Seven Lochs Wetland Park Consultation Report

42
The Seven Lochs Wetland Park masterplan and visioning study report on communication and stakeholder consultation

description

A draft vision and masterplan for the Seven Lochs Wetland Park was published September 2011. An initial consultation on the masterplan was undertaken between September 2011 and February 2012. This document is a report on the findings of the consultation.

Transcript of Seven Lochs Wetland Park Consultation Report

The Seven Lochs Wetland Park masterplan and visioning study

report on communication and stakeholder consultation

MCM ASSOCIATES LTD

Employer: Glasgow and Clyde Valley Green Network Partnership / International Resources and Recycling Institute Agent: Collective Architecture 26 Gallowgate Glasgow G1 5AB

Prepared by: ...............................................

Collective Architecture

Approved by: ...............................................

Scott Ferguson Project Manager

Status: Report on communication and stakeholder consultation (Stage 2)

Date: 27th February 2012

The Seven Lochs Wetland Park masterplan and visioning study

report on communication and stakeholder consultation

THE SEVEN LOCHS WETLAND PARK

The draft Seven Lochs Wetland Park vision and masterplan was approved by Glasgow City and North Lanarkshire councils for wider communication and stakeholder consultation in September 2011.

The communication and consultation process was undertaken through the continued partnership of the Glasgow and Clyde Valley Green Network Partnership (GCVGNP) and International Resources and Recycling Institute (IRRI) as part of the INTERREG IVC Sigma for Water project.

Glasgow City and North Lanarkshire councils and other members of the Gartloch Gartcosh Strategic Delivery Partnership (SDP) advised on the approach to communication and consultation.

This consultation and stakeholder engagement process is part of the development of a broader, long-term communication and engagement plan for the Wetland Park as a whole. This will be developed by the Gartloch Gartcosh Green Network Development

partnership with the SDP and others.

engagement process will inform and support the development of a funding strategy and grant applications to support the implementation of masterplan proposals.

The work was funded by Sigma for Water and the Central Scotland Green Network Development Fund.

Introduction

THE SEVEN LOCHS WETLAND PARK

Contents

p 06

p 18

p 30

01 The consultation process - Consulting the community, landowners, businesses and local authorities.

02 Results of the consultation - Findings from the consultation and changes to the masterplan.

03 Next steps

04 Appendix 1 - Revisions to the masterplan. Alterations and additions to the masterplan as a result of the consultation process.

p 34

Consulting the community, landowners, businesses and local authoritiesWetlands and new housing at Gartcosh

01

THE CONSULTATION PROCESS

The consultation process - Consulting the community, landowners, businesses & local authorities01

06/07

Consulting the community, landowners, businesses and local authorities

The draft report

01

THE CONSULTATION PROCESS

Objectives, Approach and Timescale 08/09

Objectives

1. Communication- Ensure good internal communication within all SDP members, and secure their commitment to the vision and masterplan proposals.- Undertake stakeholder mapping to identify key audiences for further communication and engagement on the draft vision and masterplan.

stakeholder organisations and community groups.- Identify opportunities for, and approaches to, on-going communication with key stakeholders.

2. Consultation- Gather community and stakeholder feedback on the draft vision and masterplan, focussing on delivery partners and community groups in and around the Wetland Park.- Identify opportunities to work in partnership with organisations in the public, private and third sectors to support the development and delivery of masterplan proposals.

Approach and timescale

- Collective Architecture (Project Architect and Architectural Assistant)

- Communication of the vision and masterplan proposals to key audiences through articles, publications, presentations and meetings.

feedback on the draft vision and masterplan, and seek opportunities for new partnership working.

In undertaking these activities the Project Team sought to use existing networks, events and activities to support the communication and consultation process.

The formal consultation process ran from the 3rd October 2011 to the 20th February 2012, although further meetings and presentations have taken place to enable continued communication and dialogue with stakeholders. While the masterplan sets an overall vision and strategy for the Wetland Park, it will continue to develop, both in terms of its scope and detail, as the Park itself develops.

This report outlines the approach to communication and consultation and sets out the

Consulting the community, landowners, businesses and local authorities

Stakeholder mapping - community and interest groups Stakeholder mapping - SDP and Agencies

01

THE CONSULTATION PROCESS

Communicating the vision and masterplan10/11

Stakeholder mappingWhile some stakeholders were involved in developing the draft vision and masterplan, the timescale for this did not allow for detailed consultation with community groups and delivery bodies working in the area. Some groups were aware of the proposal for a new Wetland Park, but few had been directly involved in discussing the masterplan proposals.

- SDP members- Community groups and networks in and around the Park- Delivery organisations – public, private and third sector – working in and around the Park- Elected politicians

Stakeholder mapping, based on these audiences, was split into ‘community and interest groups’ and ‘local government and agencies’ and was used to identify the key groups and organisations to be included in the consultation. Stakeholders were then prioritised

for the communication and consultation.

Contacts databaseDrawing on the stakeholder mapping, the GCV Green Network Partnership contacts database, and information from SDP members, a contacts database was developed. This has been updated throughout the consultation period and now includes over 150

- Housing Associations- Local Authorities / Community Planning- Politicians / Councillors - Health / Community Health- Community Councils- Community groups- Landowners- NGOs- Agencies

The database will be maintained as an important resource for on-going communication.

During October and November emails highlighting the publication of the draft vision and masterplan, the consultation process, and providing relevant weblinks and information about events and presentations, were sent out using the contacts database.

Communication of the Wetland Park vision and masterplan was also linked to a follow up questionnaire on the Bishop’s Estate Access Project (BEAP) being undertaken by contractors on behalf of Forestry Commission Scotland. In October 2011 a questionnaire, including information about the Wetland Park vision and masterplan and contact details for more information, was sent out to 25 contacts who had taken part in a previous consultation on the BEAP.

Consulting the community, landowners, businesses and local authorities

The consultation website

01

THE CONSULTATION PROCESS

Communicating the vision and masterplan 12/13

Consultation Website

http://www.gcvgreennetwork.gov.uk/seven-lochs-wetland-park/masterplan-consultation.html

Although the full draft masterplan was available to download from the GCV Green Network website from the beginning of September 2011, the size of the document made

Alienation Digital was commissioned in October 2011 to develop a dedicated Seven

- Introduce the consultation process;- Make the draft masterplan available for download by chapter;- Provide online and downloadable feedback forms based on key questions for each chapter;- Provide dates, venues and contact details for consultation events.

The consultation website was launched on the 8th November 2011. As well as the features noted above, the site also included a video describing the Wetland Park vision, a ‘virtual tour’ of the Wetland Park area, and links to the Gartloch Gartcosh Green Network pages on the main GCV Green Network partnership website.

As there was a delay in launching the website the deadline for comments was extended to the 20th February 2012, to allow a full 12 weeks (excluding 2 weeks over Christmas/New Year) for the consultation.

Following the consultation the website will be revised and further developed to establish the site as an ‘interim’ Seven Lochs Wetland Park website. This will be an important route for on-going communication, providing detailed information about the masterplan proposals and current activities, and allowing people to register for regular updates.

Elected representativesAll ward Councillors and Conveners of the council committees which approved the masterplan for consultation were contacted by email. Constituency MPs and MSPs, and list MSPs for Glasgow were also contacted by email. The message highlighted the draft vision and masterplan, provided links to the consultation website, and offered a presentation on the Wetland Park to council Area Committees, Community Councils or other local community networks.

Full hard copies of the draft masterplan were provided to Councillors, community councils and other community representatives on request.

LandownersOne key group of stakeholders was landowners and tenants within the proposed park boundary. A land ownership contact database and GIS database has been developed

- Information from North Lanarkshire and Glasgow City Councils’ Land and Property Gazeteer;- Contact information from the National Farmers Union Scotland; - A title search through Registers of Scotland.

owners/tenants of agricultural land within the proposed park boundary. Full hard copies of the draft masterplan were sent to landowners on request.

Some gaps in land ownership / title information remain within the proposed boundary. Further research will be undertaken to identify and contact landowners.

Newsletters and mediaThe vision and masterplan consultation and associated events were also promoted through newsletters and partner publications. Information was included in internal bulletins in Glasgow City and North Lanarkshire councils, and in North Lanarkshire News.Communication at this stage primarily focussed on organisations and community networks and communication to the wider public was not a high priority. However, where opportunities arose, information on the vision and masterplan consultation was included in local publications.

Consulting the community, landowners, businesses and local authorities

Illustrative overview of the 9 presentation boards used in consultations

Proposed LNR Boundary

Open WaterIsland

Island

Gartloch Pool - proposed LNR

Sluice

01

THE CONSULTATION PROCESS

14/15

Meetings and presentationsThe project team met with, and where required gave presentations to, a number of key stakeholder groups. A short powerpoint presentation on the Wetland Park and the masterplan proposals was prepared. This aimed to communicate the main elements of the vision and masterplan, encourage discussion, and highlight opportunities to provide more detailed feedback. Meetings / presentations included;

- Metropolitan Glasgow Strategic Drainage Partnership (MGSDP) technical group.- Glasgow East Health Network.- Central Scotland Forest Trust North Lanarkshire Forum.- N.E. Area Committee (Glasgow City).

steering group).- Glasgow City and North Lanarkshire Ranger Services.- Voluntary Action North Lanarkshire – Coatbridge local area network.- Glasgow East Arts Company.- Glasgow Building Preservation Trust / Friends of Provan Hall.- BTCV Scotland / Glasgow Life.- The Waterways Trust.- Friends of Glasgow’s Local Nature Reserves.

- Friends of Provan Hall.- Glenboig Neighbourhood House.

Consultation events and workshopsConsultation events and workshops were used to allow a wider range of stakeholders

- Drop in workshop at Gartcosh Community Centre.- Workshop linked to Christmas Fair at Glenboig Community Centre.- Lunchtime seminars at Blairtummock House (Easterhouse) and at 229 George St (Glasgow City Council).

The project team felt that formal presentation was not the best way to communicate the plan at these events, and that a more interactive approach was needed. A series of A0 boards were prepared to present a summary of the masterplan – drawing mainly on the maps and diagrams – and raise key consultation questions for each chapter.

The boards linked to information on the consultation website, with two boards showing the proposed extent of the park and the overall masterplan, and seven boards summarising chapters 2 – 8 of the masterplan. People attending events were encouraged to respond to the questions using ‘post it’ notes. A3 copies of each chapter of the masterplan allowed people to read the plan in more detail.

Feedback booklets, summarising the chapters and giving the key consultation questions and spaces for responses, were developed and distributed at workshops and events. The design for these drew on the draft masterplan and consultation website to ensure a clear link between the various communication products. Full copies of the masterplan were provided on request.

Stakeholder consultation and discussion

Consulting the community, landowners, businesses and local authorities

Community consultation, Glenboig Community Centre, December 2011 - comments from participants

Community consultation, Glenboig Community Centre, December 2011

01

THE CONSULTATION PROCESS

16/17

Lunchtime seminar at Glasgow City Council Planning

Site visits

- Site visit with Aileen Campbell MSP (then Minister for Local Government and Planning), Central Scotland Green Network, Forestry Commission Scotland and SNH.Further site visits are planned with key stakeholders to look in more detail at issues raised in the consultation.

Community councilsAll active Community Councils in and around the Wetland Park were contacted with information about the consultation, and offering a presentation. To date the following have been visited;

- Gartloch Community Council (Glasgow City)- Stepps Community Council (North Lanarkshire)- Coatbridge Community Forum (North Lanarkshire)

The Coatbridge Community Forum has now established a sub-group to work with us to identify further action along the route of the Monklands Canal. A further presentation is planned with the Northern Corridor Community Forum (also North Lanarkshire).

Feedback booklet

Findings from the consultation and changes to the masterplanRailway at Gartcosh from A752

02

RESULTS OF THE CONSULTATION

Results of the consultationFindings from the consultation and changes to the masterplan.02

18/19

Findings from the consultation and changes to the masterplan

The process of revising the masterplan document

02

RESULTS OF THE CONSULTATION

20/21

Introduction

generated very useful feedback, including new information to be incorporated into the vision and masterplan. The consultation provided an opportunity to talk to stakeholders about the proposed Wetland Park in more detail, and helped identify opportunities for

others to further develop and implement the masterplan proposals.

The vision and masterplan was discussed with representatives from over 30 organisations and over 100 people attended consultation events. Over the consultation period the Seven Lochs Wetland Park webpage received over 750 hits. The number of visits to the

from 70 in August / September to 380 in October and November, with the Wetland Park video viewed almost 60 times. In total 15 online forms were submitted. Further written

- SEPA.- MGSDP.- Friend’s of Glasgow’s LNRs.- North Lanarkshire Greenspace Development.- Central Scotland Forrest Trust.

Consultation Findings

Further Consultation RequiredWhile the level of participation in the consultation has generally been good, there are a number of key stakeholder groups where communication and engagement effort is still needed;- Community groups and networks – particularly in Glasgow City.- Landowners.

Further work over the coming months will target these groups.

The following sections outline the main consultation feedback for each chapter. A detailed summary of comments is given in the appendix. Notes from consultation events, on-line submissions and written comments available from GCV Green Network partnership.

Findings from the consultation and changes to the masterplan

GeneralOverall consultees were positive about the vision and masterplan proposals. The potential to create a new outdoor attraction based around the seven lochs was recognised by public sector and voluntary organisations working in the area, and by groups representing communities living in and around the proposed park area.

The visual elements and maps within the document were appreciated as they helped set out the vision and proposals clearly. Consultees felt that the balance between the different elements of the plan, i.e. habitat enhancement, access and engagement and development, were well balanced. Some restructuring of the plan to help highlight the overall vision and strategy was suggested.

Chapter 1 - ApproachA number of respondents highlighted the need to update the policies and strategies

- Update references to GCV Strategic Development Plan and Local Development Plans for both GCC and NLC- Include Final Core Path Plans for GCC and NLC

Chapter 2 - Context The scale of the project, both in terms of the size of the proposed park and the scale of ambition were noted, and many respondents felt the case for the Wetland Park was strong. The level of ambition was generally welcomed, although this was often linked to a question on where the resources to deliver a project of this scale will come from. An observation made by some stakeholders was that while the vision and masterplan presents ‘what’ the wetland park vision is, it does not set out ‘how’ this will be realised.

The need to update this section to link to the publication of the Gartloch Garcosh Hydrological Study and Surface Water Management Strategy was noted. More generally

particularly because the area is the headwaters for a number of burns that then drain through existing communities. A number of important water bodies and waterways need to be added to masterplan maps.

The consultation has highlighted the need for a clearer link to local and Scottish

- Badger.- Overwintering wildfowl – Graylag geese, Widgeon, Whooper swan.

Historical maps of the area could be included in this section. Further heritage features

- Crannog at Bishop Loch.

- Mining – i.e. Cardowan Colliery.

02

RESULTS OF THE CONSULTATION

22/23

Chapter 3 - Constraints and OpportunitiesMost comments on this chapter focussed on development within the Wetland Park. The need for very careful assessment of the impact of development, and clear guidance for development of GCAs, was noted. Careful consideration as to how developments are linked to the park was highlighted as crucial to ensuring that development engages positively with the park to enhance habitats, access networks and the wider landscape. Plans should ensure areas of development are clearly shown. Respondents also noted a need to manage ‘stalled spaces’ within and around the Wetland Park, i.e. Gartloch Hospital and sites in Easterhouse.

Some respondents questioned the inclusion of Gartloch Farm as a housing site as it is currently stalled. However, GCC noted that this proposal is ‘minded to grant’ subject to the signing of a Section 75 Agreement. Any revised proposal would be expected to comply with updated policy guidance.

Some respondents felt the potential impact of the Easterhouse Regeneration Route on the Park should be more thoroughly examined in the plan. More broadly there is a need to draw more information about proposals in / around the Wetland Park from local plan maps in Glasgow and North Lanarkshire.

Other respondents noted the need to work with landowners to implement the masterplan. The plan to highlight priorities for working with landowners, or (if the opportunity arises) where land should be brought into public ownership. Changes to land ownership as a result of current and planned development, could be examined in more detail.

Many comments noted the good transport infrastructure around the Wetland Park and the opportunity this offers. Additional and proposed new railway stations should be included on the maps, as should Sustrans routes.

Fragmentation and loss of habitat was also highlighted. Habitat Network opportunities mapping – for wetland, grassland and woodland - should be included in this section. The link between habitat management and expansion and wider ecosystem services was also noted. In particular the opportunity to look at the wider, downstream impacts of wetland habitat management, particularly where this links to wider government priorities

an opportunity to work with SEPA and the Metropolitan Glasgow Strategic Drainage Partnership on this.

Chapter 4 - The VisionThe vision was generally supported, with no comments suggesting this should be revised. Some further precedents, such as Dams to Darnley Country Park, were noted.

- More species rich grassland.- Wetland opportunities east of M73.- Woodland / grassland network through wood pasture.- Additional hedgerows associated with development proposals and access networks.

Chapter 5 - Accessing the ParkThe opportunity to update this section with more information about access in and around the park was noted by a number of respondents. This included updating the

designated Rights of Way, and making reference to ‘access for all’. The proposed routes

- Route from Bishop Loch to Drumpellier via Lochwood Farm.- Route north from Commonhead Moss to Lochwood Rd.- Off-road link from Glenboig to Drumpellier Country Park.- Link to Gadloch through Stepps.

and wider access networks, i.e. cycle paths around Coatbridge, path network around Stepps.

Proposals for gateways were generally supported, although developing and sustaining seven individual gateways was questioned by a number of respondents. The need for some gateways to include ‘Wetland Park staff’ to help people engage positively with the Wetland Park was noted. The proposed new visitor gateway at Provan Hall / Auchinlea Park was the focus for most comments. While a new facility here was generally welcomed, some concerns were raised over the extent to which planned development will cut this area off from the rest of the Wetland Park.

Findings from the consultation and changes to the masterplan

The process of revising the masterplan map

02

RESULTS OF THE CONSULTATION

24/25

Chapter 6 - Engaging with the parkThe proposal for cluster areas was welcomed, although a number of responses suggested greater overlap between clusters to avoid issues of territorialism.

Chapter 7 – Community growthMost of the comments on development and the CGAs were made in chapter 03 – constraints and opportunities. Further, more detailed comments relating to development

- Use of sustainable building methods and materials- Reference to the Surface Water Management Strategy report and the requirement for Sustainable Urban Drainage Systems (SuDS) to be included.- The need for development within the Wetland Park to include affordable housing and a mix of tenures, although GCC noted that they have no affordable housing requirement as part of the CGA programme.- Opportunity for Easterhouse South CGA to create a new water feature along the route of Monklands canal.

Chapter 8 – Implementation and action planMost comments relating to this section focussed on the need for the vision and masterplan to be linked to a clear development Plan or Business Plan and funding strategy for the Wetland Park. The vision and masterplan sets out an ambitious and wide ranging programme, but some respondents noted a gap between the vision and the ‘means to realise this on the ground’.

Masterplan Proposals MapThe consultation has highlighted a number of areas to be removed from the proposed area of the Wetland Park, and a number of suggestions for further areas to be included. The exclusions were all minor, and relate to areas which have been, or are being, developed. Some of the suggestions for areas that could be included are more substantial. They

- All the CGAs around Gartcosh and Glenboig, including land between the two settlements and land along the Bothlin Burn to Garncaval Quarry.- Land north of Townhead to the North and East of Drumpellier Country Park.- Land along the Monklands canal to Blairbridge.

- Incorporate more information from local plan maps.- Include more areas of current and proposed wetland habitat.- Include other access points to the park, particularly where associated with public transport.- Include further opportunities for locations for activity within the proposed park, i.e. mountain biking, access to water.

Findings from the consultation and changes to the masterplan

The process of revising the masterplan document

02

RESULTS OF THE CONSULTATION

26/27

Introduction

and workshops, whilst the second meeting looked at written feedback and responses submitted online.

This section sets out those issues / comments raised in the consultation that require further discussion with the Gartloch Gartcosh Strategic Delivery Partnership, and with other delivery partners. Amendments and updates agreed by the Project Team are listed in the appendix.

Issues to discuss with SDP

Park boundary

park boundary.

Development proposals

was concern in the consultation that this was underplayed in the masterplan – particularly with regard to the Easterhouse Regeneration Route and the development at Gartloch Farm. Also, the GCC Main Issues Report Spatial Regeneration map also indicates that further land within / around the Wetland Park could be released for housing.

The SDP and GCV Green Network Partnership need to consider;- Further information to be included in the masterplan to demonstrate how the impact of development on the Wetland Park vision will be minimised – particularly with regard to impacts on habitat networks.- Whether any development is incompatible with the vision;- The extent to which any further development could be accommodated within the Wetland Park.

Revision of the Masterplan

Approach to implementing the vision and masterplanWhile the scope and scale of the vision was recognised and welcomed by respondents, a number also noted a ‘gap between the vision…. and the means to realise this’. Some stakeholders felt that the vision and masterplan needed to provide more information about how the masterplan proposals would be resourced and implemented. It should be noted that a Development Report which examined the structures and funding strategy to support delivery was prepared alongside the vision and masterplan, but was not included

1. The SDP felt that further ‘internal’ discussion was needed on the approach to developing the park.

‘what’ was proposed rather that how it would be implemented.

Feedback from stakeholders on the need for a clear approach to developing the Park should be taken into account by the SDP and GCV Green Network Partnership in

- Aim for a 20 year implementation strategy with partner commitment to this.- Need to make a stronger link to stand alone Business plan.- Opportunities to develop social enterprise to support delivery should be explored.- Need a clear framework to develop community involvement and active participation.

Unless the strategy for developing the park addresses these issues a number of consultees felt that the sustainability of the park was at risk.

Findings from the consultation and changes to the masterplan

Provan Hall gateway

Park – a multi-million pound project part funded through developer contributions. If successful, the new centre will play a major role in the development of the Wetland Park. Similarly, the development of the Wetland Park is a major factor in the success of the new visitor centre.

However, the regeneration of the park and the development of the new visitor centre has to date been led by the Bishop’s Estate Steering Group, and will be taken forward through the creation of a Community Trust that will take responsibility for Auchinlea Park, Provan Hall and the proposed Wetland Park Gateway Centre, and which will operate separately from the Wetland Park. In addition a number of developments, including the Easterhouse Regeneration Route are planned between Auchinlea Park and the ‘wetland core’ of the Wetland Park. Consultation comments also highlighted the extent to which the footprint of these developments risks separating the proposed Gateway Centre ‘physically’ from the wetlands. There is limited scope for environmental enhancement / wetland creation within and around Auchinlea Park, and some consultees questioned the ‘wetland’ visitor offer that could therefore be made there.

- The risk that proposed gateway at Provan Hall could become separated – both strategically and physically – from the Wetland Park, and actions required to minimise these risks.- What is required to ensure close co-ordination of the Provan Hall and Wetland Park projects.

Bishop’s Estate Access Project Alongside the consultation on the Wetland Park vision and masterplan, Forestry Commission Scotland (FCS) undertook stakeholder questionnaires / interviews to review the Bishop’s Estate Access Project (BEAP). The Review Report notes that awareness of the Wetland Park was mixed, but that there was overwhelming agreement from stakeholders that the BEAP and Wetland Park projects should be ‘merged or better co-ordinated’.

- Consider how plans for the woodlands within the BEAP, and other managed sites, are merged with the Wetland Park masterplan;- Examine how delivery of the Wetland Park and BEAP projects can be better coordinated

02

RESULTS OF THE CONSULTATION

28/29

Issues to discuss with other partners

LandownersA number of respondents highlighted the need to work with landowners to develop and implement the vision and masterplan. Over half of the Wetland Park is privately owned, and while some of the proposals made in the masterplan focus on publicly owned land, many will require the co-operation and support of private landowners. Land ownership in the area is a mix of marginal agriculture, leisure activities (i.e. horse riding) and development aspiration.

and habitat protection / management, and issues linked to poor (or no) land management, are addressed. Engagement of landowners with the consultation was poor, and further work is needed to investigate;- Opportunities for leisure activities / business development within the Wetland Park.- Opportunities to work in partnership with landowners on applications to the Scottish Rural Development Programme, both for land management and business development.

Further work is underway to identify and contact all landowners within the Wetland

opportunities the creation of the Wetland Park can create.

SEPA / MGSDPThe consultation has emphasised the importance of sustainable water management and

Surface Water Management Strategy developed alongside the vision and masterplan provides a lot of detailed information which can be referred to in the masterplan, they

has highlighted that there is an opportunity to also look at the role that surface water and

risk further down the catchments. This links to wider objectives of the MGSDP and Scottish Government. Both SEPA and MGSDP have indicated a willingness to work with Wetland Park partners to investigate these issues in more detail.

Community CouncilsDiscussions with Community Councils in Coatbridge, Stepps and Gartloch, and with Glenboig Neighbourhood House, all highlighted the importance of local access to people. At all of these meetings opportunities to enhance and expand path networks were raised. Given this interest there may be scope for the Wetland Park to lead / co-ordinate a project working with Community councils and other access NGOs – i.e. Sustrans / Paths for All / Scottish Ramblers - on a project to further develop access networks. This would need to be linked to the work with landowners noted above.

Glenboig Neighbourhood HouseGlenboig Neighbourhood House (GNH) runs a wide range of activities that aims to meet the needs of the community as a whole. They were very closely involved in developing the Glenboig Village Park, which includes Garnqueen Loch, helping to secure almost £450,000 to regenerate the park. They regularly run activities at Gartcosh LNR. Since 2009 they have been working on a project to establish a Life Centre adjacent to Garnqueen Loch. The Life Centre will provide space for community events and educational activities, and will include a café / restaurant. Plans for the centre have been drawn up, and business planning and fundraising is underway.

The Life Centre could be an important gateway to the Wetland Park, providing a hub for a range of activities to encourage people to get involved in the park through, for example, volunteering, education and training programmes. As at Provan Hall / Auchinlea Park there is a need to look at how to ensure close co-ordination of the Glenboig Life Centre and Wetland Park projects.

British Waterways / Waterways TrustThe consultation highlighted an opportunity to work with the Waterways Trust on the

Wetland Park with the centre of Coatbridge, Summerlee Heritage Centre and Coatbridge Sunnyside railway station.

A number of respondents suggested a more ambitious project to investigate the feasibility of creating a new water body along route of the old Monklands canal – extending the currently open section westwards. This could be linked to the Easterhouse South CGA, the southern boundary of which follows the line of the canal.

Discussion and ActionsExisting residential area from proposed gateway at Stepps

03

NEXT STEPS

Next stepsFurther discussion and action for the development of the masterplan03

30/31

Discussion and Actions

The process of revising the masterplan map

03

NEXT STEPS

32/33Next Steps

- Undertake further consultation and engagement with landowners.- Undertake further consultation and engagement with community groups in / around the proposed park – including a mapping workshop.- Work with SEPA / MGSDP to examine opportunities for the Wetland Park to reduce

- Finalise the Wetland Park vision and masterplan in partnership with the SDP and Collective Architecture, and present to council committees in GCC and NLC.

and masterplan being taken to council committees in September / October 2012.

Discussion and ActionsMonklands Canal - Coatbridge

04

APPENDIX

Appendix - Revisions to the masterplanAlterations and additions to the masterplan as a result of the

consultation process.

04

34/35

Revisions to the masterplan

Further to the completion of the consultation events and presentations, two meetings were held between Glasgow and Clyde Valley Green Network Partnership and Collective

feedback from the consultation events, whilst the second meeting was concerned with written feedback and website response.

This appendix summarises the changes which the Glasgow and Clyde Valley Green

the two meetings, an A0 masterplan map was overmarked to indicate the proposed changes.

Revisions to the masterplan as a result of the consultation process

04

APPENDIX

36/37

General - Re-order report to show vision chapter at start of report. To be discussed in more detail with GCVGNP.- Update all diagrams to show potential revisions to boundary and potential changes to the shape and size of the clusters.- Highlight more strongly issues to do with fragmentation, as a result of the proposed

for less mobile species. - Highlight need for sensitive design for housing with CGAs.- Highlight opportunity at Gartcosh Business centre for an amenity and positive relationship with business. - Highlight opportunity for temporary greening of business centre site. - Include context of local development plan - Main Issues Report.- Include road and rail as existing landscape restrictions.- Consider views of water from main access gateway into park from Glasgow as essential. This may therefore challenge the proposal for Provan Hall to be a gateway and / or will challenge the proposal of CGAs around it. - Refer to latest Provan Hall study by Moffat group.

Burn. - State that the buildings built as part of the Wetland Park should be sustainable. - Consider the design of access routes to minimise disturbance to wildlife. - Note that it is envisaged that the park will work in partnership with private landowners through funding schemes and initiatives.- Consider inclusion of overnight accommodation - within existing buildings including possibility of youth hostel accommodation for visiting groups.- Consider the inclusion of adrenalin type activities.- Emphasise opportunities for green credentials of proposed new buildings and structures.

Chapter 1 - Approach

green network.- Update North Lanarkshire Local Plan Executive Summary 2009, will be adopted by the

- Update Glasgow City Plan 2009, replace with Main Issues Report for Glasgow -

Strategic Development Plan.- Update Glasgow and North Lanarkshire Draft Core Path Plans, may be adopted by the time the masterplan report is published.

Chapter 2 - Context - Revisit Sustrans route potential links from park into these. Page 16

Loch. Page 20

- Show crannogs at Bishop Loch and Lochend Loch.- Refer to Bishop’s Palace but do not show its location- Add additional two pages with incorporation of historical maps (weblink from GCVGNP).

- Include additional 2 pages to expand this section.

carried out by Aecom. Include version of catchment diagram 4.2 from Aecom.- Note that the ditch under Avenue End road takes some of the water away from

- Show Burginsholme Burn to Coatbridge area (part of Monkland Canal).

- Draw in information from the hydrological report / study by AECOM to emphasize the role that the area plays in the hydrological cycle not just locally ,but also on large swathes of North Glasgow including East Dunbartonshire.

and MGSDP objectives, but also help to deliver Scottish Government objective, including protecting communities at risk of climate change impact.- Add reference to an issue which emerged from the Mouchel report - during the 1 in 200

Bothlin Burn, coalesced into a single body of water and started to drain southwards via

- Add new section on climate change adaptation and mitigation.

Revisions to the masterplan

- The Scottish Government through the Flood Risk Management Act is also encouraging

waterbodies and this could provide real and substantial improvement to downstream

- Refer to improvements being undertaken by The Waterways Trust Scotland along the route of the Monklands Canal.

- Note Scottish bluebell as British Blue bell.- Add further references to LBAPs (local biodiversity action plans).

Chapter 3 - Constraints and opportunities

- Update text to give more emphasis to the ERR. GCVGNP to discuss text relating to ERR and the detrimental effect this will have on the park with GCC.- Refer also to need to manage stalled spaces within the boundary of the park e.g

- Extend text to include reference to the management of the CGA sites within the park and need to ensure these are zoned for development with development guidelines strictly set down before these areas are developed.- Include the development of future developer guidance for the CGAs.- Include more of the proposed development to be developed under the remit / boundary of the wetland park.

- Add Coatbridge Central and Blairhill and proposed Millerston / Robroyston railway stations to railway diagram. Page 40

- Update landownership.- Revise landownership map to include information from registers of Scotland.- Include section examining opportunities / aspirations to bring more land into public ownership linked to development proposals.

- Update diagram to highlight public areas between proposed CGAs.- Note the need to work in partnership with private landowners through management

agreements / funding schemes for positive management.- Include better graphic representation of how and why CGAs are to be integrated.- Make reference to Main Issues Report.

- Add text from GCVGNP about fragmentation and loss of habitat due to ERR. This needs to be discussed in more depth with SDP.- Include new two page spread to show Local Development Plan proposals within / around the Wetland Park

- Include IHN map showing expansion opportunities of woodland habitat as well. However, note that wetland and grassland are the priority in the core of the area. - Update Community Growth Areas. GCVGNP to provide IHN information in relation to this.

Chapter 4 - The vision

- Replace Kielder Water precedent with Dams to Darnley Country Park.- Add reference to London Wetlands which is a created site.

Pages 66 & 67 - Integrated Habitat Network future opportunities- Add information related to woodland habitat to be supplied by GCVGNP.

04

APPENDIX

38/39

Chapter 5 - Accessing the Park

- Note that gateway buildings could / should be staffed by those who positively engage people with the Wetland Park.- Note that the Provanhall visitor facility is being funded by the expansion of The Fort. - Note the concern as to how the visitor facility is related to the park as the entrance to the park at this location is being compressed by housing developments.

- Revise to show adopted core paths (currently only proposed but should be adopted by the time the report is complete).- Add rights of way. Could be incorporated into corepaths or shown as separate map.

- Remove reference to cyclists and horses. Make all paths accessible to all. Pages 84 & 85

- Drumpellier to Coatbridge and Summerlee. Note that British Waterways intend to open the gates under the bridge at the end of the park during the day time for increased connectivity. - Show Drumpellier viewing platform.- Include cycle route from town centre.

- Highlight the preference for sustainable mixed tenure housing including affordable housing.- Encourage SUDs. Management of surface water at the onset of any core developments should be encouraged.

Chapter 6 -Engaging with the park- Make additional reference to Provanhall visitor centre within the report. Pages 104 & 105.

- Revise clusters to new overlapping variant.- Refer to Bishop’s Palace within section that relates to Provan hall (cluster 3) and Bishop Loch (cluster 4).

- Add text relating to Blairbridge and Drumpellier viewing platform by British Waterways, and aspirational connection across Monklands canal.- Add text relating to the Gartcosh Business Interchange and the opportunities the park affords this development in terms of amenity, and also increased footfall to park. Chapter 7 - Community Growth- Note water feature to form edge of allotments along route of Monklands canal. Also note Tollcross Burn. Page 128

- Note that all buildings constructed within the boundary of the park should aim to be sustainable including housing and visitor facilities.- Include North Lanarkshire concept statement for CGAs and supplementary planning guidance notes that NLC are currently developing.- Emphasise the placement / management of surface water at the onset and at the core of the CGAs. This should be highlighted as demonstrated in Aecom’s surface water management strategy report.- Ensure that text clearly shows the careful rational regarding how the CGA’s are to be linked into the park. If the CGA’s go ahead, their inclusion within the park should ensure that they engage positively with the park in terms of safeguarding the existing ecology, wildlife, habitat access, water management on the site and include opportunities for mixed tenure.- Consider impact locally for each development. Developer contributions may form an appendix that looks at the development approach.

Chapter 8 - Implementation and action plan- Make reference to possible inclusion of the provision of overnight accommodation within the park. Page 139.- Remove reference to paths exclusively for cyclists or horses. Page 140.- Action Plan - GCVGNP to revise to emphasise stronger link to stand alone business plan. Page 151.

Revisions to the masterplan

New housing adjacent to proposed connection below railway line at Gartcosh

04

APPENDIX

40/41Changes to masterplan map as a result of the consultation process

1. Show new school at Coatbridge which is in the boundary of the park.2. Show Drumpellier golf course (private) adjacent to the park to the north east.3. Label and show British Waterways new platform at the end of the Monklands Canal.4. Highlight and label the Monklands Canal route on the plan.5. Show Monklands Canal extending outwith the boundary of the park.6. Culverted Tollcross Burn to the left of the Monklands Canal should be shown in the hydrology section water diagram.7. Indicate West Maryston wood as being an area ideal for mountain biking.8. Change land designation to bog at the western end of Easterhouse as shown on the SINC designation diagram.9. Show alternative primary route on plan, which will be in place until all land acquisition issues have been resolved.10. Highlight Easterhouse Regeneration Route to make it obvious on plan (to match the way the M73 is indicated).

14. Show proposed Millerston railway station on map.15. Highlight route between park and Millerston station as a more important green route.16. Indicate additional entry point at junction of park and green route to Millerston station.17. Show an additional secondary route along Lochend Road between proposed Easterhouse northern CGA and Lochend Farm.18. Indicate Lochwood Farm on the plan. This has been offered up for sale to Glasgow City Council and could form an interpretation visitor facility related to the remains of the Bishop’s Palace.19. Show the Bishop’s Palace on the map.20. This land will become GCC owned and is related to proposed North Easterhouse. CGA. Show this area as an extension to Commonhead Moss.21. Item no 35 in key should be labelled as Coatbridge Golf Course which is municipal.22. Highlight the ruins of the distillery as a potential visitor attraction.23. Show secondary route connection into new area of housing and proposed new area of housing to east of Stepps.

the quarry on the map.

27. Show aspirational wind turbine locations to east of M73 below Drumpellier park as highlighted in GCC main issues report and to the south of the Fort.28. Show Bargeddie church on plan as this is a landmark and highlight in report with image within historical section.29. Label the Tollcross Burn on the map.30. Show an aspirational link across railway line back into Drumpeller Park - British Waterways are carrying out works to Monklands Canal to the north of Drumpelier Golf club. 31. Show additional planted bridge labelled 30 to the end of Lochend Road, leading across into road between Lochend and Woodend Lochs.32. As per community consultation comments, show Lochend Road as a secondary route, with small link to Bishop Palace site.33. Add new east-west route that has been included in SRDP application. 34. Update map to show boundary of Strathclyde University (to be forwarded by GCVGNP).35. Show cycling route to Kirkintilloch.36. Show entry point to park at proposed Millerston / Robroyston Station. Possible developer contributions for route from CGA to park.37. Show entry point at Muirhead. 38. Show route from Glenboig to Drumpellier.39. Show Coatbridge cycle path.40. Show Coatbridge Central railway station.41. New school to edge of park at Townhead to be included and shown within park boundary. 42. Consider routes to be lit within park from school to surrounding community, particularly to south.