Sendong Housing Summit 2 Presentation

59
DSWD MULTI-STAKEHOLDERS COORDINATING COUNCIL FOR SENDONG OPERATION HOUSING SUMMIT 2 “Sustaining Life After Sendong: Land Summit” Grand Caprice Restaurant & Convention Center Limketkai Complex, Lapasan, Cagayan de Oro City May 10, 2012

description

State of the Housing Program for Typhoon Sendong victims in Cagayan de Oro, May 10 2012

Transcript of Sendong Housing Summit 2 Presentation

Page 1: Sendong Housing Summit 2 Presentation

DSWD MULTI-STAKEHOLDERS COORDINATING COUNCIL FOR

SENDONG OPERATIONHOUSING SUMMIT 2

“Sustaining Life After Sendong: Land Summit” Grand Caprice Restaurant & Convention Center

Limketkai Complex, Lapasan, Cagayan de Oro CityMay 10, 2012

Page 2: Sendong Housing Summit 2 Presentation

Situationer on Emergency and Permanent Shelter for Typhoon Sendong Survivors in

Cagayan de Oro City

Presented by Mariano V. NavaCluster Coordination OfficerInternational Organization For Migration (IOM)

Page 3: Sendong Housing Summit 2 Presentation

Tropical Storm Washi (known locally as Sendong) struck the northeastern coast of Mindanao on 16 December 2011, with over 142 millimeters of rain in just 12 hours. This triggered deadly flash floods from three major rivers, which killed over 1,000 people and displaced thousands of families – most of whom have sought refuge in makeshift evacuation centers.

Page 4: Sendong Housing Summit 2 Presentation

Number of People and Area Affected

• Based on the January 23, 2012 report of the Regional Disaster Risk Reduction and Management Council-X, there are 69,666 families, equivalent to 384,431 persons, affected by the December 2011 disaster event.

• A total of three cities and 25 municipalities of four provinces, covering a total of 253 barangays experienced flooding of various levels of severity

• • 41 barangays were affected in Cagayan de Oro City and 32

barangays in Iligan City

Page 5: Sendong Housing Summit 2 Presentation

Damage To Property

The reported damage is estimated at Php 4.989 billion The social sector comprised the biggest share at 45 percent which is for housing at Php 2.3 billion The infrastructure sector placed second at 34 percent due to damage to roads, bridges and other facilities The economic sector at 20 percent were mostly accounted by agriculture, fishery, followed by trade and industry

Page 6: Sendong Housing Summit 2 Presentation
Page 7: Sendong Housing Summit 2 Presentation
Page 8: Sendong Housing Summit 2 Presentation
Page 9: Sendong Housing Summit 2 Presentation
Page 10: Sendong Housing Summit 2 Presentation

Statistical Data on Casualties from DSWD As of Apr 25. 2012

Area/Places Dead Persons

Injured Persons

Missing Persons

Total Casualties

1. Cag de Oro 737 225 555 1,517

2. Iligan city 693 1,518 466 2,677

3. Misamis Oriental 6 3 1 10

4. Bukidnon 36 2 52 90

Total 1,472 1,748 1,074 4,294

Page 11: Sendong Housing Summit 2 Presentation

Cluster Approach in the Philippine Disaster Management System

• NDCC Circular No. 05, S-2007 on the Subject: Institutionalization of the Cluster Approach in the Philippines

• A cluster is essentially a “sectoral group” … for filling gaps and ensuring adequate preparedness and response.

• At global level, ensure leadership and accountability.• At country level, ensure effective response…in

support of existing government structure and emergency response mechanisms.

Page 12: Sendong Housing Summit 2 Presentation

Cluster Government Lead

IASC Country Team Counterpart

1. Nutrition DOH United Nations Children’s Fund (UNICEF)

2. Water, Sanitation and Hygiene (WASH)

DOH UNICEF

3. Health DOH World Health Organization (WHO)

4. Emergency Shelter DSWD International Federation of the Red Cross (IFRC)

5. Camp Coordination and Camp Management

DSWD International Organization for Migration (IOM)

6. Protection DSWD UNICEF

7. Early Recovery OCD United Nations Development Programme (UNDP)

8. Logistics OCD World Food Programme (WFP)

9. Food DSWD WFP

10. Agriculture DA Food and Agriculture Organization (FAO)

11. Livelihood DSWD International Labor Organization (ILO)

Page 13: Sendong Housing Summit 2 Presentation

DSWD Assistance

• DSWD extended food and non-food items worth P 79,448,364.61 to 69,720 families who were Tropical Storm Sendong victims

• NGOs who channelled goods to DSWD provided P 46,762,725.63 worth of food and non-food items

Page 14: Sendong Housing Summit 2 Presentation

Cash for Work

• As of Apr 25, 2012, 4091 IDPs were served and a total of Php 8,795,650.00 were released (60.72%) with P 14,484,550 for 6,737 IDPs in Cag de Oro City and P 11,870,150. For 5,521 IDPs in Iligan City

Page 15: Sendong Housing Summit 2 Presentation

City Government Financial Assistance

The City Mayor, Hon. Vicente Y. Emano, revealed that after 12 phases of financial aid distribution, a total of P90,305,900.00 has been given to the victims of the flood caused by typhoon Sendong. The amount was sourced from the city’s 5% Calamity Fund. – reported May 7, 2012

Page 16: Sendong Housing Summit 2 Presentation

Evacuation Centers and Transitory Evacuation Centers (Tents)

• DSWD update reports show that as of Dec 23, 2011 a total of 7,314 families composed of 33,363 persons were in 21 evacuation centers around the city

• DSWD reports that as of Apr 25 there are 3,151 IDP families in 40 evacuation centers and Transitional Sites in the City with 12,931 individuals.

Page 17: Sendong Housing Summit 2 Presentation
Page 18: Sendong Housing Summit 2 Presentation
Page 19: Sendong Housing Summit 2 Presentation
Page 20: Sendong Housing Summit 2 Presentation
Page 21: Sendong Housing Summit 2 Presentation

Transitory Sites: Bunkhouses & Amakan Houses

Donor & Kind of Structure

Number of Units

Number of Locations

Total Cost

DSWDBunkhouses

120 1 P 7.3 M

International OrganizationFor Migration (IOM)Bunkhouses

745 2 P 20,860,000.

Catholic Relief Services (CRS)Amakan Houses

577 8 P 11,540,000.

Page 22: Sendong Housing Summit 2 Presentation
Page 23: Sendong Housing Summit 2 Presentation
Page 24: Sendong Housing Summit 2 Presentation
Page 25: Sendong Housing Summit 2 Presentation
Page 26: Sendong Housing Summit 2 Presentation

• There is a need to build no less than 800 transitional shelter units to house the remaining IDPs in evacuation centers so that they will be in better living conditions while waiting for the permanent housing units that will provided to them.

• This will require at least 6 to 8 hectares of land that is made available for use for at least six months or more depending on how long the transitory site will be closed.

Page 27: Sendong Housing Summit 2 Presentation

Statistical Data from DSWD on Damaged Houses As of Apr 25, 2012

Areas/Places Totally Damaged

Houses

Partially Damaged

Houses

Totals

1. Cagayan de Oro City 5,801 12,635 18,4362. Iligan City 5,246 14,874 20,1203. Misamis Oriental 131 389 5204. Bukidnon 253 75 328Total 11,431 27,973 39,404

Page 28: Sendong Housing Summit 2 Presentation

From the Strategic Action Plan of the Regional Development Council 10

• Data Estimates As of Jan 23, 2012

• The budgetary requirement for the rehabilitation and recovery reached Php 43.017 billion

• The infrastructure sector demands the biggest allocation at Php 30.525 billion or 71 percent of the total budget

• The provision of basic services particularly housing, education and health requires an estimated budget of Php 11.037 billion or 25 percent of the total budget

Page 29: Sendong Housing Summit 2 Presentation

Shelter Assistance to Community Based IDPs who live in Build Zones and have Partially Damaged Houses

Name of Organization & Assistance Provided

No. of Barangays No. of Kits

Cost

Habitat for Humanity PhilRepair kits Worth P 700.

4 1000 P 700,000

Habitat for Humanity PhilRepair kits Worth P 3,000.

10 800 P 2,400,000.

International Organization for Migration (IOM) Shelter Repair Kits worth P 7,000.

7 1,742 P 12,194,000.

International Organization for Migration (IOM) Emergency Shelter Kits worth P 25,000.

3 140 P 13,900,00.

Philippine Red Cross Shelter Repair Kits worth P 7,000.

6 1,390 P 3,500,000.

Page 30: Sendong Housing Summit 2 Presentation

The Local Inter-Agency Committee For

Permanent Housing (LIAC)

Major Function:

Serves as the decision-making, coordinating and consultative body to include supervision and monitoring of the sub-committees that shall implement and/or cause the carrying-out of the various activities, plans, programs and projects.

Page 31: Sendong Housing Summit 2 Presentation

ORGANIZATION

• Information dissemination

• Adequate Consultation

• Community assemblies

• Orientation of leaders

• Other community-related concerns

• Housing Survey• Validation of list of affected households• Formulation of Code of Policies• Inclusion and other claims resolution• Pre-Qualification of Households against NHA Alpha Listing• Final List of Qualified Families

• Identification of resettlement site

• Acquisition and Development of Site

• Coordination with receiving LGU, if off-city

• Provision of Basic Services and Facilities

• Housing options• Work plan and

budgetfor transfer of families

• Actual transfer• Issuance of

Transfer Notices• Estate

management

Chairman

Secretariat

Sub-Committee 2 Sub-Committee 3

Social Preparation

Sub-Committee 1

Beneficiary Selection, Arbitration

And Awards

Resettlement Projects Sites

Sub-Committee 4

Relocation and Transfer to Permanent Housing

Page 32: Sendong Housing Summit 2 Presentation

Composition as agreed:

• PCUP• NHA• LGU/BARANGAYS/

CPDO/EMB• DSWD/CSWD• DILG• DENR• DOST• CONCERNED

BARANGAYS

• PCUP•LGU/CSWD•DSWD•POs•LGU/BARANGAYS•LGU CPDO/EMD•XAVIER UNIV

Xavier UniversityLGU/CITY

ENGINEERING/CPDOCENRO

DPWHNHAH4HORO HABITATGKDOHDEPEDWATER/POWER

PROVIDERS

Chairman

Secretariat

Sub-Committee 2 Sub-Committee 3

Social PreparationCHAIR: CSWD

CO-CHAIR: PCUP

Sub-Committee 1

Beneficiary Selection, Arbitration

And AwardsCHAIR: LGU-EMD

CO-CHAIR: NHA/HUDCC

Resettlement Projects SitesCHAIR: NHA

CO-CHAIR : LGU City Engineers

Office

Sub-Committee 4

Relocation and Transfer to Permanent

HousingChair:

LGU –EMD/CPDO CO-CHAIR: CSWD

LGU/CPDO/EMD/CITY ENGR/CITY HEALTHPNP/AFPNHADSWD/CSWDDEPEDXAVIERDOH

Page 33: Sendong Housing Summit 2 Presentation

Land Available for Permanent Shelter From the City Government of Cagayan de Oro City

Barangay & Project Site Area in Has.

Value of Lot Site Development

CostBarangay CanitoanCalaanan Phase 3 (CDORSHP I) 13.7 P 22,606 M P 1.357 MCalaanan Phase 3 5.9District 6, Canitoan 2.82 P 3,006 M P 3.006 MBarangay IndahagIndahag Phase 1 & 2 10.0 P 1.287 M P 1.287 MBarangay Camaman-anGK-Berjaya Village 2.0 P 4.0 M P 0.367 MTotal 28.4 P 59.380 M P 6.217 M

Page 34: Sendong Housing Summit 2 Presentation

Land Available for Permanent Shelter From the Private Donors in Cagayan de Oro City

Barangay & Project Site Land Owner/Donor

Area in Has

No. of Units

Barangay LumbiaXavier Ecoville Xavier University 5 570Barangay IndahagSAC ACDO CARITAS Village 1 91

Page 35: Sendong Housing Summit 2 Presentation

Donors of Grant Houses for Permanent Shelters for Cagayan de Oro City

Donor Amount of Donation

No. of House s

House Builders

1. DSWD P 203,037,000 2,901 Habitat Philippines2. San Miguel Corp. P 250,000,000 2,500 Habitat Philippines3. Berjaya Group 20,000,000 200 Gawad Kalinga4. Banco de Oro 10,000,000 100 Gawad Kalinga5. SM City CDO 20,000,000 200 Gawad Kalinga6. Shell Corp. 20,000,000 200 Gawad Kalinga7. Fil-Chinese Chambers 300 Fil-Chinese Chambers8. Cargill Corp 3,150,000. 29 Habitat Philippines9. Rotary Club 40 Habitat Philippines

Page 36: Sendong Housing Summit 2 Presentation

CDORSHP PHASE IIIUNITS TURNOVERED TO THE BENEFICIARIES LAST APRIL 27, 2012

FINISHING UNITS

ON GOING FOUNDATION UP TO WALLING

ROOFING LEVEL

CONSTRUCTOR HABITAT PHILS.

Lots Generated = 1,474 units

Page 37: Sendong Housing Summit 2 Presentation

502 UNITS COMPLETED AND 286 ON GOING CONSTRUCTION AT VARIOUS

STAGES

CDORSHP PHASE III

Page 38: Sendong Housing Summit 2 Presentation

UNITS WITH BENEFECIARIES

CDORSHP PHASE III

Page 39: Sendong Housing Summit 2 Presentation

LGU 34 UNITS ROW HOUSES AT 90% COMPLETION

LGU – ROW HOUSES

NOTE: NEW CONTSRUCTOR GALVA STEEL CORPORATION

CDORSHP PHASE III

Page 40: Sendong Housing Summit 2 Presentation

FILIPINO CHINESE COMMUNITY

ON-GOING CONSTRUCTION OF FOUNDATION UP TO WALLING (20 UNITS)

UP TO FINISHING 30 UNITS)

COMPLETED UNITS (60 UNITS)

CDORSHP PHASE III

Page 41: Sendong Housing Summit 2 Presentation

COMPLETED UNITS

ON GOING CONSTRUCTION FOUNDATION UP TO WALLING

CDORSHP PHASE II

Lots Generated = 656 units

Page 42: Sendong Housing Summit 2 Presentation

BLOCK 16

COMPLETED 26 UNITS

CONSTRUCTOR ORO HABITAT PHILS.

CDORSHP PHASE II

Page 43: Sendong Housing Summit 2 Presentation

ON GOING CONSTRUCTION FOUNDATION UP TO WALLING (58 UNITS 50 % COMPLETION & 10 UNITS 10% COMPLETION)

CDORSHP PHASE II

Page 44: Sendong Housing Summit 2 Presentation

CANITOAN RELOCATION SITE

CONSTRUCTOR GAWAD KALINGA

Lots Generated = 444 units

Page 45: Sendong Housing Summit 2 Presentation

ON GOING UP TO WALLING LEVEL 8 UNITS

CANITOAN RELOCATION SITE

Page 46: Sendong Housing Summit 2 Presentation

ON GOING UP TO WALLING LEVEL 8 UNITS

CANITOAN RELOCATION SITE

Page 47: Sendong Housing Summit 2 Presentation

CAMAMAN-AN RELOCATION SITEON GOING CONSTRUCTION UP TO ROOFING LEVEL

ON GOING CONSTRUCTION FINISHING TO ROOFING LEVE

Lots Generated = 206 units

Page 48: Sendong Housing Summit 2 Presentation

ON GOING CONSTRUCTION UP TO FINISHING & ROOFING LEVEL

61 UNITS

CONSTRUCTOR GAWAD KALINGA

CAMAMAN-AN RELOCATION SITE

Page 49: Sendong Housing Summit 2 Presentation

INDAHAG RELOCATION SITE PHASE I FINISHING UP TO WALLING

ROOFING LEVEL

ON GOING CONSTRUCTION FOUNDATION UP TO WALLINGLAID OUT

CONSTRUCTOR HABITAT PHILS.

COMPLETED

Lots Generated = 495 units

Page 50: Sendong Housing Summit 2 Presentation

COMPLETED (208 UNITS)

INDAHAG RELOCATION SITE PHASE I

Page 51: Sendong Housing Summit 2 Presentation

ON GOING CONSTRUCTION AT VARIOUS STAGES (230 UNITS)

INDAHAG RELOCATION SITE PHASE I

Page 52: Sendong Housing Summit 2 Presentation

CONSTRUCTOR HABITAT PHILS.

INDAHAG RELOCATION SITE PHASE II

Lots Generated = 1,127 units

Page 53: Sendong Housing Summit 2 Presentation

18 QUADROPLEX (72 UNITS) FOUNDATION UP TO WALLING

INDAHAG RELOCATION SITE PHASE II

Page 54: Sendong Housing Summit 2 Presentation

NHA CDO – BAYANIHAN VILLAGE

RUFINO PROPERTY

Lots Generated = 434 units

Page 55: Sendong Housing Summit 2 Presentation

NASSA & SAC-ACDO CARITAS VILLAGE

NEW SITEAREA = 1 HECTARELOTS GENERATED = 91 UNITSMODAL LOTS = 63 SQ.MFLOOR AREA = 20 SQ.MHOUSE MODEL = SINGLE DETACH

Page 56: Sendong Housing Summit 2 Presentation
Page 57: Sendong Housing Summit 2 Presentation

COMMUNITY ASSOCIATION No. of MB’s

CMP Mobilizer

Relocation Site

1. Villeview I HOAI 2042. Villeview II HOAI 2153. Villeview III HOAI 2324. Villeview IV HOAI 193 Total 844

GROUP Foundation

Brgy. Indahag

Brgy. Lumbia

5. Consolacion N-hood HOAI 1356. Tibasak united N-hood HOAI 256 Total 391

TOUCH Foundation

Brgy. Camaman-an(upper Camaman-an)

7. Virgen Del Rosario HOAI 1658. Balacanas Consolacion HOAI 1889. Bognao Village HOAI (Ph-I) 277 (Ph-II) 97 Total 727

TOUCH Foundation

Brgy. Gusa

Page 58: Sendong Housing Summit 2 Presentation

COMMUNITY ASSOCIATION No. of MB’s

CMP Mobilizer

Relocation Site

10. Fresch Ville HOAI 16511. Greenfield HOAI 17512. Mikha Island Ville HOAI 14013. Bermundo Zone A&B HOAI 20014. Washi Ville HOAI 8615. Blesses Ville HOAI 145 Total 907

Social Action Center (SAC)

Brgy. Indahag

Brgy. Lumbia

Grand Total 2,807

Page 59: Sendong Housing Summit 2 Presentation

RemarksFamiliarity with the Cluster System for Emergency Response is Needed for the LGU and Line Agencies so that they can understand their role and participate in the relief operations. This can help in coordinating all the parallel relief operations initiated within the city early in the emergency and avoid duplication and facilitate the sharing of resources especially manpower and other logistics.The need to evacuate school classrooms forced the putting up of tents as additional emergency shelters and caused problems that could have been avoided if they were moved to transitional shelters. The experience of Cagayan de Oro in responding to Typhoon Sendong from emergency relief up to providing permanent shelter provides a rich source of learnings that could be effective if replicated in other cities that will face similar disasters.The availability of land owned by the LGU has facilitated a lot of solutions faced in the emergency like land to put up tents and transitory shelters to the immediate site development and building of permanent shelters.