SENG 380 Software Project Management – LAB-3

Lei Zheng

[email protected]

Mar. 26th

1

Page 2: SENG 380 Software Project Management LAB-3zhengl/seng380/materials/lab3.pdf · SENG 380 Software Project Management – LAB-3 ... •Review of Lab-2 & assignment-2 •Lab-3: Project

Outline

• Review of Lab-2 & assignment-2

• Lab-3: Project Monitoring & reporting

• LAB-3: Assignment

2

Page 3: SENG 380 Software Project Management LAB-3zhengl/seng380/materials/lab3.pdf · SENG 380 Software Project Management – LAB-3 ... •Review of Lab-2 & assignment-2 •Lab-3: Project

LAB-3: Review of lab-2

• Resources management in MS project 2003

– The viewers for resource allocation by Gantt chart, resource sheet, resource graph, resource usage

–Adding and assigning resources

3

Page 4: SENG 380 Software Project Management LAB-3zhengl/seng380/materials/lab3.pdf · SENG 380 Software Project Management – LAB-3 ... •Review of Lab-2 & assignment-2 •Lab-3: Project

LAB-3: Review of lab-2

• Resources management in MS project 2003

– The viewers for resource allocation by Gantt chart, resource sheet, resource graph, resource usage

–Adding and assigning resources

4

Page 5: SENG 380 Software Project Management LAB-3zhengl/seng380/materials/lab3.pdf · SENG 380 Software Project Management – LAB-3 ... •Review of Lab-2 & assignment-2 •Lab-3: Project

• Q1: Please generate the resource sheet using MS project 2003.

• It’s easy…

• Q2: If Spencer is assigned to another project, then with only three programmers,

– Five sub questions

– The core one is “how would you plan the tasks?”

» only three programmers

» also only three analysts/designers

5

last Assignment

Page 6: SENG 380 Software Project Management LAB-3zhengl/seng380/materials/lab3.pdf · SENG 380 Software Project Management – LAB-3 ... •Review of Lab-2 & assignment-2 •Lab-3: Project

LAB-3: review of Asg-2

• To reschedule project with limited resources

– To combing two tasks into one

– To delay a task

– To split one task into two sub-tasks

• To assign resource to tasks

– Priority to critical tasks

– Cost sensitivity

6

Page 7: SENG 380 Software Project Management LAB-3zhengl/seng380/materials/lab3.pdf · SENG 380 Software Project Management – LAB-3 ... •Review of Lab-2 & assignment-2 •Lab-3: Project

LAB-3: review of Asg-2

7

Solutions Duration Cost Methods

A 116 48, 800 Delay tasks

• Three solutions:

Page 8: SENG 380 Software Project Management LAB-3zhengl/seng380/materials/lab3.pdf · SENG 380 Software Project Management – LAB-3 ... •Review of Lab-2 & assignment-2 •Lab-3: Project

LAB-3: review of Asg-2

• Three solutions:

8

Solutions Duration Cost Methods

B 106 47, 500 Split task: check specification

Page 9: SENG 380 Software Project Management LAB-3zhengl/seng380/materials/lab3.pdf · SENG 380 Software Project Management – LAB-3 ... •Review of Lab-2 & assignment-2 •Lab-3: Project

LAB-3: review of Asg-2

• Three solutions:

9

Solutions Duration Cost Methods

A 116 48, 800 Delay tasks

B 106 47, 500 Split task: check specification

Is there any better plan with fewer duration or less cost?

Email your plan to me, and earn bonus mark.

Page 10: SENG 380 Software Project Management LAB-3zhengl/seng380/materials/lab3.pdf · SENG 380 Software Project Management – LAB-3 ... •Review of Lab-2 & assignment-2 •Lab-3: Project

• How to set baseline?

• How to set the progress of the project?

• How to use EAV analysis?

• How to use report?

10

LAB-3: Project Monitoring &

reporting

Page 11: SENG 380 Software Project Management LAB-3zhengl/seng380/materials/lab3.pdf · SENG 380 Software Project Management – LAB-3 ... •Review of Lab-2 & assignment-2 •Lab-3: Project

• How to set or update or delete baseline?

• How to set the progress of the project?

– Three ways with different accuracy:

• track by entering the Percent of Work Complete ;

• track by entering the Actual Work Done and Work Remaining

• track by entering the hours of work done per time period

11

LAB-3: Project Monitoring &

reporting

Page 12: SENG 380 Software Project Management LAB-3zhengl/seng380/materials/lab3.pdf · SENG 380 Software Project Management – LAB-3 ... •Review of Lab-2 & assignment-2 •Lab-3: Project

• How to set baseline?

• How to set the progress of the project?

• How to use EAV analysis?

– BCWS/PV, BCWP/EV, ACWP/AC;

– CV, SV;

– CPI, SPI;

– EAC;

12

LAB-3: Project Monitoring &

reporting

Page 13: SENG 380 Software Project Management LAB-3zhengl/seng380/materials/lab3.pdf · SENG 380 Software Project Management – LAB-3 ... •Review of Lab-2 & assignment-2 •Lab-3: Project

• How to set baseline?

• How to set the progress of the project?

• How to use EAV analysis?

• How to use report?

– Six report viewer: summary, current activities, costs, assignments, workload, custom

13

LAB-3: Project Monitoring &

reporting

Page 14: SENG 380 Software Project Management LAB-3zhengl/seng380/materials/lab3.pdf · SENG 380 Software Project Management – LAB-3 ... •Review of Lab-2 & assignment-2 •Lab-3: Project

• Last but Important:

– Due on Apr. 2nd 2:30PM

– Please Hand your paper to Dr. Amany

14

LAB-3: Assignment (cont’d)

Any feed back is welcomed