Seminar on Research and Development Work...modeling and Wind Tunnel Simulation were adopted. Design,...
Transcript of Seminar on Research and Development Work...modeling and Wind Tunnel Simulation were adopted. Design,...
Seminar on Research and Development
Work
Ms. Connie YEUNGChief Architect / Development & Standards
Housing Department24 May 2010
Seminar on R&D Work
Research & Development Works
Sustainability Micro-climate Studies and Air Ventilation Assessment and its Verification Environmental Responsive Façade Vertical Green Panel + Green Roof Noise Mitigation Measures – Arc Screen Design and Acoustic Window
Design Life Cycle Assessment & Life Cycle Costing Method and its Review
Health & Hygiene Common W-trap system Mail Box Type Disposal System for Recycling Materials Fungal Resistance Test for multi-layer Acrylic Paint
Universal Design Tactile Guide Path System with Multi-sensory Map
3
Seminar on R&D Work
SustainabilityMicro-climate Studies & Air Ventilation Assessment Since 2004, micro-climate studies were employed as one of
the design tools of public rental housing estates
For large public rental housing developments planned and designed after July 2006, Air Ventilation Assessmentswere conducted to consider whether the development would pose any restriction to air flow.
Computational Fluid Dynamics Simulations, daylight modeling and Wind Tunnel Simulation were adopted.
Design, orientation and disposition of building blocks is enhanced through optimum use of natural recourses such as local wind direction, natural ventilation, daylighting, and solar radiant.
Way Forward Further verification would be carried out on studies
conducted with the completion of estates.
4
Seminar on R&D Work
SustainabilityEnvironmental Responsive Facade Since 2002, the development of Environmental Responsive Façade Engineering
was accepted as one of the Housing Authority Research Fund (HARF) projects. The R&D was carried out by the research team from Building Services
Engineering Department of The Hong Kong Polytechnic University. To enhance livability, sustainability and energy conversation in local PRH
through optimizing the envelope design. A series of detailed evaluations were conducted on:-
(i) cross ventilation in flats and wing wall effect by multi-zone air flow simulations and CFD simulations; and
(ii) temperature control by detailed buildingheat transfer simulation.
5
Seminar on R&D Work
SustainabilityEnvironmental Responsive Facade The findings have been incorporated in the design guide for
environmental responsive façade.
The most effective measure is the use of tinted glass or glass with lower shading coefficients. Other measures include:-(i) Reduction of glazing area;(ii) Use of light colour wall finishes materials to increase reflectance of external
wall; and(iii) Use of the appropriate length of
overhangs and side fins / wing walls over the glazing.
Way Forward Further study on other green materials
and systems for building enclosure.
6
Seminar on R&D Work
SustainabilityVertical Green Panel
1
2
4
3
Externalwall
Schematic Section of VGP
The Study for Vertical Green Panel commenced in 2007. In collaboration with Department of Biology, Chinese University of
Hong Kong and Shui On Building Contractor Ltd.. In the form of modular prefabricated external cladding. Aim of enhance the provision of greening in the congested urban
environment. Enables easy assembling on-site and future maintenance. Carries the multiple benefits of enhancing visual comfort,
strengthening ecology and reducing heat island effect. Study findings suggested the vertical green panel covered wall is
about 16 ºC cooler than bare concrete wall in a hot afternoon
Schematic Section of VGP1. Aluminum tray overall size 50 x 100cm 2. 50 mm thick growth medium3. 25 mm thick soil and grass turf (Zoysia
japonica , 朝鮮草)4. Built-in automatic irrigation system
7
Seminar on R&D Work
SustainabilityVertical Green PanelCommunity Participation Fostering sense of belonging and ownership. Engagement workshops with adjacent
schools for pictorial design of the VGP. Design Guide To compile several type of VGP systems
currently available at market to form part of the “Design Guide for External Greening”. Implemented in PRH Projects, such as East
Harbour Crossing Site 4 (Yau Lai Estate).Way Forward To review the technicality and maintainability
of various systems for further development of standard details, design guide and specification.
Bio-Technical Study for VGP Study 1 : Plant performance under different watering regimes for individual panels and panel clusters Study 2 : Fertility persistence of the system and nutrient loss from the panels. Study 3 : Water use efficiency of panel clusters Study 4 : Species selection Study 5 : Heat Reduction Capacity of Green Panels Page
8
Seminar on R&D Work
SustainabilityGreen Roof Since 2004, HA is committed to enhance green and
healthy living in the high-rise high density urban living environment by providing green roofs in low-rise structures with extensive planting, such as commercial centres, carparks and refuse collection compounds wherever feasible for new housing developments. By 2009/10, over 8,000 square meters of green roofs
were completed in more than 18 new estates in using different types of vegetation. We have been piloted in three vegetation types (e.g. grass,
sedums, small shrubs and groundcovers) in green roof installation, such as (i) grassed commercial centre roofs in Choi Ying Estate
and Tin Ching Estate;(ii) Sedums in Ching Ho Estate; and(iii) small shrubs and groundcovers in Upper Ngau Tau
Kok Estate
Pilot Green Estate (Ching Ho Estate in Sheung Shui) provide green roof or green decking to covered walkways, low-rise structures, carparks and/or vehicular access Findings from the test case carried out in early 2009
Sedums are the most drought tolerant among the three types of trial vegetation.
High capital installation cost but less subsequent maintenance.
The best drought tolerant sedum species include 金葉佛甲草 and 三七景天 which could survive over a dry season without irrigation;
9
Seminar on R&D Work
SustainabilityGreen RoofWay Forward – Continue to conduct technical feasibility study
on the choice of plant, irrigation and drainage system required and the long-term maintenance implication.
Sau Mau Ping South Estate provide green roof or green decking to covered walkways
Yau Tong Shopping Centre
10
Seminar on R&D Work
Sustainability Noise Mitigation Measures Since 2009, Housing Authority has carried out in-house studies on special
mitigation measures that will help to resolve traffic noise issues where public housing developments are located close to noisy roads.
To foster an improved and quieter living environment in PRH estates.Innovative Arc Screen Design Developed an innovative arc screen design to
alleviate the traffic noise problem in Sai Chuen Road PRH Development in Sham Shui Po.
Using a prototype installation in Dongguan to verify by in-situ noise measurements.
Close liaison with EPD Achieve noise reductions of 2.5 dB(A)
on the lower floors to 6.4 dB(A) on higher levels.
Way Forward To further refine the design
configuration into a balcony structure.
11
Seminar on R&D Work
Sustainability Noise Mitigation MeasuresSpecial Acoustic Window Design
For more severe noise problem such as sites situated very close to trunk roads with heavy traffic, the design of acoustic windows is being investigated allowing residents to enjoy more open views.
Laboratory tests of this window design concept gave promising results.
Way Forward
Mock Up Flats for Site Testing
Mock up flats with these special window prototypes have been constructed on site for further investigation and testing.
12
Seminar on R&D Work
Sustainability Life Cycle Assessment (LCA) & Life Cycle Costing (LCC) Method The HA has, since 2005, developed LCA and LCC method to assess and
determine more accurately and effectively the use of new materials at the design stage. New materials which are more environment-friendly and cost effective from the life cycle perspective have been progressively used in pilot projects since 2006. e.g. East Harbour Crossing Site Phase 4 (Yau Lai Estate). The Consultants were Business Environment Council, the University of Hong
Kong and Davis Langdon & Seah Management Ltd. The deliverables were –
(a) A LCA & LCC database for >100 building materials; and
(b) A computerized combined LCA/LCC “Decision Making Tool”.
Final Report has been launched onto HA’s web site for “KnowledgeSharing”.
Way Forward After implementation for 5 years,
further review would be carried outfor updating and expanding thedatabase of building materials.
13
Seminar on R&D Work
Health and HygieneCommon W-Trap System The outbreak of SARS in March 2003 has aroused
concern from the public over the problem of dried up floor traps with possible transmission of virus into the bathroom / kitchen from a contaminated soil and waste stack.
Collaboration with Department of Building & Construction, City University of Hong Kong to study the common trap system.
A series of reiterative tests successfully verified the operational stability.
14
Seminar on R&D Work
Health and HygieneCommon W-Trap System Buildings Department approved in principle to the use
of Common W-trap for connection to the floor drains in toilets and/or kitchens of PRH flats on conditions that :(a) only waste water from basin and shower shall be used for replenishing
purpose; and (b) length of untrapped pipework between W-trap and floor/shower drain not
exceeding 750mm. Design Guide and Technical Specification for drainage
design and site verification testing procedure were compiled for project implementation. Implemented in all new PRH projects since the first
completed project, East Harbour Crossing Site 3 (Yau Lai Estate), in 2008.
Way Forward Continue to study on the drainage system to prevent loss of
water seal and blockage of pipe at lower floors by adopting fluid dynamic engineering.
15
Seminar on R&D Work
Health and HygieneMail Box Type Disposal System For Recycling Materials Since 2007, an in-house development of Mail-box Type
Disposal System for Recycling Materials was carried out. To encourage the source separation of domestic waste
by PRH tenants at the Refuse Storage and Material Recovery Room (RSMRR) at typical domestic floors.
The research involved :- Consultation with EPD, FSD, BD, Estate
Management & Cleansing Contractors.In term of Safety and Security Hot Smoke Test; Fire Test on fire rated hatch doors with smoke seal Installation of Sprinkle System and Use of door sensors and CCTV for
operation and management control. In term of Noise Control Hydraulic self-closing hatch doors
with magnetic door catch.
16
Seminar on R&D Work
Health and HygieneMail Box Type Disposal System For Recycling MaterialsTo provide convenience to PRH tenants - Provision available on every domestic floor; Easily Accessible location from common area i.e.
corridor or lift lobby; and Easily reachable level by all users (including the
elderly and wheelchair users)To provide Hygienic Environment - Separated collecting points with
self-closing hatch doors Washable finishes; and Designated space for collection bins.Implementation The pilot project is East Harbour Crossing Site
Phase 5 (Yau Lai Estate) to be completed in Mid 2011.Way Forward To collect feedbacks from the tenants and the Estate
Management; and to further enhance the users friendliness.
17
Seminar on R&D Work
Health and HygieneFungal Resistance Test for Multi-layer Acrylic Paint Consultancy study commenced in October 2009 by Department of
Biology, Chinese University of Hong Kong. Current BS 3900:G6:1989 for testing ‘Resistance to Fungal Growth’ for multi-
layer acrylic paint takes 4 to 6 months to complete the test is considered too long. There is also feedback on increasing algae growth on the external wall adjoining natural slope or planters.
Currently, the testing of paint samples by the proposed testing method is completed and the result is being analyzed.
Way Forward To propose a test with a more appropriate testing time and the testing regime
which covers the common fungi and algae growth found locally. To establish a Hong Kong standard and regime for fungal test in multi-layer
acrylic paint.
18
Seminar on R&D Work
Universal Design Tactile Guide Path System with Multi-sensory Map We started developing multi-sensory map to enhance universal accessibility for all
residents including persons with visual impairment in 2005 as an integral part of tactile guide path system.
The multi-sensory maps are installed at strategic locations of housing estates to assist people to orientate and identify the tactile guide path leading to domestic blocks and major estate facilities.
Provide visual, tactile and voice messages to provide directions for all people, regardless of their age or quality of vision.
Collaborate with Hong Kong Society for the Blind to develop the multi- sensory map. Pilot projects at Redevelopment of Shek Kip Mei
Phase 1 and Kwai Chung Estate. Multi-sensory map together with tactile guide
path system has became a standard provision for new public housing estates since August 2006.
19
Seminar on R&D Work
Universal Design Tactile Guide Path System with Multi-sensory Map Visually impaired person using the tactile guide path system with multi-sensory map to
travel safely and effectively from Shek Kip Mei MTR Station to the domestic block.
Way Forward To further explore means to promote universal accessibility
and to meet diversified needs of all ages and person with disabilities.
Shek Kip Mei Phase 1
20