Selected Findings from Scenario Analysis Conducted To...

31
Selected Findings from Scenario Analysis Conducted To Date Power Committee Webinar June 26, 2014

Transcript of Selected Findings from Scenario Analysis Conducted To...

Page 1: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Selected Findings from Scenario Analysis

Conducted To Date

Power Committee Webinar June 26, 2014

Page 2: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Progress Since The June Council Meeting – Model Inputs

RPM inputs have been updated: Revised peak load forecast to reflect historical

relationship between weather and other factors (e.g., day of week) a peak loads Include announced retirement of Valmy coal

plants in 2026 Resource adequacy penalty was increased This guarantees that paying the penalty every

period is more expensive than building any of the resources that are available for selection in the model

2

Page 3: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Progress Since The June Council Meeting – Model Structure

RPM has been revised: Resource expansion logic modified to reflect need

for capacity resources and contract status Resource adequacy penalty was changed to only

apply to capacity shortfalls that can be addressed by the resources in the model, i.e. penalties are not added into the NPV unless it’s possible for the model to avoid them All graphs used in this presentation show NPV

without any penalties added 3

Page 4: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Progress Since The June Council Meeting – Model Structure

RPM has been revised: Resource expansion logic modified to reflect need

for capacity resources and contract status The model was given close to “perfect foresight” so that

in each future it forecast close to exact need for capacity that will be needed in that future. While this reduces the risk associated with “forecast error” it was deemed acceptable given the short lead times for new resource development.

Resource adequacy penalty was changed to only apply to capacity shortfalls that can be addressed by the resources in the model, i.e. penalties are not added into the NPV unless it’s possible for the model to avoid them 4

Page 5: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Progress Since The June Council Meeting – Model Structure (2)

RPM revisions “in progress”: Testing of revised peak load forecast inputs and RPM

model revisions revealed the need for additional modifications

The hourly time-step of the GENESYS model allows it to use of hydro-system for peaking and dispatch other resources to provide energy (e.g., replaces water used for “peaking” with energy generated by wind and gas turbines)

RPM is being revised to allow peak/energy substitution to reflect NW system operation that is more consistent with GENESYS This is done by adjusting all resources to reflect their “System

Capacity Contribution”

5

Page 6: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

What Is “System Capacity Contribution”? (2)

System Capacity Contribution is the capacity credit of resources (e.g. wind, solar PV, CCCT) when integrated into an existing power system.�

The System Capacity Contribution may exceed the nameplate capacity of a plant in power systems that have storage Example:

A standalone battery can supply 10 MW, but without a system to charge it cannot provide either capacity or energy.

Coupling this battery to 100 MW thermal plant that supplies both the energy to charge the battery and 100 MW of capacity provides the system with 110 MW of capacity

6

Page 7: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Why Does System Capacity Contribution Matter in the RPM?

NW Hydro-generation can be used to provide “peaking” and/or “energy” capability

There are “tradeoffs” Adding resources, like DR, that primarily provide

peaking capacity, allows the hydro system to be used more for energy production

Adding resources, like conservation and CCCTs, that can provide both energy and capacity, allows the hydro system to be used either more for peaking capacity or for energy production

Adjusting resources to reflect their capacity contribution allows the RPM to recognize resource that provide energy to “release” hydro-generation to meet short term peaking requirements

7

Page 8: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Now, On To Scenario Comparisons and Observations Net System Cost

Least Cost Strategies for 1B, 2B, 2C and 3 A

53 97 123 135 167 178 266Net System Cost (Billions 2012 $)

Prob

abili

ty

Scenario1B2B2C3A

8

Page 9: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

The Average Present Value Net System Cost and Risk for Least Cost Strategies Under All Carbon Reduction

Are Similar

$-

$50

$100

$150

$200

$250

Average System Cost

System Risk (TailVar90)

Pres

ent V

alue

Net

Sys

tem

Cos

t (b

illio

ns 2

012$

)

Scenario 1B - Current Policy, No Carbon Risk

Scenario 2B - Carbon Reduction - Social Cost of Carbon Scenario 2C - Carbon Risk

Scenario 3A - Maximum Carbon Reduction, Existing Technology

9

Page 10: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Observations from Scenarios To Date: Demand Response

Demand Response is the preferred resource to meet short-term peaking capacity requirements*

Why It is lowest cost option for maintaining capacity reserves It has a shorter lead-time and comes in more “modular”

sizes than generation About 1000 MW of DR resources can be optioned and built before

SCCT can be built (Q1 2018) DR defers the size of the SCCT build until after 2030.

It does not have fuel price risk It does not produce significant “energy” in an already

surplus market

10

*Assumes that the limits to reliance on external market imports for winter capacity used in the Regional Resource Adequacy are constraining additional market purchases.

Page 11: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Observations from Scenarios To Date: Energy Efficiency

All least cost resource strategies rely heavily on conservation to meet both winter capacity and energy needs

Under 90 percent of the futures energy efficiency meets all load growth through 2030 and under 60 - 70 percent of the futures all load growth through 2035.

Why Significant amounts are available below projected future market prices

(e.g., 1200 aMW by 2021 and 3500 aMW by 2035 <$30/MWh It produces 2.0 MW/MWh saved during winter It has a shorter lead-time and comes in more “modular” sizes than

generation It does not have fuel price risk It does not have carbon price risk Its development is essential to attaining carbon emissions reductions, but

the quantity developed under least cost resources strategies does not significantly increase when carbon risk is considered

11

Page 12: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Average Conservation Development Across Scenarios Increases When Carbon Risk Are Considered

But Does Not Increase With Full Coal Retirement or Consideration of the Social Cost of Carbon

-

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

5,000

Scenario 1B - Current Policy, No Carbon

Risk

Scenario 2B - Carbon Reduction - Social

Cost of Carbon

Scenario 2C - Carbon Risk

Scenario 3A - Maximum Carbon Reduction, Existing

Technology

Aver

age

Reso

urce

Dev

elop

men

t (aM

W)

2021

2026

2035

12

5% Increase No Difference

Page 13: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Average Conservation Winter Peak Development in Least Cost Resource Strategies for Scenarios 1B, 2B, 2C and 3A

-

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

2021 2026 2035

Win

ter P

eak

Capa

city

(MW

)

Scenario 1B - Existing Policy, No Carbon Risk

Scenario 2B - Carbon Reduction - Social Cost of Carbon

Scenario 2C - Carbon Risk

Scenario 3A - Maximum Carbon Reduction, Existing Technology

13

Page 14: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Regional Net Load After Conservation Remains “Flat On Average” Through 2035 Under the Least Cost

Strategy in Scenarios 1B, 2B, 2C and 3A

10,000

12,000

14,000

16,000

18,000

20,000

22,000

2015 2020 2025 2030 2035

PNW

Sys

tem

Loa

d (a

MW

)

Median - Scenario 1B - Existing Policy, No Carbon Risk

Median - Scenario 2B - Carbon Reduction - Social Cost of Carbon

Median - Scenario 2C - Carbon Risk

Median - Scenario 3A - Maximum Carbon Reduction, Existing Technology

14

Page 15: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

This Result is Very Similar To The 6th Plan Net Load After Conservation Scenarios 1B, 2B, 2C and 3A Least

Cost Strategy and 6th Plan

0

5,000

10,000

15,000

20,000

25,000

2010 2015 2020 2025 2030 2035

PNW

Pow

er S

yste

m L

oad

(aM

W)

6th Plan - Medium Forecast

Median - Scenario 1B - Existing Policy, No Carbon Risk

Median - Scenario 2B - Carbon Reduction - Social Cost of Carbon

Median - Scenario 2C - Carbon Risk

Median - Scenario 3A - Maximum Carbon Reduction, Existing Technology

15

Page 16: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Observations from Scenarios To Date: Renewable Resources

All least cost resource strategies build renewable resources to satisfy state RPS requirements

Why REC banking delays the need for constructing RPS resources

until well past the action plan period Renewable resources are not deployed to mitigate future

carbon risk/cost even when the Social Cost of Carbon and future resource cost reductions (15% for solar PV and 5% for wind by 2030) are assumed

Why GHG gas reductions are achievable at a lower cost through

energy efficiency and the substitution of (mostly existing) natural gas for existing coal generation

16

Page 17: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Average Renewable Resource Development for Energy Occurs After RECs are Used and Loads Begin To Increase

-

50

100

150

200

250

300

2021 2026 2035

Annu

al E

nerg

y Co

ntrib

utio

n (a

MW

) Scenario 1B - Existing Policy, No Carbon Risk

Scenario 2B - Carbon Reduction - Social Cost of Carbon

Scenario 2C - Carbon Risk

Scenario 3A - Maximum Carbon Reduction, Existing Technology

17

Page 18: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Observations from Scenarios To Date: Thermal Resources

Thermal resource construction is driven by announced coal plant retirements

Why Energy efficiency and demand response meet most near

term capacity needs Combined cycle combustion turbines appear to be

favored over less efficient “peakers.” Why Future carbon risk, and to some extent fuel price risk, favor

more efficient gas-fired generation technologies Note: This finding is limited to meeting the

region’s capacity and energy needs and does not address the need for flexibility and balancing resources

18

Page 19: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Observations from Scenarios To Date: Carbon Emissions Reduction

The least cost resource strategies that meet proposed CO2 Emissions Limits at the regional level: Meet all (or nearly all) load growth with energy efficiency Meet near term needs for capacity with demand response Replace retiring existing coal plans with increase gas-fired

generation, primarily from existing gas resources and later with combined cycle combustion turbines

Do not significantly expand the use of renewable resources

Why The lowest cost strategy to achieve CO2 reductions

19

Page 20: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Scenario 2B and 2C Cost of Carbon Assumptions

$-

$20

$40

$60

$80

$100

$120

$140

$160

$180

$200

2015 2020 2025 2030 2035

Cost

of C

arbo

n (2

012$

/met

ric to

n)

Social Cost of Carbon (5% Discount) Scenario 2B - Social Cost of Carbon (3% Discount) Social Cost of Carbon (2.5% Discount) Social Cost of Carbon (3% Discount, 95th Percentile) Scenario 2C - Carbon Risk

20

Page 21: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

CO2 Emissions Across Least Cost Resources Strategies - 2030

-

5

10

15

20

25

30

35

40

45

50

Average 111(d) 90th Percentile 111(d)

Average PNWSystem

90th Percentile PNWSystem

MM

TE in

203

0

Scenario 1B - Existing Policy, No Carbon Risk

Scenario 2B - Carbon Reduction - Social Cost of Carbon

Scenario 2C - Carbon Risk

Scenario 3A - Maximum Carbon Reduction, Existing Technology

21

EPA Proposed 111(d) Emissions Limits – 26.2 MMTE

Page 22: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Thermal Resource Dispatch without Carbon Risk – 1B

0

2,000

4,000

6,000

8,000

10,000

12,000

2016 2018 2020 2022 2024 2026 2028 2030 2032 2034

Annu

al D

ispa

tch

(aM

W)

Coal Natural Gas Solar Wind Must Run

22

Page 23: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Thermal Resource Dispatch with Social Cost of Carbon – 2B

0

2,000

4,000

6,000

8,000

10,000

12,000

2016 2018 2020 2022 2024 2026 2028 2030 2032 2034

Annu

al D

ispa

tch

(aM

W)

Coal Natural Gas Solar Wind Must Run

23

Page 24: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Thermal Resource Dispatch with Carbon Risk - 2C

0

2,000

4,000

6,000

8,000

10,000

12,000

2016 2018 2020 2022 2024 2026 2028 2030 2032 2034

Annu

al D

ispa

tch

(aM

W)

Coal Natural Gas Solar Wind Must Run

24

Page 25: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Thermal Resource Dispatch with Coal and Inefficient Gas Retirement

0

2,000

4,000

6,000

8,000

10,000

12,000

2016 2018 2020 2022 2024 2026 2028 2030 2032 2034

Annu

al D

ispa

tch

(aM

W)

Coal Natural Gas Solar Wind Must Run

25

Page 26: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Change in Coal Dispatch Scenarios 1B, 2B, 2C and 3A

0

1,000

2,000

3,000

4,000

5,000

2016 2018 2020 2022 2024 2026 2028 2030 2032 2034

Annu

al D

ispa

tch

(aM

W)

Scenario 1B - Existing Policy, No Carbon Risk Scenario 2B - Carbon Reduction - Social Cost of Carbon Scenario 2C - Carbon Risk Scenario 3A - Maximum Carbon Reduction, Existing Technology

26

Page 27: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Change in Existing Gas Dispatch Scenario 1B, 2B, 2C and 3A

0

1,000

2,000

3,000

4,000

5,000

6,000

2016 2018 2020 2022 2024 2026 2028 2030 2032 2034

Annu

al D

ispa

tch

(aM

W)

Scenario 1B - Existing Policy, No Carbon Risk Scenario 2B - Carbon Reduction - Social Cost of Carbon Scenario 2C - Carbon Risk Scenario 3A - Maximum Carbon Reduction, Existing Technology

27

Page 28: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Change in Renewable Resource Dispatch Scenarios 1B, 2B, 2C and 3A

0

500

1,000

1,500

2,000

2,500

3,000

3,500

2016 2018 2020 2022 2024 2026 2028 2030 2032 2034

Annu

al D

ispa

tch

(aM

W)

Scenario 1B - Existing Policy, No Carbon Risk

Scenario 2B - Carbon Reduction - Social Cost of Carbon

Scenario 2C - Carbon Risk

Scenario 3A - Maximum Carbon Reduction, Existing Technology

28

Page 29: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Scenario 3B – Carbon Reduction with Emerging Technology

“The Energy Problem Statement”

29

0

1,000

2,000

3,000

4,000

5,000

6,000

2016 2018 2020 2022 2024 2026 2028 2030 2032 2034

Annu

al D

ispa

tch

(aM

W)

Scenario 3A – Remaining Gas-Fired Generation ~ 5300 aMW of “Shaped Energy” That Must Be Supplied by Non-GHG Producing Resources or Additional Load Reduction from Conservation

Page 30: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Scenario 3B – Carbon Reduction with Emerging Technology

“The Capacity Problem Statement”

30

0

2,000

4,000

6,000

8,000

10,000

12,000

2016 2018 2020 2022 2024 2026 2028 2030 2032 2034 2036

Annu

al W

inte

r Pea

k D

ispa

tch

(MW

)

Scenario 3A – Remaining Gas-Fired Generation ~ 10,000 MW of “Peak Capacity” That Must Be Supplied by Non-GHG Producing Resources or Additional Peak Load Reduction from Conservation or Demand Response

Page 31: Selected Findings from Scenario Analysis Conducted To Dateapp.nwcouncil.org/media/7149339/p4_webinar_scenarioanalysisstat… · Scenario Analysis Conducted To Date Power Committee

Next Steps

Power Committee Meeting Revised analysis reflecting model input and

model structure changes for scenarios 1B, 2B, 2C, 3A – Updates S3 – No Demand Response

31