SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary...

51
SERTP - 1 st Quarter Meeting First RPSG Meeting & Interactive Training Session March 20 th , 2019 Charlotte, NC 1 2019 SERTP

Transcript of SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary...

Page 1: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

SERTP - 1st Quarter Meeting

First RPSG Meeting & Interactive Training Session

March 20th, 2019

Charlotte, NC

1

2019 SERTP

Page 2: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Process Information

• The SERTP process is a transmission planning process.

• Please contact the respective transmission provider for questions related to real-time operations or Open Access Transmission Tariff (OATT) transmission service.

• SERTP Website Address:– www.southeasternrtp.com

2

2019 SERTP

Page 3: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Agenda

• 2019 SERTP Process Overview

• Form the “RPSG”– Regional Planning Stakeholders Group– Committee Structure & Requirements

• Economic Planning Studies– Review Requested Sensitivities for 2019– RPSG to Select up to Five Economic Planning Studies

• Interactive Training Session– Inverter Based Generation – Connection Standards

• Miscellaneous– Public Policy Requirement Stakeholder Requests

• Next Meeting Activities

3

2019 SERTP

Page 4: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

2019 SERTP Process Overview

SERTP

4

2019 SERTP

Page 5: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Southeastern Regional Transmission Planning (SERTP)

5

SERTP Sponsors

2019 SERTP

Page 6: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Upcoming 2019 SERTP Process

• SERTP 1st Quarter – 1st RPSG Meeting & Interactive Training Session

March 2019– Form RPSG– Select Economic Planning Studies– Interactive Training Session

• SERTP 2nd Quarter – Preliminary Expansion Plan Meeting

June 2019– Review Modeling Assumptions– Preliminary 10 Year Expansion Plan– Stakeholder Input & Feedback Regarding the Plan

6

2019 SERTP

Page 7: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Upcoming 2019 SERTP Process

• SERTP 3rd Quarter – 2nd RPSG Meeting

September 2019– Preliminary Results of the Economic Studies– Stakeholder Input & Feedback Regarding the Study Results– Discuss Previous Stakeholder Input on the Expansion Plan

• SERTP 4th Quarter – Annual Transmission Planning Summit & Input Assumptions

December 2019– Final Results of the Economic Studies– Regional Transmission Plan– Regional Analyses– Stakeholder Input on the 2020 Transmission Model Input Assumptions

7

2019 SERTP

Page 8: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Regional Planning Stakeholder Group (RPSG)

SERTP

8

2019 SERTP

Page 9: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

The SERTP Stakeholder Group

• RPSG – Regional Planning Stakeholder Group

• Serves Two Primary Purposes

1) The RPSG is charged with determining and proposing up to five (5) Economic Planning Studies on an annual basis

2) The RPSG serves as stakeholder representatives for the eight (8) industry sectors in interactions with the SERTP Sponsors

9

2019 SERTP

Page 10: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

RPSG Committee Structure

RPSG Sector Representation

1. Transmission Owners / Operators

2. Transmission Service Customers

3. Cooperative Utilities

4. Municipal Utilities

5. Power Marketers

6. Generation Owner / Developers

7. Independent System Operators (ISOs) / Regional Transmission Operators (RTOs)

8. Demand Side Management / Demand Side Response

10

2019 SERTP

Page 11: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

RPSG Committee Structure

• Sector Representation Requirements

– Maximum of two (2) representatives per sector

– Maximum of sixteen (16) total sector members

– A single company, and all of its affiliates, subsidiaries, and parent company, is limited to participating in a single sector

11

2019 SERTP

Page 12: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

RPSG Committee Structure

• Annual Reformation

– Reformed annually at 1st Quarter Meeting

– Sector members elected for a term of approximately one year

– Term ends at start of following year’s 1st Quarter SERTP Meeting

– Sector Members shall be elected by the Stakeholders present at the 1st Quarter Meeting

– Sector Members may serve consecutive, one-year terms if elected

– No limit on the number of terms that a Sector Member may serve

12

2019 SERTP

Page 13: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

RPSG Committee Structure

• Simple Majority Voting

– RPSG decision-making that will be recognized by the Transmission Provider for purposes of Attachment K shall be those authorized by a simple majority vote by then-current Sector Members

– Voting by written proxy is allowed

13

2019 SERTP

Page 15: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Economic Planning Studies

SERTP

15

2018 Economic Planning Studies2019 Economic Planning Studies

Page 16: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

SERTP Regional Models

• SERTP Sponsors developed 12 coordinated regional models*

• Models include the latest load forecasts and resource decisions as provided by Load Serving Entities (LSEs) within the SERTP region

* Will be available on the secure area of the SERTP website upon satisfying access requirements

16

2019 Economic Planning Studies

No. Season Year

1

SUMMER

2020

2 2022

3 2024

4 2025

5 2027

6 2029

7

SHOULDER

2022

8 2024

9 2027

10 2029

11WINTER

2024

12 2029

Page 17: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Economic Planning Study Process

• SERTP Sponsors identify the transmission requirements needed to move large amounts of power above and beyond existing long-term, firm transmission service commitments

– Analysis is consistent with NERC standards and company-specific planning criteria

• These studies represent analyses of hypothetical scenarios requested by the stakeholders and do not represent an actual transmission need or commitment to build

• Scoping Meeting typically held in April/May

17

2019 Economic Planning Studies

Page 18: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Economic Planning Study Process

• 2018 Economic Planning Studies

• 2019 Economic Planning Study Requests

• Vote on 2019 Economic Planning Studies

18

2019 Economic Planning Studies

Page 19: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Interactive Training Session

Inverter Based Generation – Connection Standards

Manish PatelSouthern Company Services, Transmission Planning

SERTP

19

2018 Interactive Training Session2019 SERTP

Page 20: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Process Information

• The SERTP process is a transmission planning process.

• Please contact the respective transmission provider for questions related to real-time operations or Open Access Transmission Tariff (OATT) transmission service.

• SERTP Website Address:– www.southeasternrtp.com

20

Interactive Training

Page 21: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Presentation Outline

• Penetration in SERTP

• Interconnection Configurations & GSU Connections

• Anti-Islanding Policy

• Ride-through Requirements – Voltage & Frequency

• SCR Calculation – Voltage Stability/Inrush Stability

• Power Quality Policy

• Response to a three phase fault

• IEEE P2800 project

• OASIS Website – Additional Information

Interactive Training

Page 22: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Penetration Level

• Existing utility scale IBRs (Transmission ICs)– SERTP: ~3170 MW

• Future: – 2021: ~5940 MW

Interactive Training

SERTP

Page 23: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Interconnection Configuration – Express Feeder

Substation C

CNetwork

System

Substation D

DNetwork

System

Solar PV

Substation A

A G

Load

Substation BPOI

Utility

Solar

B Load

Load

• System Voltage ≤ 46kV

• GSU HS Winding:• Delta (preferred)

Interactive Training

*Southern Company common practice

Page 24: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Interconnection Configuration – Line TapSubstation C

CNetwork

System

Substation D

DNetwork

System

Utility

Solar

B

Solar PV

Substation A

A G

LoadLoad

Substation B

POI

• System Voltage ≤ 115kV

• New Single Breaker station at POI.

• GSU HS Winding:• Delta (preferred)• Y-grounded (Delta LS)

Interactive Training

*Southern Company common practice

Page 25: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Interconnection Configuration – Ring Bus

Solar PV

Substation A

Substation D

Substation B

So

lar

Utility

B3

B1

B2

D

A

Substation C

C

Network

System

Network

System

POI G

• Installed Capacity ≥ 50MW

• System Voltage 115kV and 230kV

• GSU Winding Configurations:• Y-grounded on HS and Delta on LS• Y-grounded on HS and LS with buried delta tertiary

Interactive Training

*Southern Company common practice

Page 26: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Multiple Interconnections – Starting Point

Interactive Training

*Southern Company common practice

Page 27: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Multiple Interconnections – Optional configuration #1

Interactive Training

When IC#1 is in notice to proceed

*Southern Company common practice

Page 28: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Multiple Interconnections – Optional configuration #2

Interactive Training

When IC#1 is in notice to proceed

*Southern Company common practice

Page 29: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Anti-Islanding Policy (Before 2017)

• Policy: Sustained island for an N-1 Contingency is not allowed. – Islanded generator may not be able to control voltage and frequency within

acceptable limits.

– Safety concerns for utility personal working in the area.

• With solar generators:– Is anti-islanding protection needed?

➢ Yes: But why?

– Line commutated or self commutated inverters.

– Inverters with ride-through & grid support capabilities.

– Multiple sites supporting each other.

➢ When should anti-islanding protection be required?

➢ How to protect for islanding?

➢ Communication based DTT

Interactive Training

Page 30: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Anti-Islanding Policy• Policy

– Anti-islanding protection is required, if MDTL< 2 X Total Generation capacity.

– Applies to all generation connected directly totransmission, even at distribution voltage.

G20

MW

Total MDTL = 30 MW

Anti-islanding protection is required

46kV bus

115 or 230kV system

Margin

0

10

20

30

40

50

60

70

80

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

Summer

Winter

Fall

Spring

MW

s

20 MW solar gen

Hours (mid-night to mid-night)

Interactive Training

Page 31: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Is anti-islanding protection needed here?

Solar PV

Substation A

Substation D

Substation B

So

larU

tility

B3

B1

B2

D

A

Substation C

C

Network

System

Network

System

POI G

• System Voltage 115kV and 230kV

Tapped Load

Tapped Load

Interactive Training

Page 32: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Anti-Islanding Policy (Now)• Policy - sustained island for an N-2 contingency is not allowed.

– Anti-islanding protection isrequired, if MDTL < 2 X TotalGeneration Capacity.

– Anti-islanding protection isrequired, if GenerationCapacity < 2 X Max. Load.

Condition # 1

Can we add another condition to allow exclusion?

No – because of variable natureof the generation.

Interactive Training

Page 33: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Variable Nature of the Generation

MW Output

Interactive Training

Page 34: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Voltage Ride-Through Requirement

• IBRs are expected to stayconnected and operate normallyduring and following a three-phase fault with clearing not toexceed 9 cycles.

• Momentary Cessation is notallowed.

• Emphasize on “May Trip Zone”

• P/Q priority control settings:– Operate in Q-priority mode – optimize its

available MVA rating to produce more Qduring LV condition.

Interactive Training

Page 35: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Frequency Ride-Through Requirement

• IBRs shall remain connected to the system during frequency excursion events.

• Momentary Cessation is not allowed.

• Emphasize on “May Trip Zone”.

• Frequency Response/Regulation– IBRs shall have the capability to provide

primary frequency response for over-frequency events.

– Droop: adjustable with default value of 5%. – Deadband: adjustable with a value not to

exceed +/- 36mHz.

Interactive Training

Page 36: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Voltage Control Stability

• Voltage Control Stability - Example

G20MW

46kV bus

230kV bus

Momentary Cessation

Generation ramping up

~ 1 second 6Hz voltage swing

~ 1 second

Vo

ltag

e (

kV)

Interactive Training

Page 37: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Short Circuit Ratio Calculation – Before 2019

• The GO must design its facility to reliably operate for the Short Circuit Ratio (SCR) provided in the study report.

• The generating facility shall be designed to reliably manage both – steady state voltage regulation

– Provide support when during transient voltage deviations.

• Too conservative when there are multiple interconnections electrically close to each other.

SCR =𝑇ℎ𝑟𝑒𝑒 − 𝑃ℎ𝑎𝑠𝑒 𝑆𝐶 𝑀𝑉𝐴@ 𝑃𝑂𝐼

𝑀𝑎𝑥 𝑟𝑎𝑡𝑒𝑑 𝑀𝑊 𝑜𝑢𝑡𝑝𝑢𝑡 𝑜𝑓 𝑡ℎ𝑒 𝑓𝑎𝑐𝑖𝑙𝑖𝑡𝑦

Interactive Training

Page 38: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Short Circuit Ratio Calculation – 2019 onwards

• Evaluated GE’s Composite and ERCOT’s Weighted Short Circuit Ratio calculation methods.

– Composite SCR: calculated on low side of the GSU

– WSCR: calculated at the POI.

• Adopted WSCR as it offers a correct technical representation of a group of interconnecting facilities to evaluate against the system strength at the POI.

• The GO must design its facility to reliably operate for the Short Circuit Ratio (SCR) of 2.0 or higher.

• If WSCR < 2.0, assign delivery related transmission capital projects designed to maintain relative system strength OR impose delivery limits

– Capital projects may include:

• New transmission elements

• Adding synchronous machines or condensers

Interactive Training

Page 39: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Transformer Inrush Performance

• Transformer Inrush - Example

Interactive Training

Page 40: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Transformer Inrush Performance

• Transformer Inrush - Example

Interactive Training

Page 41: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Power Quality Policy

• All IBRs shall comply with company’s Power Quality Policy. – Consists of harmonics, voltage fluctuations & voltage imbalance.

• Permanent power quality monitoring device is installed at the POI for monitoring purposes.

• Interconnection Studies: – Determine impact of harmonics produced by IBRs on electrically close

synchronous generators.

– Determine if mitigation plan is necessary

– This could result in stricter harmonic injection limits.

– Transformer energization studies:

➢ Energization of large transformers could have impact on power quality. (voltage

drop and/or TOV)

Interactive Training

Page 42: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Synchronous Machine – Response to a Three Phase Fault

1.0

0.8

0.6

0.4

0.3

0.5

0.7

0.9

1.1

3.2

2.4

1.6

0.8

0.4

1.2

2.0

2.8

3.6Terminal Voltage

Current

1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.70.9

Time (seconds)

Vo

ltag

e (p

er u

nit

) Cu

rrent (p

er un

it)

uncontrolled response

controlled response

Interactive Training

Page 43: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Inverter Based Resource – Response to a Three Phase Fault

1.0

0.8

0.6

0.4

0.3

0.5

0.7

0.9

1.1

0.96

0.72

0.48

0.24

0.12

0.36

0.60

0.84

1.08

1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.70.9

Time (seconds)

Vo

ltag

e (p

er u

nit

) Cu

rrent (p

er un

it)

Terminal Voltage

Reactive Current

Active Current

Reactive Current

IBRs offer a controlled response

Interactive Training

Page 44: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Southern Company OASIS Website

– Additional & Detailed information available on Southern

Company’s OASIS website.

• Interconnection requirements for inverter based

generation

• Voltage Schedule Procedure

• Reactive Power Requirements

• Power Quality Policy

Interactive Training

Page 45: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

IEEE P2800 Project

• Title: Standard for Interconnection and Interoperability of IBRs Interconnecting with Associated Transmission Electric Power Systems

• Scope: This standard establishes the recommended interconnection capability and performance criteria for inverter-based resources interconnected with transmission and networked sub-transmission systems. Included in this standard are recommendations on performance for reliable integration of inverter-based resources into the bulk power system, including, but not limited to, voltage and frequency ride-through, active power control, reactive power control, dynamic active power support under abnormal frequency conditions, dynamic voltage support under abnormal voltage conditions, power quality, negative sequence current injection, and system protection.

Interactive Training

Page 46: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

IEEE P2800 Leadership TeamRole Name Affiliation Stakeholder Group Liaison

Chair Jens C. Boemer EPRI Academic/Research EDP&G, SCC21

Secretary Wesley Baker Power Grid Eng. Service Provider/ Consulting EMC, IRPTF

Vice-Chair Bob Cummings NERC Regulatory and Governmental Bodies NERC IRPTF

Vice-Chair Kevin Collins FirstSolar Users, Industrial NERC IRPTF

Vice-Chair Babak Enayati NationalGrid Stakeholders represented in IEEE Power & Energy Society

T&D, SCC21, PES GovBrd

Vice-Chair Ross Guttromson SANDIA National Lab Academic/Research DOE

Vice-Chair Chenhui Niu State Grid Corporation of China

Stakeholders represented in IEEE P2800.1 Working Group

IEEE P2800.1

Vice-Chair Manish Patel Southern Company Utility, Transmission PSRC, IRPTF

Interactive Training

Page 47: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

IEEE P2800 Project – Tentative Sub-Working Groups

I. Overall Document

II. General Requirements

III. Active Power – Frequency Control

IV. Reactive Power – Voltage Control

V. Low Short-Circuit Power VI. Power Quality

VI. Ride-Through Capability Requirements

VII. Ride-Through Performance Requirements

VIII. Inverter-Based Resource Protection

IX. Modeling, Validation, Measurement Data and

Performance Monitoring

X. Interoperability, information exchange,

information models, and protocols

XI. Tests and verification requirements

▪ Sub-WG scoping is currently underway

▪ If you are interested, please sign up at https://www.surveymonkey.com/r/MRW9SLQ

▪ Plan to kick off Sub-WG soon (likely bi-weekly calls)

Interactive Training

Page 48: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Public Policy Requirements Stakeholder Proposal

SERTP

48

2019 SERTP

Page 49: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

SERTP Evaluation

Transmission Needs Driven by Public Policy Requirements (PPRs)

• The SERTP process did not receive any proposals for transmission needs driven by Public Policy Requirements for the 2019 planning cycle. Therefore, no transmission needs have been identified for further evaluation of potential transmission solutions in the 2019 SERTP planning cycle.

49

2019 SERTP

Page 50: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Next Meeting Activities

• 2019 SERTP 2nd Quarter Meeting

– Location: Louisville, KY

– Date: June 2019

– Purpose:

o Review Modeling Assumptions

o Discuss Preliminary 10 Year Expansion Plan

o Stakeholder Input & Feedback Regarding the Plan

50

2019 SERTP

Page 51: SERTP - 1st Quarter Meeting · 2019. 3. 27. · –Determine if mitigation plan is necessary –This could result in stricter harmonic injection limits. –Transformer energization

Questions?

www.southeasternrtp.com

51

2019 SERTP