BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO
* * * * *
SEMI-ANNUAL PROGRESS REPORT OF PUBLIC SERVICE COMPANY OF COLORADO FOR THE CHEROKEE 2x1 COMBINED CYCLE PLANT PROJECT
) ) Proceeding No. 11A-609E ) )
Semi-Annual Progress Report
Cherokee 2x1 Combined Cycle Plant
April 6, 2015
Colo
rado
PUC
E-Fil
ings
Syst
em
1
INTRODUCTION
The Commission has authorized Public Service Company of Colorado (“Public
Service”) to proceed with the completion of specific components of its Clean Air Clean
Jobs Act (“CACJA”) compliance plan, which the Commission approved in Proceeding
No. 10M-245E. This report is the sixth semi-annual status report on the Cherokee 2 X 1
Combined Cycle power plant (“Cherokee 2X1 CC”) construction and describes the
status of the project as of December 31, 2014.
OVERALL PROJECT STATUS
Currently the Cherokee 2x1 CC plant construction is approximately 87%
complete. All major powerblock equipment has been erected including combustion
turbine generators, steam turbine generator, heat recovery steam generators
(“HRSG’s”) and generator step up (“GSU”) transformers. Several other key activities
were completed during this reporting period as well.
The 2x1 CC power plant design-build contract (“DBC”) awarded to Kiewit is
progressing on schedule. Kiewit performed engineering, procurement and construction
activities throughout this reporting period. Engineering is now 100% complete,
procurement of engineered equipment is 100% complete, and construction is
approximately 87% complete. In addition to setting the major powerblock equipment
mentioned above, Kiewit completed erection of the steam turbine building, completed
erection and piping for the CTG’s, completed the lube oil flushes for the CTG’s,
completed erection and hydrotesting of the HRSG’s, set the boiler feed pumps,
completed the major piping systems, pulled the majority of electrical cable, and
continued terminating electrical cable. The natural gas supply line to the new site has
been completed and blown clean. The buildings have been completed with heating,
2
ventilation and air conditioning (“HVAC”), lighting and electrical service. Nooter/Eriksen
completed all deliveries of equipment and materials for the HRSG supply contract, and
General Electric (“GE”) completed deliveries of miscellaneous equipment and materials
for the combustion turbine generators (“CTG’s”) supply contract and the replacement
generator for the Steam Turbine Generator (“STG”).
Startup activities commenced during this reporting period. Power was backfed
into the Unit 5 GSU on November 15, 2014 allowing equipment and system checkout to
commence. The Distributed Control System (“DCS”) was energized on temporary power
in November as well, allowing checkout of control loops to begin. All electrical gear was
checked out and energized in early December and the instrument air compressors were
checked out and energized.
Progress photos of the construction are included as Attachment 1 of this report.
PROJECT FINANCIAL PERFORMANCE
In our application in Proceeding No. 11A-609E, we provided a cost estimate for
the project of $534.518 million, which we subsequently revised to $531.525 million. In
this report, we use the revised $531.525 million estimate as our “Baseline Budget”.
Attachment 2 is the Baseline Budget. Attachment 3 converts the Baseline Budget into a
format consistent with the Company’s systems for managing and tracking the project.
The Company tracks costs by contracts and purchase orders.
The term “Current Estimate” is the current expected completion cost for each
planned contract. As contracts are awarded, the current estimate includes the actual
contract value plus an allowance for changes over the contract lifecycle. The current
estimate also includes forecasted costs not yet under contract. The term “spent to date”
means the actual costs incurred through December 31, 2014.
3
We currently have 98% of the total project direct cost under contract. The
budgets shown in Attachment 3 are divided into direct costs and indirect costs. The
direct cost contracts and purchase orders account for approximately 93% of the total
project costs. The indirect costs account for 7% of the total project costs. As of
December 31, 2014, we have spent $471.197 million or 88.7% of the Baseline Budget
of $531.525 million.
PROJECTED VS. ACTUAL CONSTRUCTION SCHEDULE
The Level 2 projected construction schedule was included with the CPCN. The
schedule showed a completion in December 2015 for the 2x1 CC power plant. The
schedule has been updated to show actual progress through December 31, 2014,
including a comparison of projected versus actual progress. The activities to date have
been completed ahead of the original baseline, and the overall project is currently
tracking to meet the required date of December 2015. A current Level 2 Critical Path
Schedule is included as Attachment 4.
4
ATTACHMENTS
1. Progress Photos 2. CPCN Settlement Amount and Baseline Cost Estimate 3. Summary Cost Estimate and Spent to Date amounts 4. Project Schedule
5
Attachment 1 - Project Photos Steam Turbine Building Siding Complete
Installing Fuel Gas Line into new Plant
6
Steam Turbine Generator Sound Enclosure
Tanks Insulation Complete
7
Setting up for Boiler Hydrotest
Site View
ATTACHMENT 2. Baseline Cost Estimate
ATTACHMENT 3. Summary Cost Estimate and Spend to Date Report
ATTACHMENT 4. Project Schedule