Semi-annual Environmental Monitoring Report · This environmental monitoring report is a document...
Transcript of Semi-annual Environmental Monitoring Report · This environmental monitoring report is a document...
Environmental Monitoring Report
Semestral Report June 2016 For the period January - June 2015
IND: Jammu and Kashmir Urban Sector
Development Investment Program, Project 2
Prepared by the Economic Reconstruction Agency for the Government of Jammu and Kashmir
and the Asian Development Bank.
This environmental monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Semi-Annual Environmental Monitoring Report
Loan Number: 2925 IND Period: January 2015 to June 2015
IND: Jammu and Kashmir Urban Sector Development Investment Program
Submitted By:
Economic Reconstruction Agency, Government of Jammu and Kashmir
Contents
1. INTRODUCTION ..................................................................................................... 1
2. COMPLIANCE STATUS WITH NATIONAL /STATE /LOCAL STATUTORY ENVIRONMENTAL REQUIREMENTS .................................................................... 6
3. COMPLIANCE STATUS WITH THE ENVIRONMENTAL COVENANTS AS STIPULATED IN THE LOAN AGREEMENT ......................................................... 11
4. COMPLIANCE STATUS WITH ENVIRONMENTAL MANAGEMENT AND MONITORING PLANS AS STIPULATED IN THE ENVIRONMENTAL DOCUMENTATION AS AGREED WITH ADB. ...................................................... 12
5. APPROACH AND METHODOLOGY ENGAGED FOR ENVIRONMENTAL MONITORING OF THE PROJECT ........................................................................ 16
6. MONITORING OF ENVIRONMENTAL RECEPTORS/ ATTRIBUTES ................... 16
7. ANY OTHER ENVIRONMENTAL ASPECTS, IMPACTS OBSERVED DURINGIMPLEMENTATION WHICH WERE NOT COVERED EARLIER .............. 48
8. DETAILS OF COMPLAINTS RECEIVED FROM PUBLIC AND ACTIONS TAKEN THEREOF TO RESOLVE ......................................................................... 48
9. FOLLOW-UP ACTIONS AND CONCLUSIONS ..................................................... 48
APPENDIX-1: PUBLIC CONSULTATION ATTENDANCE DETAILS OF FLYOVER-JEHANAGIR CHOWK TO RAMBAGH ................................................ 49
APPENDIX-2: PUBLIC CONSULTATION ATTENDANCE DETAILS OF FLYOVER AT KRALPORA PLANT SITE .............................................................. 50
APPENDIX-3: PUBLIC CONSULTATION ATTENDANCE DETAILS OF DRAINAGE SUBPROJECT AT ATHWAJAN ........................................................ 51
APPENDIX-4: PHOTOGRAPHS-PUBLIC CONSULTATION OF TRANCHE 2 .............. 52
APPENDIX-5:SAMPLING SITE LOCATION MAP OF FLYOVER FROM JEHANGIRCHOWK-RAMBAGH, SRINAGAR ...................................................... 53
APPENDIX-6:SAMPLING SITE LOCATION MAP OF FLYOVER- LABOUR CAMP/ BATCHING PLANT AT KRALPORA, SRINAGAR .................................... 54
APPENDIX-7: SAMPLING SITE LOCATION MAP OF STORM WATER DRAINAGE ALONG NH-1A, ATHWAJAN, SRINAGAR ........................................ 55
APPENDIX-8: SAMPLING SITE LOCATION MAP OF MULTI-STORIED PARKING LOT AT LAL CHOWK, SRINAGAR ..................................................... 56
APPENDIX-9: SAMPLING SITE LOCATIONS OF AIR AND NOISE QUALITY UNDER SUBPROJECT IN JAMMU SECTOR, TRANCHE II ................................. 57
APPENDIX-10: WATER SAMPLING SITE LOCATIONS UNDER SUBPROJECT IN JAMMU SECTOR, TRANCHE II .............................................. 58
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
1. INTRODUCTION
1.1. Overall Project Description:
1. The State of Jammu and Kashmir lies in the northernmost part of the country and
shares international border with Pakistan and China. This physiographic situation
attaches strategic importance to the region as well as the infrastructural development in
the state. The state has three main geographical regions namely Jammu, Kashmir valley
and highlands of Ladakh. As per details from Census 2011, Jammu and Kashmir has
population of 1.25 Crores, an increase from figure of 1.01 Crore in 2001 census. The
population forms 1.04% of India in 2011, compared to 0.99% in 2001. As per census
2011, the Sex Ratio of female is 889 per 1000 male, which is below national average of
940. While, in 2001 the sex ratio of female was 900 per 1000 males. The literacy rate
has seen an upward trend at 67.16% as per 2011 census as compared to the national
literacy rate of 64.80%, while in 2001 literacy rate stood at 55.52%.
2. Jammu and Srinagar are the two major cities where majority of urban population is
concentrated while other smaller towns share the rest. Urban infrastructure in these
places for long has been neglected and hence, is subject to severe urban infrastructure
problems. Although, at least, majority of population in Jammu and Srinagar cities have
been provided with piped water supplies, the other urban amenities remain neglected.
This is mainly due to meager investments made in the urban infrastructure either by
private or by public sector.
3. The Government of Jammu and Kashmir (GoJK), apart from the ADB financed Multi-
Sector Project for Infrastructure Rehabilitation (MPIR) in Jammu and Kashmir, again
approached ADB for assistance in urban sector development for more development
works and studies so as to implement comprehensively the urban sector reforms. The
GoJK through Jammu and Kashmir Economic Reconstruction Agency has conceived the
Jammu and Kashmir Urban Sector Development Investment Program (JKUSDIP) in its
effort to boost economic growth in Jammu and Kashmir State. The primary objective of
JKUSDIP is to promote economic development in Jammu and Kashmir State through
expansion of basic services such as water supply, sewerage, sanitation, drainage, solid
waste management, urban transport and other municipal functions in Jammu, Srinagar
and other important urban centers of the State. JKUSDIP will also strengthen the service
delivery capacity of the responsible state urban agencies and urban local bodies through
management reforms, capacity building and training.
1.2. Project Objectives:
4. The proposed JKUSDIP will foster the economic growth in Jammu and Kashmir State. The long term Project objectives are to contribute to the economic development of Jammu and Kashmir through enhanced and sustainable growth in the main urban areas with emphasis on promoting commerce and on improvement of livelihood for the poor.
5. The urban sector sub-projects are aimed at expansion of basic services such as
water supply, sanitation, waste management, urban transport and other municipal
functions in Jammu and Srinagar cities and other urban centers in order to cater to the
demands and requirements of the increasing population. The overall program envisages
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
2
the following broad benefits:
i. Improved water supply system ii. Improved sewerage/drainage systems iii. Improved solid waste management iv. Improved road and traffic (urban transport) conditions v. Other municipal facilities
1.3. Environmental Category:
6. The Project 2 under JKUSDIP was categorized as Environmental Category “B”, according to ADB’s Safeguard Policy Statement-2009. All the subprojects under
execution in Srinagar and Jammu have been categorized as Category “B”. 1.4. Environmental Performance Indicators, if any:
7. For effective monitoring, selected environmental parameters have been identified as
indicators which may be qualitatively and quantitatively measured and compared over a period of time in order to assess/ensure the compliance to environmental management plans (EMPs). The environmental performance indicators selected are physical, biological and social characteristics identified as most important in affecting the environment at critical locations all along the sub-project corridors. The parameters identified as performance indicators are:
i. Compliance with environmental management and monitoring plan. ii. Compliance to State/National environmental regulations. iii. Monitoring of ambient air quality, water quality and noise levels and
comparison with baseline environmental quality and State/National standards.
1.5. Overall project progress, agreed milestones and implementation schedules:
8. In Srinagar, construction work for the following three sub-projects are in progress:
i. Construction of Elevated Expressway Corridor from Jehangir Chowk to Rambagh- Natipora in Srinagar City (Physical progress of 28.08%).
ii. Construction of Multi-storied mechanized Parking Facility at KMDA Stand in Srinagar city (Physical progress of 13.75%).
iii. Construction of storm water drains in the adjoining areas of NH-Bypass in Srinagar (Physical progress of 22.59%).
9. In Jammu, construction work for the following fivesub-projects are in progress:
i. Construction of Bikram Chowk Flyover and Widening /Strengthening of Road
from Bikram Chowk to Govt. Women’s Degree College on Bikram Chowk–Satwari Chowk Road Corridor, Jammu Under Contract Package JKUSDIP Jammu/UT-01 (Physical Progress of 26.87).
ii. Rehabilitation and Channelization of Storm Water Drains at Channi Himmat in Jammu City, Under Contract Package JKUSDIP Jammu/SWD-02 (Physical progress of 48.67%).
iii. Construction of Tube wells, Installation Water Supply Rehabilitation Programme (19 Nos, tube well) (lot-1 =12 Nos. & lot-2=7) Under Contract Package JKUSDIP Jammu/ WS-01 (Physical progress of 11.52%)
iv. Replacement of Worn-out pipe lines, laying of new pipelines in distribution
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
3
network and Construction of OHT at Jammu city Under Contract Package JKUSDIP Jammu/ WS-02 (Physical progress of 3.90%).
v. Rehabilitation and Channelization of Storm Water drain at Gangyal and Digiana areas in Jammu City JKUSDIP Jammu / SWD-01 (Physical progress of 41.41%).
1.6. Any other information useful for assessing environmental performance
of the project:
10. Sensitisation Workshop with Contractors on Gender responsive targets and Core Labour Standards In order to attain one of the objectives enlisted in the gender action plan, i) to build awareness on gender issues and to ensure labour safety and safeguard; ERA organized 3 workshops at the construction sites of Tranche-2 in collaboration with the consultants and contractors to develop understanding on gender awareness, social inclusion, core labour standards and safeguard of the labours and local community. The workshop cum training programme were organized on 11thand 12th May in Srinagar in the following locations
Kralpora Labor Camp Site – Jehangir Chowk Flyover Project
Rawalpora Drainage Construction Site – Rawalpora Chanpora Drainage Project
Pantha Chowk – Storm Water Drainage at Athwajan along NH Bypass Multi-Level Parking Site - Multi-Level Parking Project
11. The workshop sessions were divided into three parts (i) inaugural session (ii) generic and site specific discussion on Gender and Safety and Safeguards of workers and local communities along the working corridor (iii) interactive discussion with labours/ workers and finding solutions to challenges.
The key areas of discussion are as follows:
The co-relation between infrastructure, gender, improved health and hygiene;
The importance of the safety gears (Personal Protective Equipment) and constant use while on site/ during construction activity. Few real life examples were also shared with the labours as a motivation to wear safety gears;
Brief introduction on applicable labour Laws and issues like minimum wages and insurance policy, provisions against use of child labour and equal wages irrespective of gender, caste / creed and religion.
The provision of environmental protection in every contract document and implementation of EMP.
12. Nearly 200 participants belonging to ERA, Contractors (site workers and officials), PMC and DSC participated in the said workshops. Most importantly site workers participated positively and openly discussed their concerns. Many even openly admitted to their reluctance for using Personal Protective Equipment while as some workers opined that adequate PPE were not provided timely by the contactor. Every point were discussed earnestly and possible solutions were also discussed.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
4
Photographs of the Workshop
Workshop in progress at construction site near Pantha Chowk under “Construction of Surface water drainage system in Athwajan catchment on National highway Byepass at Srinagar”
Workshop in progress at construction site at Labour Camp, Kralpora under “Construction of Flyover / Expressway Corridor from Jehangir Chowk to Rambagh- Natipura in Srinagar City”
Workshop in progress at construction site at “Multi-Storied Parking Facility at Lal Chowk Srinagar“
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
5
A Safeguard induction training program was also conducted on safeguard issues and application of Environmental Management Plan (EMP) at DSC office, Gandhi Nagar, Jammu on 14th April 2015.
13. Team Leader, DSC Jammu, Construction Manager of DSC, Project Manager of
contractors, Supervision Engineers and Safety Officers of contractor, and Support Engineers of DSC and Support Environment Specialist of DSC participated in the Training Program.
14. Team Leader, DSC Jammu, Construction Manager of DSC, Project Manager of contractors, Supervision Engineers and Safety Officers of contractor, and Support Engineers of DSC and Support Environment Specialist of DSC participated in the Training Program.
15. Public consultation was conducted for the subprojects under Tranche-2. During
consultation with different stakeholders, some of the issues addressed by public were
mostly “dust generation”related of Flyover and Storm Water drainage in Srinagar. They have also suggested measures apart from normal water sprinkling by way of water
tankers like “frequent mopping and scrapping of the left-over soil produced from
excavation activities” must be implemented in order to suppress dust comprehensively. Same has been instructed to the contracting firms for implementation. Refer section 6.4
under air Quality data and comparison, which depicts RSPM10 values of Jan-June 2015
below baseline data. This shows the effective EMP implementation.
16. Whereas, public has no issue pertaining to ongoing works of the parking lot at Lal
Chowk. However, they have shown a keen interest for early completion of the project so
that the concerned area of the Lal Chowk will have a better parking facility of that quality.
Refer Appendix 1-4 for Public Consultation (Participation) details.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
6
2. COMPLIANCE STATUS WITH NATIONAL /STATE /LOCAL STATUTORY ENVIRONMENTAL REQUIREMENTS
17. Status of statutory environmental requirements is shown in the following table:
S. N. Name of Sub-project Statutory Environmental Requirements
Status of Compliance Actions Required
1. Construction of Flyover/Expressway Corridor from JehangirChowk to Rambagh – Natipora in Srinagar.
Environmental clearance under EIA Notification, 2006.
Not Required. Contractor instructed to comply and follow-up with SPCB for the required renewal of consents for the (2 no) batching plants, (11 no) D.G sets on priority basis. Contractor was also assisted in getting the early process at SPCB level. Fresh renewal of consents expecting soon.
Approval for tree cutting
Permission obtained from the concerned authority PIU for cutting of 13 no’s Chinar trees (all trees cleared by concerned department)
Consent to establish/ operate Batch Mix Plant
Batch Mix Plant: 2 No’s installed at Kralpora, Budgam. Consent to Establish details:
60 RDK of 2013 Dated: 30/10/2013 (Capacity-216000 m
3/A)
61 RDK of 2013 Dated: 30/10/2013 (Capacity-216000 m
3/A)
Consent to Operate details: (Validity upto March 2015)
108 RDK of 2014 Dated: 29/03/2014 (Capacity-216000 m
3/A)
112 of RDK of 2014 Dated: 29/03/2014 (Capacity-216000 m
3/A)
Contractor has initiated the process of renewal of Consent to operate 2 No of Batch plants vide application no: 02/SRINAGAR-FLYOVER/P&A/001/VOL.1/338 Dated 20-03-2015
Consent to operate for stone crusher.
Stone crusher Plant (Outsourced):
Consent no: 1593 of 2015, Valid up to January 2016
The stone aggregate material is being procured from approved Stone Crusher Plants. Other outsourced plants from the contractor awaited.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
7
Program Management Consulting Services
Consent to establish & operate Hot Mix Plant
Hot Mix Plant : Consent obtained and valid up to Feb 2016
Consent to establish and operate DG Sets
D.G Sets: Consent of Operate (Consent submitted details as below):
109 RDK of 2014 Dated: 29/03/2014 (1 No-125KVA)
110 RD of 2014 Dated: 29/03/2014 (1 No- 82.5 KVA)
111 RDK of 2014 dated: 29/03/2014 (1 No- 250 KVA)
97 of 2014 Dated: 22/05/2014 (2 No’s- 125 & 82.5 KVA)
Renewal processes initiated by the contractor vide application no. 012/Srinagar/flyover/ P&A/001/vol-1/337 dated 20-03-2015.
PUC certificates for contractor’s vehicles.
Submitted by contractor
2. Construction of Multi-storied mechanized parking facility on M A Road near Lal Chowk Srinagar.
Environmental clearance under EIA Notification (MoEF), 2006.
Not required. Contractor directed to comply with fresh consent of Stone crusher plant from the plant owner. Since contractor is procuring stone aggregate from outsourced agency.
Approval for tree cutting Not required
Consent to establish/ operate Stone Crusher Plant from SPCB
Stone Crusher Plant (Outsourced): 902 of 2013, Valid up to September 2014 (Consent expired- renewal initiated). The aggregate material is being procured from approved crusher plant.
Consent to establish/ operate for Batching Plant
Batching Plant (Mini- mobile type): Consent No: 43 of 2014, Dated:25/04/2014 Validity expired
Renewal process to SPCB initiated by the contractor.
Consent to establish/ operate DG Sets from SPCB.
D.G Set: Consent No: 44 of 2014 Dated: 25/04/2014 valid upto April 2015
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
8
Program Management Consulting Services
Renewal process to SPCB initiated by the contractor.
PUC certificates for contractor’s vehicles.
Submitted by the Contractor.
3. Construction of Surface Water Drainage System in Athwajan catchment on national Highway Bypass at Srinagar.
Environmental clearance under EIA Notification, 2006.
Not Required.
Contractor directed to comply and follow-up with SPCB for the required consents (1 no) D.G set on priority basis.
Approval for tree cutting. Not required
Consent to operate for Stone Crusher Plant from SPCB.
The aggregate material is being procured from approved crusher plant. Consent No. 119 of 2015, valid upto April 2016
Consent to operate for HMM Plant from SPCB.
HMM Plant Consent No: 1593 of 2015, Valid up to January 2016
Consent to establish/ operate DG Sets from SPCB.
D.G Set Consents (to establish/ operate) yet to submit. Contractor applied to SPCB vide PCB/1980/DR Sabina and is under process
PUC certificates for contractor’s vehicles.
Submitted by Contractor.
Jammu.
4 Construction of Bikram Chowk Flyover and Widening/ Strengthening of Road from Bikram Chowk to Govt. Women’s Degree College on Bikram Chowk – Satwari Chowk Road Corridor, Jammu Under Contract Package JKUSDIP Jammu/UT-01
Approval for tree cutting
Approval for tree cutting obtained from the concerned department.
Consent to establish and operate stone crusher
Stone aggregate material is being procured from approved Stone Crusher Plant. Copy of consent letter from utility owner obtained and submitted by contractor. Consents to operate (Renewal) for stone crusher vide consent no148 of 2015 dated 21-04-2015 valid up to November 2015.
Consent to establish and operate concrete batching plant
Consents to Establish / Operate of Batching plant vide consent no: 190 of 2014 dated 05-03-2014 valid upto March 4, 2015.
Contractor applied for Consents to Establish / Operate (Renewal) of Batching plant and renewal awaited.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
9
Program Management Consulting Services
Consent of D.G. set Contractor using 3 DG Sets- Consents to establish / operate for D.G set (35 KVA) vide consent no: 191 of 2014 dated 05-03-2014 valid upto March 4, 2017. Obtained and submitted by the Contractor.
Contractor applied to SPCB for Consents to establish / operate for second and third D.G set (25 KVA and 65 KVA). Submission awaited.
PUC certificates for contractor’s vehicles
Obtained and submitted by the Contractor.
5. Rehabilitation and Channelization of Storm Water Drains at Channi Himmat in Jammu City, Under Contract Package JKUSDIP Jammu/SWD-02
Approval for tree cutting.
134 numbers of trees (non-scheduled) are coming in the alignment of R1 and R2 drains. Permission of tree cutting is required and process of permission through PIU (ERA) in process.
Letter for the permission of tree cutting has been issued by the competent authority.
Consent to establish and operate stone crusher
Stone aggregate material is being procured from approved Stone Crusher Plant having the Consent to operate (renewed) from SPCB vide consent No. 1563 of 2014, dated 24-03-2014. Valid up to March 2015.
Contractor asked to get the copy of consent certificate (renewal) from utility owner for submission.
PUC certificates for contractor’s vehicles.
Obtained and submitted by the contractor
6. Construction of Tube wells, Installation Water Supply Rehabilitation Programme (19 Nos, tube well) (lot-1 =12 Nos. & lot-2=7) Under Contract Package JKUSDIP Jammu/ WS-01
Approval for tree cutting
Cutting of Forest tree or any other schedule tree not required
Consent to establish and operate stone crusher
Obtained and submitted by the Contractor
PUC certificates for contractor’s vehicles
Obtained and submitted by the Contractor
7. Replacement of Worn-out pipe lines, laying of new pipelines in
Approval for tree cutting
Cutting of Forest tree or any other schedule tree not required
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
10
Program Management Consulting Services
distribution network and Construction of OHT at Jammu city Under Contract Package JKUSDIP Jammu/ WS-02
Consent to establish and operate stone crusher
Obtained and submitted by the Contractor
PUC certificates for contractor’s vehicles
Obtained and submitted by the Contractor.
8. Rehabilitation and Channelization of Storm Water drain at Gangyal and Digiana areas in Jammu City JKUSDIP Jammu/ SWD-01
Approval for tree cutting
Cutting of Forest tree or any other Schedule tree not required.
Consent to establish and operate stone crusher
Stone aggregate material is being procured from approved Stone Crusher plant having the Consent to operate from SPCB vide consent No. 179 of 2014 dated 15-12-2014 valid up to 14-12- 2015.
Consent to establish and operate for Batch mix plant
Obtained from SPCB vide consent no: 1317 of 2014 dated 18-11-2014 valid upto 17-11-2015. and submitted by the Contractor.
PUC certificates for contractor’s vehicles
Obtained and submitted by the Contractor
Consent of D.G set. Consent of one D.G set awaited To pursue for submission of consent of DG set from Contractor.
9. Replacement of Worn-out machineries and electrical equipment including essential civil works in Tube wells and Central Pumping Station (CPS) at Jammu City Water Supply Rehabilitation Programme under Contract Package JKUSDIP Jammu / WS – 03.
Approval for tree cutting
Cutting of Forest tree or any other schedule tree not required
Consent to establish and operate stone crusher
Not required at this stage because no physical work started yet.
PUC certificates for contractor’s vehicles
Not required at this stage because no physical work started yet.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
11
3. Compliance Status with the Environmental Covenants as Stipulated in the Loan Agreement
18. The status of compliance with environmental loan covenants of Tranche-2 is presented below:
Loan Covenants Compliance status
The Borrower shall ensure, or cause the EA to ensure that;
the preparation, design, construction, implementation, operation and decommissioning of the project, and all subproject facilities comply with; (i)all applicable laws and regulations of the Borrower and the State relating to environment, health, safety; (ii) the Environmental Safeguards;(iii) EARF; and (iv) all measures and requirements set forth in the respective IEE and EMP, and any corrective or preventative actions set forth in a Safeguards Monitoring Report.
Being complied with.
All bidding documents and contracts for Works contain provisions that require contractors to:-
Comply with the measures and requirements relevant to the contractor set forth in the IEE and EMP; and any corrective or preventive actions set out in a Safeguards Monitoring Report.
The bidding documents and contract agreements for work are incorporated with the provisions set forth in the IEE and EMP and are being complied with.
Make available a budget for all such environmental measures.
Environmental monitoring and mitigation costs allocated/ incorporated in contract agreements.
Provide the EA with a written notice of any unanticipated environmental impacts that arise during construction, implementation or operation of the project that were not considered in the IEE and in the EMP.
Being complied with
Adequately record the condition of roads, agricultural land and other infrastructure prior to starting to transport materials and construction.
The existing condition of roads and other infrastructure has been recorded in the form of photographs and video recording as well.
Fully reinstate pathways, other local infrastructure, and agricultural land to at least their pre-project condition upon the completion of construction.
All the areas that if disturbed by construction activities will be cleared and restored to pre-project condition.
Submitsemi-annual Safeguards Monitoring to ADBand disclose relevant information from such reports to affected persons promptly upon submission;
Semi-annual reports are prepared and submitted to ADB as per the guidelines.
If any unanticipated environmental risks and impacts arise during construction, implementation or operation of the Project that were not considered in the IEE and EMP as applicable, promptly inform ADB of the occurrence of such risks or impacts, with detailed description of the event and proposed corrective action plan; and
In case of any unanticipated environmental risks and impacts arise during construction, implementation or operation of the Project that were not considered in the IEE and EMP as applicable that shall be immediately informed to ADB with detailed description of the event and proposed corrective action plan.
Report any breach of compliance with the measures and requirements set forth in the EMP, promptly after becoming aware of the breach.
Breach will be reported to ADB immediately after becoming aware of it.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
12
4. COMPLIANCE STATUS WITH ENVIRONMENTAL MANAGEMENT AND MONITORING PLANS AS STIPULATED IN THE
ENVIRONMENTAL DOCUMENTATION AS AGREED WITH ADB. 19. The compliance status with environmental management and monitoring plan is shown in the following table:
S. No Sub-project Name EMP Part of Contract Documents
EMP Being Implemented
Status of EMP Implementation
Actions Proposed/ Additional Corrective Measures Required
(Yes/No) (Yes/No) (Excellent/ Satisfactory/ Partially Satisfactory/ Below Satisfaction)
1. Construction of Flyover/ Expressway Corridor from JehangirChowk to Rambagh - Natipora in Srinagar.
Yes Yes Satisfactory Frequency of water sprinkling to be increased at Section –D. Necessary safety measures should be taken during girder launching and other activities by way of cranes and heavy machinery
2. Construction of Multi-storied mechanized parking facility on M A Road near Lal Chowk Srinagar.
Yes Yes Satisfactory
3. Construction of Surface Water Drainage System in Athwajan catchment on national Highway Bypass at Srinagar.
Yes Yes Partially Satisfactory At dust prone or sensitive zones where traffic movement more frequent “regular mopping and scrapping of the left-over soil produced from excavation activities” must be implemented in order to suppress dust comprehensively and to be followed by water sprinkling measures.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
13
Program Management Consulting Services
Contractor to ensure further strengthening of traffic and public safety measures at NH road. .
Jammu.
4.
Construction of Bikram Chowk Flyover & Widening/Strengthening of Road from Bikram Chowk to Govt. Women’s Degree College on Bikram Chowk-SatwariChowk Road Corridor, Jammu Under Contract Package JKUSDIP Jammu/UT-01
Yes
Yes
Satisfactory
For previous non-compliance of EMP measures certain amount from IPCs of contractors was deducted and the details for the same are mentioned in table-(a).
5.
Rehabilitation and Channelization of Storm Water Drains at ChanniHimmat in Jammu City, Under Contract Package JKUSDIP Jammu/SWD-02/
Yes
Yes
Partially Satisfactory
Contractor is continuously instructed to strengthen PPEs for workers, traffic safety measures, and to further improve dust suppression measures by way of frequent water sprinkling at dust prone zones.
6 Rehabilitation and Channelization of Storm Water drain at Gangyal and Digiana areas in Jammu City JKUSDIP Jammu / SWD-01
Yes
Yes
Satisfactory
----
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
14
Program Management Consulting Services
7.
Construction of Tube wells, Installation Water Supply Rehabilitation Programme (19 Nos, tube well) (lot-1 =12 Nos. &lot-2=7) Under Contract Package JKUSDIP Jammu/ WS-01
Yes
Yes
Satisfactory
-
8.
Replacement of Worn-out pipe lines, laying of new pipelines in distribution network and Construction of OHT at Jammu city Under Contract Package JKUSDIP Jammu/ WS-02
Yes
Yes
Satisfactory
---
9. Replacement of Worn-out machineries and electrical equipment including essential civil works in Tube wells and Central Pumping Station (CPS) at Jammu City Water Supply Rehabilitation Programme under Contract Package JKUSDIP Jammu / WS – 03.
Yes
No
Physical Work not yet started
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
15
20. Details of amount deducted from the IPC's for Non-compliance of various components of EMP,in
accordance with ERA Circular No.: ERA/CEO/1038/ADM/9629-42, DATED 10/01/2013, during
the period January 2015 – June 2015.
Table-4a: Updated status ofamount withheld from the IPC's for Non-compliance of EMP, Srinagar
Table-4b: Updated status of amount withheld from the IPC's for Non-compliance of EMP, Jammu
S. No. Contract Package Bill No. Total Recommended
Deductions 1 Construction of Flyover/Expressway Corridor from
Jehangir Chowk to Rambagh – Natipora in Srinagar. IPC-14th 1,24370 IPC-15th 2,53528
2 Construction of Surface Water Drainage System in Athwajan catchment on National Highway Bypass at Srinagar.
IPC-7th 9,21,351
S. No. Contract Package Bill No. Total Recommended
Deductions 1 Rehabilitation and Channelization of Storm Water
Drains at ChanniHimmat in Jammu City, Under Contract Package JKUSDIP Jammu/SWD-02/
1. IPC -10 57864 2. IPC -11 55530
2 Construction of Bikram Chowk Flyover & Widening/Strengthening of Road from Bikram Chowk to Govt. Women’s Degree College on Bikram Chowk-SatwariChowk Road Corridor, Jammu Under Contract Package JKUSDIP Jammu/UT-01
IPC-09 163160
3 Construction of Tube wells, Installation Water Supply Rehabilitation Programme (19 Nos, tube well) (lot-1 =12 Nos. & lot-2=7) Under Contract Package JKUSDIP Jammu/ WS-01
IPC-04 (LOT- 1)
65096
IPC-04 (LOT- 2)
125278
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
16
Program Management Consulting Services
5. APPROACH AND METHODOLOGY ENGAGED FOR ENVIRONMENTAL MONITORING OF THE PROJECT
21. In Srinagar and Jammu, construction work on eight packages is under execution. All Contractors
have nominated and mobilized Environmental Safety Officers for ensuring EMP implementation at
site and reporting thereof. Monthly environmental reports are being submitted at the end of each
month by the Contractors.
22. Site visit/ inspections are being carried out on regular basis to assess the EMP implementation of
Tranche-2 subprojects under execution.
23. The safeguards staff conducts frequent site visits to monitor the implementation of safeguard
measures on sites and report to concerned official about issues/problems related to environmental
non-compliance. Necessary directions in the form of corrective action measures, in case of non-
compliances, are being issued to the contractors on the site and through letters about the
procedures to resolve problems/issues or requirements.
6. MONITORING OF ENVIRONMENTAL RECEPTORS/ ATTRIBUTES
1.7. Monitoring basis:
24. Air quality, water quality and noise levels are required to be monitored to check if any adverse
impact is being caused by the construction activities. The monitoring of these variables is to be
carried out in construction areas at sensitive locations within 100m impact zone of the subproject.
The monitoring of environmental variables is being carried out as per the agreed Environmental
Monitoring Plan.
1.8. Type of environmental receptor/attribute to be monitored(for each type):
25. The environmental attributes to be monitored include the air, noise and water quality parameters at
the construction sites in sub-project corridors. The air quality parameters monitored include RSPM
(PM10) and (PM2.5), SO2 and NO2. The water quality parameters include temperature, pH, electrical
conductivity (EC), dissolved oxygen (DO), biochemical oxygen demand (BOD5), chemical oxygen
demand (COD), total suspended solids (TSS), total dissolved solids (TDS), Turbidity, Total
Alkalinity, Total hardness, Calcium Hardness and Magnesium Hardness. In case of noise, the day
time Leq values are monitored.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
17
Program Management Consulting Services
1.9. Methodology, Regulatory Standards of monitoring and equipment’s adopted for Environmental Monitoring Laboratory (EML):
26. The following Assessment Methodology, Acceptable Standards and Equipment’s adopted for monitoring:
S.No Parameters Assessment Methodology
1Acceptable
Standards Cause for rejection
Equipment’s in Use
A. Ambient Air Quality (2NAAQ Standards, 2009)- Time weighted average
1. RSPM–particulate matter PM10
GravimetricHigh Volume Sampler method (attached with cyclone).
100 µg/m
3
60 µg/m3
Respirable Dust Sampler, Envirotech -APM 460 BL Digital Balance, Schimadzu – BL-220H
2 3Fine
particulate matter
PM2.5,
Gravimetric method. Beta Attenuation
60µg/m3
40µg/m3
Ambient Fine Dust Sampler, Instrumex.
3. SO2 Modified West and Gaeke Method.
80 µg/m3 High Volume Air
Sampler, Envirotech –APM 460BL. Thermo-electrically cooled gaseous sampling attachment, Envirotech –APM 411TE Digital Spectrophotometer, EI-305.
4. NO2 Modified Jacob &HochheiserMethod.
80 µg/m3 High Volume Air
Sampler, Envirotech –APM 460BL. Thermo-electrically cooled gaseous sampling attachment, Envirotech –APM 411TEDigital Spectrophotometer, EI-305.
B. 4Ambient Noise Level
1. Residential Area
Direct Reading in Decibel Sound Level Meter.
55dB(A) Leq
(Day time)
Digital Sound Level Meter, AZ-8928
2. Commercial Area
Direct Reading in Decibel Sound Level Meter.
65 dB(A) Leq
(Day time))
Digital Sound Level Meter, AZ-8928
1CPHEEO Manual, MoUD, GOI, May 1999; and MoEF, Act and Rules, 1986& Amendments 2000
2 National Ambient Air Quality Standards (NAAQS)
3 RSPM2.5 sampler procured by the JK ERA and will part of environmental monitoring from next monitoring period.
4 Standards specified in the schedule of Noise Pollution (Regulation And Control) Rules, 2000 of Government of India The
Principal Rules were published in the Gazette of India, vide S.O. 123(E), dated 14.2.2000 and subsequently amended vide
S.O. 1046(E), dated 22.11.2000, S.O. 1088(E), dated 11.10.2002, S.O. 1569 (E), dated 19.09.2006 and S.O. 50 (E) dated
11.01.2010 under the Environment (Protection) Act, 1986.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
18
Program Management Consulting Services
C. 5Ambient Water Quality (For Drinking / Ground Water)
1. Temp (in ºC)
Digital/Mercury Thermometer Method.
>20 ºC Digital/Mercury Thermometer
2. Color (Hazen units)
Hazen Method 5 Platinum cobalt scale
25 -
3. Taste and Odour
Unobjectionable
Objectionable
-
4. pH value Electrometric Method.
6.5-8.5 >8.5 Digital pH Meter, HANNA – HI98127,
5. Electrical Conductivity (EC) µs/cm
Electrometric Method.
≤ 500 µs/cm 1000 µs/cm
Digital TDS/EC Meter, HANNA – HI-96311
6. Dissolved Oxygen (DO) mg/l
Winkler's Method Using Azide Modification
> 6 mg/l Winkler's Method
7. Total Suspended Solids (TSS) mg/l
Gravimetric (Filtration and Drying at 105°C)
<120 mg/L Hot Air Oven, Digital Balance, Schimadzu-BL-220H
8. Total Dissolved Solids (TDS) mg/l
Digital Meter Method.
≤ 500 mg/l 2000 mg/l BOD Incubator
9. Turbidity (NTU)
Nephelo Turbidity Method.
1mg/l 10 mg/l Nephelo Turbidity Meter, Systronics – 132
10. Total Hardness (as CaCO3) mg/l
EDTA Titrimetric
300 mg/l 600 mg/l -
11. Total Alkalinity (as CaCO3) mg/l
Titrimetric (Methyl Orange)
200 mg/l 600 mg/l -
12. Calcium Hardness (Ca) mg/l
EDTA Titrimetric
75 mg/l 200 mg/l -
13. Magnesium Hardness (Mg) mg/l
Calculation from total Hardness and Calcium
30 mg/l 150 mg/l -
D. 6Waste Water Quality (Leachate- from Solid waste landfill, Storm/ drain water, dry weather flow and Inland water)
1. Temp (in ºC)
Digital/Mercury Thermometer Method.
Shall notexceed 5
oCabove
thereceivingwater temperature
Digital/Mercury Thermometer
2. Color (Hazen units) Platinum cobalt scale
- 5
25 -
5 Drinking water Specifications, IS-10500
6 Standards for Discharge of Environmental Pollutants, IS-10500
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
19
Program Management Consulting Services
3. Odour Objectionable/ Non-objectionable
Non-objectionable
-
4. pH value Electrometric Method.
5.5-9.2 Digital pH Meter, HANNA – HI98127,
5. Electrical Conductivity (EC) µs/cm
Electrometric Method.
< 2000 Digital TDS/EC Meter, HANNA – HI-96311
6. Dissolved Oxygen (DO) mg/l
Winkler's Method Using Azide Modification
> 6 mg/L Winkler's Method
7. Biochemical Oxygen Demand (BOD5) mg/l
Five Days BOD as per APHA 2005
30 mg/l BOD Incubator
8. Chemical Oxygen Demand (COD) m/l
Dichromate Method (APHA 2005)
250 mg/l
9. Total Dissolved Solids (TDS) mg/l
Digital Meter Method.
≤500 mg/L 2100 mg/L Digital TDS/EC Meter, HANNA – HI-96311
10. Total Suspended Solids (TSS) mg/l
Gravimetric (Filtration and Drying at 105°C)
<120 mg/L Hot Air Oven, Digital Balance, Schimadzu-BL-220H
11. Turbidity (NTU)
Nephelo Turbidity Method.
5 mg/L 10 mg/L Nephelo Turbidity Meter, Systronics – 132
12. Total Alkalinity (as CaCO3) mg/l
Titrimetric (Methyl Orange)
200 600
Annotation: BOD= biochemical oxygen demand; DO= dissolved oxygen; EC= electrical conductivity; NO2= nitrogen dioxide; PM10= particulate matter with particle size less than 10μ; RSPM= respirable suspended particulate matter; SO2=Sulphur dioxide; TDS= total dissolved solids; TSS= total suspended solids.
1.10. Monitoring results and comparison with statutory requirements at National levels.
27. The environmental monitoring data for air quality, water quality and noise levels for the subprojects
under execution of Tranche-2 at Srinagar and Jammu was carried out during the period of January 2015 to June 2015 by the Environmental Monitoring Laboratory of J&K ERA. Results are tabulated below;
A. Air Quality
28. The results of air quality monitoring conducted during period on various subproject sites are depicted below;
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
20
Program Management Consulting Services
29. Construction of Flyover/ Expressway Corridor from JehangirChowk to Rambagh/ Natipora, Srinagar
Srinagar Subprojects
Ambient Air Quality Site Code
Quarter Month of Sampling with date
Sampling Site/ Location
Site Type RSPM10 (µg/m
3)
SO2
(µg/m3)
NO2
(µg/m3)
Permissible Limits/ Standards 100 80 80
S-A1 Q1 (Jan-March)
27-03- 2015 Solina (Near Allochibagh)
Commercial 120.45 15.35 19.67
Q2 (April- June)
12-6-2015 116.43 8.22 11.45
S-A2 Q1 (Jan–March)
06-01-2015 Near Bakshi Stadium
Commercial 176.23 18.87 27.44
Q2 (April- June)
11-6-2015 157.60 12.23 21.33
S-A3 Q1 (Jan-March)
05-01-2015 Near School at Solina
Commercial 137.34 14.23 19.67
Q2 (Apr- June)
* * * * *
S-A4 Q1 (Jan- March)
8 Batching Plant/ Labour Camp at Kralpora Site
Residential * * *
Q2 (Apr-June)
29-06-2015 78.56 6.54 8.33
S-A9 Q1 (Jan- March)
* Near Iqra Masjid
Commercial * * *
Q2 (Apr-June)
22-06-2015 161.28 15.74 22.56
*Monitoring of the Air Quality sampling was not possible due to the technical problem with environmental mobile lab (vehicle) and bad weather
30. Air quality monitoring results shows oxide pollutants (SO2& NO2) are within the prescribed
standards however the particulate matter (RSPM10) show value higher than permissible limit
resulting mainly due to the dust generated by ongoing construction related activities at the site
and heavy vehicular movement closer to the site. Whereas, RSPM values of Kralpora batching
plant/ campsite is well within the permissible limits.
31. To effectively improve dust suppression measures, corrective measures were instructed and
implemented for frequent removal (by way of scrapping, mopping etc) of excavated muck/ soil
or loose soil at dust sensitive zones and where traffic movement is frequent and moreover
followed by regular water sprinkling at dust prone zones in order to control the dust emanating
from plying of vehicles.
32. Since the present fugitive dust generation is directly correlated to construction activities and
hence is non-continuous and limited to construction period. The above mitigation measures as
per EMP are being implemented as evident from above results and far below during baseline
monitoring conducted over the project Corridors. The recorded baseline data of RSPM10 Bakshi
Stadium Junction [(Section A & B) and Solina-Tulsi bagh (Section-C)] is 235.45 and
189.36μg/m3.Practically, this shows effective onsite implementation.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
21
Program Management Consulting Services
33. The Q2 monitoring carried out at Kralpora Labour Camp site shows all air quality parameters viz;
RSPM10, SO2 and NO2 were within the acceptable criteria and this is attributed to proper
sprinkling system at camp/ batching plant site. The trend of air quality parameters of site S-A1 to
S-A4 and S-A9 is illustrated in Figure-1(a-d) and 2 below;
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
22
Program Management Consulting Services
Figure 2: Comparative analysis of RSPM10, SO2 and NO2concentration at each monitoring sites of Flyover with NAAQ standard for subprojects in Srinagar.
Figure 2: Comparative analysis of RSPM10, SO2 and NO2concentration at different monitoring sites of Flyover with NAAQ standard for subprojects in Srinagar.
Construction of Multi-Storied Mechanized Car Parking Facility at Lal Chowk, Srinagar
Srinagar Subprojects
Site Code
Quarter Month of Sampling with date
Sampling Site/ Location
Site Type RSPM10 (µg/m
3)
SO2
(µg/m3)
NO2
(µg/m3)
Permissible Limits/ Standards
100 80 80 S-A5 Q1
(Jan-March) March 12-03-2015
Outside Parking Lot (Towards Barbarshah)
Commercial 126.4 13.54 10.54
Q2 (Apr-June)
June 08-06-2015
Outside Parking Lot (Towards Barbarshah)
Commercial 121.38 11.32 15.78
S-A6 Q1 (Jan-March)
March 19-03-2015
Within Parking Lot
Commercial 89.56 10.45 13.29
Q2 (Apr-June)
June 09-06-2015
Within Parking Lot
Commercial 94.43 10.71 14.12
34. The RSPM10 results shows higher values of particulate matter outside parking lot (towards
Barbarshah) while monitoring conducted for inside parking lot shows RSPM10values well within the permissible level. Whereas, the oxide pollutants (SO2 & NO2) were well within the prescribed standards.
35. RSPM10 values were 2-5% higher than baseline characteristics and are attributed to the heavy vehicular movement near site domain and settling of fine dust/ silt in and around the Lal Chowk area due to the September 2014 floods and ongoing different construction activities. This is the main reason of dust generation outside subproject area. Air quality results are illustrated in Figure 3a, 3b and 4 of Site S-A5 and S-A6.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
23
Program Management Consulting Services
Fig 3a and 3b: Showing Air Quality characteristics inside and outside parking lot.
Figure 4: Concentration of RSPM (PM10), SO2 and NO2 of monitoring site (Parking Lot- S-A5 & S-A6) with NAAQ standards in Srinagar subprojects.
36. Construction of Storm Water Drainage along National Highway, Athwajan in Srinagar
Srinagar Subprojects
Site Code
Quarter Month of Sampling with date
Sampling Site/ Location
Site Type RSPM10 (µg/m
3)
SO2
(µg/m3)
NO2
(µg/m3)
Permissible Limits/ Standards
100 80 80 S-A7 Q1
(Jan-March)
March 13-03-2015
Near Construction Site (Within 100 mtr. impact corridor from School at Athwajan/ Panthachowk)
Commercial 143.21 18.32 24.11
Q2 (Apr-June)
June 13-06-2015
153.73 16.81 20.37
37. The monitoring results indicate that the oxide pollutants (SO2& NO2) are within the permissible
limits. The particulate matter (RSPM)10 shows higher values exceeds the prescribed limits in
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
24
Program Management Consulting Services
both Q1 and Q2 monitoring at S-A7 resulting mainly due to the fugitive dust generation from plying of heavy National Highway traffic at Pantha-Chowk Athwajan Junction (National Highway- 1A road) and partly due to the construction related activity on trunk drain and wind driven dust.
38. To effectively improve dust suppression measures, corrective measures were instructed and
implemented for frequent removal (by way of scrapping, mopping etc) of excavated muck/ soil
or loose soil at dust sensitive zones (throughout the NH-1A corridor) as traffic movement is
frequent and moreover followed by regular water sprinkling at dust prone zones. This has
improved the situation and contractor was further instructed to follow strict dust suppression
protocol.
39. These impacts are temporary (till completion of construction period) and are mitigated through
proper implementation of EMP. The RSPM10 values stands well below the baseline
characteristics of the said site domain area.
40. Air quality characteristics of subproject as illustrated in Figure-5 below;
Figure 5: Concentration of RSPM (PM10), SO2 and NO2 at monitoring site near construction (100 mtr. impact corridor from school at Athwajan/ Pantha-chowk junction) with NAAQ standards in Srinagar subprojects.
41. Air Quality Monitoring Results of sub-projects executed under Tranche – II, Jammu Air Quality- Jammu Subprojects (Tranche – 2)
Site Code
Quarter Month of Sampling with date
Sampling Site/ Location
Site Type PM 2.5 RSPM10 (µg/m
3)
SO2
(µg/m3)
NO2
(µg/m3)
Permissible Limits
60 100 80 80 Construction of Elevated Expressway Corridor (flyover) from Bikram Chowk to Gandhi Nagar in Jammu City.
S1 Q1 23-01-15 Bikram Chowk near starting point of flyover.
Residential, Rural and
other areas
130.20 24.24 66.36
Q2 10-04-15 179.66 31.77 88.92
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
25
Program Management Consulting Services
S2 Q1 29-01-15 Women College, Gandhi nagar
Residential, Rural and
other areas
112.31 23.16 74.24
Q2 22-04-15 134.46 31.25 60.34
S3 Q1 23-02-15 Bhagwati Nagar near Batching
plant
Residential, Rural and
other areas
107.95 19.73 40.78
Q2 28-04-15 146.39 18.75 33.94
Rehabilitation and Channelization of Storm Water drain at Channi Himmat in Jammu City.
S4 Q1 13-02-15 R-3 Drain (Channi Himmat)
Residential, Rural and
other areas
129.50 30.70 61.10
Q2 28-05-15 176.76 219.19 36.45 58.43
S5 Q1 12-02-15 R-2 Drain (Channi Himmat)
Residential, Rural and
other areas
126.14 24.67 28.08
Q2 30-05-15 101.01 82.94 20.83 39.38
S6 Q1-Q2 10-02-15 R-1 Drain (Channi Himmat)
Residential, Rural and
other areas
93.00 17.54 36.77
Rehabilitation and Channelization of Storm Water drain at Gangyal and Digiana areas in Jammu City
S7 Q1-2 15-05-15 Gangyal Market near Satyam
Resort
Residential, Rural and
other areas
113.63 106.02 27.08 55.25
S8 Q1 13-03-15 Channi Himmat, near Tangar Nallah (T4).
Residential, Rural and
other areas
169.30 23.29 60.28
Q2 18-05-15 126.26 106.93 25.52 33.02
S9 Q1-2 10-03-15 Gangyal Nallah at Dilli
Residential, Rural and
other areas
75.41 36.18 49.47
S10 Q1 16-01-15 Batching plant at Chowadi
Residential, Rural and
other areas
133.92 28.50 47.47
Q2 20-05-15 138.88 110.61 29.68 54.62
S11 Q1-2 20-01-15 At the confluence of Gangyal and Digiana Nallah
Residential, Rural and
other areas
169.27 17.54 37.44
Construction of Tube Wells under Water Supply System
S12 Q1-2 06-01-15 Channi- Himmat Tube well
Residential, Rural and
other areas
204.61 19.18 74.88
S13 Q1-2 08-01-15 At New plot, Janipur
Residential, Rural and
other areas
161.83 28.01 53.18
S14 Q1-2 17-04-15 Malik market Tube well
Residential, Rural and
other areas
94.44 27.60 52.08
S15 Q1-2 30-06-15 At Rajinder Nagar,Bantalab
Residential, Rural and
other areas
148.51 72.62 32.29 23.50
Construction of Over Head Tanks in Jammu City
S16 Q1-2 24-03-15 Baba Kailakhnath Temple
Residential, Rural and
other areas
60.33 19.18 27.41
S17 Q1-2 30-06-15 At Rajinder Nagar,Bantalab
Residential, Rural and
other areas
148.51 72.62 32.29 23.50
S18 Q1-2 27-03-15 Fruit Market Residential, Rural and
other areas
117.18 39.47 56.16
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
26
Program Management Consulting Services
42. In case of Sub-project-Construction of Flyover from Bikram Chowk to Women College Gandhi
Nagar, the values of the RSPM (PM10) were found to be higher than the permissible limit at all
the sitesduring Q1 and Q2. The same was the case during baseline monitoring conducted over
the project Corridor. The contractor was instructed to increase the frequency of water sprinkling
and strengthen other dust suppression measures at all sites. The concentration of SO2and NO2
remained within permissible limit at all monitoring sites where as value of NO2 on one site at S1
during Q2 is above permissible limit that due to high frequency of traffic movements at Bikram
Chowk.
43. In case of Sub-project-Rehabilitation and Channelization of Storm Water drain at Channi Himmat
in Jammu City the values of the RSPM (PM10) and fine particulate matter (PM2.5) were above
permissible limit at all the sites. The same was the case during baseline monitoring conducted
over the project Corridor for RSPM (PM10) and monitoring of fine particulate matter (PM2.5) was
conducted first time, the values of fine particulate matter seems higher side. The contractor was
instructed to increase the frequency of water sprinkling and strengthen other dust suppression
measures at all sites. The concentration of SO2and NO2 remained within permissible limit at all
the monitoring sites of the project corridor.
44. The monitoring was conducted at Rehabilitation and Channelization of Storm Water drain at
Gangyal and Digiana areas in Jammu City. The value of RSPM and fine particulate matter PM2.5
was found to be above the permissible limit. This may be due to proximity of the sites with the
Gangyal Industrial area. Whereas the value of SO2and NO2was within the range same was
observed during baseline data and additional baseline data that was generated during
preconstruction activity. The monitoring on site S11 was carried out prior to the start of work to
have the preconstruction values of RSPM, NO2and SO2as additional baseline to compare the
monitoring date generated during construction phase. The value of the RSPM was much more
than the permissible limit. In case of gaseous pollutant the value of SO2 and NO2 was within
permissible limit at this site. The comparison of air quality monitoring results for the subprojects in
Jammu is depicted in Figure 6 and 10.
Figure 6: Concentration of RSPM (PM10), SO2 and NO2at site S1, S2 and S3 on Bikram Chowk Flyover project corridor
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
27
Figure 7: Concentration of RSPM (PM10), SO2 and NO2at site S4, S5 and S6 on Storm Water Drain (R1, R2 and R3) at Channi Himmat.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
28
Program Management Consulting Services
Figure 8: Concentration of RSPM (PM10), SO2 and NO2at site S7, S8, S10 and S11 on Storm Water Drain at Gangyal , Thangar Area,Gangayal Nallah at Delli ,Batchin plant and at the confluence of Gangyal and Digiana Nallah.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
29
Figure 9: Concentration of RSPM (PM10), SO2 and NO2at S12, S13, S14 and S15 Tube-well sites under sub project Water Supply Rehabilitation Program.
Figure 10: Concentration of RSPM (PM10), SO2 and NO2at site S15, S16, S17 and S18 on Construction of OHT project corridor.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
30
Program Management Consulting Services
B. Noise Quality
45. The measured noise quality data at various locations is given below:
46. Construction of Flyover/ Express Corridor from JehangirChowk to Rambagh
Srinagar Subprojects
Site Code
Quarter Month of Sampling with date
Sampling Site/ Location
Site Type Day Time Noise Levels dB (A) Leq
Day Time Noise Quality Standards dB (A) Leq
Construction of Flyover/ Express Corridor from JehangirChowk to Rambagh
S-N1
Q1 (Jan-Mar)
March 27-03-2015
Solina near Allochibagh
Commercial 64.8 65
Q2 (Apr-June)
June 12-06-2015
60.3 65
S-N2 Q1 (Jan-Mar)
January 06-01-2015
Near Bakshi Stadium/ Iqbal Park
Commercial 67.5 65
Q2 (Apr-June
June 11-06-2015
68.7 65
S-N3 Q1 (Jan-Mar)
January 05-01-2015
Near School at Solina
Commercial 66.2 65
Q2 (Apr-June)
* * * *
S-N4 Q1 (Jan-Mar)
* Labour Camp/ Batching Plant at Kralpora Site
Residential * *
Q2 (Apr-June)
June 29-06-2015
50.6 55
S-N9 Q2 (Apr-June)
June 22-06-2015
Near Iqra Masjid
Commercial Area
69.6 65
*Monitoring of the Noise Quality sampling was not possible due to the technical problem with environmental mobile lab (vehicle) and bad weather
47. Q1 and Q2 noise monitoring shows slightly higher than the national noise level standards for commercial area as observed at above monitoring sites of S-N1, S-N2, S-N3, S-N4 and S-N9. Increase in noise level is normally anticipated as heavy influx of traffic movement is very high at these sections and in general throughout flyover corridor and heavy machinery engaged in construction activity. However, the contractor has been instructed to ensure the proper mitigation measures as per EMP of all machinery deployed by the contractor.
48. Whereas, at Kralpora batching plant/ camp site (S-N4), shows noise level at 50.6 dB which is well within the permissible level. Comparative illustration is depicted in Figure 11 below;
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
31
Program Management Consulting Services
Figure 11: Comparison of day time noise levels observed at different monitoring sites of Flyover subproject with National noise standards of subprojects in Srinagar.
49. Construction of Multi-Storied Mechanized Parking Facility at Lal Chowk, Srinagar Srinagar Subprojects
Site Code
Quarter Month of Sampling with date
Sampling Site/ Location
Site Type Day Time Noise Levels dB (A) Leq
Day Time Noise Quality Standards dB (A) Leq
Construction of Multi-Storied Mechanized Parking Facility at Lal Chowk, Srinagar
S-N5
Q1 (Jan-Mar)
March 12-03-2015
Outside Parking Lot (Towards Barbarshah)
Commercial 69.8 65
Q2 (Apr-June)
June 08-06-2015
Outside Parking Lot (Towards Barbarshah)
Commercial 69.4 65
S-N6 Q1 (Jan-Mar)
March 19-03-2015
Inside Parking Lot
Commercial 60.2 65
Q2 (Apr-June)
June 09-06-2015
Inside Parking Lot
Commercial 63.3 65
50. Noise quality (day time) observed during Q1 and Q2 sampling for S-N6 site outside Parking facility
lot(towards Barbarshah area) was slightly higher than the prescribed noise level standards for
commercial area. Whereas, in Q1 and Q2 monitoring of site S-N6 (Inside parking lot) shows noise
level well within the permissible standards.
51. Subproject domain area is main commercial hub and frequent movement of vehicular and
pedestrian traffic is always present. This is the main reason noise generation as a constant
feature. Further, limited machinery is engaged at construction site is also source of some noise
generation which is short-term in nature. Corrective instructions to maintain machinery at site and
application of proper oiling, greasing and managing of machinery. Comparative illustration is
depicted in Figure 12
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
32
Program Management Consulting Services
Figure 12:Comparison of day time noise levels observed at different monitoring sites with National noise standards of subprojects in Srinagar.
52. Construction of Storm Water Drainage at Athwajan, Srinagar Srinagar Subprojects
Site Code
Quarter Month of Sampling with date
Sampling Site/ Location
Site Type Day Time Noise Levels dB (A) Leq
Day Time Noise Quality Standards dB (A) Leq
Construction of Storm Water Drainage at Athwajan, Srinagar S-N7
Q1 (Jan-March)
March 13-03-2015
Near Construction Site (Within 100 mtr. impact corridor from School at Panthachowk)
Commercial 67.7 65
Q2 (Apr-June)
June 13-06-2015
69.4 65
53. Noise quality (day time) observed at monitoring site S-N7, showsslightly higher values than the
prescribed national noise level standards for commercial area. This is attributed mainly to higher
influx of heavy traffic movement at PanthaChowk/ Athwajan junction (National Highway 1A road)
and partly due the heavy machinery engaged in construction activity. Comparative illustration is
depicted in Figure 13.
Figure 13: Comparison of day time noise levels observed at monitoring site (S-N7) with National noise standards of subprojects in Srinagar.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
33
Program Management Consulting Services
54. The measured noise quality data at various locations of Jammu sub-projects are given below:
Noise Quality Results- Jammu Subprojects (Tranche – 2)
Site Code
Quarter Month of Sampling with date
Sampling Site/ Location
Site Type Noise Levels (dB Leq)
Standards
Construction of Elevated Expressway Corridor (flyover) from Bikram Chowk to Gandhi Nagar in Jammu City.
S1 Q1 23-01-15 Bikram Chowk near starting point of flyover.
Residential, Rural and
other areas
71.2 55
Q2 10-04-15 74.5
S2 Q1 29-01-15 Women College, Gandhi nagar
Residential, Rural and
other areas
71.3
Q2 22-04-15 75.1
S3 Q1 23-02-15 Bhagwati Nagar near Batching
plant
Residential, Rural and
other areas
64.7
Q2 28-04-15 68.1
Rehabilitation and Channelization of Storm Water drain at Channi Himmat in Jammu City.
S4 Q1 13-02-15 R-3 Drain (Channi Himmat)
Residential, Rural and
other areas
77.0 55
Q2 28-05-15 71.6
S5 Q1 12-02-15 R-2 Drain (Channi Himmat)
Residential, Rural and
other areas
74.9
Q2 30-05-15 69.3
S6 Q1-Q2 10-02-15 R-1 Drain (Channi Himmat)
Residential, Rural and
other areas
73.1
Rehabilitation and Channelization of Storm Water drain at Gangyal and Digiana areas in Jammu City
S7 Q1-2 15-05-15 Gangyal Market near Satyam
Resort
Residential, Rural and
other areas
72.2 55
S8 Q1 13-03-15 Channi Himmat, near Tangar Nallah (T4).
Residential, Rural and
other areas
71.3
Q2 18-05-15 72.9
S9 Q1-2 10-03-15 Gangyal Nallah at Dilli
Residential, Rural and
other areas
72.4
S10 Q1 16-01-15 Batching plant at Chowadi
Residential, Rural and
other areas
70.0
Q2 20-05-15 73.9
S11 Q1-2 20-01-15 At the confluence of Gangyal and Digiana Nallah
Residential, Rural and
other areas
62.4
Construction of Tube Wells under Water Supply System
S12 Q1-2 06-01-15 Channi- Himmat Tube well
Residential, Rural and
other areas
73.1 55
S13 Q1-2 08-01-15 At New plot, Janipur
Residential, Rural and
other areas
68.4
S14 Q1-2 17-04-15 Malik market Tube well
Residential, Rural and
other areas
65.1
S15 Q1-2 30-06-15 At Rajinder Nagar,Bantalab
Residential, Rural and
other areas
80.8
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
34
Program Management Consulting Services
Construction of Over Head Tanks in Jammu City
S16 Q1-2 24-03-15 Baba Kailakhnath Temple
Residential, Rural and
other areas
62.5 55
S17 Q1-2 30-06-15 At Rajinder Nagar,Bantalab
Residential, Rural and
other areas
80.8
S-18 Q1-2 27-03-15 Fruit Market Residential, Rural and
other areas
69.6
55. Noise levels at sites (S1, S2, S3, S4, S5, S6, S7, S8, S9 ,S10, S11, S12, S13, S14,
S15,S16,S17 and S18) were found to be above the National Noise Quality standards (Figure
14& 18). Same was the case in baseline monitoring whereas on site S11 monitoring was
conducted before start of any construction activity for generation of additional baseline data for
comparing with construction phase. The monitoring was done during day time. Major source of
noise at these sites was the movement of vehicles on adjacent roads and lanes. Contractors
were instructed to implement various mitigation measures as mentioned in EMP so as not to
allow any increase in present noise levels.
Figure 14: Comparison of day time noise levels observed at monitoring site (S1, S2, & S3) with National noise standards of subprojects in Jammu.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
35
Program Management Consulting Services
Figure 15: Comparison of day time noise levels observed at monitoring site (S4, S5, & S6) with National noise standards of subprojects in Jammu.
Figure 16: Comparison of day time noise levels observed at monitoring site (S7, S8, S10 & S11) with National noise standards of subprojects in Jammu.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
36
Program Management Consulting Services
Figure 17: Comparison of day time noise levels observed at monitoring site (S12, S13, S14 & S15) with National noise standards of subprojects in Jammu.
Figure 18: Comparison of day time noise levels observed at monitoring site (S16, S17& S18) with National noise standards of subprojects in Jammu.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
37
C. Water Quality
56. The results of water quality analysis conducted at various subproject sites in Srinagar are presented below:
57. Construction of Flyover/ Express Corridor from Jehangir Chowk to Rambagh, Srinagar Site
Code
Quarter Month of Sampling with date
Sampling Site
Location Temp ºC
pH E.C µs/cm
D.O mg/l
B.O.D mg/l
TDS mg/l
TSS mg/l
Turb. NTU
T.A T.H C. H
M.H
Permissible Limits - 6.5-
8.5 ≤500 >6 2-5
≤500 ≤120 5-10 200 -
600 300 - 600
75-200
30-75
S-W1
Q1 (Jan-March)
January 16-01-2015
Flood spill Channel at Rambagh
Upstream 5 8.0 627 3.2 8.2 311 180 10.0 276 328 193.2 32.7
Downstream 5 8.1 634 3.0 8.9 315 190 10.5 272 352 151.2 48.7
Q2 (Oct-Dec)
May 06-05-2015
Upstream 11 7.5 180 3.0 8.0 90 260 59.2 68 124 105 4.61
Downstream 11 7.6 190 2.9 8.5 97 270 59.0 72 124 105 4.61
S-W2 Q1 (Jan-March)
March 13-03-2015
Batching/ Camp site at Kralpora
Tube Well (40 m depth)
15
7.6
762
4.0
3.0
380
190
8
64
104
96.6
8
S-W4 Q1 (Jan-March)
March 13-03-2015
DoodhgangaStream near Kralpora site
Upstream (Near Batching Plant)
6 8.9 476 5.5 3.0 251 230 28 160 324 205.8 28.72
Downstream (Near Casting Yard)
6 8.9 437 5.0 3.5 217 235 29 164 340 214.2 30.56
Q2 (Apr-June)
June 01-06-2015
Upstream (Near Batching Plant)
16 8.3 139 8.8 1.6 71 190 8.0 64 104 96.6 80.5
Downstream (Near Casting Yard)
16 8.2 139 8.5 1.6 70 199 8.5 60 104 100.8 79.5
Annotations: TA- Total Alkalinity; TH- Total Hardness; CH- Calcium Hardness; MH-Magnesium Hardness
58. The water samples were taken from the Jhelum Flood Spill channel at Rambagh bridge (near Section-C & D of Flyover).Throughout the Q2 monitoring period, spill channel has recorded maximum discharge of water volume due to the high precipitation (780 mm of rainfall) received upto June 2015. The physio-chemical characteristics of spill channel are illustrated in Figure 19 & 20.
59. Number of dewatering stations is located along the Floodspill channel. The water from the storm water drainages at
Gogjibagh, Mehjoor Nagar, Rajabagh,Jawahar Nagar, Solina, old Barzulla etc are directly disposed into spill channel. This leads to change in physio-chemical characteristics of the water like BOD, conductivity, TSS and decline in DO etc.Turbidity factor was normal in Q1 monitoring but trend changed sharply to higher turbidity at 59 NTU which is mainly attributed to high silted discharge from River Jhelum into spill channel.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
38
Program Management Consulting Services
Figure 19: Water quality characteristics during Q-3 sampling of Flyover site- Flood spill channel (Surface Water) at Rambaghbridge.
Figure 20: Water quality characteristics during Q-4 sampling of Flyover site- Flood spill channel (Surface Water) at Rambaghbridge. 60. The physio-chemical characteristics of ground water analysis of Tube Well (S-W2) at Kralpora site show most of the
parameters well within the permissible level. Conductivity and TSS values were on higher side only. The comparative analysis
of water characteristics is illustrated in Figure-21 below;
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
39
Program Management Consulting Services
Figure 21: Water quality characteristics of ground water-Tube Well (S-W2) Kralpora site
61. The S-W4 Water Samples were taken from the upstream and downstream of Doodhganga near Kralpora Batching Plant
and Casting Yard respectively. The water was flowing with moderate speed. Direct dumping of domestic wastes by the locals
was also observed during the sampling period. Water was found to be highly turbid during Q1 monitoring and non- turbid in Q2
period..
62. The analysis of the Water samples revealed that the DO of the stream was found to be normal due to the moderate flow of
the water. BOD was found to be in permissible limits. TSS was observed to be higher and it may be due to the presence of lot
of litter and may also be due to the presence of silt which the stream brings from the upper reaches of the mountain. Moderate
concentrations of Alkalinity and Hardness were found in the water body. Comparative analysis is illustrated in Figure 22 & 23
below;
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
40
Program Management Consulting Services
Figure 22: Water quality characteristics of Doodhganga Stream near Kralpora plant site during Q1 monitoring.
Figure 23: Water quality characteristics of Doodhganga Stream near Kralpora plant site during Q2 monitoring.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
41
Program Management Consulting Services
63. Construction of Storm Water Drainage along National Highway at Athwajan
Site Code
Quarter Month of Sampling with date
Sampling Site/ Location
Temp ºC
pH E.C µs/cm
D.O mg/l
B.O.D mg/l
TDS mg/l
TSS mg/l
Turbidity NTU
T.A T.H C.H M.H
River Jhelum near Lasjan bridge
Permissible Limits
- 6.5-
8.5 ≤500 >6 2-5
≤500 ≤120 5-10 200 -
600 300 - 600
75-200
30-75
S-W3
Q1 (Jan-March)
March 13-03-2015
Upstream 7 8.8 350 9.2 2.0 165 200 25 116 244 134.4 26.63
Downstream 7 8.8 346 9.0 2.2 158 210 27 112 240 142.8 23.61
Q2 (Apr-June)
June01-06-205
Upstream 13 7.8 140 8.8 2.0 70 190 7.0 60 88 55.4 8.0
Downstream 13 7.7 138 8.4 2.0 68 205 7.3 56 80 51.2 7.0
64. Water samples were taken from the upstream and downstream of the River Jhelum site (S-W3) near Lasjan Bridge, Athwajan.The
water was flowing with moderate speed in water body. The water was found turbid (Q1) and clear (visible transparency) during Q2
and odourless. Dissolved Oxygen (DO) was found in healthy state due to the flow regime dynamics of Jhelum river system.
65. Conductivity and TDS values were normal. BOD values of the concerned river were also normal due to less organic load. TSS and
Turbidity was observed higher side which may be attributed to siltation process which the river brings from the upper reaches of
the mountain. Alkalinity and Hardness were also found in optimum level in the water body. The physio-chemical characteristic
reveals least or no impact on water body due to the ongoing construction activity. Comparative analysis is illustrated in Figure 24
and 25 below.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
42
Program Management Consulting Services
Figure 24: Water quality characteristics of Storm Water Drainage site- Jhelum River near Lasjan (Quarter 1)
Figure 25: Water quality characteristics of Storm Water Drainage site- Jhelum River near Lasjan (Quarter 2)
66. The sampling site of S-W5(Ground Water)of Multi-Storied Parking Lot subproject is ancillary site of sampling and is not a
routine site hence not conducted and included in this report.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
43
Program Management Consulting Services
67. The results of water quality analysis conducted during Q1 and Q2 monitoring at Rehabilitation and Channelization of Storm Water drain at Gangyal and Digiana Area in Jammu City is presented below.
Rehabilitation and Channelization of Storm Water drain at Gangyal and Digianaarea in Jammu City. S. No.
Date Site Code
Quarter Site Location Air Temp
Water Temp
Electrical conduct..
TDS PH Residual Chlorine
DO TSS Turbidity Cl Ca Mg BOD Total Alkalinity
Total Hardness
0C
0C 2000 µs/ cm <500mg/l 5.5 to
9.2 ppm <6mg/l <120mg/l 5-10 NTU 1000 <30mg/
l 200-600 300-600
1 30-03-15
S-01 Q1 GangyalNallah 100m upstream before the confluence with BalolNallah
22.9 21.3 - - 8.1 0.4 3.6 117.77 61.8 73.84 224 163 90 470 387
29-06-15
Q2 32.4 28.8 433 282 7.89 0.5 3.8 45 20.1 59.64 272 120 110 360 392
2 30-03-15
S-02 Q1 BalolNallah 100m upstream before the confluence with GangyalNallah
22.9 21.0 - - 8.1 0.5 4.9 164.38 122.7 68.16 272 192 75 590 464
29-06-15
Q2 32.5 28.7 428.0 279.0 7.73 0.4 5.6 42 42.6 59.64 244 108 54 240 352
3 30-03-15
S-03 Q1 BalolNallah 100m downstream before the confluence with GangyalNallah
22.7 21.2 - - 8.4 0.5 4.7 376.92 165 85.2 278 198 83 640 476
29-06-15
Q2 32.6 28.7 430 280 7.73 0.4 4.1 60 50.1 62.48 284 96 66 260 380
4 30-03-15
S-04 Q1 BalolNallah 100m upstream before the confluence with River Tawi
23.3 21.1 - - 8.2 0.4 5.6 82.05 78.3 62.48 204 160 19.37 490 364
29-06-15
Q2 35.6 29.1 520 338 7.55 0.4 5.7 88 48.2 76.68 276 128 21.25 360 404
Inland Surface Water
S. No.
Date Site Code
Quarter Site Location Air Temp
Water Temp
Electrical conductivity
(TDS) 6.5 to 8.5
1.0 6- 8.5 mgl
<120mg/l 1-10 NTU
200-1000
75-200
30-150 mg/l
<2-5mg/l
200-600 300-600
( 0C ) (
0C ) 2000 µs/ cm <500mg/l>
5 30-03-15
S-05 Q1 River Tawi 500m upstream before the confluence with BalolNallah.
23.4 21.0 - - 8.6 0.3 5.9 637.5 68.9 79.5 268 116 2.9 610 384
29-06-15
Q2 35.1 29.0 314.0 204.0 7.80 0.3 6.2 112.12 154.7
62.48 116 180 3.4 340 296
6 30-03-15
S-06 Q1 River Tawi 500m
23.4 21.1 - - 8.6 0.4 5.8 677.77 70.2 82.3 264 125 6.4 630 389
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
44
Program Management Consulting Services
29-06-15
Q2 35 29.0 325 270 7.82 0.4 6.1 126.66 197.2
67.13 188 164 5.8 350 352
Note: Samples with S-5 to S-10 were sampled the day after a continuous spell of rain. N.D: Not Detected Guidelines or standards prescribed in reference to IS 10500- 1991 and Schedule-VI of Environmental Protection Rule 1986.
68. Water samples were collected from all above mention sites. The water quality analysis results show that the values of BOD,
Magnesium, Calcium and turbidity are higher in the Gangyal drainsbefore their confluence with Balol drain. Balol drain itself
shows high value of these parameters before the outfall of Gangyal drain into it, which further raises its BOD and turbidity value.
69. However, Balol drain after outfall of Gangyal drain travels a distance of about 10 km before its outfall into river Tawi, which serves
as revival zone and reduces the organic load of the drain water by enrichment of dissolved oxygen. Ultimately, before the outfall of
Balol into river Tawi the BOD value gets sufficiently reduced (from 83mg/l to 5.8mg/l).The BOD value of the River Tawi before the
outfall of Ballol Nallah into it was 2.9 mg/l and that of Ballol nallah at this point was 19.37 and 21.25mg/l during Q1 and Q2
respectively. The BOD value of River Tawi 500m downstream of this confluence was found to be 6.4 and 5.8 mg/l during Q1 and
Q2 respectively which shows that the river has good reviving potential. Same pattern of water quality were observed during the
baseline monitoring. Comparative analysis of water characteristics is illustrated in Figure 26 to 32below;
Figure 26: Water quality characteristics of Gangyal Nallah, 100m upstream before the confluence with BalolNallah
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
45
Program Management Consulting Services
Figure 27: Water quality characteristics of Balol Nallah, 100m upstream before the confluence with Gangyal Nallah
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
46
Program Management Consulting Services
Figure 28: Water quality characteristics of BalolNallah 100m downstream before the confluence with GangyalNallah
Figure 29: Balol Nallah 100m upstream Water quality characteristics of Balol Nallah 100m upstream before the confluence with River Tawi.
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
47
Program Management Consulting Services
Figure 30: Inland Surface Water quality characteristics of River Tawi 500m upstream before the confluence with BalolNallah
Figure 31: Inland Surface Water quality characteristics of River Tawi 500m downstream before the confluence with Balol
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
48
7. ANY OTHER ENVIRONMENTAL ASPECTS, IMPACTS OBSERVED DURINGIMPLEMENTATION WHICH WERE NOT COVERED EARLIER
70. No such aspect/impact observed during this period under report.
8. DETAILS OF COMPLAINTS RECEIVED FROM PUBLIC AND ACTIONS TAKEN THEREOF TO RESOLVE
71. No such complaints received from Jammu sub-projects during this period.
72. During this period some minor complaints from Srinagar subprojects (maintained in
Public Grievance Register at site) were received from public and addressed accordingly.
Details are mentioned below;
S. No
Subproject Name
Date of compliant registered
Type of Compliant Received (Public Grievance Register at Site)
Action Taken/ Corrective Action Measures
Remarks
01
Flyover Subproject (Srinagar)
25/02/2015 Surface drain at sector B got choked due to ongoing construction at Iqbal Park
M/s Simplex Infrastructure was directed to clear the said drain on priority
Addressed and resolved.
Records maintained at site and DSC.
02 02-03-2015 Locals complained about pot holes on the service road
Contractor was instructed for filling and restoration of service roads. Further, all the service roads from Sec-B to Sec-C were macadamized in May 2015.
Addressed and resolved. Records maintained at site and DSC.
03 15-03-2015
Locals complained about the noise generated by the pump.
After assessment of the pump it was found that pump has some fault, so the same was replaced by the fresh one by the contractor on priority
Addressed and resolved. Records maintained at site and DSC
9. FOLLOW-UP ACTIONS AND CONCLUSIONS
73. Monitoring of the sub-projects is being carried out regularly to ensure that environmental
impacts are adequately mitigated and to ensure continuation of compliance with statutory
regulations as required by laws and agreed upon EMP. The contractors are being regularly
guided and instructed to adhere to the provisions of EMP and contractual conditions.
74. As part of capacity building programme for JKUSDIP subprojects more training programs for
the engineers, the contractors and project staff will be conducted and regular informal onsite
orientation for the contractor’s supervisory staff and site engineers on EMP implementation will be continued.
Signed by: Authorized signatory from implementing agency/ executing agency
(Vinod Sharma)
Director Safeguards J&K ERA
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
49
Program Management Consulting Services
Appendix-1: Public Consultation Attendance Details of Flyover-Jehanagir Chowk to Rambagh
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
50
Program Management Consulting Services
Appendix-2: Public Consultation Attendance Details of Flyover at Kralpora plant Site
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
51
Program Management Consulting Services
Appendix-3: Public Consultation Attendance Details of Drainage Subproject at Athwajan
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
52
Program Management Consulting Services
Appendix-4: Photographs-Public Consultation of Tranche 2
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
53
Appendix-5:Sampling site location map of Flyover from JehangirChowk-Rambagh, Srinagar
S-A1
S-N3
S-A3
S-N2
S-N1
S-A2
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
54
Program Management Consulting Services
Appendix-6:Sampling site location map of Flyover- Labour Camp/ Batching Plant at Kralpora, Srinagar
S-N4
S-W3
S-A4
S-W4
S-W4
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
55
Program Management Consulting Services
Appendix-7: Sampling site location map of Storm Water Drainage along NH-1A, Athwajan, Srinagar
S-A7
S-N7
S-W4
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
56
Program Management Consulting Services
Appendix-8: Sampling site location map of Multi-Storied Parking Lot at Lal Chowk, Srinagar
S-N6
S-A6 S-W5
S-A5
S-N5
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
57
Program Management Consulting Services
Appendix-9: Sampling site locations of Air and Noise Quality under subproject in Jammu Sector, Tranche II
LEGENDS:
AIR AND NOISE SAMPLING SITES
S1: Bikram Chowk
S2: Women College, Gandhinagar
S3: Bhagwatnagar near Batching
Plant
S4: R3 Drain (ChanniHimmat)
S5: R2 Drain (ChanniHimmat)
S6: R1 Drain (ChanniHimmat)
S7: near Starting Point of the
Gangyal Drain
S8: ChanniHimmat near
ThangarNallah (T4)
S9: Batching Plant at Chowadi
S10: GangyalNallah at Dilli
S11: GangyalNallah at Marble
Market
S12: ChanniHimmatTubewell
S13: Malik Market Tubewell
S14: At New Plot, Janipur
S15: Baba Kalaknath Temple
S17: Fruit Market, Narwal
S18: At Rajinder Nagar, Bantalab
JKUSDIP – Semi-Annual Environmental Monitoring Report (January 2015 – June 2015)
58
Program Management Consulting Services
Appendix-10: Water Sampling site locations under subproject in Jammu Sector, Tranche II
LEGENDS:
WATER SAMPLING SITE LOCATIONS
S-01: GangyalNallah, 100mtr Upstream
before confluence with BalolNallah
S-02: BalolNallah, 100mtr Upstream
before confluence with GangyalNallah
S-03: BalolNallah, 100mtr Downstream
before confluence with GangyalNallah
S-04: BalolNallah, 100mtr Upstream
before confluence with River Tawi
S-05: River Tawi, 500mtr. Upstream
before confkuence with BalolNallah
S-06: River Tawi, 500mtr. Downstream
before confkuence with BalolNallah