Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast Concrete Bridge Piers Chris P. Pantelides, PhD, PE, SE M.J. Ameli, PhD Candidate Saratoga Springs, NY April 2015

Transcript of Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast...

Page 1: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Seismic Evaluation of Grouted Splice Sleeve Connections for

Reinforced Precast Concrete Bridge Piers

Chris P. Pantelides, PhD, PE, SEM.J. Ameli, PhD Candidate

Saratoga Springs, NYApril 2015

Page 2: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Introduction 2

Accelerated Bridge Construction

ABC Connections Modified for High-Seismic Regions

Khaleghi et al. (2012)

Utah Transit Authority (2012)

Page 3: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Introduction 3

GGSSFGSS

Page 4: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Air Tests 4

GGSS FGSS

Page 5: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Air Tests 5

• Rebar fracture• 169%fy on average• Type 2 (Building)• FMC (Bridge)

• Pull-out failure• 145%fy on average• Type 1 (Building)• FMC (Bridge)

fy = 76 ksi

FGSS

GGSS

Page 6: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Tests 6

• Prototype bridges in Utah considered• Capacity-based design procedure • AASHTO LRFD and AASHTO Seismic for detailing• Sectional and Pushover analyses conducted

–•

GGSS

FGSS

Page 7: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Half-Scale Tests 7

Page 8: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Construction of Specimens1 2

3 4

8

Page 9: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Half-Scale Tests/GGSS-1 Construction 9

Page 10: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Half-Scale Tests/GGSS-2 Construction 10

Page 11: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Half-Scale Tests/GGSS-3 Construction 11

Page 12: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Half-Scale Tests/GGSS-CIP Construction 12

Page 13: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Half-Scale Test/FGSS-1 Construction 13

Page 14: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Half-Scale Test/FGSS-2 Construction 14

Page 15: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Half-Scale Test/FGSS-CIP Construction 15

Page 16: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Test Procedure 16

GGSS-2 Construction and Installation

POT#1

Strain Gauges

String Potentiometers

LVDTs

Page 17: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Test Procedure 17

GGSS-2 Construction and Installation

-12-10-8-6-4-202468

1012

0 2 4 6 8 10 12 14 16 18 20 22

Drif

t (%

)

Cycles

Page 18: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Test Results 18

Column-to-Footing Connections: Hysteretic Response

GGSS-2

GGSS-3 GGSS-CIP

GGSS-1

Page 19: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Test Results/GGSS-2 19

Column-to-Footing Connections: Observations

Page 20: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Test Results/GGSS-3 20

Column-to-Footing Connections: Observations

@ 3% Drift @ 6% Drift (Peak)

@ 8% Drift

Page 21: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Test Results 21

Column-to-Footing Connections: Comparison

Column-to-Footing Connections: Curvature ProfileGGSS-2 GGSS-3

Page 22: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Test Results 22

Column-to-Cap Beam Connections: Hysteretic ResponseFGSS-1 FGSS-2

FGSS-CIP

Page 23: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Test Results/FGSS-1 23

Page 24: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Test Results/FGSS-2 24

Page 25: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Test Results 25

Column-to-Cap Beam Connections: Comparison

Column-to-Cap Beam Connections: Curvature ProfileFGSS-1 FGSS-2

Page 26: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

26

Repairability CFRP composite doughnut with headed steel bars

Page 27: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

27

Repairability CFRP composite doughnut with headed steel bars

Repaired specimenperformed as good or better than the precast GSS specimen

18% larger ultimate load capacity18% larger ultimate displacement

capacity5% larger displacement ductility

15% larger energy dissipation capacity at 6% drift ratio

GSS

Page 28: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

Conclusions 28

Column-to-Cap Beam Connections [FGSS]

Column-to-Footing Connections [GGSS]

General Findingso Desirable ductile performance of the CIP specimens o Failure of CIP specimens was rebar fracture due to low cycle fatigue o Localized damage for precast specimens with GSS in column baseo Similar damage state, strength capacity, curvature distribution, and hysteretic

performance to CIP specimens when GSS located in footing or cap beam, BUT different termination point and displacement ductility capacity for all precast specimens

o Repairable ABC Connections

o Failure of all precast specimens due to premature rebar fractureo Improved displacement ductility capacity when GGSS in the footing – harder to buildo Superior displacement ductility capacity when debonding implemented

o Pull-out failure for FGSS-1 due to excessive bond-slipo Pull-out failure and premature rebar fracture occurred for FGSS-2o Improved overall performance when FGSS located in the cap beam – harder to build

Page 29: Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast …sp.bridges.transportation.org/Documents/2015 SCOBS... · 2015-05-27 · Seismic Evaluation of Grouted

29

o University of Utaho Joel Parkso Dylan Browno Prof. Lawrence D. Reaveleyo Mark Bryant

o Utah Department of Transportationo Carmen Swanwicko Joshua Sletten

o New York State Department of Transportationo Harry White

o Texas Department of Transportationo Mountain Plains Consortiumo NMB Splice Sleeve North America & Erico

Acknowledgements