SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do...

42
SITE CLEARING 02230 - 1 Additions to Potomack Intermediate School SECTION 02230 - PART 1 - GENERAL SITE CLEARING 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section. 1.2 SUMMARY A. This Section includes the following: 1. Protecting existing grass to remain. 2. Removing existing grass. 3. Clearing and grubbing. 4. Stripping and stockpiling topsoil. 5. Removing above- and below-grade site structures and features. B. Related Sections include the following: 1. Division 1 Section "Temporary Facilities and Controls" for temporary utilities, temporary construction and support facilities, temporary security and protection facilities. 2. Division 1 Section "Execution Requirements" for verifying utility locations and for recording field measurements. 3. Division 2 Section "Earthwork" for soil materials, excavating, backfilling, and site grading. 4. Division 2 Section "Lawns and Grasses" for finish grading including preparing and placing planting soil mixes and testing of topsoil material. 1.3 DEFINITIONS A. Topsoil: Natural or cultivated surface-soil layer containing organic matter and sand, silt, and clay particles; friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more than 2 inches (50 mm) 1.4 MATERIAL OWNERSHIP in diameter; and free of subsoil and weeds, roots, toxic materials, or other nonsoil materials. A. Except for stripped topsoil or other materials indicated to remain Owner's property, cleared materials shall become Contractor's property and shall be removed from Project site.

Transcript of SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do...

Page 1: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

SITE CLEARING 02230 - 1 Additions to Potomack Intermediate School

SECTION 02230 -

PART 1 - GENERAL

SITE CLEARING

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Protecting existing grass to remain. 2. Removing existing grass. 3. Clearing and grubbing. 4. Stripping and stockpiling topsoil. 5. Removing above- and below-grade site structures and features.

B. Related Sections include the following: 1. Division 1 Section "Temporary Facilities and Controls" for temporary utilities, temporary

construction and support facilities, temporary security and protection facilities. 2. Division 1 Section "Execution Requirements" for verifying utility locations and for

recording field measurements. 3. Division 2 Section "Earthwork" for soil materials, excavating, backfilling, and site

grading. 4. Division 2 Section "Lawns and Grasses" for finish grading including preparing and

placing planting soil mixes and testing of topsoil material.

1.3 DEFINITIONS

A. Topsoil: Natural or cultivated surface-soil layer containing organic matter and sand, silt, and clay particles; friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more than 2 inches (50 mm)

1.4 MATERIAL OWNERSHIP

in diameter; and free of subsoil and weeds, roots, toxic materials, or other nonsoil materials.

A. Except for stripped topsoil or other materials indicated to remain Owner's property, cleared materials shall become Contractor's property and shall be removed from Project site.

Page 2: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

SITE CLEARING 02230 - 2 Additions to Potomack Intermediate School

1.5 SUBMITTALS

A. Photographs or videotape, sufficiently detailed, of existing conditions of trees and plantings, adjoining construction, and site improvements that might be misconstrued as damage caused by site clearing.

B. Record drawings, according to Division 1 Section "Project Record Documents," identifying and accurately locating capped utilities and other subsurface structural, electrical, and mechanical conditions.

1.6 QUALITY ASSURANCE

A. Preinstallation Conference: Conduct conference at Project site to comply with requirements in Division 1 Section "Project Management and Coordination."

1.7 PROJECT CONDITIONS

A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during site-clearing operations.

1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction.

2. Provide alternate routes around closed or obstructed traffic ways if required by authorities having jurisdiction.

B. Salvable Improvements: Carefully remove items indicated to be salvaged and store on Owner's premises where indicated.

C. Utility Locator Service: Notify utility locator service for area where Project is located before site clearing. 1. Miss Utility of West Virginia: Call 1-800-245-4848.

D. Do not commence site clearing operations until temporary erosion and sedimentation control measures are in place.

PART 2 - PRODUCTS

2.1 SOIL MATERIALS

A. Satisfactory Soil Materials: Requirements for satisfactory soil materials are specified in Division 2 Section "Earthwork."

1. Obtain approved borrow soil materials off-site when satisfactory soil materials are not available on-site.

Page 3: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

SITE CLEARING 02230 - 3 Additions to Potomack Intermediate School

2.2 MISCELLANEOUS OTHER MATERIALS

A. Contractor is to provide materials as necessary to control erosion and sediment on this site, as part of this contract.

PART 3 - EXECUTION

3.1 PREPARATION

A. Protect and maintain benchmarks and survey control points from disturbance during construction.

B. Locate and clearly flag vegetation to remain or to be relocated.

C. Protect existing site improvements to remain from damage during construction.

1. Restore damaged improvements to their original condition, as acceptable to Owner.

D. Provide erosion control measures to prevent soil erosion and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways.

3.2 UTILITIES

3.3 CLEARING AND GRUBBING

A. Remove obstructions, grass, and other vegetation to permit installation of new construction.

B. Fill depressions caused by clearing and grubbing operations with satisfactory soil material unless further excavation or earthwork is indicated.

3.4 TOPSOIL STRIPPING

A. Strip topsoil to whatever depths are encountered in a manner to prevent intermingling with underlying subsoil or other waste materials.

1. Remove subsoil and nonsoil materials from topsoil, including trash, debris, weeds, roots, and other waste materials.

B. Stockpile topsoil materials away from edge of excavations without intermixing with subsoil. Grade and shape stockpiles to drain surface water. Cover to prevent windblown dust. 1. Stockpile surplus topsoil to allow for respreading deeper topsoil.

3.5 SITE IMPROVEMENTS

A. Remove existing above- and below-grade improvements as indicated and as necessary to facilitate new construction.

Page 4: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

SITE CLEARING 02230 - 4 Additions to Potomack Intermediate School

B. Remove slabs and aggregate base as indicated.

1. Unless existing full-depth joints coincide with line of demolition, neatly saw-cut length of existing pavement to remain before removing existing pavement. Saw-cut faces vertically.

3.6 DISPOSAL

A. Disposal: Remove surplus soil material, unsuitable topsoil, obstructions, demolished materials, and waste materials including trash and debris, and legally dispose of them off Owner's property.

END OF SECTION 02230

Page 5: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

EARTHWORK 02300 - 1 Additions to Potomack Intermediate School

SECTION 02300 -

PART 1 - GENERAL

EARTHWORK

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Site excavation and grading. 2. Preparing subgrades for slabs-on-grade, walks, and lawns and grasses. 3. Excavating and backfilling for buildings and structures. 4. Drainage fill course for slabs-on-grade.

B. Related Sections include the following:

1. Division 1 Section "Construction Progress Documentation" for recording preexcavation and earthwork progress.

2. Division 1 Section "Temporary Facilities and Controls" for temporary controls, utilities, and support facilities.

3. Division 2 Section "Site Clearing" for temporary erosion and sedimentation control measures.

4. Division 2 Section "Lawns and Grasses" for finish grading, including preparing and placing topsoil and planting soil for lawns.

1.3 DEFINITIONS

A. Backfill: Soil material used to fill an excavation.

B. Borrow Soil: Satisfactory soil imported from off-site for use as fill or backfill.

C. Drainage Fill Course: Course supporting the slab-on-grade that also minimizes upward capillary flow of pore water.

D. Excavation: Removal of material encountered above subgrade elevations and to lines and dimensions indicated.

1. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions without direction by Architect. Unauthorized excavation, as well as remedial work directed by Architect, shall be without additional compensation.

E. Fill: Soil materials used to raise existing grades.

Structures: Buildings, footings, foundations, slabs, or other man-made stationary features constructed above or below the ground surface.

Page 6: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

EARTHWORK 02300 - 2 Additions to Potomack Intermediate School

G. Subgrade: Surface or elevation remaining after completing excavation, or top surface of a fill or backfill immediately below subbase, drainage fill, or topsoil materials.

H. Utilities: On-site underground pipes, conduits, ducts, and cables, as well as underground services within buildings.

1.4 SUBMITTALS

A. Material Test Reports: From a qualified testing agency indicating and interpreting test results for compliance of the following with requirements indicated:

1. Classification according to ASTM D 2487 of each on-site and borrow soil material proposed for fill and backfill.

2. Laboratory compaction curve according to ASTM D 698 for each on-site and borrow soil material proposed for fill and backfill.

B. Preexcavation Photographs or Videotape: Show existing conditions of adjoining construction and site improvements, including finish surfaces, that might be misconstrued as damage caused by earthwork operations. Submit before earthwork begins.

1.5 QUALITY ASSURANCE

A. Contractor’s Geotechnical Testing Agency Qualifications: Qualified according to ASTM E329 and ASTM D3740 for additional testing required by Contractor including, but not limited to, testing of offsite borrow material.

B. Preexcavation Conference: Conduct conference at Project site to comply with requirements in Division 1 Section "Project Management and Coordination."

1.6 PROJECT CONDITIONS

A. Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted in writing by Architect and then only after arranging to provide temporary utility services according to requirements indicated.

1. Notify Architect and Owner not less than seven days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Architect's written permission. 3. Contact utility-locator service for area where Project is located before excavating.

a. Miss Utility of West Virginia; 1-800-245-4848.

B. Demolish and completely remove from site existing underground utilities indicated to be removed. Coordinate with utility companies to shut off services if lines are active.

C. Site Information: Design is based on the geotechnical investigation report from the construction of the Potomack Elementary School building which was originally called North Elementary School. Data on indicated subsurface conditions are not intended as representations or warranties of accuracy or continuity between soil borings. It is expressly understood that neither the owner nor the architect will be responsible for interpretations or conclusions drawn there from by the contractor. Data are made available for convenience of the contractor. Data

Page 7: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

EARTHWORK 02300 - 3 Additions to Potomack Intermediate School

may be obtained from Architect by requesting same on contractor’s letterhead, signed by a legal representative of the contractor, in the following form:

“Please forward a copy of the Report of Geotechnical Investigation for ‘PROPOSED NORTH ELEMENTARY SCHOOL’ dated July 12, 1996. (Contractor) releases the Owner and Architect from any and all responsibility or obligations as to its accuracy or completeness or for any additional compensation for work performed under the contract due to the assumptions based on use of such furnished information or data.”

1. The Owner’s geotechnical engineer is to be notified by the Contractor and be on site during earthwork to confirm adequate bearing conditions.

2. Geotechnical data will only be released to prospective bidders. 3. Test borings and other exploratory operations may be made by the contractor at no cost to

the Owner. Permission must be obtained from the Owner prior to Contractor’s explorations.

PART 2 - PRODUCTS

2.1 SOIL MATERIALS

A. General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from on-site excavations.

B. Satisfactory Soils: ASTM D 2487 Soil Classification Groups GW, GP, GM, GC, ML, CL, SC, SW, SP, and SM, or a combination of these groups; free of rock or gravel larger than 3 inches

1. Maximum Plasticity Index: 15.

in any dimension, debris, waste, frozen materials, vegetation, and other deleterious matter.

2. Maximum Liquid Limit: 40. 3. Satisfactory soils shall be free of coal, coal mine refuse and containing greater than 0.5

percent by weight of pyritic sulphur material

C. Unsatisfactory Soils: Soil Classification Groups OL, CH, MH, OH, and PT according to ASTM D 2487, or a combination of these groups.

1. Unsatisfactory soils also include satisfactory soils not maintained within specified percentage of optimum moisture content at time of compaction.

D. Backfill and Fill: Satisfactory soil materials.

E. Drainage Fill: Narrowly graded mixture of crushed stone, or crushed gravel; ASTM D 448; coarse-aggregate grading Size 57; with 100 percent passing a 1-1/2-inch sieve and 0 to 5 percent passing a No. 8

2.2 CONTROLLED LOW-STRENGTH MATERIAL

sieve.

A. Controlled Low-Strength Material (CLSM): Low-density, self-compacting, flowable concrete material as follows:

1. Portland Cement: ASTM C 150, Type I. 2. Fly Ash: ASTM C 618, Class C or F. 3. Normal-Weight Aggregate: ASTM C 33, 3/4-inch nominal maximum aggregate size.

Page 8: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

EARTHWORK 02300 - 4 Additions to Potomack Intermediate School

4. Foaming Agent: ASTM C 869. 5. Water: ASTM C 94/C 94M. 6. Air-Entraining Admixture: ASTM C 260.

B. Produce low-density, controlled low-strength material with the following physical properties:

1. As-Cast Unit Weight: 36 to 42 lb/cu. ft.

2. Compressive Strength:

at point of placement, when tested according to ASTM C 138/C 138M.

140 psi

PART 3 - EXECUTION

, when tested according to ASTM C 495.

3.1 PREPARATION

A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earthwork operations.

B. Provide, protect and maintain erosion control measures to prevent soil erosion and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways."

3.2 DEWATERING

A. Prevent surface water and ground water from entering excavations, from ponding on prepared subgrades, and from flooding Project site and surrounding area.

B. Protect subgrades from softening, undermining, washout, and damage by rain or water accumulation.

1. Reroute surface water runoff away from excavated areas. Do not allow water to accumulate in excavations. Do not use excavated trenches as temporary drainage ditches.

2. Install a dewatering system, to keep subgrades dry and convey ground water away from excavations. Maintain until dewatering is no longer required.

3.3 EXPLOSIVES

A. Explosives: Do not use explosives.

3.4 EXCAVATION, GENERAL

A. Unclassified Excavation: Excavate to subgrade elevations regardless of the character of surface and subsurface conditions encountered. Unclassified excavated materials may include rock, soil materials, and obstructions. No changes in the Contract Sum or the Contract Time will be authorized for rock excavation or removal of obstructions.

1. This is a lump sum bid project and Contractor is responsible for his own quantity estimates of earthwork for bidding purposes.

Page 9: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

EARTHWORK 02300 - 5 Additions to Potomack Intermediate School

2. Contractor is responsible for constructing to proposed grades regardless of whether or not cut and fill quantities balance. Contractor will be responsible for importing or exporting material to achieve indicated grades.

3. If excavated materials intended for fill and backfill include unsatisfactory soil materials and rock, replace with Satisfactory Soil materials.

4. Remove rock to lines and grades indicated to permit installation of permanent construction without exceeding the following dimensions: a. 6 inchesb.

outside of minimum required dimensions of concrete cast against grade. 6 inches

B. Stability of Excavations: Slope sides of excavations to comply with codes and ordinances having jurisdiction. Shore and brace where sloping is not possible because of space restrictions or stability of material being excavated.

beneath bottom of concrete slabs on grade.

1. Shoring and Bracing: Provide materials for shoring and bracing, such as sheet piling, uprights, stringers, and cross-braces, in good serviceable condition.

2. Maintain excavations in safe condition until completion of backfilling.

C. Sensitivity of Excavations: Concrete for foundations is to be placed same day as excavation occurs. Degraded bearing materials must be removed prior to concrete placement.

3.5 EXCAVATION FOR STRUCTURES

A. Excavate to indicated elevations and dimensions within a tolerance of plus or minus 1 inch

1. Excavations for Footings and Foundations: Do not disturb bottom of excavation. Excavate to final grade just before placing concrete reinforcement. Trim bottoms to required lines and grades to leave solid base to receive other work.

. If applicable, extend excavations a sufficient distance from structures for placing and removing concrete formwork, for installing services and other construction, and for inspections.

3.6 EXCAVATION FOR WALKS AND PAVEMENTS

A. Excavate surfaces under walks and pavements to indicated lines, cross sections, elevations, and subgrades.

3.7 SUBGRADE INSPECTION

A. Notify Owner’s construction testing agency when excavations have reached required subgrade.

1. Refer to Field Quality Control for more information.

B. If Owner’s construction testing agency determines that unsatisfactory soil is present, continue excavation and replace with compacted backfill or fill material as directed.

C. Proof-roll subgrade under the direction of Owner’s testing agency to identify soft pockets and areas of excess yielding. Do not proof-roll wet or saturated subgrades.

1. Excavate soft spots, unsatisfactory soils, and areas of excessive pumping or rutting, as determined by Architect, and replace with compacted backfill or fill as directed.

D. Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated water, or construction activities, as directed by Owner’s testing agency, without additional compensation.

Page 10: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

EARTHWORK 02300 - 6 Additions to Potomack Intermediate School

3.8 UNAUTHORIZED EXCAVATION

A. Fill unauthorized excavation under foundations or wall footings by extending bottom elevation of concrete foundation or footing to excavation bottom, without altering top elevation. Controlled low-strength material may be used when approved by Owner’s testing agency.

1. Fill unauthorized excavations under other construction or utility pipe as directed by Architect.

3.9 STORAGE OF SOIL MATERIALS

A. Stockpile borrow soil materials and excavated satisfactory soil materials without intermixing. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.

1. Stockpile soil materials away from edge of excavations.

3.10 BACKFILL

A. Place and compact backfill in excavations promptly, but not before completing the following:

1. Construction below finish grade including perimeter insulation. 2. Surveying locations of underground utilities for Record Documents. 3. Removing concrete formwork. 4. Removing trash and debris. 5. Removing temporary shoring and bracing, and sheeting.

B. Place backfill on subgrades free of mud, frost, snow, or ice.

C. Do not backfill over building weep holes.

3.11 SOIL FILL

A. Notify Owner’s construction testing agency when compaction operations are ready to begin.

1. Refer to Field Quality Control for more information.

B. Place soil fill on subgrades free of mud, frost, snow, or ice.

C. Place and compact Satisfactory Soil as fill material in layers to required elevations as follows:

1. Under building foundations. 2. Under building slabs. 3. Under walks and pavements. 4. Under grass and planted areas.

3.12 SOIL MOISTURE CONTROL

A. Uniformly moisten or aerate subgrade and each subsequent fill or backfill soil layer before compaction to within 3 percent of ‘wet’ optimum moisture content as determined by test ASTM D 698.

1. Do not place backfill or fill soil material on surfaces that are muddy, frozen, or contain frost or ice.

Page 11: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

EARTHWORK 02300 - 7 Additions to Potomack Intermediate School

2. Remove and replace, or scarify and air dry otherwise satisfactory soil material that exceeds ‘wet’ optimum moisture content by 3 percent and is too wet to compact to specified dry unit weight.

3.13 COMPACTION OF SOIL BACKFILLS AND FILLS

A. Notify Owner’s construction testing agency when compaction operations are ready to begin.

1. Refer to Field Quality Control for more information.

B. Place backfill and fill soil materials in layers not more than 12 inches in loose depth for material compacted by heavy compaction equipment, and not more than 6 inches in loose depth for material compacted by hand-operated tampers.

C. Place backfill and fill soil materials evenly on all sides of structures to required elevations, and uniformly along the full length of each structure.

D. Compact soil materials to not less than the following percentages of maximum dry unit weight according to ASTM D 698:

1. Under structures, buildings, and up to 10 feet outside of building lines compact each layer of backfill or fill soil material at 100 percent.

2. Under structures, buildings, and up to 10 feet outside of building lines scarify and recompact top 12 inches

3. Under walkways, steps and pavements, compact each layer of backfill or fill soil material at 98 percent.

of existing subgrade material at 100 percent.

4. Under walkways, steps and pavements, scarify and recompact top 6 inches

5. Under lawn or unpaved areas, compact each layer of backfill or fill soil material at 90 percent.

of existing subgrade material at 98 percent.

6. Under lawn or unpaved areas, scarify and recompact top 6 inches

3.14 GRADING

of existing subgrade material at 90 percent.

A. General: Uniformly grade areas to a smooth surface, free of irregular surface changes. Comply with compaction requirements and grade to cross sections, lines, and elevations indicated.

1. Provide a smooth transition between adjacent existing grades and new grades. 2. Cut out soft spots, fill low spots, and trim high spots to comply with required surface

tolerances.

B. Site Grading: Slope grades to direct water away from buildings and to prevent ponding.

1. Finish subgrades to required elevations within the following tolerances: a. Lawn or Unpaved Areas: Plus or minus 1 inchb. Walks: Plus or minus

. 1 inch

c. Pavements: Plus or minus .

1/2 inch2. At buildings, finished grades are to be below weep holes as follows:

.

a. Lawn or Unpaved Areas: 2 inch minimum clearanceb. Walks or Pavements:

. 1/2 inch minimum clearance

C. Grading inside Building Lines: Finish subgrade to a tolerance of

.

1/2 inch when tested with a 10-foot straightedge.

Page 12: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

EARTHWORK 02300 - 8 Additions to Potomack Intermediate School

3.15 DRAINAGE FILL COURSE

A. Place drainage fill course on subgrades free of mud, frost, snow, or ice.

B. On prepared subgrade, place and compact drainage fill course of minimum 4 inch final thickness under cast-in-place concrete slabs-on-grade as follows:

1. Place drainage fill course 6 inches2. Place drainage fill course that exceeds

or less in compacted thickness in a single layer. 6 inches in compacted thickness in layers of equal

thickness, with no compacted layer more than 6 inches thick or less than 3 inches3. Compact each layer of drainage fill course to required cross sections and thicknesses to

not less than 95 percent of maximum dry unit weight according to ASTM D 698.

thick.

3.16 FIELD QUALITY CONTROL

A. Testing Agency: Owner will engage a qualified independent geotechnical engineering testing agency to perform field quality-control testing. Contractor is to coordinate testing schedule with testing agency. Contractor is to allow minimum 48 hours notice for testing agency.

B. Allow testing agency to inspect and test subgrades and each fill or backfill layer. Proceed with subsequent earthwork only after test results for previously completed work comply with requirements.

C. Footing Subgrade: At footing subgrades, at least one test of each soil stratum will be performed to verify design bearing capacities. Subsequent verification and approval of other footing subgrades may be based on a visual comparison of subgrade with tested subgrade when approved by Architect.

D. Testing agency will test compaction of soils in place according to ASTM D 1556, ASTM D 2167, ASTM D 2922, and ASTM D 2937, as applicable. Tests will be performed at the following locations and frequencies:

1. Paved and Building Slab Areas: At subgrade and at each compacted fill and backfill layer, at least 1 test for every 2000 sq. ft.

2. Foundation Wall Backfill: At each compacted backfill layer, at least 1 test for each

or less of paved area or building slab, but in no case fewer than 3 tests.

100 feet

E. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil to depth required; recompact and retest until specified compaction is obtained.

or less of wall length, but no fewer than 2 tests.

3.17 PROTECTION

A. Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion. Keep free of trash and debris.

B. Repair and reestablish grades to specified tolerances where completed or partially completed surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions.

Page 13: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

EARTHWORK 02300 - 9 Additions to Potomack Intermediate School

1. Scarify or remove and replace soil material to depth as directed by Architect; reshape and recompact.

C. Where settling occurs before Project correction period elapses, remove finished surfacing, backfill with additional soil material, compact, and reconstruct surfacing.

1. Restore appearance, quality, and condition of finished surfacing to match adjacent work, and eliminate evidence of restoration to greatest extent possible.

3.18 DISPOSAL OF SURPLUS AND WASTE MATERIALS

A. Disposal: Remove surplus satisfactory soil and waste material, including unsatisfactory soil, trash, and debris, and legally dispose of it off Owner's property.

END OF SECTION 02300

Page 14: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

EARTHWORK 02300 - 10 Additions to Potomack Intermediate School

This page has been left blank intentionally.

Page 15: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

TERMITE CONTROL 02361 - 1 Additions to Potomack Intermediate School

SECTION 02361 -

PART 1 - GENERAL

TERMITE CONTROL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Soil treatment with termiticide.

1.3 PERFORMANCE REQUIREMENTS

A. Service Life of Soil Treatment: Soil treatment by use of a termiticide that is effective for not less than five years against infestation of subterranean termites.

1.4 SUBMITTALS

A. Product Data: For termiticide.

1. Include the EPA-Registered Label for termiticide products.

B. Product Certificates: For termite control products, signed by product manufacturer.

C. Qualification Data: For Installer of termite control products.

D. Soil Treatment Application Report: After application of termiticide is completed, submit report for Owner's record information, including the following:

1. Date and time of application. 2. Moisture content of soil before application. 3. Brand name and manufacturer of termiticide. 4. Quantity of undiluted termiticide used. 5. Dilutions, methods, volumes, and rates of application used. 6. Areas of application. 7. Water source for application.

E. Warranty: Special warranty specified in this Section.

1.5 QUALITY ASSURANCE

A. Installer Qualifications: A specialist who is licensed according to regulations of authorities having jurisdiction to apply termite control treatment and products in jurisdiction where Project is located.

Page 16: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

TERMITE CONTROL 02361 - 2 Additions to Potomack Intermediate School

B. Regulatory Requirements: Formulate and apply termiticides according to the EPA-Registered Label.

C. Preinstallation Conference: Conduct conference at Project site to comply with requirements in Division 1 Section "Project Management and Coordination" to schedule application of termiticide products.

1.6 PROJECT CONDITIONS

A. Environmental Limitations: To ensure penetration, do not treat soil that is water saturated or frozen. Do not treat soil while precipitation is occurring. Comply with requirements of the EPA-Registered Label and requirements of authorities having jurisdiction.

1.7 COORDINATION

A. Coordinate soil treatment application with excavating, filling, grading, and concreting operations. Treat soil under footings before construction.

1.8 WARRANTY

A. Special Warranty: Manufacturer's standard form, signed by Applicator and Contractor certifying that termite control work, consisting of applied soil termiticide treatment, will prevent infestation of subterranean termites. If subterranean termite activity or damage is discovered during warranty period, re-treat soil and repair or replace damage caused by termite infestation.

1. Warranty Period: Five years from date of Substantial Completion.

1.9 MAINTENANCE SERVICE

A. Continuing Service: Beginning at Substantial Completion, provide a proposal for continuing service including monitoring, inspection, and re-treatment for occurrences of termite activity. Provide a standard continuing service agreement. State services, obligations, conditions, and terms for agreement period; and terms for future renewal options.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

1. Termiticides:

a. Aventis Environmental Science USA LP; Termidor. b. Bayer Corporation; Premise 75. c. Dow AgroSciences LLC; Dursban TC Equity. d. FMC Corporation, Agricultural Products Group; Talstar Prevail FT Torpedo.

Page 17: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

TERMITE CONTROL 02361 - 3 Additions to Potomack Intermediate School

e. Syngenta; Demon TC.

2.2 SOIL TREATMENT

A. Termiticide: Provide an EPA-registered termiticide complying with requirements of authorities having jurisdiction, in an aqueous solution formulated to prevent termite infestation. Provide quantity required for application at the label volume and rate for the maximum termiticide concentration allowed for each specific use, according to product's EPA-Registered Label.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Applicator present, for compliance with requirements for interfaces with earthwork, slab and foundation work, landscaping, and other conditions affecting performance of termite control.

1. Proceed with application only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. General: Comply with the most stringent requirements of authorities having jurisdiction and with manufacturer's written instructions for preparation before beginning application of termite control treatment. Remove all extraneous sources of wood cellulose and other edible materials such as wood debris, roots, stakes, and construction waste wood from soil within and around foundations.

B. Soil Treatment Preparation: Remove foreign matter and impermeable soil materials that could decrease treatment effectiveness on areas to be treated. Loosen, rake, and level soil to be treated except previously compacted areas under slabs and footings. Termiticides may be applied before placing compacted fill under slabs if recommended in writing by termiticide manufacturer.

1. Fit filling hose connected to water source at the site with a backflow preventer, complying with requirements of authorities having jurisdiction.

3.3 APPLICATION, GENERAL

A. General: Comply with the most stringent requirements of authorities having jurisdiction and with manufacturer's EPA-Registered Label for products.

3.4 APPLYING SOIL TREATMENT

A. Application: Mix soil treatment termiticide solution to a uniform consistency. Provide quantity required for application at the label volume and rate for the maximum specified concentration of termiticide, according to manufacturer's EPA-Registered Label, to the following so that a continuous horizontal and vertical termiticidal barrier or treated zone is established around and under building construction. Distribute treatment evenly.

Page 18: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

TERMITE CONTROL 02361 - 4 Additions to Potomack Intermediate School

1. Slabs-on-Grade: Under ground-supported slab construction, including footings, building slabs, and attached slabs as an overall treatment. Treat soil materials before concrete footings and slabs are placed.

2. Foundations: Adjacent soil including soil along the entire inside perimeter of foundation walls, along both sides of interior partition walls, around plumbing pipes and electric conduit penetrating the slab; also along the entire outside perimeter, from grade to bottom of footing. Avoid soil washout around footings.

3. Penetrations: At expansion joints, control joints, and areas where slabs will be penetrated.

B. Avoid disturbance of treated soil after application. Keep off treated areas until completely dry.

C. Protect termiticide solution, dispersed in treated soils and fills, from being diluted until ground-supported slabs are installed. Use waterproof barrier according to EPA-Registered Label instructions.

D. Post warning signs in areas of application.

E. Reapply soil treatment solution to areas disturbed by subsequent excavation, grading, landscaping, or other construction activities following application.

END OF SECTION 02361

Page 19: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

CEMENT CONCRETE PAVEMENT 02751 - 1 Additions to Potomack Intermediate School

SECTION 02751 -

PART 1 - GENERAL

CEMENT CONCRETE PAVEMENT

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes: 1. Door pads. 2. Walks.

B. Related Sections:

1. Division 2 Section "Pavement Joint Sealants" for joint sealants in expansion and contraction joints within concrete paving and in joints between concrete paving and adjacent construction.

2. Division 3 Section "Cast-in-Place Concrete" for general building applications of concrete.

1.3 DEFINITIONS

A. Cementitious Materials: Portland cement alone or in combination with one or more of blended hydraulic cement, fly ash and other pozzolans, and ground granulated blast-furnace slag.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

B. Shop Drawings: Indicate pavement markings, lane separations, and defined parking spaces. Indicate, with international symbol of accessibility, spaces allocated for people with disabilities.

C. Other Action Submittals:

1. Design Mixtures: For each concrete paving mixture. Include alternate design mixtures when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments.

1.5 INFORMATIONAL SUBMITTALS

A. Material Certificates: For the following, from manufacturer:

Page 20: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

CEMENT CONCRETE PAVEMENT 02751 - 2 Additions to Potomack Intermediate School

1. Cementitious materials. 2. Steel reinforcement and reinforcement accessories. 3. Fiber reinforcement. 4. Admixtures. 5. Curing compounds. 6. Joint fillers.

B. Material Test Reports: For each of the following:

1. Aggregates: Include service-record data indicating absence of deleterious expansion of concrete due to alkali-aggregate reactivity, when requested.

C. Field quality-control reports.

1.6 QUALITY ASSURANCE

A. Ready-Mix-Concrete Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment.

B. Testing Agency Qualifications: Qualified according to ASTM C 1077 and ASTM E 329 for testing indicated.

C. Concrete Testing Service: Engage a qualified testing agency to perform material evaluation tests and to design concrete mixtures.

D. ACI Publications: Comply with ACI 301 (ACI 301M)

E. Mockups: Build and designate mockups to verify selections made under sample submittals and to demonstrate aesthetic effects and set quality standards for materials and execution.

unless otherwise indicated.

1. Build mockups of full-thickness sections of concrete paving to demonstrate typical joints; surface finish, texture, and color; curing; and standard of workmanship.

2. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing.

3. Approved mockups will become part of the completed Work if undisturbed at time of Substantial Completion.

F. Preinstallation Conference: Conduct conference at Project site.

1. Review methods and procedures related to concrete paving, including but not limited to, the following:

a. Concrete mixture design. b. Quality control of concrete materials and concrete paving construction practices. c. Concrete delivery travel time and related procedures.

2. Require representatives of each entity directly concerned with concrete paving to attend, including the following:

Page 21: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

CEMENT CONCRETE PAVEMENT 02751 - 3 Additions to Potomack Intermediate School

a. Contractor's superintendent. b. Owner’s testing agency responsible for field quality control testing. c. Ready-mix concrete manufacturer. d. Concrete paving subcontractor.

1.7 PROJECT CONDITIONS

A. Traffic Control: Maintain access for vehicular and pedestrian traffic as required for other construction activities.

PART 2 - PRODUCTS

2.1 FORMS

A. Form Materials: Plywood, metal, metal-framed plywood, or other approved panel-type materials to provide full-depth, continuous, straight, and smooth exposed surfaces.

B. Form-Release Agent: Commercially formulated form-release agent that will not bond with, stain, or adversely affect concrete surfaces and that will not impair subsequent treatments of concrete surfaces.

2.2 STEEL REINFORCEMENT

A. Plain-Steel Welded Wire Reinforcement: ASTM A 185/A 185M, fabricated from as-drawn steel wire into flat sheets.

B. Plain-Steel Wire: ASTM A 82/A 82M, as drawn.

C. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars, welded wire reinforcement, and dowels in place. Manufacture bar supports according to CRSI's "Manual of Standard Practice" from steel wire, plastic, or precast concrete of greater compressive strength than concrete specified, and as follows:

2.3 CONCRETE MATERIALS

A. Cementitious Material: Use the following cementitious materials, of same type, brand, and source throughout Project:

1. Portland Cement: ASTM C 150, gray portland cement Type I or Type II. Supplement with the following:

a. Fly Ash: ASTM C 618, Class F. b. Ground Granulated Blast-Furnace Slag: ASTM C 989, Grade 120.

B. Normal-Weight Aggregates: ASTM C 33, Class 4S, uniformly graded. Provide aggregates from a single source with documented service-record data of at least 10 years' satisfactory

Page 22: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

CEMENT CONCRETE PAVEMENT 02751 - 4 Additions to Potomack Intermediate School

service in similar paving applications and service conditions using similar aggregates and cementitious materials.

1. Maximum Coarse-Aggregate Size: 1-1/2 inches (38 mm)2. Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.

nominal.

C. Water: Potable and complying with ASTM C 94/C 94M.

D. Air-Entraining Admixture: ASTM C 260.

E. Chemical Admixtures: Admixtures certified by manufacturer to be compatible with other admixtures and to contain not more than 0.1 percent water-soluble chloride ions by mass of cementitious material.

1. Water-Reducing Admixture: ASTM C 494/C 494M, Type A. 2. Retarding Admixture: ASTM C 494/C 494M, Type B. 3. Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type D. 4. High-Range, Water-Reducing Admixture: ASTM C 494/C 494M, Type F. 5. High-Range, Water-Reducing and Retarding Admixture: ASTM C 494/C 494M,

Type G. 6. Plasticizing and Retarding Admixture: ASTM C 1017/C 1017M, Type II.

2.4 FIBER REINFORCEMENT

A. Synthetic Fiber: fibrillated virgin polypropylene fibers engineered and designed for use in concrete paving, complying with ASTM C 1116/C 1116M, Type III, ¾ inch long minimum. Provide fiber lengths recommended by fiber manufacturer to be compatible with nominal coarse aggregate size.

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:

a. Fibrillated Fibers: 1) FORTA Corporation; FORTA Super-Net. 2) Performance Concrete Fibers; Genesis. 3) Propex Concrete Systems Corp.; Fibermesh 300.

2.5 CURING MATERIALS

A. Absorptive Cover: AASHTO M 182, Class 3, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. (305 g/sq. m)

B. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.

dry.

C. Water: Potable.

D. Evaporation Retarder: Waterborne, monomolecular, film forming, manufactured for application to fresh concrete.

Page 23: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

CEMENT CONCRETE PAVEMENT 02751 - 5 Additions to Potomack Intermediate School

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following: a. Dayton Superior Corporation; Sure Film (J-74). b. Euclid Chemical Company (The), an RPM company; Eucobar. c. L&M Construction Chemicals, Inc.; E-CON. d. Meadows, W. R., Inc.; EVAPRE.

E. Clear, Waterborne, Membrane-Forming Curing Compound: ASTM C 309, Type 1, Class B, dissipating.

1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following: a. Dayton Superior Corporation; Day-Chem Rez Cure (J-11-W). b. Euclid Chemical Company (The), an RPM company; Kurez W VOX. c. L&M Construction Chemicals, Inc.; L&M CURE R. d. Meadows, W. R., Inc.; 1100-CLEAR SERIES.

2.6 RELATED MATERIALS

A. Joint Fillers: Full depth of slab less sealant space and as follows. Provide either of the following in ½ inch thickness in preformed strips. 1. Asphalt-saturated cellulosic fiber meeting ASTM D 1751. 2. Closed cell non-crosslinked polyethylene foam meeting ASTM D 1752 except that

compression requirements of Section 5.3 are 10 psi minimum and 25 psi maximum. a. Available Manufacturers: Subject to compliance with requirements, manufacturers

offering products that may be incorporated into the Work include, but are not limited to, manufacturers specified. 1) Foamtech; NMW, Inc. 800-253-4237.

2.7 CONCRETE MIXTURES

A. Prepare design mixtures, proportioned according to ACI 301 (ACI 301M)

1. Use a qualified independent testing agency for preparing and reporting proposed concrete design mixtures for the trial batch method.

, for each type and strength of normal-weight concrete, and as determined by either laboratory trial mixtures or field experience.

B. Proportion mixtures to provide normal-weight concrete with the following properties:

1. Compressive Strength (28 Days): 4500 psi (31 MPa)2. Maximum Water-Cementitious Materials Ratio at Point of Placement: 0.45.

.

3. Slump Limit: 4 inches (100 mm), plus or minus 1 inch (25 mm)

C. Add air-entraining admixture at manufacturer's prescribed rate to result in normal-weight concrete at point of placement having an air content as follows:

.

1. Air Content: 5-1/2 percent plus or minus 1.5 percent for 1-1/2-inch (38-mm) nominal maximum aggregate size.

Page 24: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

CEMENT CONCRETE PAVEMENT 02751 - 6 Additions to Potomack Intermediate School

2. Air Content: 6 percent plus or minus 1.5 percent for 1-inch (25-mm)

3. Air Content: 6 percent plus or minus 1.5 percent for

nominal maximum aggregate size.

3/4-inch (19-mm)

D. Limit water-soluble, chloride-ion content in hardened concrete to 0.15 percent by weight of cement.

nominal maximum aggregate size.

E. Chemical Admixtures: Use admixtures according to manufacturer's written instructions.

1. Use water-reducing admixture high-range, water-reducing admixture high-range, water-reducing and retarding admixture and plasticizing and retarding admixture in concrete as required for placement and workability.

2. Use water-reducing and retarding admixture when required by high temperatures, low humidity, or other adverse placement conditions.

F. Cementitious Materials: Use fly ash, pozzolan, ground granulated blast-furnace slag, and silica fume as needed to reduce the total amount of portland cement, which would otherwise be used. Limit percentage, by weight, of cementitious materials other than portland cement in concrete according to ACI 301 requirements as follows:

1. Fly Ash or Pozzolan: 25 percent of Portland cement content by weight. 2. Ground Granulated Blast-Furnace Slag: 50 percent of Portland cement content by

weight. 3. Combined Fly Ash or Pozzolan, and Ground Granulated Blast-Furnace Slag: 50 percent,

with fly ash or pozzolan not exceeding 25 percent of Portland cement content by weight.

G. Synthetic Fiber: Uniformly disperse in concrete mixture at manufacturer's recommended rate, but not less than 1.5 lb/cu. yd. (0.90 kg/cu. m)

2.8 CONCRETE MIXING

.

A. Ready-Mixed Concrete: Measure, batch, and mix concrete materials and concrete according to ASTM C 94/C 94M and ASTM C 1116/C 1116M. Furnish batch certificates for each batch discharged and used in the Work.

1. When air temperature is between 85 and 90 deg F (30 and 32 deg C), reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F (32 deg C)

PART 3 - EXECUTION

, reduce mixing and delivery time to 60 minutes.

3.1 EXAMINATION

A. Examine exposed subgrades and subbase surfaces for compliance with requirements for dimensional, grading, and elevation tolerances.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

Page 25: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

CEMENT CONCRETE PAVEMENT 02751 - 7 Additions to Potomack Intermediate School

3.2 PREPARATION

A. Remove loose material from compacted subbase surface immediately before placing concrete.

3.3 EDGE FORMS AND SCREED CONSTRUCTION

A. Set, brace, and secure edge forms, bulkheads, and intermediate screed guides to required lines, grades, and elevations. Install forms to allow continuous progress of work and so forms can remain in place at least 24 hours after concrete placement.

B. Clean forms after each use and coat with form-release agent to ensure separation from concrete without damage.

3.4 STEEL REINFORCEMENT

A. General: Comply with CRSI's "Manual of Standard Practice" for fabricating, placing, and supporting reinforcement. 1. All exterior concrete is to be reinforced with synthetic fiber reinforcement and

additionally reinforced with steel reinforcement as indicated on the Drawings.

B. Clean reinforcement of loose rust and mill scale, earth, ice, or other bond-reducing materials.

C. Arrange and space bar supports to hold reinforcement in position during concrete placement. Maintain minimum cover to reinforcement.

3.5 JOINTS

A. General: Form construction, isolation, and contraction joints and tool edges true to line, with faces perpendicular to surface plane of concrete. Construct transverse joints at right angles to centerline unless otherwise indicated.

B. Construction Joints: Set construction joints at side and end terminations of paving and at locations where paving operations are stopped for more than one-half hour unless paving terminates at isolation joints.

C. Isolation Joints: Form isolation joints of preformed joint-filler strips abutting concrete curbs, catch basins, manholes, inlets, structures, other fixed objects, and where indicated.

1. Locate expansion joints at intervals of 20 feet unless otherwise indicated. 2. For slabs placed in contact with an irregular material, use flexible joint-filler strips. 3. Extend joint fillers full width and depth of joint. 4. Terminate joint filler not less than 1/2 inch (13 mm) or more than 1 inch (25 mm)

5. During concrete placement, protect top edge of joint filler with metal, plastic, or other temporary preformed cap. Remove protective cap after concrete has been placed on both sides of joint.

below finished surface for joint sealant.

Page 26: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

CEMENT CONCRETE PAVEMENT 02751 - 8 Additions to Potomack Intermediate School

D. Contraction Joints: Form weakened-plane contraction joints, sectioning concrete into areas as indicated. Construct contraction joints for a depth equal to at least one-fourth of the concrete thickness, as follows, to match jointing of existing adjacent concrete paving:

1. Grooved Joints: Form contraction joints after initial floating by grooving and finishing each edge of joint with grooving tool to a 1/4-inch (6-mm)

E. Edging: After initial floating, tool edges of paving, gutters, curbs, and joints in concrete with an edging tool to a

radius. Repeat grooving of contraction joints after applying surface finishes.

1/4-inch (6-mm)

3.6 CONCRETE PLACEMENT

radius. Repeat tooling of edges after applying surface finishes.

A. Before placing concrete, inspect and complete formwork installation, steel reinforcement, and items to be embedded or cast-in.

B. Remove snow, ice, or frost from subbase surface and steel reinforcement before placing concrete. Do not place concrete on frozen surfaces.

C. Moisten subbase to provide a uniform dampened condition at time concrete is placed. Do not place concrete around manholes or other structures until they are at required finish elevation and alignment.

D. Comply with ACI 301 (ACI 301M)

E. Do not add water to concrete during delivery or at Project site. Do not add water to fresh concrete after testing.

requirements for measuring, mixing, transporting, and placing concrete.

F. Deposit and spread concrete in a continuous operation between transverse joints. Do not push or drag concrete into place or use vibrators to move concrete into place.

G. Consolidate concrete according to ACI 301 (ACI 301M)

1. Consolidate concrete along face of forms and adjacent to transverse joints with an internal vibrator. Keep vibrator away from joint assemblies, reinforcement, or side forms. Use only square-faced shovels for hand spreading and consolidation. Consolidate with care to prevent dislocating reinforcement and joint devices.

by mechanical vibrating equipment supplemented by hand spading or tamping.

H. Screed paving surface with a straightedge and strike off.

I. Commence initial floating using bull floats or darbies to impart an open-textured and uniform surface plane before excess moisture or bleed water appears on the surface. Do not further disturb concrete surfaces before beginning finishing operations or spreading surface treatments.

J. Cold-Weather Placement: Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing, or low temperatures. Comply with ACI 306.1 and the following:

Page 27: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

CEMENT CONCRETE PAVEMENT 02751 - 9 Additions to Potomack Intermediate School

1. When air temperature has fallen to or is expected to fall below 40 deg F (4.4 deg C), uniformly heat water and aggregates before mixing to obtain a concrete mixture temperature of not less than 50 deg F (10 deg C) and not more than 80 deg F (27 deg C)

2. Do not use frozen materials or materials containing ice or snow.

at point of placement.

3. Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in design mixtures.

K. Hot-Weather Placement: Comply with ACI 301 (ACI 301M)

1. Cool ingredients before mixing to maintain concrete temperature below

and as follows when hot-weather conditions exist:

90 deg F (32 deg C)

2. Cover steel reinforcement with water-soaked burlap so steel temperature will not exceed ambient air temperature immediately before embedding in concrete.

at time of placement. Chilled mixing water or chopped ice may be used to control temperature, provided water equivalent of ice is calculated in total amount of mixing water. Using liquid nitrogen to cool concrete is Contractor's option.

3. Fog-spray forms, steel reinforcement, and subgrade just before placing concrete. Keep subgrade moisture uniform without standing water, soft spots, or dry areas.

3.7 FLOAT FINISHING

A. General: Do not add water to concrete surfaces during finishing operations.

B. Float Finish: Begin the second floating operation when bleed-water sheen has disappeared and concrete surface has stiffened sufficiently to permit operations. Float surface with power-driven floats or by hand floating if area is small or inaccessible to power units. Finish surfaces to true planes. Cut down high spots and fill low spots. Refloat surface immediately to uniform granular texture. 1. Medium-to-Fine-Textured Broom Finish: Draw a soft-bristle broom across float-finished

concrete surface perpendicular to line of traffic to provide a uniform, fine-line texture.

3.8 CONCRETE PROTECTION AND CURING

A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures.

B. Comply with ACI 306.1 for cold-weather protection.

C. Evaporation Retarder: Apply evaporation retarder to concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h (1 kg/sq. m x h)

D. Begin curing after finishing concrete but not before free water has disappeared from concrete surface.

before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete but before float finishing.

E. Curing Methods: Cure concrete by moisture curing moisture-retaining-cover curing curing compound or a combination of these as follows:

Page 28: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

CEMENT CONCRETE PAVEMENT 02751 - 10 Additions to Potomack Intermediate School

1. Moisture Curing: Keep surfaces continuously moist for not less than seven days with the following materials:

a. Water. b. Continuous water-fog spray. c. Absorptive cover, water saturated and kept continuously wet. Cover concrete

surfaces and edges with 12-inch (300-mm)

2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover, placed in widest practicable width, with sides and ends lapped at least

lap over adjacent absorptive covers.

12 inches (300 mm)

3. Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas that have been subjected to heavy rainfall within three hours after initial application. Maintain continuity of coating, and repair damage during curing period.

and sealed by waterproof tape or adhesive. Immediately repair any holes or tears occurring during installation or curing period using cover material and waterproof tape.

3.9 PAVING TOLERANCES

A. Comply with tolerances in ACI 117 and as follows:

1. Elevation: 3/4 inch (19 mm)2. Thickness: Plus

. 3/8 inch (10 mm), minus 1/4 inch (6 mm)

3. Surface: Gap below .

10-foot- (3-m-) long, unleveled straightedge not to exceed 1/2 inch (13 mm)

4. Joint Spacing: .

3 inches (75 mm)5. Contraction Joint Depth: Plus

. 1/4 inch (6 mm)

6. Joint Width: Plus , no minus.

1/8 inch (3 mm)

3.10 FIELD QUALITY CONTROL

, no minus.

A. Testing Agency: Owner will engage a qualified testing agency to perform tests and inspections.

B. Testing Services: Testing of composite samples of fresh concrete obtained according to ASTM C 172 shall be performed according to the following requirements:

1. Testing Frequency: Obtain at least one composite sample for each 50 cu yds or fraction thereof of each concrete mixture placed each day.

a. When frequency of testing will provide fewer than five compressive-strength tests for each concrete mixture, testing shall be conducted from at least five randomly selected batches or from each batch if fewer than five are used.

2. Slump: ASTM C 143/C 143M; one test at point of placement for each composite sample, but not less than one test for each day's pour of each concrete mixture. Perform additional tests when concrete consistency appears to change.

3. Air Content: ASTM C 231, pressure method; one test for each composite sample, but not less than one test for each day's pour of each concrete mixture.

Page 29: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

CEMENT CONCRETE PAVEMENT 02751 - 11 Additions to Potomack Intermediate School

4. Concrete Temperature: ASTM C 1064/C 1064M; one test hourly when air temperature is 40 deg F (4.4 deg C) and below and when it is 80 deg F (27 deg C)

5. Compression Test Specimens: ASTM C 31/C 31M; cast and laboratory cure one set of three standard cylinder specimens for each composite sample.

and above, and one test for each composite sample.

6. Compressive-Strength Tests: ASTM C 39/C 39M; test one specimen at seven days and two specimens at 28 days.

a. A compressive-strength test shall be the average compressive strength from two specimens obtained from same composite sample and tested at 28 days.

C. Strength of each concrete mixture will be satisfactory if average of any three consecutive compressive-strength tests equals or exceeds specified compressive strength and no compressive-strength test value falls below specified compressive strength by more than 500 psi (3.4 MPa)

D. Test results shall be reported in writing to Architect, concrete manufacturer, and Contractor within 48 hours of testing. Reports of compressive-strength tests shall contain Project identification name and number, date of concrete placement, name of concrete testing and inspecting agency, location of concrete batch in Work, design compressive strength at 28 days, concrete mixture proportions and materials, compressive breaking strength, and type of break for both 7- and 28-day tests.

.

E. Nondestructive Testing: Impact hammer, sonoscope, or other nondestructive device may be permitted by Architect but will not be used as sole basis for approval or rejection of concrete.

F. Additional Tests: Testing and inspecting agency shall make additional tests of concrete when test results indicate that slump, air entrainment, compressive strengths, or other requirements have not been met, as directed by Architect.

G. Concrete paving will be considered defective if it does not pass tests and inspections.

H. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements.

3.11 REPAIRS AND PROTECTION

A. Remove and replace concrete paving that is broken, damaged, or defective or that does not comply with requirements in this Section. Remove work in complete sections from joint to joint unless otherwise approved by Architect.

B. Drill test cores, where directed by Architect, when necessary to determine magnitude of cracks or defective areas. Fill drilled core holes in satisfactory paving areas with portland cement concrete bonded to paving with epoxy adhesive.

C. Protect concrete paving from damage. Exclude traffic from paving for at least 14 days after placement. When construction traffic is permitted, maintain paving as clean as possible by removing surface stains and spillage of materials as they occur.

Page 30: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

CEMENT CONCRETE PAVEMENT 02751 - 12 Additions to Potomack Intermediate School

D. Maintain concrete paving free of stains, discoloration, dirt, and other foreign material. Sweep paving not more than two days before date scheduled for Substantial Completion inspections.

END OF SECTION 02751

Page 31: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

PAVEMENT JOINT SEALANTS 02764 - 1 Additions to Potomack Intermediate School

SECTION 02764 -

PART 1 - GENERAL

PAVEMENT JOINT SEALANTS

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Expansion and contraction joints within cement concrete pavement.

B. Related Sections include the following:

1. Division 2 Section "Cement Concrete Pavement" for constructing joints in concrete pavement.

2. Division 7 Section "Joint Sealants" for sealing nontraffic and traffic joints in locations not specified in this Section.

1.3 SUBMITTALS

A. Product Data: For each joint-sealant product indicated.

B. Compatibility and Adhesion Test Reports: From sealant manufacturer, indicating the following:

1. Materials forming joint substrates and joint-sealant backings have been tested for compatibility and adhesion with joint sealants.

2. Interpretation of test results and written recommendations for primers and substrate preparation needed for adhesion.

C. Product Test Reports: Based on evaluation of comprehensive tests performed by a qualified testing agency, for sealants.

1.4 QUALITY ASSURANCE

A. Installer Qualifications: An experienced installer who has specialized in installing joint sealants similar in material, design, and extent to those indicated for this Project and whose work has resulted in joint-sealant installations with a record of successful in-service performance.

B. Source Limitations: Obtain each type of joint sealant through one source from a single manufacturer.

C. Materials and applications are to comply with WVDOT specifications.

Page 32: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

PAVEMENT JOINT SEALANTS 02764 - 2 Additions to Potomack Intermediate School

1.5 DELIVERY, STORAGE, AND HANDLING

A. Deliver materials to Project site in original unopened containers or bundles with labels indicating manufacturer, product name and designation, color, expiration date, pot life, and curing time.

B. Store and handle materials to comply with manufacturer's written instructions to prevent their deterioration or damage due to moisture, high or low temperatures, contaminants, or other causes.

1.6 PROJECT CONDITIONS

A. Do not proceed with installation of joint sealants under the following conditions:

1. When ambient and substrate temperature conditions are outside limits permitted by joint-sealant manufacturer.

2. When joint substrates are wet or covered with frost. 3. Where joint widths are less than those allowed by joint-sealant manufacturer for

applications indicated. 4. Where contaminants capable of interfering with adhesion have not yet been removed

from joint substrates.

PART 2 - PRODUCTS

2.1 MATERIALS, GENERAL

A. Compatibility: Provide joint sealants, backing materials, and other related materials that are compatible with one another and with joint substrates under conditions of service and application, as demonstrated by joint-sealant manufacturer based on testing and field experience.

B. Colors of Exposed Joint Sealants: Grey or Limestone.

2.2 COLD-APPLIED JOINT SEALANTS

A. Type NS Silicone Sealant for Concrete: Single-component, low-modulus, neutral-curing, nonsag silicone sealant complying with ASTM D 5893 for Type NS.

1. Available Products: Subject to compliance with requirements, products that may be incorporated into the Work include, but are not limited to, products listed in other Part 2 articles. a. Crafco Inc.; RoadSaver Silicone. b. Dow Corning Corporation; 888. c. Tremco; Spectrem 800.

Page 33: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

PAVEMENT JOINT SEALANTS 02764 - 3 Additions to Potomack Intermediate School

2.3 JOINT-SEALANT BACKER MATERIALS

A. General: Provide joint-sealant backer materials that are nonstaining; are compatible with joint substrates, sealants, primers, and other joint fillers; and are approved for applications indicated by joint-sealant manufacturer based on field experience and laboratory testing.

B. Round Backer Rods for Cold-Applied Sealants: ASTM D 5249, Type 3, of diameter and density required to control sealant depth and prevent bottom-side adhesion of sealant.

2.4 PRIMERS

A. Primers: Product recommended by joint-sealant manufacturer where required for adhesion of sealant to joint substrates indicated.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine joints indicated to receive joint sealants, with Installer present, for compliance with requirements for joint configuration, installation tolerances, and other conditions affecting joint-sealant performance.

1. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with joint-sealant manufacturer's written instructions.

B. Joint Priming: Prime joint substrates where recommended in writing by joint-sealant manufacturer. Apply primer to comply with joint-sealant manufacturer's written instructions. Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining surfaces.

3.3 INSTALLATION OF JOINT SEALANTS

A. General: Comply with joint-sealant manufacturer's written installation instructions for products and applications indicated, unless more stringent requirements apply. Install products in accordance with WVDOT specifications.

B. Sealant Installation Standard: Comply with recommendations in ASTM C 1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.

C. Install backer materials of type indicated to support sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.

1. Do not leave gaps between ends of backer materials. 2. Do not stretch, twist, puncture, or tear backer materials.

Page 34: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

PAVEMENT JOINT SEALANTS 02764 - 4 Additions to Potomack Intermediate School

3. Remove absorbent backer materials that have become wet before sealant application and replace them with dry materials.

D. Install sealants using proven techniques that comply with the following and at the same time backings are installed:

1. Place sealants so they directly contact and fully wet joint substrates. 2. Completely fill recesses provided for each joint configuration. 3. Produce uniform, cross-sectional shapes and depths relative to joint widths that allow

optimum sealant movement capability.

E. Tooling of Nonsag Sealants: Immediately after sealant application and before skinning or curing begins, tool sealants according to requirements specified below to form smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion of sealant with sides of joint.

1. Remove excess sealants from surfaces adjacent to joint. 2. Use tooling agents that are approved in writing by joint-sealant manufacturer and that do

not discolor sealants or adjacent surfaces.

F. Provide joint configuration to comply with joint-sealant manufacturer's written instructions, unless otherwise indicated.

3.4 CLEANING

A. Clean off excess sealants or sealant smears adjacent to joints as the Work progresses by methods and with cleaning materials approved by manufacturers of joint sealants and of products in which joints occur.

3.5 PROTECTION

A. Protect joint sealants during and after curing period from contact with contaminating substances and from damage resulting from construction operations or other causes so sealants are without deterioration or damage at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, cut out and remove damaged or deteriorated joint sealants immediately and replace with joint sealant so installations with repaired areas are indistinguishable from the original work.

END OF SECTION 02764

Page 35: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

LAWNS AND GRASSES 02920 - 1 Additions to Potomack Intermediate School

SECTION 02920 -

PART 1 - GENERAL

LAWNS AND GRASSES

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Permanent Lawn Seeding 2. Temporary Lawn Seeding.

B. Related Sections:

1. Division 2 Section "Site Clearing" for topsoil stripping and stockpiling. 2. Division 2 Section "Earthwork" for excavation, filling and backfilling, and rough

grading.

1.3 DEFINITIONS

A. Duff Layer: The surface layer of native topsoil that is composed of mostly decayed leaves, twigs, and detritus.

B. Finish Grade: Elevation of finished surface of planting soil.

C. Manufactured Topsoil: Soil produced off-site by homogeneously blending mineral soils or sand with stabilized organic soil amendments to produce topsoil or planting soil.

D. Pesticide: A substance or mixture intended for preventing, destroying, repelling, or mitigating a pest. This includes insecticides, miticides, herbicides, fungicides, rodenticides, and molluscicides. It also includes substances or mixtures intended for use as a plant regulator, defoliant, or desiccant.

E. Pests: Living organisms that occur where they are not desired or that cause damage to plants, animals, or people. These include insects, mites, grubs, mollusks (snails and slugs), rodents (gophers, moles, and mice), unwanted plants (weeds), fungi, bacteria, and viruses.

F. Planting Soil: Standardized topsoil; existing, native surface topsoil; existing, in-place surface soil; imported topsoil; or manufactured topsoil that is modified with soil amendments and perhaps fertilizers to produce a soil mixture best for plant growth.

G. Subgrade: Surface or elevation of subsoil remaining after excavation is complete, or top surface of a fill or backfill before planting soil is placed.

Page 36: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

LAWNS AND GRASSES 02920 - 2 Additions to Potomack Intermediate School

H. Subsoil: All soil beneath the topsoil layer of the soil profile, and typified by the lack of organic matter and soil organisms.

I. Surface Soil: Soil that is present at the top layer of the existing soil profile at the Project site. In undisturbed areas, the surface soil is typically topsoil, but in disturbed areas such as urban environments, the surface soil can be subsoil.

1.4 SUBMITTALS

A. Product Data: For each type of product indicated.

1. Pesticides and Herbicides: Include product label and manufacturer's application instructions specific to this Project.

B. Certification of Grass Seed: From seed vendor for each grass-seed monostand or mixture stating the botanical and common name, percentage by weight of each species and variety, and percentage of purity, germination, and weed seed. Include the year of production and date of packaging.

C. Qualification Data: For qualified landscape Installer, if requested.

D. Product Certificates: For soil amendments and fertilizers, from manufacturer.

E. Planting Schedule: Indicate anticipated planting dates for each type of planting.

F. Maintenance Instructions: Recommended procedures to be established by Owner for maintenance of lawns during a calendar year. Submit before expiration of required initial maintenance periods.

1.5 QUALITY ASSURANCE

A. Installer Qualifications: A qualified landscape Installer whose work has resulted in successful lawn establishment. 1. Installer's Field Supervision: Require Installer to maintain an experienced full-time

supervisor on Project site when work is in progress.

B. Soil-Testing Laboratory Qualifications: An independent laboratory or university laboratory, recognized by the State Department of Agriculture, with the experience and capability to conduct the testing indicated and that specializes in types of tests to be performed.

C. Topsoil Analysis: For each unamended soil type, furnish soil analysis and a written report by a qualified soil-testing laboratory stating percentages of organic matter; gradation of sand, silt, and clay content; cation exchange capacity; deleterious material; pH; and mineral and plant-nutrient content of the soil.

1. Testing methods and written recommendations shall comply with USDA's Handbook No. 60.

2. Report suitability of tested soil for turf growth.

Page 37: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

LAWNS AND GRASSES 02920 - 3 Additions to Potomack Intermediate School

a. Based on the test results, state recommendations for soil treatments and soil amendments to be incorporated. State recommendations in weight per 1000 sq. ft. or volume per cu. yd.

b. Report presence of problem salts, minerals, or heavy metals, including aluminum, arsenic, barium, cadmium, chromium, cobalt, lead, lithium, and vanadium. If such problem materials are present, provide additional recommendations for corrective action.

for nitrogen, phosphorus, and potash nutrients and soil amendments to be added to produce satisfactory planting soil suitable for healthy, viable plants.

D. Preinstallation Conference: Conduct conference at Project site.

1.6 DELIVERY, STORAGE, AND HANDLING

A. Seed and Other Packaged Materials: Deliver packaged materials in original, unopened containers showing weight, certified analysis, name and address of manufacturer, and indication of conformance with state and federal laws, as applicable.

1.7 PROJECT CONDITIONS

A. Weather Limitations: Proceed with planting only when existing and forecasted weather conditions permit planting to be performed when beneficial and optimum results may be obtained. Apply products during favorable weather conditions according to manufacturer's written instructions.

PART 2 - PRODUCTS

2.1 SEED

A. Grass Seed: Fresh, clean, dry, new-crop seed complying with AOSA's "Journal of Seed Technology; Rules for Testing Seeds" for purity and germination tolerances.

B. Seed Species: Seed of grass species as follows, with not less than 85 percent germination, not less than 85 percent pure seed, and not more than 0.5 percent weed seed: 1. Permanent Lawn Turf type blend: Proportioned by weight as follows:

a. 75 percent Lawn Turf type tall/drought resistant fescue. b. 20 percent Lawn Turf type/drought resistant Kentucky bluegrass c. 5 percent perennial ryegrass.

2. Temporary Seed Mix: Proportioned by weight as follows: a. Spring and Fall: 100 percent Annual Ryegrass – 1 lb per 1,000 sf. b. Summer: 85 percent German Millet, 15 percent Annual Ryegrass – 1 lb per 1,000

sf. c. Winter: 50 percent Wheat, 50 percent rye – 4 lb per 1,000 sf.

2.2 TOPSOIL

Page 38: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

LAWNS AND GRASSES 02920 - 4 Additions to Potomack Intermediate School

A. Topsoil: ASTM D 5268, pH range of 5.5 to 7, a minimum of 4 percent organic material content; free of stones ½ inch

1. Topsoil Source: Reuse surface soil stockpiled on-site. Verify suitability of stockpiled surface soil to produce topsoil. Clean surface soil of roots, plants, sod, stones, clay lumps, and other extraneous materials harmful to plant growth.

or larger in any dimension and other extraneous materials harmful to plant growth.

a. Supplement with imported or manufactured topsoil from off-site sources when quantities are insufficient. Obtain topsoil displaced from naturally well-drained construction or mining sites where topsoil occurs at least 4 inches

2.3 INORGANIC SOIL AMENDMENTS

deep; do not obtain from agricultural land, bogs or marshes.

A. Lime: ASTM C 602, agricultural liming material containing a minimum of 80 percent calcium carbonate equivalent and applied at a rate of 150 lbs. per 1,000 sf.

B. Sulfur: Granular, biodegradable, containing a minimum of 90 percent sulfur, and with a minimum of 99 percent passing through No. 6 sieve and a maximum of 10 percent passing through No. 40

C. Iron Sulfate: Granulated ferrous sulfate containing a minimum of 20 percent iron and 10 percent sulfur.

sieve.

D. Aluminum Sulfate: Commercial grade, unadulterated.

E. Perlite: Horticultural perlite, soil amendment grade.

F. Agricultural Gypsum: Minimum 90 percent calcium sulfate, finely ground with 90 percent passing through No. 50

G. Sand: Clean, washed, natural or manufactured, and free of toxic materials.

sieve.

H. Diatomaceous Earth: Calcined, 90 percent silica, with approximately 140 percent water absorption capacity by weight.

I. Zeolites: Mineral clinoptilolite with at least 60 percent water absorption by weight.

2.4 FERTILIZERS

A. Commercial Fertilizer: Commercial-grade complete fertilizer of neutral character, consisting of fast- and slow-release nitrogen, 50 percent derived from natural organic sources of urea formaldehyde, phosphorous, and potassium in the following composition:

1. Composition: 10 percent nitrogen, 20 percent phosphorous, and 10 percent potassium, by weight applied at a rate of 12 lbs. per 1,000 sf.

Page 39: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

LAWNS AND GRASSES 02920 - 5 Additions to Potomack Intermediate School

2.5 MULCHES

A. Straw Mulch: Provide air-dry, clean, mildew- and seed-free, salt hay or threshed straw of wheat, rye, oats, or barley.

2.6 PESTICIDES AND HERBICIDES

A. General: Pesticide, registered and approved by EPA, acceptable to authorities having jurisdiction, and of type recommended by manufacturer for each specific problem and as required for Project conditions and application. Do not use restricted pesticides unless authorized in writing by authorities having jurisdiction.

B. Pre-Emergent Herbicide (Selective and Non-Selective): Effective for controlling the germination or growth of weeds within planted areas at the soil level directly below the mulch layer.

C. Post-Emergent Herbicide (Selective and Non-Selective): Effective for controlling weed growth that has already germinated.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine areas to be planted for compliance with requirements and other conditions affecting performance.

1. Verify that no foreign or deleterious material or liquid such as paint, paint washout, concrete slurry, concrete layers or chunks, cement, plaster, oils, gasoline, diesel fuel, paint thinner, turpentine, tar, roofing compound, or acid has been deposited in soil within a planting area.

2. Do not mix or place soils and soil amendments in frozen, wet, or muddy conditions. 3. Suspend soil spreading, grading, and tilling operations during periods of excessive soil

moisture until the moisture content reaches acceptable levels to attain the required results. 4. Uniformly moisten excessively dry soil that is not workable and which is too dusty.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

C. If contamination by foreign or deleterious material or liquid is present in soil within a planting area, remove the soil and contamination as directed by Architect and replace with new planting soil.

3.2 PREPARATION

A. Install erosion-control measures to prevent erosion or displacement of soils and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways.

Page 40: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

LAWNS AND GRASSES 02920 - 6 Additions to Potomack Intermediate School

3.3 LAWN AREA PREPARATION

A. Limit lawn subgrade preparation to areas to be planted.

B. Newly Graded Subgrades: Loosen subgrade to a minimum depth of 8 inches. Remove stones larger than 1 inch

1. Apply fertilizer directly to subgrade before loosening.

in any dimension and sticks, roots, rubbish, and other extraneous matter and legally dispose of them off Owner's property.

2. Thoroughly blend planting soil off-site before spreading or spread topsoil, apply soil amendments and fertilizer on surface, and thoroughly blend planting soil. a. Delay mixing fertilizer with planting soil if planting will not proceed within a few

days. b. Mix lime with dry soil before mixing fertilizer.

C. Unchanged Subgrades: If turf is to be planted in areas unaltered or undisturbed by excavating, grading, or surface-soil stripping operations, prepare surface soil as follows:

1. Apply fertilizer directly to surface soil before seeding. 2. Remove stones larger than 1 inch

3. Drill seed or slit seed to minimize disturbance to existing turf.

in any dimension and sticks, roots, trash, and other extraneous matter.

4. Legally dispose of waste material, including grass, vegetation, and turf, off Owner's property.

D. Finish Grading: Grade planting areas to a smooth, uniform surface plane with loose, uniformly fine texture. Grade to within plus or minus 1/2 inch

E. Moisten prepared area before planting if soil is dry. Water thoroughly and allow surface to dry before planting. Do not create muddy soil.

of finish elevation. Roll and rake, remove ridges, and fill depressions to meet finish grades. Limit finish grading to areas that can be planted in the immediate future.

F. Before planting, obtain Architect's acceptance of finish grading; restore planting areas if eroded or otherwise disturbed after finish grading.

3.4 SEEDING

A. Sow seed with spreader or seeding machine. Do not broadcast or drop seed when wind velocity exceeds 5 mph

1. Do not use wet seed or seed that is moldy or otherwise damaged.

. Evenly distribute seed by sowing equal quantities in two directions at right angles to each other.

2. Do not hydroseed.

B. Sow seed at a total rate of 5 to 8 lb/1000 sq. ft.

C. Rake seed lightly into top

.

1/8 inch of soil, roll lightly, and water with fine spray.

Page 41: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

LAWNS AND GRASSES 02920 - 7 Additions to Potomack Intermediate School

D. Protect seeded areas by spreading straw mulch. Spread uniformly at a minimum rate of 2 tons/acre to form a continuous blanket 1-1/2 inches

3.5 HYDROSEEDING

in loose thickness over seeded areas. Spread by hand, blower, or other suitable equipment.

A. Hydroseeding is not permitted.

3.6 LAWN MAINTENANCE

A. Begin maintenance immediately after each area is planted and continue until acceptable lawn is established, but for not less than the following periods: 1. Seeded Lawns: Maintain up to the date of Substantial Completion.

a. Lawns must be fully established at the date of Substantial Completion.

B. Maintain and establish lawn by watering, fertilizing, weeding, mowing, trimming, replanting, and other operations. Roll, regrade, and replant bare or eroded areas and remulch to produce a uniformly smooth lawn. 1. In areas where mulch has been disturbed by wind or maintenance operations, add new

mulch. Anchor as required to prevent displacement.

C. Watering: Provide and maintain temporary piping, hoses, and lawn-watering equipment to convey water from sources and to keep lawn uniformly moist to a depth of 4 inches1. Schedule watering to prevent wilting, puddling, erosion, and displacement of seed or

mulch. Lay out temporary watering system to avoid walking over muddy or newly planted areas.

.

2. Water lawn at a minimum rate of 1 inch

D. Mow lawn as soon as top growth is tall enough to cut. Repeat mowing to maintain specified height without cutting more than 33 percent of grass height. Remove no more than 33 percent of grass-leaf growth in initial or subsequent mowings. Do not delay mowing until grass blades bend over and become matted. Do not mow when grass is wet. Schedule initial and subsequent mowings to maintain the following grass height:

per week.

1. Mow grass 2 to 3 inches

E. Failure to mow and maintain grass at specified mowing height will be considered non-performance of contract and will administered accordingly.

high.

F. Lawn Postfertilization: Apply fertilizer after initial mowing and when grass is dry. 1. Use fertilizer that will provide actual nitrogen of at least 1 lb/1000 sq. ft.

3.7 SATISFACTORY LAWNS

to lawn area.

A. Turf installations shall meet the following criteria as determined by Architect:

1. Satisfactory Seeded Lawn: At end of maintenance period, a healthy, uniform, close stand of grass has been established, free of weeds and surface irregularities, with coverage

Page 42: SECTION SITE CLEARING PART 1 - GENERAL...Miss Utility of West Virginia: Call 1-800-245-4848. D. Do not commence site clearing operations until temporary erosion and sedimentation control

LAWNS AND GRASSES 02920 - 8 Additions to Potomack Intermediate School

exceeding 90 percent over any 10 sq. ft.

B. Use specified materials to reestablish lawns that does not comply with requirements and continue maintenance until lawns are satisfactory.

and bare spots not exceeding 3 inches by 3 inches.

3.8 PESTICIDE APPLICATION

A. Apply pesticides and other chemical products and biological control agents in accordance with requirements of authorities having jurisdiction and manufacturer's written recommendations. Coordinate applications with Owner's operations and others in proximity to the Work. Notify Owner before each application is performed.

B. Post-Emergent Herbicides (Selective and Non-Selective): Apply only as necessary to treat already-germinated weeds and in accordance with manufacturer's written recommendations.

3.9 CLEANUP AND PROTECTION

A. Promptly remove soil and debris created by turf work from paved areas. Clean wheels of vehicles before leaving site to avoid tracking soil onto roads, walks, or other paved areas.

B. Erect temporary fencing or barricades and warning signs as required to protect newly planted areas from traffic. Maintain fencing and barricades throughout initial maintenance period and remove after plantings are established.

END OF SECTION 02920