Sources and Uses of Funds x$1000 

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering                     

1  Final Engineering                     

  Permitting                     

Name:  Construction  $5,070.0                 $5,070.0

WWTP

 Phase 1  Construction Engineering  $382.0                 $382.0

Other     $5.0               $5.0 

Project Phase Totals  $5,452.0  $5.0              $5,452.0

Funds From 402  $5,452.0  $5.0              $5,457.0

Total Annual Spending  $5,452.0  $5.0              $5,457.0

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering                     

2  Final Engineering        $466.2           $466.2

Name:  Permitting                     

WWTP

 Reclaim

ed 

Water Pump Station   Construction           $1,958.0  $3,571.7     $5,529.7

Construction Engineering           $217.0  $369.9     $586.9

Other/End of Project                 $5.0  $5.0

Project Phase Totals        $466.2  $2,175.0  $3,941.6  $5.0  $6,587.8

Funds From 402        $307.7  $1,435.3  $2,619.3  $2.5  $4,364.8

Funds From 403        $158.5  $739.7  $1,349.3  $2.5  $2,250.0

   Total Annual Spending        $466.2  $2,175.6  $3,968.6  $5.0  $6,614.8

 

Page 98: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 92 October 2016

Project 3 ‐ Wastewater Treatment Plant ‐ Solids Handling Expansion The solids handling system will have insufficient capacity by 2020. This planning project will begin looking at options for the next phase of the solids handling process.  Project 4 ‐ Wastewater Treatment Plant ‐ Digester Rehabilitation With the completion of Phase 1 of the WWTP Expansion Project, two new digesters will come on‐line. Once the new digesters are fully operational the three existing units will be put on a regular maintenance schedule, with the all units on a five‐year rotation to undertake cleaning, inspection, and spot repairs. The three existing units will be used as storage for treated wastewater when not in use as digesters.   

Capital Facilities Planning ‐ Sources and Uses of Funds x$1000 

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering                     

3  Final Engineering  $225.0  $3,120.0              $3,345.0

Name:  Permitting        $600.0           $600.0

WWTP

 Solid

s Han

dlin

g Expan

sion   Construction        $9,082.4  $8,980.4        $18,062.8

Construction Engineering        $1,009.2  $997.8        $2,007.0

Other        $481.7  $394.1  $5.0     $880.8

Project Phase Totals  $225.0  $3,120.0  $11,173.3  $10,372.3  $5.0     $24,895.6

Funds From 402  $112.5  $1,560.0  $5,586.65  $5,186.15  $2.5     $12,447.8

Funds From 403  $112.5  $1,560.0  $5,586.65  $5,186.15  $2.5     $12,447.8

   Funds From 404                     

   Total Annual Spending  $225.0  $3,120.0  $11,173.3  $10,372.3  $5.0     $24,895.6

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering                     

4  Final Engineering                     

Name:  Permitting                     

WWTP

 Digester 

Rehab

ilitation  Construction                     

Construction Engineering                     

Other  $350.0  $255.0  $256.0  $275.0  $286.0  $297.4  $1,719.4

Project Phase Totals  $350.0  $255.0  $256.0  $275.0  $286.0  $297.4  $1,719.4

Funds From 402                     

   Funds From 403                     

   Funds From 404  $350.0  $255.0  $256.0  $275.0  $286.0  $297.4  $1,719.4

   Total Annual Spending  $350.0  $255.0  $256.0  $275.0  $286.0  $297.4  $1,719.4

Page 99: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 93 October 2016

Project 5 ‐ Wastewater Treatment Plant ‐ Fertilizer Manufacturing Facility Furnace Replacement The furnace is an essential component in the FMF, without which it cannot operate.  If inoperable, the Division is unable to produce Class A Exceptional Quality biosolids and would be required to haul and then land apply Class B biosolids using a contracted vendor, with anticipated costs of $20,000‐$25,000 per week. The recommended scope of work is to replace the furnace with a new, stainless steel furnace which will be less susceptible to corrosion than the existing steel unit. The balance of the work, estimated at $347,000, would be completed in 2017‐2018.  

Project 6 ‐ Wastewater Treatment Plant ‐ Fertilizer Manufacturing Facility Gas Delivery The Fertilizer Manufacturing Facility (FMF) was designed to utilize up to 60% digester gas that is readily available onsite through the digestion process. Utilizing this energy source has been hampered by inadequate system pressure, piping, and condensate removal, to allow the gas from the digestion system to be delivered properly. This project will install a new pressure boosting blower, install a new condensate removal system, and provide adjustments from the digesters to the FMF to allow digester gas use. This project is anticipated to save an estimated $100,000 annually on natural gas usage. 

Capital Facilities Planning ‐ Sources and Uses of Funds x$1000 

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering                     

5  Final Engineering                     

Name:  Permitting                     

FMF Furnace 

Replacement 

Construction  $35.0                 $35.0

Construction Engineering  $20.0                 $20.0

Equipment/Hauling  $162.0  $5.0              $167.0

Project Phase Totals  $217.0  $5.0              $222.0

Funds From 402  $117.0  $5.0              $122.0

   Total Annual Spending  $117.0  $5.0              $122.0

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering  $5.0                 $5.0

6  Final Engineering  $15.0                 $15.0

Name:  Permitting                   

FMF Gas Delivery  Construction  $115.0                 $115.0

Construction Engineering  $20.0                 $20.0

Other/End of Project  $18.3  $5.0              $23.3

Project Phase Totals  $173.3  $5.0              $178.3

Funds From 402  $173.3  $5.0              $178.3

   Total Annual Spending  $173.3  $5.0              $178.3

 

Page 100: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 94 October 2016

Project 7 ‐ Collections Improvement ‐ B Street Interceptor Phase 3 This project was created by the split of the B Street Interceptor Phase 2 project as identified in the 2011 Capital Facilities Plan and budget into two phases. This improvement project includes the installation of approximately 5,900 feet of 30” diameter gravity pipeline along “B” Street East and Mountain Highway from 192nd Street East to 204th Street East.  Project 8 ‐ Collections Improvement ‐ Miscellaneous Sewer Line Connections  This operations and improvement project will construct gravity collector sewer line extensions. This includes sewer improvements in conjunction with other jurisdiction’s road improvement projects. This also includes the cost of raising existing manhole rims located in road improvement projects. 

Capital Facilities Planning ‐ Sources and Uses of Funds x$1000 

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering                     

7  Final Engineering     $225.0  $225.0           $450.0

Name:  Permitting                     

B Street In

terceptor 

Phase 3  

Construction           $8,726.0  $3,675.4     $12,401.4

Construction Engineering           $969.6  $408.4     $1,378.0

Other/End of Project                 $5.0  $5.0

Project Phase Totals     $225.0  $225.0  $9,695.6  $4,083.8  $5.0  $14,234.4

Funds From 402                        

Funds From 403     $225.0  $225.0  $225.0  $9,695.6  $4,083.8  $14,229.4

   Funds From 404                     

   Total Annual Spending     $225.0  $225.0  $225.0  $9,695.6  $4,083.8  $14,229.4

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering                     

8  Final Engineering                     

Name:  Permitting                     

Miscellaneous Sewer 

Line Extensions  

Construction  $150.0  $150.0  $150.0  $150.0  $150.0  $150.0  $900.0

Construction Engineering                     

Other                     

Project Phase Totals  $150.0  $150.0  $150.0  $150.0  $150.0  $150.0  $900.0

Funds From 402                      

Funds From 403  $150.0  $150.0  $150.0  $150.0  $150.0  $150.0  $900.0

   Funds From 404                     

   Total Annual Spending  $150.0  $150.0  $150.0  $150.0  $150.0  $150.0  $900.0

 

Page 101: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 95 October 2016

Project 9 ‐ Collections Improvement ‐ Upper Leach Creek Interceptor This project will install 2,400 lineal feet of 30‐inch interceptor line in Upper Leach Creek. The interceptor will serve areas of University Place and provide sewer access to the City of Fircrest should they wish to contribute to the project.   Project 10 ‐ Collections Improvement ‐ Woodland Pump Station and Temporary Force Main This project will construction a new regional pump station and temporary force main connecting into the 112th Street East sewer line extension. The temporary force main will be replaced in 2030, when the Brookdale Interceptor is installed from Woodland Avenue to Waller Road. 

Capital Facilities Planning ‐ Sources and Uses of Funds x$1000 

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering        $156.0           $156.0

9  Final Engineering        $312.0           $312.0

Name:  Permitting        $58.7           $58.7

Upper Leach Creek 

Interceptor 

Construction           $3,534.4  $2,494.0     $6,028.4

Construction Engineering           $392.6  $272.0     $664.6

Other/End of Project                 $5.0  $5.0

Project Phase Totals        $526.7  $3,927.0  $2,766.0  $5.0  $7,224.7

Funds From 402                     

   Funds From 403        $526.7  $3,927.0  $2,766.0  $5.0  $7,224.7

   Funds From 404                     

   Total Annual Spending        $526.7  $3,927.0  $2,766.0  $5.0  $7,224.7

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering              $104.0     $104.0

10  Final Engineering              $208.0     $208.0

Name:  Permitting              $42.1     $42.1

Woodland Pump Station 

and Force Main  

Construction                 $2,452.4  $2,452.4

Construction Engineering                 $381.4  $381.4

Other                   

Project Phase Totals              $354.1  $2,833.8  $3,187.9

Funds From 402                     

Funds From 403              $354.1  $2,833.8  $3,187.9

Funds From 404                     

   Total Annual Spending              $354.1  $2,833.8  $3,187.9 

Page 102: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 96 October 2016

Project 11 ‐ Collections Improvement ‐ 122nd Avenue East Interceptor This project will install 3,000 lineal feet of 15‐inch sanitary sewer mainline east on 136th Street East to the intersection of 136th Street East and 122nd Avenue East and then south along 122nd Avenue East to the intersection of 122nd Avenue East and 144th Street East.  Project 12 ‐ Collections Improvement ‐ Thun Field Employment Center Sewer Line Extension This project will install 1,925 lineal feet of 8‐inch sanitary sewer mainline southerly from the intersection of 158th Street East on 110th Avenue East to provide sewer collection services for the approximately 914 acres of underdeveloped Employment Center parcels along the eastern side of Thun Field. These are the last EC zoned parcels available for development in Pierce County. Existing and new residential and commercial developments can also be accommodated should they wish to connect.  

Capital Facilities Planning ‐ Sources and Uses of Funds x$1000 

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering           $104.0        $104.0

11  Final Engineering           $156.0        $156.0

Name:  Permitting           $50.8        $50.8

122nd Street East 

Interceptor 

Construction              $963.1     $963.1

Construction Engineering              $102.0     $102.0

Other/End of Project                 $5.0  $5.0

Project Phase Totals           $310.8  $1,065.1  $5.0  $1,380.9

Funds From 402                     

   Funds From 403           $310.8  $1,065.1  $5.0  $1,380.9

   Funds From 404                     

   Total Annual Spending           $310.8  $1,065.1  $5.0  $1,380.9

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering                     

12  Final Engineering                     

Name:  Permitting                     

Thun Field EC 

Sewer Line 

Extension 

Construction                     

Construction Engineering                     

Other  $5.0                 $5.0 

Project Phase Totals  $5.0                 $5.0

Funds From 402  $5.0                 $5.0

   Total Annual Spending  $5.0                 $5.0

 

Page 103: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 97 October 2016

Project 13 ‐ Collections Improvement ‐ Fife Heights Trunk The project, a 7,255 lineal foot 12” diameter line, starts at Pacific Highway and Porter Way, easterly to 70th Avenue East, southerly along 70th Avenue East to 10th Street East, then westerly along 10th Street East to 66th Avenue East to the intersection of 66th Avenue East and 4th Street East. The line provides sewer service to the urban area of Fife Heights and will discharge to the existing Interceptor in Pacific Highway.    Project 14 ‐ Collections Renovation/Rehabilitation ‐ Collections Manhole Rehabilitation. This is a preservation project to continue the rehabilitation/repair and replacement of existing manhole installations throughout the County’s sewer service area due to changing road and field conditions such as repaving, and normal wear and tear.   

Capital Facilities Planning ‐ Sources and Uses of Funds x$1000 

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering                 $149.0  $149.0

13  Final Engineering                 $167.3  $167.3

Name:  Permitting                 $16.7  $16.7

Fife Heights Trunk  Construction                     

Construction Engineering                     

Other                     

Project Phase Totals                 $333.0  $333.0

Funds From 402                     

   Funds From 403                 $333.0  $333.0

   Funds From 404                     

   Total Annual Spending                 $333.0  $333.0

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering  $6.8  $7.0  $7.3  $7.7  $8.0  $8.3  $45.1

14  Final Engineering  $13.7  $14.2  $14.8  $15.4  $16.0  $16.6  $90.7

Name:  Permitting  $6.8  $7.1  $7.4  $7.7  $8.0  $8.3  $45.3

Collections Man

hole 

Rehab

ilitation 

  

Construction  $193.0  $200.7  $208.7  $217.1  $225.7  $234.6  $1,279.8

Construction Engineering     $14.2  $14.8  $15.4  $16.0  $16.7  $77.1

Other                     

Project Phase Totals  $220.3  $243.2  $253.0  $263.3  $273.7  $284.5  $1,538.0

Funds From 402                     

Funds From 403                     

   Funds From 404  $220.3  $243.2  $253.0  $263.3  $273.7  $284.5  $1,538.0

   Total Annual Spending  $220.3  $243.2  $253.0  $263.3  $273.7  $284.5  $1,538.0

Page 104: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 98 October 2016

Project 15 ‐ Collections Renovation/Rehabilitation ‐ Parkland/Brookdale Interceptor Phase 3 The project, a 12,121 lineal foot 72” diameter interceptor, will provide future capacity relief for the interceptor located between the Brookdale Interceptor (Brookdale Sub‐basin) and the Spanaway Loop Bypass and will serve the East, Rainier Terrace, Frederickson, and Brookdale/Golden Given Sub‐basins, as well as the Parkland Sub‐basin.  Project 16 ‐ Collections Renovation/Rehabilitation ‐ Brown’s Point Generators Replacement This is a preservation project that will replace emergency generators that have come to the end of their useful life at two pump station sites in Brown’s Point.   

Capital Facilities Planning ‐ Sources and Uses of Funds x$1000 

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering           $560.4        $560.4

15  Final Engineering              $1,200.0     $1,200.0

Name:  Permitting              $100.0     $100.0

Parklan

Brookdale Phase 3  Construction                 $9,784.3  $9,784.3

Construction Engineering                 $2,537.2  $2,537.2

Other                     

Project Phase Totals           $560.4  $1,300.0  $12,321.5  $14,181.9

Funds From 402                     

   Funds From 403           $280.2  $650.0  $6,160.75  $7,090.95

   Funds From 404           $280.2  $650.0  $6,160.75  $7,090.95

   Total Annual Spending           $560.4  $1,300.0  $12,321.5  $14,181.9

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering                     

16  Final Engineering  $10.0                 $10.0

Name:  Permitting                     

Browns  Point 

Generator 

Replacements 

  

Construction  $90.0                 $90.0

Construction Engineering  $30.0                 $30.0

Other/End of Project     $5.0              $5.0

Project Phase Totals  $130.0  $5.0              $135.0

Funds From 402                     

Funds From 403                     

   Funds From 404  $130.0  $5.0              $135.0

   Total Annual Spending  $130.0  $5.0              $135.0

 

Page 105: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 99 October 2016

Project 17 ‐ Collections Renovation/Rehabilitation ‐ Collections Sewer Line Rehabilitation This is a preservation project to rehabilitate/repair and replacement of existing pipe throughout the County’s service area damaged by hydrogen sulfide gases within the collection system.  Project 18 ‐ Collections Renovation/Rehabilitation ‐ Hidden Hills Pump Station Rehabilitation This is a preservation project to rehabilitate an existing pump station in the City of University Place within the County’s service area.  

Capital Facilities Planning ‐ Sources and Uses of Funds x$1000 

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering  $13.6  $14.2  $14.7  $15.4  $16.0  $16.7  $90.6

17  Final Engineering  $20.5  $21.3  $21.3  $23.1  $24.0  $24.9  $135.1

Name:  Permitting  $6.8  $7.1  $7.1  $7.7  $8.0  $8.6  $45.3

Collections Sewer 

Line Rehab

ilitation 

Construction  $437.9  $455.5  $473.7  $492.6  $512.3  $532.5  $2,904.5

Construction Engineering  $13.7  $14.2  $14.8  $15.3  $16.0  $16.7  $90.5

Other/End of Project                     

Project Phase Totals  $492.5  $512.3  $531.6  $554.1  $576.3  $599.4  $3,266.2

Funds From 402                     

   Funds From 403                     

   Funds From 404  $492.5  $512.3  $531.6  $554.1  $576.3  $599.4  $3,266.2

   Total Annual Spending  $492.5  $512.3  $531.6  $554.1  $576.3  $599.4  $3,266.2

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering                     

18  Final Engineering                     

Name:  Permitting                     

Hidden

 Hills Pump 

Station Reh

abilitation 

  

Construction  $1,000.0                 $1,000.0

Construction Engineering  $35.0                 $35.0

Other/End of Project     $5.0              $5.0

Project Phase Totals  $1,035.0  $5.0              $1,040.0

Funds From 402                     

Funds From 403                     

   Funds From 404  $1,035.0  $5.0              $1,040.0

   Total Annual Spending  $1,035.0  $5.0              $1,040.0

 

Page 106: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 100 October 2016

Project 19 ‐ Collections Renovation/Rehabilitation ‐ Lakewood Generators Replacement This is the final year of a eight year preservation project to replace emergency generators at 28 pump station sites in the City of Lakewood within Utility Local Improvement District 73‐1 service area that have come to the end of their useful life.  Project 20 ‐ Collections Renovation/Rehabilitation ‐ Philips/Alard Pump Station Rehabilitation This is a preservation project to rehabilitate an existing pump station in the City of Lakewood within the County’s service area.  

Capital Facilities Planning ‐ Sources and Uses of Funds x$1000 

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total   

Number:  Preliminary Engineering                     

19  Final Engineering                     

Name:  Permitting                     

Lakewood Generator  

Construction  $500.0                 $500.0

Construction Engineering 

$25.0                 $25.0

Other/End of Project     $5.0              $5.0

Project Phase Totals  $525.0  $5.0              $530.0

Funds From 402                     

   Funds From 403                     

   Funds From 404  $525.0  $5.0              $530.0

   Total Annual Spending  $525.0  $5.0              $530.0

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total   

Number:  Preliminary Engineering                     

20  Final Engineering                     

Name:  Permitting                     

Philips Alard  Pump 

Station 70/80 

Construction  $275.0                 $275.0

Construction Engineering 

$25.0                 $25.0

Other/End of Project     $5.0              $5.0 

Project Phase Totals  $300.0  $5.0              $305.0

Funds From 402                     

   Funds From 403                     

   Funds From 404  $300.0  $5.0              $305.0

   Total Annual Spending  $300.0  $5.0              $305.0

Page 107: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 101 October 2016

Project 21 ‐ Miscellaneous Scoping and Feasibility Studies Funds miscellaneous studies to determine scope and budget for future Sewer Division projects. These are separate from Major Studies as were completed for the JBLM Proposal.  Project 22 ‐ Wastewater Treatment Plant and Collection System Repair and Replacement Funds miscellaneous rehabilitation and replacement projects in the Collection System. As projects are identified, monies will be reallocated from this project to fund identified projects.  

Capital Facilities Planning ‐ Sources and Uses of Funds x$1000 

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering  $50.0  $50.0  $50.0  $50.0  $50.0  $50.0  $300.0

21  Final Engineering                     

Name:  Permitting                     

Miscellaneous 

Scoping an

d  

Feasibility Studies  Construction                     

Construction Engineering                     

Other                     

Project Phase Totals  $50.0  $50.0  $50.0  $50.0  $50.0  $50.0  $300.0

Funds From 402  $50.0  $50.0  $50.0  $50.0  $50.0  $50.0  $300.0

   Funds From 403                     

   Funds From 404                     

   Total Annual Spending  $50.0  $50.0  $50.0  $50.0  $50.0  $50.0  $300.0

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering     $50.0  $188.9  $247.1  $396.2  $419.0  $1,301.2

22  Final Engineering     $150.0  $377.8  $494.2  $792.3  $837.0  $2,651.3

Name:  Permitting                     

WWTP

  Collection 

System

s Rehab

ilitation  Construction        $2,833.1  $3,706.2  $5,942.3  $6,278.5  $18,760.1

Construction Engineering        $377.8  $494.1  $792.2  $837.0  $2,501.1

Other                     

Project Phase Totals     $200.0  $3,777.6  $4,941.6  $7,923.0  $8,371.5  $25,213.7 

Funds From 402                     

   Funds From 403                     

   Funds From 404     $200.0  $3,777.6  $4,941.7  $7,923.1  $8,371.5  $25,213.7

   Total Annual Spending     $200.0  $3,777.6  $4,941.7  $7,923.1  $8,371.5  $25,213.7

 

Page 108: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 102 October 2016

Project 23 ‐ Operations and Maintenance Projects Funds miscellaneous operations, maintenance, and efficiency/optimization projects throughout the Chambers Creek Regional Wastewater Treatment Plant.   Project 24 ‐ Chambers Creek Properties Pier and Moorage (Funded through State Appropriation) An improvement project to continue the construction of Phase 3 of the Pier and Moorage project on the Chambers Creek Properties. The project is currently funded through a 2015 State budget appropriation of $1.7 million that will complete Phase 3. Additional grant and loan opportunities are currently being investigated to secure funding for the final phase of construction. 

Capital Facilities Planning ‐ Sources and Uses of Funds x$1000 

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering                     

23  Final Engineering                     

Name:  Permitting                     

WWTP   Construction  $200.0  $200.0  $200.0  $200.0  $200.0  $200.0  $1,200.0

Operations an

Maintenan

ce 

Projects   

Construction Engineering 

                   

Other                     

Project Phase Totals  $200.0  $200.0  $200.0  $200.0  $200.0  $200.0  $1,200.0

Funds From 402  $200.0  $200.0  $200.0  $200.0  $200.0  $200.0  $1,200.0

Funds From 403                     

   Funds From 404                     

   Total Annual Spending  $200.0  $200.0  $200.0  $200.0  $200.0  $200.0  $1,200.0

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total 

Number:  Preliminary Engineering                     

24  Final Engineering                     

Name:  Permitting                     

CCP Pier an

Moorage 

Construction  $1,100.0                 $1,100.0

Construction Engineering 

$150.0                 $150.0

Other/End of Project  $195.0  $5.0              $200.0

Project Phase Totals  $1,445.0  $5.0              $1,450.0

Funds From 402  $1,445.0  $5.0               

   Funds From 403                     

   Funds From 404                     

   Total Annual Spending  $1,445.0  $5.0              $1,450.0

Page 109: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 103 October 2016

Project 25 ‐ Chambers Creek Properties Remedial Beach Clean‐up (Funded through State Appropriation) A maintenance project to continue the ongoing clean‐up of the Chambers Creek Properties shoreline, or to pursue additional toxics removals from the Chambers Creek Properties Regional Wastewater Treatment Plant. Currently this project is funded through the remaining $567,000 of a 2015 State budget appropriation of $2.5 million used for the removal of derelict structures including two docks, a concrete pump house and boat ramp, and an operator’s shack on the Properties shoreline. The funds are currently on hold by the state legislature.  Project 26 ‐ Environmental Services Building Roof Rehabilitation An improvement project that will provide for the rehabilitation of the roof of the Environmental Services Building.  Project 27 ‐ Environmental Services Building Boiler Replacement An improvement project that will provide for the replacement of the main boilers in the Environmental Services Building.   

Capital Facilities Planning ‐ Sources and Uses of Funds x$1000 

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total   

CCP Beach 

Clean

up  Other/End of Project     $562.0  $5.0           $567.0

Project Phase Totals     $562.0  $5.0           $567.0

    

  Funds From 402     $562.0  $5.0           $567.0

#25  Total Annual Spending     $562.0  $5.0           $567.0

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total   

ESB Roof 

Rehab

ilitation  Construction  $845.0                 $845.0

Construction Engineering  $20.0                 $20.0

Other/End of Project     $5.0              $5.0

Project Phase Totals  $865.0  $5.0              $870.0

 #26  Funds From 404  $865.0  $5.0              $870.0

   Total Annual Spending  $865.0  $5.0              $870.0

Project  Project Phase  2017  2018  2019  2020  2021  2022 

Six Year Total   

ESB Boiler 

 

Other/End of Project  $5.0                 $5.0

Project Phase Totals  $5.0                 $5.0

Funds From 402  $5.0                 $5.0

 #27  Total Annual Spending  $5.0                 $5.0

 

Page 110: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 104 October 2016

Summary  tables  of  Capital  Facilities  Plan  spending  by  Project  Phase,  by  Accounts,  and  Projected  Funding  from Funds/Loans/Grants Revenues. All sources and uses of fund dollars expressed in units to be multiplied by $1000. 

Sewer Division Spending by Project Phase 

Item  2017  2018  2019  2020  2021  2022  Six Year Total 

Preliminary Engineering  $25.4  $21.2  $178.0  $687.5  $128.0  $174.0  $1,214.1

Final Engineering  $284.2  $3,380.5  $1,039.3  $419.5  $1,448.0  $208.8  $6,780.3

Permitting  $13.6  $14.2  $673.2  $66.2  $158.1  $33.6  $958.9

Construction  $7,865.9  $806.2  $9,914.8  $15,332.5  $16,642.8  $16,829.2  $67,391.4

Construction Engineering 

$550.7  $28.4  $1,038.8  $1,638.1  $1,745.5  $3,360.4  $8,361.9

Other/End of Project  $535.3  $285.0  $737.7  $669.1  $291.0  $317.4  $2,835.5

Totals  $9,275.1  $4,535.5  $13,581.8  $18,812.9  $20,413.4  $20,923.4  $87,542.1

Sewer Division Annual Spending by Fund Account 

Fund Account  2017  2018  2019  2020  2021  2022  Six Year Total 

Fund 402  $7,554.8  $1,830.0  $6,369.35  $7,096.45  $12,567.4  $4,336.3  $40,321.3

Fund 403  $262.5  $1,935.0  $6,646.85  $10,818.85  $16,032.6  $13,573.85  $49,269.65

Fund 404  $3,917.8  $1,235.5  $4,818.2  $6,314.3  $9,709.1  $15,713.55  $41,708.45

Fund 402 CCP  $1,495.0  $562.0  $5.0        $1,500.0

Totals  $11,735.1  $5,562.5  $17,839.4  $24,229.6  $38,309.1  $33,623.7  $131,299.4

Sewer Division Project Funding from Funds/Loans/Grants/Revenues 

Funds/Loans/Grants  2017  2018  2019  2020  2021  2022  Six Year Total 

Projected 402/403/404  $46,350.7  $48,741.9  $48,907.80  $38,149.10  $15,892.50  $12,501.70  $211,110.70

Net Revenues  $11,525.0  $9,432.0  $13,217.0  $17,307.0  $20,981.0  $25,985.0  $98,447.0

Grant/Loan Funds  $1,450.0  $562.0  $5.0        $1,450.0

Funds All Sources  $59,325.7  $58,735.9  $62,129.8  $55,456.1  $36,873.5  $38,486.7  $311,007.7 

Projected Budget Expenditures 

Item  2017  2018  2019  2020  2021  2022  Six Year Total 

Debt Service  $18,414.3  $22,244.6  $22,201.0  $22,254.6  $22,290.3  $21,337.1  $128,741.9 

Operating Reserve  $11,379.2  $12,043.5  $12,218.3  $12,559.5  $12,952.0  $13,307.8  $74,460.3 

Surplus/Deficit  $29,532.2  $24,447.8  $27,710.5  $33,188.9  $1,631.2  $3,841.8  $120,352.4 

Page 111: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 105 October 2016

Appendix C ‐ Adopting Ordinance 2016‐xx    Sponsored by: Councilmember File No. Requested by: County Executive/Public Works Department

ORDINANCE NO. 2016-XX

An Ordinance of the Pierce County Council Adopting the 2017-2037 Sewer Improvement Program, Pursuant to Pierce County Ordinance 2006-115s, and the Revised Code of Washington (RCW) 36.70A.040, and 36.70.530, Finding that Each Project Contained in the Program is a Public Necessity.

Whereas, the Growth Management Act (GMA) required Pierce County to develop, adopt, and implement a Comprehensive Plan, Revised Code of Washington (RCW) 36.70A.040, and

Whereas, pursuant to Chapter 36.70A RCW, on November 29, 1994, the Pierce County Council adopted Ordinance 94-82s which enacted the Pierce County Comprehensive Plan, and

Whereas, Ordinance 2006-115s provides that the County legislative authority shall

annually adopt a revised and extended comprehensive Sewer Improvement Program for the ensuing twenty calendar years; and

Whereas, the County Council finds that the County Executive has submitted the “Pierce

County Sewer Improvement Program 2017-2037” for review and approval by the County Planning Commission, Exhibit A; and

Whereas, pursuant to RCW 36.70.530, the Pierce County Planning Commission, at its August 23rd, 2016, meeting reviewed and recommended approval of the Sewer Improvement Program to the County Council; and

Whereas, the County Council, following its consideration of the action of the Planning Commission, and all testimony presented at public hearings, finds that the Sewer Improvement Program is necessary and required, and should be adopted;

Page 112: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 106 October 2016

Now Therefore, BE IT ORDAINED by the Council of Pierce County: Section 1. The Pierce County Council hereby adopts the “Pierce County Sewer

Improvement Program 2017-2037” attached hereto as Exhibit A and incorporated herein by reference.

Section 2. The Pierce County Council finds that the improvement projects set forth in

Exhibit A are a public necessity.

PASSED this day of , 2016. ATTEST: PIERCE COUNTY COUNCIL

Pierce County, Washington

Denise D. Johnson Dan Roach Clerk of the Council Council Chair

Pat McCarthy Pierce County Executive Approved Vetoed______, this day of 2016.

Date of Publication of Notice of Public Hearing: Effective Date of Ordinance:

Page 113: Sewer Division of Public Works · 2016-08-22 · requests and questions, and sewer billing are also regarded as activities associated with the efficient operations of a system. Preservation:

Sewer Division of Public Works

Sewer Improvement Program 107 October 2016