QSB 2134 - Estimating
CHAPTER 6 - EXCAVATION
Example 3 (Tutorial/ Seminar 1)
Calculate the cost required to excavate and backfill 4 pits for the following pad footing in sand
using hand.
Pad footing size 500mm x 500mm x 250mm
Column size 250mm x 250mm
250mm
Data:
a) Type of Excavation
Excavation
OutputBackfill Output
hour / m3 hour / m3
Oversite <250mm 1.25 - 1.50 0.50
Basement 2.00 - 2.25 1.00
Trenches 2.00 - 2.75 1.00
Pits 3.00 - 4.50 1.00
Reduce level 1.75 - 2.00 1.00
b) Labour rate 8hrs day
Skilled labour RM50
Unskilled labour RM40
* Skilled labour is required for excavation exceeding 3.00m
c) Additional 25% of time required to excavate and backfill in sand
d) Allow 10% for compaction in sand.
e) Allow 10% profit and 5% overhead.
f) Also calculate the unit rate (RM/m3) for excavation including backfilling.