Seminar58 castro presentation_3
Transcript of Seminar58 castro presentation_3
CITECITE--AHU: AHU: An Automated Commissioning Tool for CAV An Automated Commissioning Tool for CAV AirAir--Handling UnitsHandling Units
Natascha Castro, NISTNatascha Castro, NISTHossein Hossein VaeziVaezi--NejadNejad, CSTB, CSTB
IEA Annex 40
2
Outline
n Commissioning Processn Development of CITE-AHU¨ Test automation¨ Expert rules¨ Interface
n Commissioning the ARIA Building¨ Design Review¨ Manual Cx Results¨ Automated Cx Results
n Savings Estimate/ Paybackn Conclusions
CITE-AHU Commissioning of the Installation and Technical Equipment-Air Handling Units
3
Step 1: Design Review-check control logic, sensor placement and sensor accuracy.
Step 2: Operator Interview-for existing buildings, ask building operator whether the air handling units are operating properly to the best of their knowledge.
Step 3: Installation Review and Verification-conduct a field inspection to determine installed characteristics of the equipment including condition and sensor availability
Step 4: Forced Response Testing and Analysis-
manipulate the system under test by means of setpoint changes and sensor overrides. Document along with mode changes. Evaluate data for compliance.
MANUAL
BEMS
AHU AHU CommissioningCommissioning ProcessProcess ((fromfrom CTPL)CTPL)
not currently emphasized in protocols
iterative!
complete passive testing with BEMS, before active testing
update documents
4
1. Verify communications link2. Run pre-coded test sequence from library
Value Displays as READ is completed
This is the line number to input to change reference value
Automation of functional test scripts
5
1. Import test data 2. Specify data relationships3. Specify system functionality4. Analyze using modified APAR rules5. Compare to archived tests for On-going Cx
CAV
VAV
ProcedureProcedure for Cx for Cx AnalysisAnalysis
CITE-AHU
6
• Enhanced for constant air volume systems
CITE-AHU
Provides greater transparency of rule logic (tool tips )
CITE-AHU
Expert rules- AHU Performance Assessment Rules (House)
• Considers additional equipment (heat recovery)
7
Commissioning the ARIA Building
¨ Design Review¨Manual Cx¨ Automated Cx
n Serves Offices & Converted space
n 100% outdoor air
n Modes:
¨ Heating
¨ Free cooling
w/ Heat recovery & Manual Bypass
Step 1 Design Review: AHU3
8
n Candid w/ good knowledge of (undocumented) system history.
Cannot change the controllers schedule, setpoints revert to a nightly shutoff at midnight and 05:00 startup
General
Zones partitioned for office spaces w/o changing ventilation configuration
AHU3
PROBLEM DESCRIPTION UNIT
Step 2 Operator Interview: Mr. Laurent Auriau
...
9
Step 3 Installation Review and VerificationOutdoor Air Temp. Sensor
10
System schedule in override. (Controls installer left test program active)
ALL
PROBLEM DESCRIPTION & EFFECT
UNIT
Step 4 Forced Response Testing and Analysis (passive w/ BEMS)
First Auto-Cx test of AHU3
- 5
0
5
10
15
20
25
30
06/10/200319:12
07/10/200300:00
07/10/200304:48
07/10/200309:36
07/10/200314:24
07/10/200319:12
08/10/200300:00
08/10/200304:48
08/10/200309:36
Temp
(°C)
-1
0
1
2
Cmd
0-1
TRA AHU3
TSA AHU3
TOA
UHC AHU3
Supply Fan
1
s t Auto-Cx testing
period without fault2n d Auto-Cx testingperiod with fault
1 am 4 a m1 a m 4 am
11
First Auto-Cx test of AHU3
-5
0
5
10
15
20
25
30
06/10/200319:12
07/10/200300:00
07/10/200304:48
07/10/200309:36
07/10/200314:24
07/10/200319:12
08/10/200300:00
08/10/200304:48
08/10/200309:36
Tem
p (°
C)
-1
0
1
2
Cm
d 0-
1
TRA AHU3
TSA AHU3
TOA
UHC AHU3
Supply Fan
1s t Auto-Cx testingperiod without fault
2nd Auto-Cx testingperiod with fault
1 am 4 am1 am 4 am
Step 3 Forced Response Testing and Analysis (active w/ BEMS)
First Auto Cx tests were conducted on AHU3 over two nights
2nd night- Faulty condition BEMS logic error causes pumps to cycle off
1st night- Fault free with pumps in manual override
Finding: Cooling coil is undersized for 17°C (62.6°F).**Laboratory needs are not met- fan coil units added.
12
Step 3 Forced Response Testing and Analysis (active w/ BEMS)AHU2 Cooling coil capacity step test:
Return Temp. setpoint is changed from 20°C -> 19°C (3 hours) -> 18°C (3 hours) -> 17°C (3 hours)
. Auto-Cx test of AHU2
13
15
17
19
21
23
25
1/22/200414:24
1/22/200416:48
1/22/200419:12
1/22/200421:36
1/23/20040:00
1/23/20042:24
1/23/20044:48
Tem
p (
°C)
-0.5
0
0.5
1
1.5
Cm
d 0
-1
Tra,s AHU2
Tra AHU2
Tsa AHU2
Ucc AHU2
Auto-Cx testing period without fault.
Auto-Cx testing period w ith fault.Tra,s not
Finding: Cooling coil is undersized for 17°C (62.6°F).**Laboratory needs are not met- fan coil units added.
13
Redesign exhaust system for AHU 1 and update design drawings
Exhaust duct from AHU1 is connected to the exhaust of AHU 3AHU1,3
Remove test programForced continual operation of AHUs due to a test program installed in 2000
AHU1, 2 and 3
AHU3
Chiller
Boilers
AHU 3
AHU1,2
AHU1, 2 and 3
AHU3
Unit
Provide sensor shadingOutdoor air temperature
Shutdown system 12 am - 5 amNighttime shutdown not in effect
Clean condenser finsCondenser is 50% fouled
Apply summer scheduleBoilers in manual override in summer
Reduce supply air temperature setpointin summer
Supply air temperature setpoint (21°C), results in nighttime heating in summer
Correct the location of the return air temperature sensor
Return air temperature sensor is located downstream of the outdoor air supply duct
Automate damper control based on outdoor and return air temperatures Operating with heat recovery in summer
SolutionFault
To-Date Results
**Green= Manual Cx Blue= Bems Assisted Cx **Orange= comfort Yellow= energy
14
AHU2
Boilers
AHU3
Boilers
AHU1
AHU2, Chiller
Unit
Ensure that the circulation pump operates independent of the boiler.
AHU3 circulation pump cycles with the boiler. The heating coils are not supplied with hot water when the boilers cycle off.
Replace faulty temp sensor
Return air temperature sensor reading does not match overlay sensor, system sensor is faulty.
Reduce the open period of the boiler isolation valves to 1mn
The open period of the boiler isolation valves (3 mn) is too long for the on/off period of the boilers (2mn)
Force at least one boiler to stop
Boilers operate even when commanded off (pumps shut down, boilers still operate)
Add a dedicated pump for cooling coil
The cooling coil of AHU1 was added after the construction of the building and is connected directly to the chiller (without a separate pump) It is not possible to suspend delivery of cooling water to this AHU
Synchronize equipment operation
AHU2 is set for 24 hour operation which does not match the operation of the chilled water pumps, stopped 12am-7am
SolutionFault
To-Date Results, cont’d
15
Gas Savings EstimateCorrect the boiler control logic n Boiler plant ran 24/7 to avoid occupant discomfort. n The control logic error was corrected January 5, 2004.
¨ improved comfort for occupants¨ decreased gas consumption¨ increased protection of the boiler plant equipment.
Weekly Gas Consumption vs Mean Outdoor Temp (C)
Winter Season Estimate:700€ ?10% Gas Energy Savings
16
Electrical Energy Savings Estimate
Correct scheduling errors for AHUs and pumps
344574168730.1Pump Zone 4 (CW)
2833775343272070.825Pump AHU & FCU (CW)
5877370314760.169Pump Zone 5
162151964100.047Pump Zone 4 (HW)
23 x 33072795850.067Pumps Zone 1,2,3
1371830166434940.4Pump AHU & FCU (HW)
27463660833280698888Fan AHU 3
798106398580192192.2Fan AHU 2
Costsavings
€
Energysavings(kWh)
Energy use after Cx (kWh)
Energy use before Cx (kWh)
Power (kW)Equipment
Annual estimate:4141€ ? 47% Electrical Energy Savings
17
Conclusionsn Some adaptation required for new systemsn CITE_AHU detected 3 faults in 4 automated tests
n Scheduling errors (€)n Cooling Coil & Heating coil Undercapacityn Boilers sequencing
n Development of automated tools must be used in conjunction with good protocol for system design reviews¨ Limitations to automated testing (i.e., detecting sensor
placement errors)n Quantitative energy benefits
¨ Excludes service requests¨ Equipment life¨ Heat recovery
n Non-quantitative benefits also achieved- comfort, operator knowledge, maintenance, documentation
3 yearsPay back
15000 €Project cost
5000 €Total gain
18
Future developmentn Define specific test scenarios (with user-changeable parameters)n Integrate test scenarios into CITE_AHU interfacen Automate documentation of test results
¨ Incorporate required manual test and documentation archiven Test VAV systems, Expand for other configurations
n Investigate Manufacturer interest to provide integrated package.
Questions?