Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200 July 27, 2017 Via eFiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 RE: Northern Natural Gas Company Northern Lights 2017 Docket No. CP16-472-000 Biweekly Report #10 Dear Ms. Bose; Pursuant to Condition 8 of the Order Issuing Certificate issued by the Federal Energy Regulatory Commission January 30, 2017, in the above-referenced docket, Northern Natural Gas Company hereby submits for filing its biweekly status report for the period ending July 21, 2017. Any questions regarding the filing should be directed to the undersigned at (402) 398-7138 or Mike Loeffler at (402) 398-7103. Respectfully Submitted, /s/ Michael T. Loeffler Michael T. Loeffler Senior Director, Certificates and External Affairs Attachment

Transcript of Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016...

Page 1: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Natural Gas Company P.O. Box 3330 Omaha, NE 68103-0330 402 398-7200

July 27, 2017 Via eFiling Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 RE: Northern Natural Gas Company Northern Lights 2017 Docket No. CP16-472-000 Biweekly Report #10 Dear Ms. Bose;

Pursuant to Condition 8 of the Order Issuing Certificate issued by the Federal

Energy Regulatory Commission January 30, 2017, in the above-referenced docket, Northern Natural Gas Company hereby submits for filing its biweekly status report for the period ending July 21, 2017.

Any questions regarding the filing should be directed to the undersigned at (402)

398-7138 or Mike Loeffler at (402) 398-7103. Respectfully Submitted, /s/ Michael T. Loeffler Michael T. Loeffler Senior Director, Certificates and External Affairs Attachment

Page 2: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

Northern Natural Gas Northern Lights 2017 Expansion Project (CP16-472-000) Biweekly Status Report No. 10 July 8, 2017 - July 21, 2017 PROJECT DESCRIPTION The project consists of a 2.0-mile Princeton branch line loop extension (Princeton Loop) in Sherburne County, a 2.8-mile St. Cloud branch line loop extension (St. Cloud Loop) in Isanti County, and the addition of a 15,900-hp compressor unit at the existing Faribault compressor station in Rice County, Minnesota. New valve settings will be installed at the end of each pipeline loop. FEDERAL AUTHORIZATION STATUS Northern Natural Gas Company (Northern) began consultation with the applicable agencies and tribes in September 2015. The status of all federal authorizations are listed in the table below.

Federal Authorization Status Agency Name Permit/Authorization/Letter of Concurrence Status Federal Energy Regulatory Commission

Certificate (Docket No. CP16-472-000) Received 1/30/2017

U.S. Army Corp of Engineers – Saint Paul District

Section 404 authorization under RGP-003-MN (MVP-2016-00742-MLV)

Received 10/31/2016

U.S. Fish and Wildlife Service – Twin Cities Field Office

Obtained USFWS concurrence of no impact to threatened and endangered species

Completed 04/22/2016

U.S. Fish and Wildlife Service – Twin Cities Field Office

Northern long-eared bat streamlined consultation form

Completed 04/22/2016

USDA FSA Isanti County

1. Conservation Reserve Program (CRP) 2. Conservation Reserve Enhancement Program (CREP) 3. Lands subject to Debt for Nature Contracts and Easements 4. Lands subject to Farm Service Agency mortgages 5. Land subject to restrictive easements to protect resources such as wetlands and threatened or endangered species.

Sent 01/27/16 Consultation complete.

1

Page 3: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

Agency Name Permit/Authorization/Letter of Concurrence Status USDA FSA Sherburne County

1. Known locations of noxious and/or invasive weed species

2. Identification of any lands/easements that may be enrolled in programs administered by the FSA

Sent 01/27/2016 Consultation complete.

USDA FSA Rice County

Sent 01/27/2016 Consultation complete.

USDA NRCS – Cambridge Service Center

Grassland Reserve Program (GRP) and Wetland Reserve Program (WRP) easements

Sent 01/27/2016 Consultation complete.

USDA NRCS – Elk River Service Center

Received 02/19/2016 Consultation complete.

USDA – NRCS - Faribault Service Center

Received 02/1/2016 Consultation complete.

MN Pollution Control Agency

401 Water Quality Certificate Authorized 02/12/2016

MN Pollution Control Agency

Clean Air Act, Major Amendment, State; Limits to avoid Part 70/ True minor for New Source Review

Received 03/28/2017

MN Pollution Control Agency

General Permit Authorization to Discharge Stormwater Associated with Construction Activities under the NPDES/State Disposal System (SDS) Permit

Received 02/27/2017

MN Department of Natural Resources

Water Appropriation General Permit Authorization for construction trench dewatering

Received 04/10/2017 and 06/05/2017

Minnesota Historical Society, State Historic Preservation Office

Section 106 Consultation Completed 08/12/2016

2

Page 4: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

PIPELINE SEGMENTS One contractor will construct the two branch line loop extensions in sequence. The environmental training totals listed below reflect all training conducted on the pipeline segments. On-site Contractor: Michels Corporation, Inc. Overall Construction Start Date: 5/8/2017 Environmental Training Conducted: This reporting period: 19 Total to date: 49 St. Cloud Branch Line Loop Extension Construct a 2.8-mile extension of Northern’s existing 12-inch-diameter St. Cloud branch line loop (MNB77502) in Isanti County, Minnesota. Construction Status The crew installed silt fencing and then top soiled and graded the corn field at MP 1.7 and the pasture areas between MP 0.07 and 0.3 for the horizontal direction drill (HDD) pads. Access roads were constructed at MP 1.7. Two sound suppression walls were constructed at MP 1.7 for noise mitigation during the HDD. In addition, the contractor cleared trees and vegetation at MP 0.5. The contractor also installed silt fencing along the drag section in a bean field east of 6th Street but no grading has occurred in this area. Machinery and equipment for the drilling arrived and both drills are fully equipped and manned. On July 19, 2017, the drilling began at MP 1.7 heading westbound. On July 20, 2017, the Michels crew began drilling eastbound from MP 2.8 under the Rum River. Materials, including two vacuum trucks (one of which is a track operated Maruka), are strategically placed at opposing sides of the Rum River and wetlands for rapid mobilization in the event of an inadvertent release of drilling fluid. No releases have occurred to date. Pipe arrived and is being strung throughout the west end of the project and continued to the east. No welding has occurred to date. Construction Modifications No construction modifications occurred during this reporting period. Stream Crossings and Environmentally Sensitive Areas The Rum River was not been crossed by HDD during this reporting period. Rain Events Three rain events occurred this reporting period in excess of 0.50 inch. One on each of the following days July 10, 12, and 18, 2017. The weekly stormwater inspections found the project to be in full environmental compliance. To date, the project has received 4.4 inches of rain.

St. Cloud Branch Line Loop Extension Construction Progress Activity Start Date Completed Notes

Survey 6/21/2017 85% Project boundary staking was completed this reporting period Clearing 6/22/2017 100% Grading 6/22/2017 90% Stringing 7/13/2017 5% Welding Ditching

3

Page 5: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

Lower-in Backfill Tie-ins Clean-up Seeding *Completed totals include either percentage completed or date all completed. All totals are approximate.

Two-Week Projection

1. Continue HDDs between MP 1.7 and MP 2.8 in both directions with the two drills. 2. Continue receiving materials and pipe. 3. Maintain access roads and noise mitigation measures for HDDs. 4. Commence welding of pipe.

Princeton Branch Line Loop Extension Construct a 2.0-mile extension of Northern’s existing 8-inch-diameter Princeton branch line loop (MNB91902) in Sherburne County, Minnesota. Construction Status Welding, ditching, lower-in, and backfill activities are complete. Restoration activities, including decompaction, topsoil replacement, seeding, and mulching have been completed from MP 0.20 to MP 1.95. The north and south tie-ins are complete and backfilled. The areas near the beginning and the end of the project will be restored as soon as weather permits. The contractor dewatered the north tie-in location July 5 - 17, 2017, via a well point system. Water was metered and dewatered through a hay bale structure to a well vegetated, upland location. Construction Modifications No construction modifications occurred during this reporting period. Stream Crossings and Environmentally Sensitive Areas No stream crossings were conducted and no construction occurred within other environmentally sensitive areas during this reporting period. Rain Events Two rain events occurred during this reporting period in excess of 0.50 inch, one July 12, 2017 and the other July 18, 2017. The weekly storm water inspections found the project to be in full environmental compliance. To date, the project has received 9.00 inches of rain.

Princeton Branch Line Loop Extension Construction Progress Activity Start Date Completed Notes

Survey 5-8-17 100% Clearing 5-9-17 100% Grading 5-9-17 100% Stringing 5-18-17 100% Welding 5-16-17 100% Ditching 6-5-17 100% HDD 5-30-17 100% Lower-in 6-5-17 100% Backfill 6-5-17 100% Tie-ins 6-7-17 100% Clean-up 6-21-17 90% Seeding 6-21-17 90% *Completed totals include either percentage completed or date all completed. All totals are approximate.

4

Page 6: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

Two-Week Projection

1. Remove temporary erosion control devices where they are no longer needed. 2. Continue to decompact soils, replace topsoil, seed, and mulch areas where it is

applicable. 3. Remove mats and revert the project back to preconstruction contours and

conditions, including the ROW, extra workspace areas, and staging areas. 4. Demobilize from the project. 5. Monitor revegetation and check erosion control devices’ functionality weekly and

within 24 hours of a rain event in excess of 0.5 inch.

COMPRESSOR STATION One contractor will construct the Faribault compressor Unit No. 2 project. The environmental training totals listed below reflect all training conducted for the compressor station project. The training was conducted for Northern employees, survey crew members, third-party inspectors and contractor personnel in preparation for the start of construction. On-site Contractor: Michels Corporation Overall Construction Start Date: 3/13/17 Environmental Training Conducted: This reporting period: 10 Total to date: 159 Faribault Compressor Unit No. 2 Install an additional natural-gas-driven 15,900-hp Solar Mars turbine unit (Unit No. 2) at the Faribault compressor station located in Rice County, Minnesota. Construction Status

• Civil: The contractor continued hanging insulation and liner panel on the compressor building walls. Installation of the exterior unit exhaust stack is complete. Work on the unit exhaust and intake ductwork continued. The contractor completed the lube oil cooler and demister support structures, set the lube oil cooler and demister, set and epoxy-anchored the Unit #2 fuel gas heater and set the emergency generator on its foundation. The canopy over roll was installed up to the compressor building door. The contractor continued hydro-vacuum excavation of the 36-inch-diameter discharge header extension tie-in area and the 36-inch-diameter suction line from Unit #2 for tie-ins. Concrete was poured for the two rest blocks for the 36-inch-diameter discharge piping. Braun Intertec was onsite to test concrete for air to meet specification requirements. The contractor backfilled and compacted around the 36-inch-diameter discharge piping and around the gas coolers after electrical conduit was installed.

• Electrical: The contractor installed cable tray in the sub-floor/trough and the connecting vertical/rising section to the overhead cable tray on the west wall. Grounding conductors were terminated and the contractor continued to install land cables in the station control panel. Rigid galvanized steel conduit for lighting, fire and gas was installed in the Unit #2 compressor building. Polyvinyl chloride coated rigid galvanized steel conduit was installed for the fuel/gas skid. The contractor installed 1-inch, 1 1/2-inch and 2 1/2-inch polyvinyl chloride coated rigid

5

Page 7: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

galvanized steel conduit for various valve yard gas operated valve applications near the gas coolers. Electrical conduit in the south workspace area was installed through the valve yard.

• Welding and Piping: Hydrostatic testing is complete for the 30-inch-diameter suction and discharge piping leading to and inside the compressor building and the 12-inch-diameter, 30-inch-diameter, and 36-inch-diameter piping with municipal water acquired from the City of Faribault. After hydrostatic testing, all pipe was dewatered and dried to -40 F dew point. Fabrication of 30-inch-diameter and 36-inch-diameter piping continued.

• Environmental: The contractor installed approximately 435 feet of silt fence along the outside south edge of the compressor station fence line. The west workspace area located just north of the existing compressor station access road was seeded and approximately 75 square yards of certified weed free erosion control blanket was installed.

Construction Modifications No construction modifications occurred during this reporting period. Stream Crossings and Environmentally Sensitive Areas No stream crossings were conducted and no construction occurred within other environmentally sensitive areas during this reporting period. Rain Events Two rain events occurred during this reporting period in excess of 0.50 inch July 10, 2017 and July 20, 2017. The weekly and rain event stormwater inspections found the project to be in full environmental compliance. To date, the project has received 15.36 inches of rain.

Faribault Compressor Unit No. 2 Construction Progress Activity Start Date Completed Notes

Site Preparation 3/13/17 95% Civil 3/23/17 78% Structural 4/28/17 75% Mechanical 5/26/17 25% Compressor Building Piping

4/17/17 32%

Mainline Tie-Ins Hydrostatic Testing

6/12/17 50%

Electrical 4/17/17 52% Instrumentation Commissioning Clean-Up and Restoration

*Completed totals include either percentage completed or date all completed. All totals are approximate. Two-Week Projection

1. Continue to install interior panels, insulation, and building ventilation system. 2. Continue pulling and terminating power and control cables. 3. Commence installation of the south suction header. 4. Continue Unit #2 suction and discharge piping assembly. 5. Continue 36-inch-diameter piping between new scrubber and Unit #2.

6

Page 8: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

6. Continue Unit #2 ancillary equipment installation. 7. Continue 36-inch-diameter header trench excavation. 8. Commence small bore piping trenches and insulation. 9. Commence piping and pulling wire in Unit #2. 10. Install lube oil piping.

PROJECT-WIDE SPILL TOTALS All project derived waste will be properly managed and every effort will be made to eliminate spills. Michels has arrangements with OSI Environmental in Anoka, Minnesota, to dispose of all waste generated on-site. There were no spills during this reporting period.

This reporting period: 0 Quantity: 0.00 gallon Total to date: 5 Total quantity: 1.76 gallons

Spill No. Date Segment Volume Notes

1 4/28/2017

Compressor Station 0.78 gallon

Hydraulic fluid leak from power-take-off unit on truck delivering water

2 5/5/2017 Compressor Station 0.23 gallon Hydraulic hose leak on truck delivering a conex box

3 6/2/17 Princeton Loop 0.002 gallon Oil leak from a hydrovac motor

4 6/6/17 Princeton Loop 0.72 gallon Hydraulic fluid leak from belly pan of trackhoe

5 6/27/17 Compressor Station 0.016 gallon Hydraulic hose failure to the vacuum boom control

*The Minnesota Department of Natural Resources (MDNR) will be notified of all spills that result in a “hazardous condition” as defined by the MDNR.

PROJECT-WIDE AGENCY COMMUNICATIONS Communication: No agency communications occurred during this reporting period Permit Approvals No permit approvals were received during this reporting period PROJECT-WIDE LANDOWNER CONCERNS No landowner issues occurred during this reporting period.

Landowner: Date: Segment: Tract: Location: Problem/Concern: Resolution:

PROJECT-WIDE NON-COMPLIANCE CONCERNS On July 17, 2017, the Princeton branch line loop extension was placed into service prior to receiving written approval from the Director of the Office of Energy Projects. Northern

7

Page 9: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

contacted Commission staff as soon as the non-compliance was realized and filed notice of the non-compliance and a belated request to place the facility into service July 18, 2017.

8

Page 10: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

St. Cloud Loop Photos

Silt fence was installed at MP 1.7, between MP 0.7 to 0.3 and east of 6th Street (MP 0.0)

Machinery and equipment arrived

9

Page 11: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

The Maruka vacuum vehicle

Two sound suppression walls were constructed at MP 1.7

10

Page 12: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

Drilling began at MP 1.7

Pipe arrived and was strung out

11

Page 13: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

Pipe was strung out along drag section

Princeton Loop Photos

Facing south, the ROW near MP 0.2 was recently seeded and mulched

12

Page 14: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

Welds were sandblasted and coated in secondary containment

Facing southwest, silt fence near MP 1.9 is in good condition and functional

13

Page 15: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

Facing west, access road west of 104th Street is in good condition

Facing west, ROW near MP 1.75 is in good condition

14

Page 16: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

Compressor Station Photos

Facing northwest, east of the compressor building, tarps were used to capture sandblast

media and coating for proper disposal

Facing southeast, north workspace area, set fuel gas heater for Unit #2

15

Page 17: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

Facing west, west workspace area, erosion control blankets were installed

Facing south, north of compressor building, exhaust stack installation

16

Page 18: Senior Director, Certificates and External Affairs Postings/2017... · form Completed 04/22/2016 USDA FSA Isanti County 1. Conservation Reserve Program (CRP) 2. Conservation Reserve

Northern Lights 2017 Expansion Project Biweekly Status Report No. 10

Facing north, west of the compressor building, the emergency generator was set

Facing east, west of compressor building, the lube oil cooler was installed

17