The Fehmarnbelt Tunnel – a world record
08 June 2016Henrik Christensen
Project features:Tunnel length: 18km Tunnel type: immersed tunnel (tube)Modes: 4 lane motorway with emergency lanesTwin track railway in separate tubes
Economy:Estimated tunnel cost: €7.1 billionLoans are state guaranteed and payedback via user tolls Total repayment period: 36 years
Regional interaction on jobs and business
§ The direct employment estimated to 25,000 man years
§ One job on site is followed by one job in supply chain
§ Strong regional business backup to our contractors
08 June 2016Henrik Christensen
Contractor – Dredging & reclamation
§ Fehmarn Belt Contractors:
Company CountryBoskalis International B.V. NetherlandsVan Oord Dredging and Marine Contractors b.v.
Netherlands
Consultants: SWECO Danmark A/S Denmark
08 June 2016Henrik Christensen
Contractor – Tunnel (North and South)
§ Fehmarn Link Contractors:Company CountryVinci Construction Grand Projets s.a.s FrancePer Aarsleff Holding A/S DenmarkWayss und Freytag Ingenieurbau AG GermanyMax Bögl Stiftung & Co KG GmbH GermanyCFE SA BelgiumSolétance-Bachy International FranceBAM Infra BV NetherlandsBAM International BV NetherlandsConsultants: COWI A/S Denmark
08 June 2016Henrik Christensen
Contractor – Portals & Ramps
§ Fehmarn Link Contractors:Company CountryPer Aarsleff Holding A/S DenmarkVinci Construction Grand Projets s.a.s FranceWayss und Freytag Ingenieurbau AG GermanyMax Bögl Stiftung & Co KG GmbH GermanyCFE SA BelgiumSolétance-Bachy International FranceBAM Infra BV NetherlandsBAM International BV NetherlandsConsultants: COWI A/S Denmark