Seven Steps to Performance Based Acquisition

Seven Steps to Performance Based Acquisition

Chris HammOperations Director

General Services Administration

GSA Training Conference

and Expo 2010

2

Seven Steps to Performance Based Acquisition

This session is sponsored by the

Federal Acquisition Institute

The primary organization providing knowledge and support to the federal civilian acquisition

workforce.

For more information about FAI, please visit our website at www.fai.gov

3

Seven Steps to Performance Based Acquisition

Topics

Introductions PBA History FAR References PBA Goals Perspectives Seven Steps Training

4

Seven Steps to Performance Based Acquisition

History 1991 – OFPP Policy Letter 91-2 (Administrator Allan Burman)

1993 – GPRA

1994 – FASA and OFPP Pilot Project for PBSC

1997 – Changed the FAR to incorporate OFPP Policy Letter 91-2 and rescinded the policy letter in 2000

2001 – Public Law 106-398, Section 821 – Added to the FAR a PBC preference

and order precedence

2004 – SARA PBC change (Section 1431 and Section 1433)

Treat certain performance-based orders and contracts as commercial items if certain conditions are met and report on these contracts and orders in FPDS

2004 published an interim rule under FAR Case 2004-004

2005 published final SARA PBA changes

*PBA formerly Performance-Based Contracting (PBC)

5

Seven Steps to Performance Based Acquisition

PBA FAR References

FAR 1.102 - Statement of Guiding Principles – highlights PM role

FAR Part 2 - Definition FAR Part 7 - Acquisition Planning FAR Part 10 - Market Research FAR Part 11 - Describing Agency Requirements FAR Part 16 - Types of Contracts FAR Part 37 - Service Contracting – recognizes use of SOO when

PWS is not suitable FAR Part 46 - Quality Assurance Requirements

6

Seven Steps to Performance Based Acquisition

PBA Goals

Fiscal Years Target Achievement Goals (eligible service contract dollars over $25,000 should be

performance-based)

Actual PBA Goal (Average Government-wide PBA Goal

achieved)

2001 10% 26%

2002 20% 34%

2003 30% 35%

2004 40% 41%

2005 40% 51%

2006 40%+ 49%

2007 45+ 45%+ approx

2008 50% TBE

7

Seven Steps to Performance Based Acquisition

Performance Based Services Acquisition

50% of all eligible services acquisitions should be PBSA

FAR Subpart 37.6 (b) Performance-based contracts for services shall include—

(1) A performance work statement (PWS); (2) Measurable performance standards (i.e., in terms of quality,

timeliness, quantity, etc.) and the method of assessing contractor performance against performance standards; and

(3) Performance incentives where appropriate. When used, the performance incentives shall correspond to the performance standards set forth in the contract (see 16.402-2).

8

Seven Steps to Performance Based Acquisition

Should Everything be Performance Based?

PBA should be used to the maximum extent practicable on eligible service contracts. Agencies are not required to use PBA on:

• Architecture and Engineering• Construction• Utility services• Services incidental to supplies• Research and Development

• Professional medical services• Tuition• Registration• Membership fees

9

Seven Steps to Performance Based Acquisition

Government Perspective

• Compliance – We have to do it• Funding – Less $ to do more work• Lower Contractor Costs – Creating better value for the taxpayer• Performance – Use of commercial best practices• Schedule – Congressional and executive mandated dates• Personnel – More work, fewer 1102s

1991 – GSA had 33,000 Acquisition Professionals, buying $150B2008 – GSA had 28,700 Acquisition Professionals, buying $560B

17% decrease is in staffing, 400% increase in volume.

PBA is hard, especially when we are overwhelmed withwork and are starting with the old SOW

10

Seven Steps to Performance Based Acquisition

Contractor Perspective

• Profitability – Companies are in business to make money first.

• Project Success – Delivering success typically results in more follow-on business

• Cash Flow – Regular payments and meeting corporate profitability is essential for publicly traded companies. Missing deliveries and failing metrics/SLAs results may lead to lower stock prices and replacement of personnel

• Personal Services – Use of PBA reduces the ability for the Government to dictate the solution

• Innovation – Increases competitor’s chances to offer a new solution and unseat an incumbent contractor

11

Seven Steps to Performance Based Acquisition

• Achieve innovative solutions from industry• Maximizes competition • Increases customer satisfaction because results are improved• Shifts the risk to the contractor• Improves contractor performance• Encourages frequent communication between the COR and the

contractor • Requires good contract management to ensure results are achieved

Why Use Performance Based?

12

Seven Steps to Performance Based Acquisition

PBA Contract Type Order of Precedence

Research Development

Government assumes

more cost riskContractor assumes

more cost risk

Production / Sustainment

Greater Performance Risk = Government Assumes More Cost Risk

Higher risk, less-defined requirements

CPFF CPFF / CPAF CPIF/CPAF

R&D Development

FPAF/FPIF/ FFP FPIF /FFPEnhancements / Production Operations &

Maintenance

Lower Risk, well-defined requirements

13

Seven Steps to Performance Based Acquisition

http://www.acquisition.gov/comp/seven_steps/index.html

12Performance-Based Acquisition©Acquisition Solutions, Inc.

Seven Steps to PBSASeven Steps to PBSA

14

Seven Steps to Performance Based Acquisition

Create an Integrated Project Team! The IPT should have your technical expert, stakeholders, financial person, and acquisition. Be sure to include contracting so that you start off on the right strategy and discuss the requirement

Start early! Get the team formed and functioning well before the procurement. Waiting until the last minute reduces your ability to increase innovation and get competition

Establish the Team

15

Seven Steps to Performance Based Acquisition

Create an Integrated Project Team! The IPT should have your technical expert, stakeholders, financial person, and acquisition. Be sure to include contracting so that you start off on the right strategy and discuss the requirement.

Interview all internal and external parties to determine the needs, desired outcome, potential solutions, obstacles. Get Buy IN!

Take notes during the meeting, send them out to everybody. Documentation takes time, but eliminates complaints and issues that may arise.

Describe the Problem that Needs Solving

16

Seven Steps to Performance Based Acquisition

Identify the elements of a good requirements document

At a minimum, include this information:

• Background to include the current state or level of performance

• Scope• Need or problem to solve• Outcomes• Performance measures• Monitoring methods for the requirement• Limitations or constraints

Consider a

Statement of

Objectives!

17

Seven Steps to Performance Based Acquisition

Requirements Documents

Writing is hard! Very few people in most organizations have the skill and interest to write good requirements. Find these people, praise them, and promote them so they can never leave.

Use Templates!

GSA has dozens of established templates for just about every type of acquisition, including Acquisition Plans, Request for Quote, Request for Proposals, Cost Estimates, and Determinations & Findings.

www.gsa.gov/fedsim Click on “Information Library”

Or email [email protected] and I’ll provide a customized set for your requirement.

18

Seven Steps to Performance Based Acquisition

Common Mistakes

Let’s start with the old statement of work”

“We really like Vendor X and can’t get along without them, so let’s just wait until it is too late and sole source it to them”

“We are unique”

“Contractor shall do X upon direction of the Government”

19

Seven Steps to Performance Based Acquisition

Conduct Market Research Contractual

Research existing contract vehicles to see if they can be used to meet your needs

There are many GWACs, MACs, and GSA Schedules out there.Generally, if you look hard enough or ask enough people, you can find somebody else has already done all of the work for you.

Technical

Research to find out possible solutions and involve your team members in market research

Research the public-sector to see what has worked for your counter-parts in other agencies

Research your industry before structuring the acquisition

20

Seven Steps to Performance Based Acquisition

Developing the PWS

• Conduct analysis – What do you really want to accomplish? What are your outcomes?

• Apply the “so-what?” test

• Capture the results of the analysis in a matrix

• Write the Statement of Objectives/Work/PWS

• Let the contractor have the opportunity to solve the problem

21

Seven Steps to Performance Based Acquisition

PBA Matrix Template

OutcomesRequiredServices

PerformanceStandards

MonitoringMethods Incentives

22

Seven Steps to Performance Based Acquisition

Using a Statement of Objectives ( SOO)

• Begin with the acquisition’s “elevator message”• Describe the scope• Write the performance objectives• Identify constraints• Develop the background• Make the final checks and balances.

A SOO can be shockingly short . . . .

23

Seven Steps to Performance Based Acquisition

Due Diligence / Industry Days

What if you don’t know what you want?

Industry Day: This is our current environment and requirement, we give a presentation to interested vendors.

Due Diligence: The Government releases a draft description of the requirement and opens up the doors to interested parties, helping each side clarify the requirement

Industry Day is good, Due Diligence is better. Both will increase the quality of your RFP and the contractor proposal.

Use FAR 15.201 -  Exchanges with industry before receipt of proposals!

24

Seven Steps to Performance Based Acquisition

Decide how to measure and manage performance

People get really wrapped up in performance measures and SLAs, but this can be made simple if you want it to be.

Think about the outcomes rather than the processes or org charts

Use the systems that you have in place

Only measure things that are meaningful, not things because you can

Bad Example: Cost Savings over IGCE

25

Seven Steps to Performance Based Acquisition

25

Good Contract Types for Measuring

“Incentive” types (CPIF / FPIP)

Firm Fixed Price (FFP) and Fixed Unit Price (FUP)

Award Fee (CPAF / FPAP)

Note: Time & Materials can have metrics, but cannot have SLAs with financial incentives

GSA FEDSIM typical PBA project with SLAs is award/incentive fee, with a few managed services that are Fixed Unit Price

26

Seven Steps to Performance Based Acquisition

26

Performance Metrics Process (Pre-Award)

Draft Incentive/Award Fee Plan and Format Evaluation Decision:

– Option 1: Specify metrics and have all vendors bid the same– Option 2: Let vendors chose metric & targets

Review requirements before release and see if tasks are sufficiently defined to create notional metrics to include as recommendations

Remember that the Government’s strongest negotiation position is pre-award

Award/ Incentive Fee Plans are unilateral before the period begins, bi-lateral during the period (if the CO allows any changes at all)

Option # 2 is harder to evaluate but better post award: Better measures, more leverage after award.

27

Seven Steps to Performance Based Acquisition

27

Performance Metrics Process (Post-Award)

Ensure Contract Award includes any contractor proposed metric and/or changes from Negotiation

Set the percentage of award fee pool that is metric based - General range from 20% to 50%. Try to increase over time - Incentive fee pool is 100% by default (Objective Measures)

Set up separate meeting from Kickoff Meeting with key stakeholders to review metrics. - Ensure that all stakeholders agree to the metrics - Set the “weight” of each metric - Make sure the metric is entirely within the control of the contractor (no mixed

responsibility) - Add further definition of the metric and all exclusions

28

Seven Steps to Performance Based Acquisition

Select the Right Contractor - Understanding the Source Selection Process

• Evaluate Risk and Associate Surveillance and Incentives to the Risk• We can’t monitor everything• Require and evaluate Contractors Quality Control Plan. Put it on

contract• Adjust the Government surveillance to the weaknesses and high risk

areas• Use award fees and incentive fees to ensure contractor attention

Best Value Process

Oral Presentation Recommended

Down Selection Procedures

Advisory Multi-Step vs. Competitive Range

29

Seven Steps to Performance Based Acquisition

Manage Performance

Conduct a post-award kick-off meeting with the ENTIRE team

Ensure all parties including the Program Manager understands contract administration roles and responsibilities

Ensure a COR/COTR is assigned to the contract

Conduct performance assessments and performance evaluations as planned and required

Manage the contract to obtain results!

30

Seven Steps to Performance Based Acquisition

Quality Assurance

37.604  Quality assurance surveillance plans. Requirements for quality assurance and quality

assurance surveillance plans are in Subpart 46.4.

The “Biggest Loser” effect – the mere act of weekly surveillance drives performance

Performance Metrics presentation at GSA EXPO

31

Seven Steps to Performance Based Acquisition

31

Metrics Measurement

Recommend use of Contractor owned automated tools If not owned by the contractor and proposed at time of award, be prepared to

pay for the tool

Some agencies have their own tools. Make sure that you can extend the license to contractors

Use an IV&V contractor to sample the data from the contractor Send the monthly results of the metrics to stakeholders so there are no surprises

when it comes time to pay the contractor

In general, contractors prefer metrics because they have control over their own destiny in terms of meeting their metrics and can obtain a very high fee amount relative to subject evaluations

32

Seven Steps to Performance Based Acquisition

Free Training

The FAI offers a FREE three-day workshop on PBA designed as a just-in-time solution for acquisition teams from various agencies.

The participants are encouraged to bring their current PBA documents and are given a chance to refine these documents in the training class.

The FREE training is offered at various locations around the country and is generally available through the Acquisition Workforce Training Fund. Students should register online at www.fai.gov.

Questions about this training should be directed to FAI student services at 703-805-2300.

33

Seven Steps to Performance Based Acquisition

More Free Training - DAU & OFPP

DAU The DAU offers a four and a half day classroom course entitled “Mission Focused

Service Acquisitions,” course number ACQ265, and two online learning modules: 1) Performance-Based Services Acquisitions, CLC 013; and 2) Work Breakdown Structure, CLM 013.

Acquisition Center of Excellence for Services Community of Practice, available at https://acc.dau.mil/ace.

OFPP Pamphlet Number 4 – Supplement to OMB Circular A-76

A Guide for Writing and Administering Performance Statements of Work for Service Contracts. OFPP literally wrote the book on PBA.

34

Seven Steps to Performance Based Acquisition

Even More Free Training: DAU Online

On-Line, Free, 24/7, Self-Paced, Continuous Learning Modules: http://clc.dau.mil/ CLC 106 COR with a Mission Focus CLC 013 Performance Based Services Acquisition CLM 013 Work Breakdown Structure CLE 003 Technical Reviews CLC 004 Market Research CLM 012 Scheduling CLC 007 Contract Source Selection Plus many more…..

COR Community of Practice: https://acc.dau.cor Connects you with training, policy, samples, community forum

35

Seven Steps to Performance Based Acquisition

35

Questions