Section 53 V Audit - Landfill Operation
Transcript of Section 53 V Audit - Landfill Operation
Section 53 V Audit - Landfill Operation
Portland Landfill - 210 Cape Nelson Road,
Portland
Service Order No. 8004905
Glenelg Shire Council
May 2016
184-01
Nolan Consulting Pty Ltd
May 2016
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Table of Contents
Executive Summary ................................................................................... i
1. Introduction ................................................................................... 11
1.1 Requirement for audit of landfill operation .....................................11 1.2 Auditor ....................................................................................................11 1.3 Compliance with audit requirements ..............................................11 1.4 Definitions ...............................................................................................11 1.5 Location of audit findings ...................................................................11
2. Audit scope and method ............................................................. 13
2.1 Scope ......................................................................................................13 2.2 Audit objective .....................................................................................13 2.3 Audit scope ...........................................................................................13 2.4 Audit tasks ..............................................................................................14 2.5 Reference documents ........................................................................15
3. Landfill development and operations ......................................... 16
3.1 Location and area ...............................................................................16 3.2 Ownership ..............................................................................................16 3.3 Land use .................................................................................................16 3.4 Landfill staging and key design features .........................................17 3.5 Landfill life...............................................................................................20 3.6 Facility operator ....................................................................................20 3.7 Human resources ..................................................................................20 3.8 Landfill operations ................................................................................21 3.9 Complaints and regulatory performance .......................................26
4. Implementation of progressive rehabilitation ............................ 28
4.1 Existing capping ....................................................................................28 4.2 Rehabilitation Plan ...............................................................................28 4.3 Scheduling .............................................................................................29 4.4 Finished surface level ...........................................................................29 4.5 Design progress .....................................................................................29 4.6 Stormwater drainage ..........................................................................30 4.7 Landfill gas management ..................................................................31 4.8 Conclusion .............................................................................................32
5. Conceptual site model ................................................................. 33
5.1 Climate ...................................................................................................33 5.2 Topography ...........................................................................................33 5.3 Soils ..........................................................................................................33 5.4 Hydrogeology .......................................................................................33 5.5 Surface water ........................................................................................40 5.6 Cultural heritage sites ..........................................................................40 5.7 Vegetation .............................................................................................40
May 2016
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
5.8 Landfill gas .............................................................................................40 5.9 Sources, pathways and receptors ....................................................41
6. Risk of landfill operations .............................................................. 45
6.1 Beneficial uses .......................................................................................45 6.2 Risk assessment method ......................................................................51 6.3 Updated landfill register ......................................................................54 6.4 Compliance risk register ......................................................................54
7. Assessment of monitoring program implementation ................. 63
7.1 The verified program ...........................................................................63 7.2 Assessment of implementation ..........................................................64 7.3 Annual reporting ...................................................................................71
8. Interpretation of monitoring results .............................................. 72
8.1 Scope ......................................................................................................72 8.2 Leachate levels ....................................................................................72 8.3 Groundwater flow direction ...............................................................72 8.4 Water quality .........................................................................................73 8.5 LFG monitoring ......................................................................................78
9. Progress with previous Auditor's recommendations .................. 82
10. Update and reverification of monitoring program ..................... 85
10.1 Updated program ................................................................................85 10.2 Environmental audit program ............................................................96 10.3 Reverification ........................................................................................96
11. Conclusions ................................................................................... 97
12. Recommendations ......................................................................102
13. Applicability .................................................................................105
14. References....................................................................................106
15. List of abbreviations and units .....................................................109
List of Figures (after Cardno; 2015b)
1. Site Locality Plan
2. Landfill Development Sequence
3. Bore Location Plan
4. Landfill Gas Bore Location Plan
5. Leachate Collection System
6. Regional Geology
7. Geological Cross-Section A-A’
8. Geological Cross-Section B-B’
9. Groundwater Elevation (April 2015)
May 2016
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
10. Groundwater Hydrographs
11. Groundwater Database Search Results
12. Groundwater Salinity (April 2015)
13. Groundwater Ammonia Concentration (April 2015)
Appendices
A EPA Licence 22492
B Photographs (March 2016)
C Nolan Consulting (2014) “Section 53V Audit – Landfill Operation, Portland Landfill –
210 Cape Nelson Road Portland”
D Cardno (2015b) “Hydrogeological Assessment for Leachate Level Management -
Portland Landfill 210 Cape Nelson Road, Portland, Vic.”
E GHD (2015b) “Portland Landfill Annual Environmental Monitoring Results Report
2014/15”
F Portland Landfill Risk Assessment Register (updated May 2016)
G Portland Landfill Compliance Risk Register (updated May 2016)
May 2016
Page i
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Executive Summary
The Glenelg Shire Council operates a landfill located at 210 Cape Nelson Road, 3 km south-
south-west of the Portland town centre. The landfill, known as the Portland Landfill, is licensed
to operate under the Environment Protection Authority licence 22492 (formerly HS776) as
amended on 30th June 2014.
The licence requires that an Environmental Auditor appointed pursuant to the Environment
Protection Act 1970 must conduct environmental audits at the frequency specified in the
verified Monitoring Program. The verified Monitoring Program was updated and re-verified in
November 2014 by John Nolan (Nolan Consulting; 2014) as the appointed Environmental
Auditor.
The re-verified Monitoring Program specified that next audit of landfill operation be undertaken
for the period from 1st July 2014 to 31st December 2015. The scope of the audit is described in
Appendix 6 of the EPA (2011b) Landfill Licensing Guidelines, Publication 1323.2.
Audit objective
The objective of the audit is to identify and, where possible, quantify the risk of any possible
harm or detriment to a segment of the environment caused by the landfill operation.
Background
The audit report has been prepared in accordance with:
Section 53V of the Environment Protection Act 1970 which sets out requirements that must
be met when an Environmental Auditor prepares an environmental audit report in
relation to the risk of any possible harm or detriment to a segment of the environment
caused by any industrial process or activity, waste, substance or noise;
Appendix 6 of the EPA Landfill Licensing Guidelines;
EPA Environmental Auditor Guidelines for the Preparation of Environmental Audit Reports
on Risk to the Environment; and
Condition L1_L2 of the EPA Licence 22492 (as amended on 30th June 2014).
In undertaking the audit, the Auditor has had regard to, among other things, the:
relevant State Environment Protection Policies;
verified Environmental Monitoring Program (Nolan Consulting; 2014);
Portland Landfill monitoring reports for the audit period of 1st July 2014 to 31st December
2015; and
the beneficial uses of the premises and surrounding land.
Audit details and audit site
Details of the audit and audit site are presented in Tables E1 and E2.
May 2016
Page ii
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Table E1: Audit report summary
Item Description
EPA file reference no. 67141-5 (CARMS No.)
8004905 (Service Order No.)
Auditor John Nolan
Auditor term of appointment 08/02/2014 to 07/02/2019
Name of person requesting audit David Hol
Relationship to premises/location Project Planning and Facilities Manager
Glenelg Shire Council
Date of request 9th October 2015
Date EPA notified of audit 31st December 2015
Completion date of the audit 26th May 2016
Reason for audit EPA Licence 22492, Condition L1_L2
Description of activity Operation of Portland Landfill
EPA region South West Region
Dominant – Lot on plan Lot 1 on Title Plan 120803
Crown Allotment 3G, Section 13 of Plan 3414
Additional – Lot on plan Crown Allotment 60M, Section D of Plan 5651
Site/premises name Portland Landfill
Building/complex sub-unit No.
Street / Lot – Lower No. 210
Street / Lot – Upper No.
Street Name Cape Nelson
Street type (road, court, etc.) Road
Street Suffix – (North, South, etc.)
Suburb Portland
Postcode 3350
GIS coordinates of centroid
-38.37059167
141.5834472
Latitude (GDA94)
Longitude (GDA94)
Members and categories of support
team utilised
Nil
Outcome of the audit Audit report with recommendations
Further work or requirements Recommendations as set out in Section 12 of this audit report and
in the Executive Summary
May 2016
Page iii
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Table E2: Physical Site information
Item Description
Groundwater segment Segment A2
Surrounding land use North: Yarraman Park, public open space, scrubland, open
grassed paddocks.
East: Cemetery, open grassed paddocks beyond cemetery.
South: Open grassed paddocks with two residences.
West: Open grassed paddocks, scrubland and one residence.
Audit findings
Risk of landfill operations to beneficial uses identified by the environmental Auditor
1. The Nolan Consulting (2014) risk assessment, including the risk registers, has been
reviewed. The risk register has been updated as part of the audit. No changes to the risk
profile have been required.
2. The following are considered to be very high risks:
groundwater contamination by leachate:
from active cell (on site);
from active cell (off site);
via unsaturated zone (on site); and
via unsaturated zone (off site).
3. The following are considered to be high risks:
LFG migration via unsaturated zone (on-site);
groundwater contamination by leachate from active waste cell impacting on
down gradient groundwater users; and
asphyxiation resulting in death or serious injury of site workers caused by a LFG
explosion via unsaturated zone migration.
4. The following are considered to be medium risks:
corrosion of on-site transmission towers via leachate through the unsaturated zone;
and
litter from active waste cell on the health of flora & fauna and visual amenity;
windblown and traffic generated litter from active waste cell on amenity of on-site
workers;
windblown dust from site activities and traffic on amenity of on-site workers;
windblown dust from site activities on health of on-site workers and humans at
nearby residences and Yarraman Park;
traffic generated on health of on-site workers;
odour from leachate storage dam on amenity of workers;
toxic gases (H2S) on health of maintenance workers;
noise from machinery, equipment, and traffic on amenity of workers;
May 2016
Page iv
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
leachate, via runoff and/or groundwater pathways, on surface water beneficial
uses;
contamination of land by overfilling of leachate storage dam;
on-site groundwater caused by increased level in leachate storage dam
increasing infiltration through unsaturated zone;
vermin from active waste cell on amenity of on-site building occupants and
humans at and in the vicinity of the landfill;
damage to flora due to fire at active waste cell;
poor weed management within the site on amenity and local flora; and
erosion from capped landfill on on-site flora and fauna.
5. The beneficial uses adopted for the atmosphere at the premises, groundwater beneath
the premises, any surface water on the premises and the environment surrounding the
premises are appropriate.
6. The environmental aspects adopted in the updated risk register are comprehensive and
appropriate.
Assessment of implementation of the Monitoring Program
7. The previously verified Monitoring Program (Nolan Consulting; 2014) was structured as
specific sub-programs for individual environmental elements.
8. There are two generic categories of monitoring within the verified environmental
programs. These are Category A for regular or incident driven inspections by trained GSC
staff and Category B for groundwater, leachate, and LFG sampling and testing based
programs.
9. The Category A monitoring activity is observation (visual and olfactory) by trained GSC
staff. The verified Monitoring Program requires evidence of the observations to be
reported.
10. Implementation of the Category A monitoring is progressing. Further improvements are
required in staff training, systematic monitoring and reporting.
11. The Environmental Monitoring contract includes most Category B monitoring
requirements presented in the verified Environmental Monitoring program.
12. The Category B groundwater and leachate monitoring sub-program was implemented
in accordance with the verified monitoring program except for:
a level data logger has not been installed in LIS bore IB5;
new groundwater bores PO34A, PO34B, PO35A and PO35B and new leachate
monitoring bores LB01R and LB02RA are yet to be not surveyed;
flow meter on LIS discharge line has failed;
pulse counters (for flow) and data loggers (for level) installed but are yet to be
reported;
chain of custody forms do not to identify sample containers;
trip blank sample not obtained during the VOC sampling; and
completed groundwater bore purging and sampling records do not report on bore
condition.
May 2016
Page v
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
13. The LFG monitoring sub-program was implemented in accordance with the verified
monitoring program except for:
monitoring records of pits and other enclosed spaces did not include location
details, evidence of corrosion, and presence of odours;
LFG monitoring in building records do not include location details (e.g. monitor
positions, building conditions, and presence of odours);
monitoring for signs of corrosion at the bore network is not undertaken, and
reporting of corrosion monitoring results needs to be documented ;
LFG surface monitoring is limited to a few (nine) locations on Area A and B and
does not include Area A and B vegetated areas and sections of Area C which has
not been filled within any three month period.
plant health at and within 50 m of the landfill while monitored is not fully reported.
14. LFG monitoring data is not incorporated into the integrated monitoring database.
15. The annual monitoring report requires a declaration that the monitoring program was
completely in accordance with the verified monitoring program and explains any non-
conformances, including names of persons responsible for each component of the
monitoring program.
Interpretation of monitoring results - groundwater
16. The background groundwater is within Segment A2 (less than 1,000 mg/L).
17. The groundwater salinity immediately down-gradient of Areas A and B is close to the
leachate salinity, and the salinity down-gradient of Area C that is elevated above
background but less than the leachate salinity. The salinity plume extends to the north-
east (including to the east of Cape Nelson Road).
18. The background groundwater ammonia concentration is less than 100 µg/L.
19. Elevated ammonia contamination of the groundwater, at concentrations of 5 mg/L and
above, occur immediately down-gradient of Area A and to the east of the landfill site.
There are moderate levels of ammonia contamination immediately down-gradient of
Area C, immediately down-gradient of Area A/B, to the east of Cape Nelson Road, and
north-west of Yarraman Park.
20. The elevated TDS and ammonia concentrations are associated with landfill leachate.
21. Evidence of nitrate concentration above the ANZECC (2000) Ecosystem Freshwater 95th
percentile guideline values are inconsistent and do not reflect the salinity and ammonia
contamination plume.
22. Volatile fatty acids are indicators of leachate contamination. Concentrations of 20 mg/L
or above were only found in April 2015 at PO32A (300 m north-east of the site entrance).
23. The average Mulvey L/N ratios at the leachate monitoring bore L/N ratio is 161. The only
groundwater bores with ratios above 10 that may be indicative of a leachate impact
are at PO18R (along eastern boundary), PO08R (between IB6 and IB7), PO32 (300 m
north-east of the site entrance), PO03 (along western boundary), and PO01 (south-side
of Derril Road).
May 2016
Page vi
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
24. There is negligible evidence of volatile organic and semi-volatile organic compounds in
the groundwater. There were no exceedances of the ANZECC (2000) Ecosystem
Freshwater 95th percentile trigger value and the Australian Drinking Water Guidelines
health guideline values for these compounds except for benzene at PO07 and LIS bores
IB4 and IB8 which marginally exceed the AWDG health guideline value of 1 µg/L.
25. The leachate plume extends at least 400 m to the north-east of Derril Road and possibly
550 m to Madeira-Packet Road as well as to the east of Cape Nelson Road.
26. This 2016 Audit of Landfill Operation has found that the October 2015 plume extent has
stabilised since June 2014 with reductions in ammonia concentrations within the main
leachate plume,
Interpretation of monitoring results – landfill gas
27. All boundary LFG probes recorded methane at concentrations below the BPEM
boundary action level of 1% v/v at all monitoring events except for LFG23 at one
monitoring event when 1.0% was recorded.
28. Of the perimeter bores LFG monitoring bores LFG02, LFG07, LFG23 and LFG24 have with
CO2 concentrations that are consistently over 1%v/v above background. These are
located along the eastern boundary except for LFG07 which is located in the south-west
corner.
29. Isolated CO2 concentrations of greater than 1%v/v above background have occurred
at monitoring bores LFG03, LFG06, LFG11, LFG12, LFG15, LFG19, and LFG22.
30. All CO2 concentrations are less than 10 % v/v above background except for LFG02 which
is up to 14.2 % v/v above background concentration.
31. The maximum gas screening value (GSV) for CO2 is 0.044 L/hr which based upon CIRIA
(2007) represents a very low risk.
32. The CO2 concentrations at joint LFG probe/EPA (2015a) Landfill BPEM compliant bores
sites for LFG08/8A, LFG10/10A, LFG18/18A and LFG20/20A are consistent between bores
and probes. The key exceptions are for LFG10/10A, and LFG20/20A in the August 2015
monitoring event. In both occasions the probes recorded 0.1% v/v and the bores
recorded 1.0% v/v to 1.1% v/v. As the results are inconclusive ongoing monitoring of the
probes and bores up to the end of 2015/16 year is recommended.
33. While the reported CO2 exceedances of the EPA (2015a) Landfill BPEM action level are
relatively minor, and are unlikely to be landfill sourced, the potential for subsurface
migration of CO2 from the landfill cannot be excluded.
34. Monitoring of the Area A and Area B landfill surface has found methane concentrations
above the 200 ppm action level at several locations. These are generally in areas with
poor vegetation development.
35. While the recapping of the majority of Area A and B should reduce methane
concentration at the surface to below the final cap action level of 100 ppm there is a risk
of lateral migration within the lower lying areas which will not be recapped due to the
presence of native vegetation.
36. The methane concentrations within all building, structures and subsurface services were
well below the EPA (2015a) Landfill BPEM action levels, except for one instantaneous
methane concentrations of 22.0 ppm found outside the stormwater drain at Cape Nelson
Road near the cemetery gate. This is well below the EPA (2015a) Landfill BPEM action
level of 5,000 ppm.
May 2016
Page vii
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
37. There are no obvious LFG trends based upon the limited set of historical records.
Updated Monitoring Program
38. The Monitoring Program (Nolan Consulting; 2014) has been updated as part of this Audit
of Landfill Operation to reflect the revised CSM, the updated risk assessment, the
verification auditor’s comment’s, the Monitoring Program assessment, and progress with
implementing the 2014 Audit of Landfill Operation recommendations.
39. The updated Monitoring Program includes the following elements:
roles and responsibilities;
Category A monitoring (visual and olfactory);
Category B monitoring (groundwater);
Category B monitoring (LFG);
reporting; and
contractor requirements.
40. In general the updates are of a minor nature. The key changes are the inclusion of one
additional groundwater monitoring bore, two additional leachate monitoring bores,
and the expansion of the methane landfill surface monitoring program.
41. The updated Monitoring Program is verified as meeting the EPA (2011b) Landfill Licensing
Guidelines requirements and being adequate for GSC and the EPA to determine
compliance with the licence.
Implementation of progressive rehabilitation
42. GSC has scheduled the landfill to close following the commissioning of the transfer
station. This is expected to occur in mid-2016.
43. The Rehabilitation Plan has been approved by the EPA. This includes the top of waste
Pre-settlement Contour Plan.
44. The Technical Specification and Construction Quality Assurance Plan for Phase 1
Capping (Stages 1 and 2 cap) have been completed.
45. Phase 1 capping is expected to occur in the 2016/17 financial year. The delay from that
scheduled in the Rehabilitation Plan is due to the need to address native vegetation
management issues as required under the Environment Protection and Biodiversity
Conservation Act 1999 and to consider alternative capping design options.
Audit Recommendations
The recommendations of this environmental audit, incorporating those outstanding from the
2014 Audit of Landfill Operation, are presented in Table E3 below.
May 2016
Page viii
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Table E3: Audit of Portland Landfill operation – Recommendations
No Recommendation Risk
rating
Recommended
completion date
Monitoring program
1 Implement updated Monitoring Program including: High Ongoing
a) Install, survey, and monitor additional leachate monitoring
bores.
Centre of Area A (to base of waste); and
Centre of Area B (to base of waste).
High Aug 2016
b) Install, survey and monitor one additional groundwater
monitoring bore in the vegetated area between Area C and
the northern site boundary.
High Aug 2016
c) Install a level data logger in LIS bore IB5. High Aug 2016
d) Install temporary weather station at site to monitor rainfall and
evaporation.
Med Nov 2016
e) Survey new groundwater bores PO34A, PO34B, PO35A and
PO35B, new leachate monitoring bores LB01R and LB02RA, and
the above proposed bores to AHD and location.
Low Dec 2016
f) Maintain the flow meter on the LIS discharge line. High Ongoing
g) Ensure chain of custody forms identify sample containers. Low Ongoing
h) Ensure trip blank sample are obtained during the VOC sampling. Low Ongoing
i) Ensure groundwater bore purging and sampling records report
on bore condition. Low Ongoing
j) Undertake methane monitoring of the capped and
intermediate landfill surface, which was not been filled within the
preceding three month period. at a 25 m grid. This should include
the vegetated area of Area A and Area B.
Med First monitoring
event following
Phase 1 capping
k) Identify the location of new service pits associated with the
transfer station and ancillary facilities. High Upon
commissioning
l) Revise building, structures and service pit LFG monitoring points
to accommodate the new transfer station and ancillary facilities High Upon
commissioning
m) Provide a more comprehensive report of plant health at specific
locations on the cap and within 50 m of the landfill. Low Next audit
2 Provide all weather 4x4 vehicle access to within 5 m of all bores for
all conditions except flooding events.
Low First monitoring
event following
Phase 1
capping.
3 Establish an integrated database to hold and enable efficient
reporting of all monitoring records and data from 1989, preferably
in ESDAT format in accordance with the prepared service
specification.
Low Next audit
Hydrogeology
4 Resolve with the EPA the potential for using the Groundwater
Quality Restricted Use Zone (GQRUZ) under SEPP Groundwaters of
Victoria as a mechanism to manage this risk.
Low Next audit
May 2016
Page ix
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
No Recommendation Risk
rating
Recommended
completion date
Conceptual model
5 Undertake a comprehensive analysis of MSA and BFA aquifers
groundwater quality analysis that identifies discrete characteristics.
This should include using Stiff and Piper diagrams and Mulvey L/N
ratios.
Mediu
m
Mar 2017
Leachate interception system (LIS)
6 Operate the LIS in accordance with the Cardno (2015b)
“Hydrogeological Assessment for Leachate Level Management -
Portland Landfill 210 Cape Nelson Road, Portland, Vic.”
High Jul 2016
7 Monitor the LIS in accordance with the verified Monitoring Program
(Table 10-2 of this report). This includes reporting of level, flow rate,
and condition at individual LIS bores, leachate level at leachate
storage dam, flow to leachate storage dam and leachate storage
dam water balance.
High Jul 2016
8 Review the LIS monitoring data every six months to determine the
effectiveness of operation whether the leachate bore level, LIS
flow, groundwater level, and groundwater chemistry triggers are
not exceeded as described in Cardno (2015b) “Hydrogeological
Assessment for Leachate Level Management - Portland Landfill 210
Cape Nelson Road, Portland, Vic”..
High Ongoing
9 Implement an Operation & Maintenance manual and program to
provide for system monitoring and optimisation.
Med Sep 2016
Infrastructure
10 Confirm with AusNet Services that they have responsibility for
monitoring structural integrity of the HV transmission line towers
(including corrosion).
Low Next audit
LFG Risk Management
11 Review monitoring results from the LFG monitoring probe/bores
monitoring sites, to determine if any changes to the risk profile are
required.
Med Jul 2016
12 Check that the GSC restriction on residential development within
500 m of the site prevents any future residential development,
particularly of buildings with unvented basements.
Med Nov 2016
13 Review the need for LFG control in Areas A and B, particularly
around the eastern part of the site, within a thin corridor along the
southern fringe and the adjoining Malings Road reserve where the
existing cap will not be remediated.
Med First monitoring
event following
Phase 1
capping.
Planning
14 Investigate and implement a mechanism to control proposed
developments within 500 m from the landfill. This would involve a
trigger to identify planning permit applications for such
developments and a process to identify and mitigate risk such as
through an Environmental Significance Overlay or an
Environmental Audit Overlay.
Low Next audit
15 Complete Aftercare Management Plan in accordance with the
Post Closure Supporting PAN.
Med In accordance
with PAN
requirements.
May 2016
Page x
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
No Recommendation Risk
rating
Recommended
completion date
Operational
16 Ensure the stormwater drainage system for the Phase 2 cap is
designed for the whole site and includes adequate stormwater
sedimentation pondage(s) to allow capture and treatment of
stormwater prior to discharge from the site.
Low With Phase 2
cap design
17 Ensure the Phase 2 cap design considers the management of the
shallow fill found to the north-west of the leachate storage dam as
part of the drilling program to install monitoring bore 35A/B.
Med With Phase 2
cap design
18 Remediate the existing perimeter drainage system. Low Next audit
19 Improve operational management procedures as per the Landfill
Compliance Risk Register (Appendix F). These include:
Establish a procedure to report on site infrastructure corrosion
inspection photographs to identify action requirements;
Low
Next audit
Ensure daily inspections are undertaken on all days in which
the landfill is operating;
Low Ongoing
Modify the daily and monthly checklists to identify the locality
where observations are made; and
Low Sep 2016
Maintain a record of visual inspections of loads at the
weighbridge.
Med Sep 2016
20 Ensure at least 300 mm of daily cover is placed on the tipping face
and the intermediate cover within Area C is maintained. This will
require additional cover over parts of Area C where litter is
emerging.
Med Ongoing
21 Fence off Area A. Low Next audit
Auditor activities
22 Review assessment of LIS system performance against triggers and
determine whether the LIS performance meets the design
objective for period from 1st January 2016 to 31st December 2016
High Feb 2017
23 Undertake for period up to 30th June 2017. Mediu
m
31st Oct 2017
May 2016
Page 11
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
1. Introduction
The Glenelg Shire Council (GSC) operates a landfill located at 210 Cape Nelson Road, 3 km
south-south-west of the Portland town centre (Figure 1). The landfill, known as the Portland
Landfill, is licensed to operate under the Environment Protection Authority (EPA) licence 22492
(formerly HS776) as amended on 30th June 2014. The licence is attached to this audit report as
Appendix A.
1.1 Requirement for audit of landfill operation
Condition L1_L2 of the licence (Appendix A) states that “You must engage an environmental
Auditor appointed pursuant to the Act to conduct the environmental audits at the frequency
specified in the verified Monitoring Program”.
The verified Monitoring Program was updated and re-verified in November 2014 by John Nolan
(Nolan Consulting; 2013) as the appointed Environmental Auditor. The re-verified Monitoring
Program specified that next audit of landfill operation be undertaken for the period from 1st July
2014 to 31st December 2015.
1.2 Auditor
John Nolan, an Environmental Auditor appointed under the Environment Protection Act 1970
(the ‘Auditor’), has been engaged by the GSC to undertake this audit of the landfill operation.
1.3 Compliance with audit requirements
The audit has been conducted in accordance with Section 53V of the Environment Protection
Act 1970.
The audit report has been prepared in accordance with:
Section 53V of the Environment Protection Act 1970 which sets out requirements that must
be met when an Environmental Auditor prepares an environmental audit report in
relation to the risk of any possible harm or detriment to a segment of the environment
caused by any industrial process or activity, waste, substance or noise;
Appendix 6 of EPA (2011b) Landfill Licensing Guidelines, EPA publication 1323.2;
EPA (2015b) “Preparation of Environmental Audit Reports on Risk to the Environment”,
Publication 952.5; and
Condition L1_L2 of EPA Licence 22492.
1.4 Definitions
The term “site” is used within this report. It refers to the area subject to the licence as shown in
the licence’s Schedule 1A – Locality Plan and in Figure 1. It is noted that this area excludes the
area in the north-west previously known as Cell 4.
1.5 Location of audit findings
The locations of the audit findings within the body of this report are listed in Table 1-1.
May 2016
Page 12
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Table 1-1: Location of audit findings within the landfill operation audit report
Audit findings Location in audit
report (section)
Implementation of progressive rehabilitation. Section 4
Comment on the risk assessment prepared by landfill operator. Section 6
Risk of landfill operations to beneficial uses identified by the Environmental
Auditor. Section 6.3
Assessment of implementation of the Monitoring Program. Section 7
Interpretation of monitoring results. Section 8
Implementation of recommendations made in previous audit reports. Section 9
Comment on the audit frequency. Section 10.2
Assessment of the adequacy of the Monitoring Program to determine
compliance with licence actions. Section 10.3
Verification of the Monitoring Program. Section 10.3
Recommendations. Section12
May 2016
Page 13
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
2. Audit scope and method
2.1 Scope
The scope of the audit of landfill operation is consistent with the Appendix 6 of the
EPA (2011b) Landfill Licensing Guidelines.
2.2 Audit objective
The objective of the audit is to identify and, where possible, quantify the risk of any possible
harm or detriment to a segment of the environment caused by operation of the landfill.
2.3 Audit scope
2.3.1 Activity to be audited
The activity to be audited is the operation of the Portland Landfill including the placement of
waste.
2.3.2 Component of the activity to be considered
The audit assesses all aspects of the landfill operation. The audit also considers and makes
comment on the risk assessment and environmental Monitoring Program and progressive
rehabilitation of landfill cells, including capping of any cells.
Commentary is provided on the ability of the Monitoring Program to generate sufficient
information to enable compliance with licence conditions to be determined.
2.3.3 Segment of the environment to be considered
The segments of the environment considered is the premises including the atmosphere at the
premises, groundwater beneath the premises and any surface water on the premises, and the
environment surrounding the premises to which the activity may pose a risk. The geographical
extent includes the landfill premises and surrounding land.
2.3.4 Elements of the environment to be considered
The audit elements are groundwater, surface water, land, odour, atmosphere and
management of landfill gases, including potential off-site migration.
2.3.5 Beneficial uses to be considered
The actual and potential beneficial uses of a segment of the environment need to be identified
before any risk of harm or detriment to them can be assessed. Beneficial use is defined in
Section 4 of the Environment Protection Act 1970. Beneficial use means a use of the
environment, or any element or segment of the environment, which:
is conducive to public benefit, welfare, safety, health or aesthetic enjoyment and which
requires protection from the effects of waste discharges, emissions or deposits or of the
emission of noise; or
is declared in a State Environment Protection Policy to be a beneficial use.
Beneficial uses that are considered are those specified in State Environment Protection Policies
(SEPPs). SEPPs identify indicators to be employed when measuring environmental quality and
environmental quality objectives that are necessary to sustain designated beneficial uses.
The beneficial uses to be considered are identified in Section 6.1 of this report.
May 2016
Page 14
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
2.3.6 Risk assessment
This audit of landfill operation reviews the method and findings of the:
Nolan Consulting (2014) S53V Audit risk assessment;
Cardno (2015b) “Hydrogeological Assessment for Leachate Level Management”; and
Glenelg Shire Council (2015) “Portland Transfer Station – Landfill Gas Risk Assessment”.
The audit updates the assessment, as appropriate, based upon the review and the evidence
obtained during the audit.
2.3.7 Period of time over which the audit is to be conducted
The audit considers operations at the landfill from 1st July 2014 to 31st December 2015 as well as
relevant past operations.
2.3.8 Audit criteria
The audit criteria are:
1. Compliance with:
Environment Protection Act 1970;
Waste Management Policy (Siting, Design and Management of Landfills) 2004;
relevant State environment protection policies;
EPA licence 22492;
the verified environmental Monitoring Program; and
progressive rehabilitation requirements.
2. The placement of waste has not had an adverse impact on the beneficial uses of the
site and its local surrounds.
2.4 Audit tasks
The audit included the following tasks:
familiarisation with landfill operations including inspection of the landfill operating area;
review of the operations including rehabilitation;
assessment of risk to the beneficial uses;
review and update of the risk assessment;
review, update, and re-verification of the environmental Monitoring Program; and
preparation of this audit report.
The Auditor undertook a site visit on 7th March 2016. During the site visit, the Auditor:
inspected relevant documents held by GSC;
interviewed GSC’s Project Planning and Facilities Manager, Resource Management
Officer, and Waste Program Manager (part);
inspected the landfill, including monitoring infrastructure and surrounds, with GSC’s
Project Planning and Facilities Manager (part), Resource Management Officer, and
Waste Program Manager.
May 2016
Page 15
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Selected photographs from the site visit are shown in Appendix B.
2.5 Reference documents
The key reference documents are:
Nolan Consulting (2014) “Section 53V Audit – Landfill Operation, Portland Landfill – 210
Cape Nelson Road Portland”, Service Order No. 8004179 [Appendix C];
Cardno (2015b), “Hydrogeological Assessment for Leachate Level Management -
Portland Landfill 210 Cape Nelson Road, Portland, Vic.” [Appendix D]; and
GHD (2015b) “Portland Landfill Annual Environmental Monitoring Results Report 2014/15”,
August 2015 [Appendix E]; and
Nolan Consulting (2014) includes the verified Monitoring Program.
The other main reference documents considered during the audit are listed in Section 14.
May 2016
Page 16
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
3. Landfill development and operations
3.1 Location and area
The site address is 210 Cape Nelson Road, Portland. It is located approximately 3 km south-
south-west of the Portland town centre (Figure 1). The site is bounded by Cape Nelson Road to
the east, Malings Road to the south, McNeillys Road to the west, and Derril Road to the north.
Access is via Derril Road.
The site is approximately 33 ha in area including 14 ha which has been subject to landfilling.
3.2 Ownership
The site is understood to be owned by Glenelg Shire Council (GSC) with the exception of one
parcel of crown land.
3.3 Land use
3.3.1 Zoning
The site
Most of the site is zoned Public Use Zone 6. A small area in the north-east corner of the site is
zoned Public Park and Recreational Zone.
Surrounding land
The zoning of the surrounding land as shown in the EPA licence is:
north – PPRZ (Public Park and Recreational Zone);
south – RCZ1 (Rural Conservation Zone 1);
west – FZ (Farming Zone); and
east – PUZ5 (Public Use Zone 5).
3.3.2 Former land use
Lane Piper (2010a) noted that the eastern portion of the site (Area A), was a limestone quarry
in the late 1950’s and early 1960’s. AGC Woodward-Clyde (1992) noted that the limestone
extraction extended “more or less to the watertable”.
3.3.3 Surrounding land use
The surrounding land uses are shown in Table 3-1.
Table 3-1: Surrounding land uses
Location Description
North Grassland, scrubland, Yarraman Park (with go-cart and horse trotting track), and open
grassed paddocks.
East Cemetery. Open grassed paddock beyond cemetery.
South Open grassed paddocks and low density residential - two dwellings (Malings Road).
West Open grassed paddocks and scrubland with one residential dwelling (McNeillys Road).
Medium density residential development occurs north-east of Madeira Packet Road; about
500 m north-east of the site entrance on Derril Road.
May 2016
Page 17
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
3.4 Landfill staging and key design features
The landfill history was researched and documented by Lane Piper (2010a) “Environmental
audit report (Groundwater - 2010)”. Landfilling commenced in the early 1960’s. The original EPA
licence was issued on 12th March 1976.
The landfill’s key features are summarised in Table 3-2. The sequence of landfill development in
Areas A, B, and C is shown in Figure 2.
Table 3-2: Key Portland landfill features
Feature Description
Landfill type Below ground with above ground mounding of the final landfill surface.
AGC Woodward-Clyde (1992) advised that the land would be pre-
stripped to 44 m AHD or a minimum of 2 m above the watertable. The
depth below ground surface is estimated to be about 6 m in the east
(Area A) to a few metres in the west (Area C).
Start of landfilling In the late 1950’s.
The original licence was issued in 1976.
Current landfill surface
area
Approximately 14 ha (includes Area A, Area B, and Area C).
Completed cells Area A (eastern area): Filling commenced in the late 1950’s – early
1960’s. Lane Piper (2010a) notes that this area was a limestone quarry
prior to filling. The base is just below the watertable. The landfill was not
constructed with a liner, below fill leachate collection system nor a gas
collection system. Rehabilitation occurred in 1983.
Area B (central area): Filling commenced in 1983. Filling is understood
to have been completed in 2013. The landfill has not been constructed
with a liner, below fill leachate collection system nor a gas collection
system. The Works Approval documentation (AGC-WWC; 1992) advised
that the land would be pre-stripped to 44 m AHD or a minimum of 2 m
above the watertable.
Operating cells Area C (western area, and south of Leachate Storage Dam): Filling
commenced in 1992. Filling was still occurring as of 7th March 2016. The
landfill has not been constructed with a liner, below fill leachate
collection system nor a gas collection system.
The feature survey conducted on 8th September 2014 found the lowest
point on the excavated surface that was about to be filled was
43.62 m AHD. The Berry Whyte Surveyors feature survey of 21st
September 2016 had a low point of 43.3 m AHD in the excavated area.
GSC advised that some areas of overfill were identified in the
September 2016 topographical survey of the landfill.
Dedicated asbestos cell
About 100 m to the west of the weighbridge (western part of Area B).
Future cells Nil
Cell 4 has been withdrawn from the current licence.
Waste placement method Deposited in layers between daily cover.
Fill depth Variable; up to 15 m.
Floor and wall treatment Nil.
Capping Area A: Has a cap that varies from 0.25 m and 0.70 m in thickness of
predominantly silty sand or sandy silt (Senversa; 2013). The cap does not
currently meet the EPA (2015a) Landfill BPEM requirements.
May 2016
Page 18
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Feature Description
Arrangements for recapping of Area A, excluding segments with
mature vegetation, have been proposed and accepted by the EPA
(Section 4.5).
Areas B&C: GSC has advised that an interim cap has been placed over
these areas and that the thickness is about 300 mm.
Gas collection Nil.
Leachate management Subsurface leachate collection system
There is no subsurface leachate collection system below Areas A, B,
and C.
A leachate collection sump has been installed in the north-east corner
of the operating area in Area C. This is pumped to the Leachate
Storage Dam.
Leachate Interception System (LIS)
A Leachate Interception System (LIS) was installed in 1993. It was
designed by AGC Woodward-Clyde (1991). The LIS currently includes
four operating interception bores (IB4, IB5, IB6R, and IB7) located along
the northern boundary that pump to the leachate storage dam
located to the north-east of Area C. The pumps are operated with
compressed air sourced from the insulated compressor house on the
northern boundary of the site to the west of the entrance gate.
The leachate collection system is shown in Figure 5.
Leachate Storage Dam
The Leachate Storage Dam was designed by AGC Woodward-Clyde
(1992) to be 200 m long, 65 m wide, and about 3.5 m deep (including
0.5 m of freeboard). The design allowed for an engineered liner of clays
with a hydraulic conductivity of 2x10-8 m/s. The design drawing
provided by GSC show the dam with a 300 mm compacted clay liner,
a floor level of 42.0 m AHD, and a crest level of 47.0 m AHD.
GSC advised that the dam always holds water, has never overflowed,
has not been pumped, and has not been desludged.
During January 2015, Berry & Whyte Surveyors Pty Ltd surveyed the
elevation of the walls, floor, and water level in the dam (and installed a
graduated survey pole near the north-west corner of the dam for water
level monitoring). At the time of the survey, the water in the dam was at
approximately 42.55 m AHD. The surveyed depth of the dam from top
of bank to floor is approximately 5.0 m, and the floor elevation of the
dam is approximately 42.0 m AHD. Allowing 0.5 m freeboard, and
assuming 14,000 m2 surface area, the dam storage volume is about
63 ML.
GHD (2015a) assessed the dam liner permeability and thickness.
Laboratory permeability test results (using tap water) reported the
permeability range of 4 x 10-9 m/s to 1 x 10-10 m/s. Cardno (2015b)
suggested the liner permeability may be higher as the salinity of water
in the dam will be higher than tap water.
Leachate pooling adjacent McNeillys Road
In 2012 leachate pooling was observed in a shallow depression on the
western boundary of Area C adjacent to McNeillys Road. Excess
stormwater was collected and pumped to the Leachate Storage Dam.
Although the shallow depression has been filled leachate still is
understood to occasionally collect at this location after heavy rains.
May 2016
Page 19
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Feature Description
Under these circumstances the leachate is pumped into the Leachate
Storage Dam.
This area was dry at the time of the 7th March 2016 site inspection.
Former sub-soil cut-off drain
GSC provided information to Lane Piper (2010a) that indicated that a
sub-soil cut-off drain had been constructed to a depth of 1 m below
the fill batter in response to the unlicensed discharge of leachate to
Derril Road in 1991. This cut-off drain was connected to a sump from
where it was recycled back into the landfill. There is no evidence that
suggest that this system still exists.
Stormwater management The GHD (2011) “Report for Further Investigation of Waste Disposal
Options – Stormwater Management Plan found that the site has no
formal drainage channels or stormwater treatment ponds designed to
manage surface water runoff.
Any water that is not evaporated, transpired by vegetation or infiltrated
into the waste mass is conveyed along internal roads following the
existing grade. Surface runoff from contaminated areas potentially
combines with uncontaminated flows through the site. Surface runoff
from the site is not captured in formal sedimentation ponds and there
are no formal means of determining whether site runoff is
contaminated.
The southern boundary of the site has an open channel (up to 2 m
deep) on the northern side of Malings Road that captures runoff from
both external catchments and the existing landfill area that drains
towards Malings Road. The channel drains to the east and west from a
topographic highpoint on the Malings Road stormwater drain midway
between McNeillys Road and Cape Nelson Road. Drainage flows to
the east are piped under Cape Nelson Road.
Drainage flows to the west of this point on Malings Road travel in a
westerly direction, then in a northward direction along the eastern side
of McNeillys Road, and then in an easterly direction along Derril Road. It
is then diverted, near the Derril Road entrance to the landfill, to the
north-east into a depression located south of Madeira Packet Road.
The drain on the eastern side of McNeillys Road is a densely vegetated
open channel (up to 0.5 m deep).
Stormwater from the east of the site entrance flows along Derril Road
and under Cape Nelson Road to the east. This stormwater is then
directed into a stormwater drain running alongside Cape Nelson Road.
The following infrastructure is located within the site:
site office and weighbridge;
toilet near the site office;
shed behind site office;
shipping container;
transfer station and recycling facility; and
transfer station shop.
May 2016
Page 20
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
The site offices and weighbridge are situated in the centre of the site on the site access road
off Derril Road. The access road is asphalted near the entrance and then gravelled.
The transfer station and recycling facility is located directly west of the site offices. It includes
recycling skips for scrap steel, concrete, and brick rubble. Waste oil and batteries are
accepted and stored. The waste oil is stored in a self bunded tank. The batteries are stored in
a covered area. Tyres, mattresses, whitegoods, and electronic waste are segregated on-site.
There is limited on-site use for crushed concrete as crushed limestone is now used as access
road aggregate.
The new transfer station, which is scheduled to commence operation in July 2016, will include
a transfer station building, a gatehouse (weighbridge and site office), a recycling building, and
small storage sheds for specialised wastes and general equipment. As such the existing site
office, weighbridge, transfer station, and recycling facility will be decommissioned.
Commercial and household separated green waste is also accepted at the site.
Overhead 500 kV transmission lines run through the site in a north-west to south-easterly
direction towards the Alcoa’s Portland Smelter. The maximum allowable landfill level below the
transmission lines is understood to be 44 m AHD.
GHD, on behalf of GSC, sought AusNet Services approval to allow part of the transfer station
to be built within the 30 m easement on either side of the centre line of transmission line towers.
This approval was provided with conditions in August 2014.
3.5 Landfill life
The landfill is scheduled to close on 1st July 2016. This is subject to the transfer station being
commissioned by this date.
3.6 Facility operator
The site is operated by GSC. Site operations include the landfill and will include the new transfer
station and ancillary facilities.
3.7 Human resources
Responsibility for managing the landfill is with GSC’s Project Planning and Facilities Manager.
Other staff that have landfill responsibilities are:
Resources Management Officer;
Waste Program Manager;
Facility Maintenance Co-ordinator (for LIS operations)
Weighbridge Attendants (one full time and casual part time);
Compactor Operator (one full time and casual part time); and
casual staff provide relief, collect litter and undertake other support activities.
The landfill staff report directly to the Resources Management Officer. GSC’s Facilities
Maintenance Officer manages and maintains the leachate interception system.
Hollyrock Hire is contracted to excavate to 44 m AHD, to place cover material at the end of
each day, to operate the compactor on weekends, and to undertake the mulching of green
waste. Kelcar is contracted to transfer on-site skips from the transfer station to the landfill. This
includes asbestos.
May 2016
Page 21
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
3.8 Landfill operations
A commentary of some key operational aspects based upon the site inspection, discussions
with GSC staff, and a review of key documents is presented below.
3.8.1 Receipt of waste at weighbridge
Wastes accepted
Historical
Prior to 1992, Lane Piper (2010a) found that the following waste products had on occasions
been accepted at the landfill:
waste oil and petroleum product up to 1977;
15 to 20 tonne of off-specification PVC product containing less than 20 ppm residual vinyl
chloride monomer;
offal and fish waste up to 1989; and
phenol contamination of an unknown source (reported by EPA in 1989).
The amended licence, as of 1992, allowed for industrial, commercial, and trade activities into
Areas B and C excluding:
liquid wastes including waste oils;
soluble chemical wastes;
prescribed wastes other than asbestos wastes;
infectious wastes, pharmaceutical wastes and pathological wastes;
triple interceptor and grease trap wastes;
automotive batteries; and
nightsoil wastes; and hazardous wastes.
Current
The landfill is currently licensed to receive:
putrescibles waste;
solid inert waste;
pneumatic automotive tyres shredded into pieces less than 250 millimetres in all
dimensions;
asbestos waste of domestic origin; and
asbestos (all forms).
The Auditor notes that on 21st June 2010 the EPA advised GSC that recreational fish waste and
fish waste from processors (provided that it is dewatered and untreated) are not prescribed
wastes. Dead animals are accepted as putrescible waste.
Most green waste that is received and mulched at the site is landfilled. A lesser component is
occasionally used as cover material. GSC is investigating future organic processing options.
Although synthetic mineral fibre (SMF) from the Portland Aluminium Smelter is classified as an
industrial waste and hence can be accepted at the landfill, GSC does not accept it at present
as it has not developed OH&S protocols to address the fibre content.
May 2016
Page 22
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Asbestos waste of a domestic origin and occasional commercial loads, through pre-existing
arrangements, are accepted at the facility. The asbestos is placed in an on-site skip and
disposed of at the dedicated area within the landfill when the skip is near full.
Waste quantities
As of 30th June 2011 the residential population of the Glenelg Shire was 19,843. The Portland
landfill services this population, excluding that serviced by the Casterton landfill and the
Dartmoor and Nelson transfer stations, as well as commercial operators.
Glenelg Shire Council’s EPA levy payment data spreadsheet provides data on the quantities
of waste received at the landfill since 2007-08. The breakdown is presented in Table 3-3.
Table 3-3: Waste quantities received at Portland Landfill (tonne)
Year Municipal Commercial Prescribed Total
2007-08 8,664 2,560 291(1) 11,515
2008-09 8,313 1,357 485(1) 10,155
2009-10 8,942 1,146 244 10,332
2010-11 9,347 795 214 10,335
2011-12 6,723 638 213 7,574
2012-13 21,721(2) 2,028 187 23,936
2013-14 23,433(3) 1623 101 25,157
2014/15 11,846 1,359 76 13,281
2015/16 (to 31st Dec)
Oct-Dec qtr.
7,477.6 616.9 20.2 8114.4
(1) The prescribed waste in 2007-08 was asbestos only. The 2008-09 prescribed waste was asbestos and fish.
(2) Includes 16,429 tonne of soil specifically sourced from projects to be used as cover material. Most of the
soil is obtained from Council stockpiles. A minor component is understood to be obtained from
industrial sources.
(3) Includes 17,300 tonne of soil specifically sourced for cover material.
The post 2013-14 reduction in the quantity on municipal waste is due to a reduction in the use
of cover material.
Private self-haul traffic is restricted to the transfer station.
Operating hours
The landfill is open from 8.00 am to 4.30 pm from Monday to Friday and 8.30 am to 4.30 pm on
Saturdays, Sundays, and public holidays.
Weighbridge
The weighbridge is manned during all operating hours.
3.8.2 Transfer of waste to active landfill cell
The landfill receives municipal waste from GSC collections and commercial waste contractors.
The landfill is closed to self-haul public traffic.
May 2016
Page 23
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
3.8.3 Tipping of waste at active landfill cell
The tipping face was observed during the audit site inspection of 7th March 2016. The tipping
area was about 20 m in width and the height of fill following compaction was less than 2 m.
The observed wastes at the tipping face were acceptable wastes under the EPA licence.
3.8.4 Compaction of waste and daily cover placement
The wastes at the tipping face are compacted each day.
Daily cover is mainly sourced from waste soil from Council road works and developments. Lesser
quantities are sourced from green waste mulch and in-situ soil. Daily cover is not removed from
the active tipping face at the commencement of each day.
The Compactor Operator visually inspects the cover to determine if the 300 mm requirement is
met. GSC advised that while they have attempted to apply 300 mm of cover material over the
active filling area at the end of each day, a lesser height has been applied on several
occasions due to difficulties in securing off-site supplies. Evidence of lesser quantities applied
are found in the completed Monitoring and Compliance Daily Checklists and the 2140-15 levy
statement. This non-compliance is also stated in the 2014/15 Annual Performance Statement.
The audit inspection of 7th March 2016 found that litter was emerging through the southern and
western segments of Area C (see photographs). Further cover is required to prevent the off-site
migration of litter.
3.8.5 Odour occurrences
GSC advised that no odour complaints were made over the July 2014 to December 2015 audit
period.
No significant odour was identified beyond the property boundary during the 7th March 2016
audit inspection.
3.8.6 Litter management
Litter is managed as follows:
a permanent cyclone fence surrounds the site except for Area A. GSC has advised that
the fences are located within the property boundary;
2.5 m x 2.5 m mobile litter fences are used in selective areas around the active tipping
face;
an internal litter fence along the southern boundary of the Leachate Storage Dam;
daily cover is applied at the tipping face;
litter is collected about three times per week; and
additional litter collections are undertaken when required by GSC staff.
GSC advise that off-site litter occurrences are infrequent as a result of high winds and only
occur on McNeillys Road to the west. Over the July 2014 to December 2015 audit period GSC
advised that no litter complaints were made.
At the time of the 7th March 2016 audit site inspection some litter was observed within isolated
non-active areas of Area C and along the western boundary (inside of the fence-line). GSC
intend to install further temporary litter fencing to the west of the operating area.
May 2016
Page 24
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
3.8.7 Mobile plant and equipment
The on-site vehicles include a Komatsu compactor, a traxcavator, a front end loader and a
ute. The Komatsu compactor is fitted with a reversing beeper. The ute is used to cart water for
dust suppression.
With the exception of the traxcavator, which is hired from Hollyrock Hire Pty Ltd, the above
vehicles are Council owned. These vehicles are maintained as part of Council’s vehicle
maintenance schedule (either per ‘000 km or a set number of services per year).
A contractor operates the tub grinder for green waste mulching.
Diesel fuel is supplied from an on-site trailer mounted and unbunded tank.
3.8.8 On-site storage of chemicals
Waste oil is stored in a double skinned self bunded tank. Small quantities of herbicides, cleaning
fluids and petrol (less than 5 L) are stored in the garden shed. GSC is not aware of other
chemicals that are stored within the site. These chemicals will be transferred to a new shed
within the new transfer station facility.
3.8.9 Leachate Interception system
Design
As described in Table 3-2 the Leachate Interception System (LIS) was designed by AGC
Woodward-Clyde (1992). It was installed in 1993 and is operated by GSC.
The original design allowed for development in three stages.
Stage 1 is the only stage that has been implemented. This stage was designed to intercept
leachate from the “old tip” in Area A. This involved the installation of bores IB4 to IB7 along the
northern boundary of the site below Area A in 1993. These bores were required to fully
penetrate the Bridgewater Formation Aquifer (the BFA). Bore IB8 was installed in 1997.
The LIS was designed with a capacity of 0.175 ML/day (63 ML/yr). It is noted that this was based
upon the bores being screened over the full sequence of the BFA, up to 20 m, that would result
in a drawdown of 4 m at the bores and about 2 m around the interception bore field. It was
assumed that the pumps would be suction pumps that are limited to a lift of about 6 m.
These interception bores were to be operated when the down-gradient groundwater
monitoring bores showed an average 20% increase in the average background salinity or
salinity above 1,500 mg/L.
Cardno LanePiper (2014c) reviewed the LIS in 2014 and concluded that it was operating below
design capacity and provides limited control on the off-site migration of contaminated
groundwater, and that the LIS could achieve the design criteria through the operation of the
existing four leachate interception bores, supplemented with three additional leachate
interception bores.
LIS upgrade
As a consequence of this finding the LIS was upgraded during 2015. The details are provided
in Cardno (2015b) and GHD (2015c). The current leachate collection system is shown in
Figure 5.
The upgrade involved the replacement of bore IB6 with IB6R. GHD (2015c) then undertook the
following works:
May 2016
Page 25
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
supervised a contractor to remove the existing pumps from the bores IB4, IB5, IB6R and
IB7and undertake bore development to remove accumulated silt from the bores;
install new leachate interception pumps in bores IB4, IB5, IB6R and IB7;
install automated water level loggers (counters) in bores IB4, IB7 and IB6R;
install an appropriate flow meter for a 50mm (OD) diameter high pressure poly pipe that
transfers leachate from the bores to the leachate pond.
Cardno (2015b) “Hydrogeological Assessment for Leachate Level Management - Portland
Landfill 210 Cape Nelson Road, Portland, Vic.” reports on the current status of the LIS. Details of
these leachate interception bores are presented in Table 3-4. All bores with installed pumps are
screened across the MSA and the upper part of the BFA.
Table 3-4: Leachate interception bore details [after Cardno (2015b)]
Bore Year
drilled
Screened
depth (m bgl)
Comments
IB4 1993 5.9-11.5 Under gatic cover, pump, data logger and pulse counter
installed.
IB5 1993 5.4-12.2 Under gatic cover, pump and pulse counter installed.
IB6R 2015 5.0-11.0 Under gatic cover, pump, data logger and pulse counter
installed.
IB7 1993 4.0-10.0 Under gatic cover, pump, data logger and pulse counter
installed.
IB8 1997 4.57-21.5 Standpipe – no pump fitted.
The data loggers have been installed to record the drawdown in the bores and how the levels
fluctuate over time, and to allow assessment of the performance of the pumps. The pulse
counters have been installed within the headworks of each bore to record the bore flow rates
and how they fluctuate over time, and to allow for the pump performance assessment.
The 125 mm diameter leachate interception bores are installed with PVC casing and screens.
The pulse counters record the number of pumping cycles that each bore completes and thus
provides an indication of the volume of groundwater extracted for each bore. The typical
pump volume per cycle is 0.95 L for the QED short AP4+ pneumatic pumps. [GHD(2015) advise
the pulse counters continue to record pumping cycles even if no groundwater is being
discharged, i.e. the water level falls below the base of the pump].
Cardno Lane Piper (2014c) noted that the water discharge lines connected to the pumps are
likely to require flushing or replacement, due to build-up of silt or slime that may cause partial
blockage and adversely affect system performance. GSC advised that the bores will be
purged regularly and that regular pump maintenance is planned.
Cardno Lane Piper (2015b) described IB5 redevelopment and installation of a new pump, and
monitoring of operation by GSC showed a relatively steady extraction rate, averaging
20 kL/day over six weeks. Cardno (2015b) reports the new pump in IB6R to be operating at
20 kL/day.
The ultimate number of extraction points and the optimum extraction rate will depend on the
actual system performance, and the drawdown achieved at each extraction point. This is
subject to a number of variables, including local variations in aquifer hydraulic properties, and
bore and pump performance.
May 2016
Page 26
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
The overall performance of the system in terms of the groundwater extraction rate and
drawdown has not yet been assessed, and therefore it is not yet known whether the actual
performance of the LIS meets the design objective. The original AGC Woodward-Clyde (1991
and 1992) design include interception bores IB9 to IB11 downgradient of Area C. Groundwater
monitoring bores PO34B and PO35B were installed downgradient of Area C with suitable
diameter casing to enable the extraction of groundwater impacted by leachate, if required.
3.9 Complaints and regulatory performance
3.9.1 Complaints
There were no complaints recorded over the July 2014 to December 2015 audit period.
3.9.2 Regulatory performance
The EPA issued a Clean Up Notice NO8243/90001966 for the landfill on 3rd March 2010 (EPA:
2010). The notice specified that both groundwater and landfill gas audits were to be
undertaken and that a Clean Up Plan be prepared to address any Clean Up and ongoing
management issues within a time-bound framework.
The Portland Landfill Clean Up Plan was prepared by GSC (2011a) in accordance with these
requirements as well as the recommendations of both the Environmental Audit Reports for
Groundwater (LanePiper; 2010a) and Landfill Gas (LanePiper; 2010b). The CUP includes
timeframes to achieve the audit recommendations.
The EPA revoked the CUN on 19th November 2014.
The EPA issued a post closure supporting Hydrogeological Assessment (HA) Pollution
Abatement Notice (PAN) [Notice ID: 90005080] for the landfill on 10th November 2014. The HA
report must be supplied to the EPA by 31st December 2015. The HA was undertaken by Cardno
(2015b) and verified by John Nolan as the EPA appointed auditor. The HA was submitted to the
EPA on 11th December 2015 together with the letter of verification. As a result the EPA revoked
the PAN on 28th January 2016.
A draft Aftercare Management Plan post closure PAN has been issued.
Annual Performance Statement
The 2014/15 Annual Performance Statement (GSC; 2015) identified that GSC has complied with
all operations related licence conditions except for:
LI_G1 Waste from the premises must not be discharged to the environment except
in accordance with this licence.
See response to Condition LI_L5 and LI_DL1.
LI_L3 By the end of each day's operations waste must be covered with a layer of
soil at least 0.30 metres thick or using another method of cover approved by
EPA.
Due to insufficient available material for daily cover, height of cove on some
occasions limited to 0.2 m. GSC advised staff are putting in measures to
ensure adequate cover material available.
LI_L5 You must prevent emissions of landfill gas from exceeding the investigation
levels specified in Best Practice Environmental Management, Siting, Design,
Operation and Rehabilitation of Landfills (EPA Publication 788).
May 2016
Page 27
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Exceedances of EPA(205) BPEM LFG Action levels recorded on 23rd July 2014,
30th October 2014, 5th February 2015,and 30th April 2015 monitoring events. An
analysis of the exceedances is provided in Section 8.5. GSC advised of the
action taken in response to the non-compliances. This included the
installation of a background LFG monitoring bore, committing to a LFG
collection system for Area C and placement of additional cover material in
areas of elevated methane emissions at the surface.
L1_L8 You must ensure that an independent annual survey is conducted for each
landfill cell to (a) determine the quantity of waste deposited and verify the
amount of landfill levy payable, (b) demonstrate the need for any new cells
and (c) confirm that cell heights are less than the approved pre-settlement
contour plan.
The July 2015 survey indicated parts of Stage 3 (Area C) have been overfilled.
GSC committed to reprofiling to ensure the top of waste levels complied with
the PSCP.
L1_L9 You must manage each landfill cell so that it’s final contour (including the
landfill cap) prior to settlement is not higher at any point than the pre-
settlement contour plan shown in Schedule 1.
See response to Condition LI_L5 and LI_DL1.
L1_DL1 You must not contaminate land or groundwater.
Non-compliances were identified from the analytical results associated with
the 23rd July 2014, 30th October 2014, 5th February 2015, and 30th April 2015
monitoring events. These results indicated a leachate plume extending at
least 400 m and possibly 550 m down gradient of the landfill. In response, GSC
subsequently upgraded the LIS.
On 5th November 2015 GSC advised the EPA that they are now compliant with licence
conditions LI_L8 and LI_L9. The survey by Berry and Whyte Surveyors Pty of 28th October 2015
confirmed that the landfill surface had been reprofiled to remove the excess waste so that the
surface was consistent with the top of waste PSCP.
EPA Inspections
The EPA did not undertake any site inspections during the audit period.
May 2016
Page 28
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
4. Implementation of progressive rehabilitation
This audit of landfill operation is required to determine if progressive rehabilitation is being
suitably implemented. Suitable implementation is deemed to occur if all filled cells are
rehabilitated, planned cell rehabilitation is underway, or the landfill operator can demonstrate
that rehabilitation works are programmed for timely commencement.
Landfill cell rehabilitation works include:
capping and revegetation in accordance with regulatory requirements and the EPA
(2015a) “Best Practice Environmental Management Siting, Design, Operation and
Rehabilitation of Landfills”;
capping in accordance with EPA approved design;
installation and ongoing maintenance and replacement of gas and leachate collection
infrastructure; and
decommissioning of infrastructure no longer required.
These matters are addressed in GHD (2013), “Portland Landfill – Landfill Rehabilitation Plan” of
October 2013. This report was approved by the EPA.
4.1 Existing capping
Area A was capped in 1983. GSC has provided anecdotal advice that the cap is about
600 mm thick.
In early 2013 Senversa (2013) undertook a site investigation to confirm the thickness and
composition of the cap in Area A. Eighteen test pits were excavated in an approximate grid
pattern across the area. The thickness varied between 0.25 and 0.70 m, with the majority of
locations having less than 0.5 m. Soil types were predominantly silty sand or sandy silt, however
the consistency of cover soils varied across the investigation area. In addition to silty sands and
sandy silts a range of soils from clay to gravelly sands were encountered.
The cover soils were dry of optimum moisture content with the moisture increasing slightly in a
number of test pits once waste was encountered. Leachate was not encountered. Slight landfill
gas odours were noted once waste was encountered. In general the cover soils were not
compacted.
An interim cap of about 300 mm (daily cover) is understood to have been placed over Area B
or Area C where the waste is at the pre-settlement top of waste level. Lane Piper (2010b) noted
1.0 m of stiff to hard silt clay above waste at monitoring bore LFG 13 in Area B which suggests
that the capping may be more extensive in some places than 300 mm of daily cover.
4.2 Rehabilitation Plan
The Rehabilitation Plan identified three stages. Alignment of these stages with the landfill areas
is provided in Table 4-1.
Table 4-1: Correlation with rehabilitation stages with filling cells/areas
Landfill Stage Cell/Area
1A A (central and eastern)
1B A (western) + B (north-east)
2 B
3 C
May 2016
Page 29
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
4.3 Scheduling
The proposed capping schedule is presented in Table 4-2.
Table 4-2: Capping schedule
Capping Phase Landfill Stage Commence Complete
1 1A(1), 1B, and 2 2016-17 (Qtr1) 2016-17 (Qtr4)
2
3 including asbestos disposal area
2017/18 (Qtr2) 2017/18
(Qtr4)
The completion date for Capping Phase 2 (Stage 3) is consistent with the GHD (2013)
Rehabilitation Plan. Rehabilitation of the landfill is nominated as a priority program within GSC’s
adopted Strategic Financial Plan 2014/2015 – 2023/2024, with a budgeted expenditure
allocation of $10.1 million.
4.4 Finished surface level
The EPA approved top of waste pre-settlement contour plan (PSCP) is attached, as
schedule 1C, to Licence 22492 as amended on 30th June 2014.
The PSCP shows separate mounds in Stage 1A, Stage 1B, Stage 2 and Stage 3 with a maximum
level of 53.5 m AHD in Stage 3. The pre-settlement slopes are generally within the EPA (2015a)
Landfill BPEM recommended range of maximum of 1:5 (20%) to 1:20 (5%). Slopes of greater
than 5% are limited to filled areas located at the perimeter of the waste mass where the landfill
batters down to the surrounding natural surface.
4.5 Design progress
4.5.1 Phase 1
This phase of the cap construction involves remediating the existing cap in accordance with
the EPA-approved Rehabilitation Plan (GHD; 2013).
Removal of the existing mature native vegetation is not proposed around the edges of
Stage 1A (the very eastern part of the site), within a thin corridor along the southern fringe of
Stage 2 and the adjoining road reserve (Malings Road) as it was considered that the
environmental damage in removing the vegetation outweighed the environmental benefit in
remediating the cap to cover the full extent of waste. Thus the existing cap in these areas will
not be remediated.
The Technical Specification, Design Drawings and CQA Plan were prepared by GHD (2015e),
GHD (2015f), and GHD (2015g)]. The design included two capping profile options.
The option 1 capping profile is as follows:
topsoil 0.2 m;
low permeability clay 0.5 m (minimum).
subgrade fill as required to meet top of waste PSCP level
The option 2 capping profile is as follows:
topsoil 0.3 m
soil sub-base 0.3 m;
geosynthetic clay liner
subgrade fill as required to meet top of waste PSCP level
May 2016
Page 30
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
The design was reviewed by Wajahat Bajwa (GHD; 2015h) as the environmental auditor
appointed under the Environment Protection Act 1970 and subsequently accepted for the
capping of Stages 1 and 2 by the EPA on 12th January 2015.
GSC is seeking tenders for both design options.
Phase 2
A Type 2 landfill cap [Table 8.1 of the EPA (2015a) Landfill BPEM is proposed for Phase 2 (Stage
3 including asbestos disposal area).
It is as follows:
topsoil and soil sub-base – 1.0 m;
filter geotextile;
protection geotextile;
LLDPE geomembrane; and
low permeability clay – 0.5 m (minimum).
The optional gas collection layer is not proposed as a passive LFG collection system is to be
installed (See Section 4.7). Similarly, due to the proposed slopes of the final surface profile it is
not presently intended that the optional drainage layer be provided.
4.5.2 Auditor verification
The EPA advised GSC on 12th August 2014 that all construction phases should be verified by an
Auditor as per EPA (2011b) and that the proposed management of the existing vegetation is
acceptable provided that the potential risks from the landfill is minimised/controlled.
4.6 Stormwater drainage
All surface drainage around the landfill will be located within the property boundary.
The Rehabilitation Plan (GHD; 2013) advises that the size and grades of the drains will be
defined during detailed design of the cap. The sizing of the drains will be based on
containment and control of a 1 in 20 year storm event with adequate freeboard and the
containment of a 1 in 100 year event with no freeboard. The drain grades should result in flow
speeds that reduce the risk of cap erosion but allow the water to exit the landfill area fast
enough as to limit percolation of runoff water through the cap.
The final design is likely to include one retardation/sedimentation pond. It is noted that the
superseded GHD (2011) stormwater management plan included a 0.5 ML capacity pond in
the south west corner and a 2.5 ML capacity pond in the north-east corner.
It is also understood that the stormwater flows into the northerly sloping drainage line from the
Derril Road entrance to the landfill, which flows into a depression located south of Madeira
Packet Road, will be diverted along Derril Road to the east.
The stormwater drainage system of the Phase 1 cap is to be comprise of:
drainage constructed along the perimeter of the cap;
cap surface diversion drains; and
and diversion bunds
to the grades and levels indicated in the Drawings.
May 2016
Page 31
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
The cap surface diversion drains and bunds are designed to direct runoff water from the cap
towards the perimeter diversion drains and then to the discharge locations. The drains will also
assist in preventing runoff water from flowing into adjacent private land.
The perimeter and cap diversion drains are to be constructed in accordance with BPEM
Guidelines for Stormwater Management. The clay cap diversion bunds are to be installed on
the slope of the final cap. These bunds shall be installed as part of the liner, prior to placement
of the topsoil layer.
The stormwater drainage system for the Phase 1 cap does not appear to involve the
construction of sedimentation pond(s) and remediation of the existing perimeter drainage
systems. This will be required as part of the Phase 2 capping.
4.7 Landfill gas management
Based upon 20,000 tonne of waste being deposited and applying LMS (2007) estimated that
the landfill is likely to generate about 760 tonne/yr of methane and up to 16,000 tonne/yr of
carbon dioxide equivalents (t CO2-e). Prior to the decision to close the landfill LMS (2007)
estimated that LFG emissions will peak at about 200 m³/hr.
Section 6.7.1 of the EPA (2015a) “Best Practice Environmental Management Siting, Design,
Operation and Rehabilitation of Landfills” suggests the following as potentially suitable landfill
gas treatment technologies for LFG generation rates of greater than 100 m3/hr and less than
250 m3/hr:
power generation;
high-temperature flaring;
low calorific flaring; and
other oxidation technology and discharge (e.g. passive flares, biofilters, and biocovers).
LMS (2007) considered power generation and flaring as possible alternatives. Passive systems
were recommended against. It was noted that about 300 m3/hr is typically required for a 1 MW
power plant.
4.7.1 Phase 1
LFG collection is not incorporated into the Phase 1 cap design.
4.7.2 Phase 2
The Rehabilitation Plan (GHD; 2013) includes a passive LFG collection system for Phase 2
(Stage 3) to be installed during cap construction.
The proposed LFG management system included:
a horizontal gas collection system installed immediately below the final cap;
riser pipes incorporating valves will be connected to the horizontal collection pipes to
enable the collected gas to be brought to the surface for treatment; and
a gas flare of sufficient capacity to flare all methane collected through the network.
GHD (2013) recommended that should the LFG generation rates, post collection system
installation and/or the perimeter LFG monitoring bore network emissions exceed the gas action
levels specified in Table 6.4 of EPA (2015a) “Best Practice Environmental Management Siting,
Design, Operation and Rehabilitation of Landfills”, consideration would be given to upgrading
the passive system to an active system by provision of a blower / booster (vacuum pump) or
to complement the horizontal system with vertical bores installed into the waste mass.
May 2016
Page 32
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
4.8 Conclusion
GSC has scheduled the landfill to close following the commissioning of the transfer station. This
is expected to occur in mid-2016.
The Technical Specification and Construction Quality Assurance Plan for Phase 1 Capping
(Stages 1 and 2 cap) have been completed and accepted by the EPA.
Phase 1 capping is expected to commence in the 1st quarter of 2016-17. The delay from that
scheduled in the Rehabilitation Plan is due to the need to address native vegetation
management issues as required under Environment Protection and Biodiversity Conservation
Act 1999 and to consider alternative capping design options.
May 2016
Page 33
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
5. Conceptual site model
The Conceptual Site Model (CSM) has been developed by Lane Piper (2010a&b), Cardno
LanePiper (2011a&b), Cardno LanePiper (2014b&c), and Cardno (2015b). It is consolidated
below and is informed by the description of the landfill and its operations as discussed in
Section 3.
The CSM describes the physical conditions as well as the pathways and receptors for key
hazards associated with each environmental element.
5.1 Climate
Meteorological data has been obtained from the Portland Meteorological Station (No. 90700).
Portland has a temperate climate with warm summers. The mean annual precipitation from
1857 to 2012 was 838 mm with the wettest month being in July (108 mm) and the driest month
being in February (33 mm).
The mean monthly evaporation ranges from 33 mm in July to 132 mm in December. Rainfall
typically exceeds pan evaporation from May to September.
5.2 Topography
Regionally the land falls away to sea level at Fawthrop Lagoon which is located 1.7 km to the
north-north-east.
The topography of the site has been modified by past quarrying and landfilling activity. The site
has a top of mound level of about 50 m AHD immediately to the east of the site office. From
here the land slopes to the north, north-east, south and south-east-south.
5.3 Soils
The soils are formed from the siliceous sands of the Malanganee Sands Formation that covered
most of the site prior to quarrying.
5.4 Hydrogeology
The hydrogeological information presented below is sourced from the various site specific
references (Section 14) and in particular:
Geological Survey of Victoria SV (1978) “Portland 1:63,000 Geological Map Sheet”;
Cardno LanePiper (2014b) “Hydrogeological Assessment - Portland Landfill at 210 Cape
Nelson Road, Portland”;
Cardno (2015b), “Hydrogeological Assessment for Leachate Level Management -
Portland Landfill 210 Cape Nelson Road, Portland, Vic.”; and
logs of on-site constructed groundwater and leachate monitoring bores.
5.4.1 Groundwater and leachate monitoring bore details
Twenty four groundwater monitoring bores were drilled on the site and immediate surrounds
between 1989 and 1997. These were termed monitoring bores PO01to PO24. These bores were
drilled to depths ranging from 3.5 m to 29 m. In 2012 six of these bore were replaced with new
bores as the original bores were dry, lost or damaged. These bores have the same number as
the original bores except for the suffix of “R”. An additional 15 bores, including five nested sites,
were installed between 2013 and 2015 under the supervision of Cardno.
May 2016
Page 34
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
The locations of all monitoring bores are shown in Figure 3 and the details are summarised in
Table 5-1. Bore logs are shown in Cardno LanePiper (2014b) and Cardno (2015a).
Table 5-1: Groundwater monitoring bore details [Cardno LanePiper (2014b) & Cardno (2015a)]
Bore Year Aquifer(1) Aquifer, Location Screen
(m bgl)
Comments
PO1 1989 MSA/BFA South side of Derril Road. 7.0-19.0 Good condition.
PO2 1989 MSA/BFA North side of Malings Road. 6.0-18.0 Good condition.
PO3 1989 MSA/BFA East side of McNeillys Road, in clearing. 4.0-16.0 Lost.
PO4 1990 MSA South side of McNeillys Road, along
road.
2.0-10.0 Covered by a felled
tree from January to
April 2015.
PO05R 2012 MSA/BFA/
NVA
Road Reserve along south side Derril
Road. West side of road.
4.68-7.68 Replacement of dry
bore.
PO06 1990 MSA/BFA/
NVA
South side of Derril Road. 1.5-11.75 Good condition.
PO07 1990 MSA/BFA South side of Derril Road. 2.0-12.0 Good condition.
PO08R 2012 MSA South side of Derril Road. 1.0-4.0 Replacement of dry
bore.
PO09 1992 MSA North of Malings Road, near intersection
with Cape Nelson Road.
6.5-9.5 Good condition.
PO10 1992 MSA North of Malings Road. 1.5-3.5 Under water in three
of four 2013/14
monitoring events.
PO11R 2012 MSA East side of Derril Road. 2.3-5.3 Replacement of dry
bore/destroyed
bore.
PO12 1992 MSA West side of Madeira Packet Road. 1.5-3.5 Good condition.
PO13 1992 MSA South west corner of Yarraman Park.
Inside Yarraman Park, within tracks.
1.0-7.0 Good condition.
PO14 1992 MSA Inside Yarraman Park, East side of park. 2.0-8.0 Good condition.
PO15R 2012 MSA North West corner of Yarraman Park.
Inside Yarraman Park, along the tracks.
2.5-7.0 Replacement of dry
bore.
PO17 1997 MSA/BFA East of Cape Nelson Road. 3.3-28.5 Good condition.
PO18R 2012 MSA East of Cape Nelson Road. 3.0-6.0 Replacement of dry
bore.
PO19R 2012 MSA/BFA Road Reserve along south end of Derril
Rd. East side of road.
3.0-6.0 Replacement of dry
bore.
PO20 1997 MSA/BFA North of Derril Road and IB6R. 3.65-25.5 Good condition.
PO21 1997 MSA/BFA Cnr. Derril Road & Cape Nelson Road. 2.4-28.6 Good condition.
PO22 2010 MSA South-east of Yarraman Park. 0.8-3.8 Good condition.
PO23 2010 MSA Along Cape Nelson Road. 0.9-3.9 Good condition.
PO24 2010 MSA Along Cape Nelson Road. 0.9-3.9 Good condition.
PO25 2013 NVA Derril Rd near entrance. 15.0-18.0 Good condition.
PO26A 2013 MSA South-west corner of site. 2.5-5.5 Good condition.
PO26B 2013 BFA Adjacent PO26A. 10.5-13.5 Good condition.
May 2016
Page 35
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Bore Year Aquifer(1) Aquifer, Location Screen
(m bgl)
Comments
PO28 2013 MSA Derril Rd - Cape Nelson Rd cnr. 2.0-5.0 Good condition.
PO29 2013 BFA Nolan123. 11.5-14.5 Good condition.
PO30 2013 BFA Madeira Packet Rd - Cape Nelson Rd
cnr.
12.0-15.0 Good condition.
PO31A 2013 MSA North, on Madeira Packet Rd. 3.0-6.0 Good condition.
PO31B 2013 BFA Adjacent PO31A. 12.0-15.0 Good condition.
PO32 2013 BFA South of PO31A. 5.5-8.5 Good condition.
PO33A 2013 MSA North-east of Derril Rd entrance. 0.5-2.5 Good condition.
PO33B 2013 BFA Adjacent PO33A. 6.0-9.0 Good condition.
PO34A 2015 MSA 30 m north-west of leachate storage
dam.
1.0-4.0 Good condition.
PO34B 2015 BFA Adjacent PO34A. 5.0-11.0 Good condition.
PO35A 2015 MSA North-west of Derril Rd entrance. 1.0-4.0 Good condition.
PO35B 2015 BFA Adjacent PO35A. 5.0-11.0 Good condition.
(1)
MSA - Malanganee Sands Aquifer
BFA - Bridgewater Formation Aquifer
NVA - Newer Volcanic Aquifer
While most of the original bores were screened across the shallow Malanganee Sands
Formation (MSA) and the deeper Bridgewater Formation (BFA) aquifers, the 15 bores installed
from 2015 onwards were screened in single aquifers only.
It was intended that monitoring bores PO34A/B and PO35A/B be installed directly
downgradient of the leachate storage dam to monitor groundwater directly down-gradient of
Area C. It was not possible to install these bore at the targeted locations due to the presence
vegetation that would require approval under the Environment Protection and Biodiversity
Conservation Act 1999 to establish an access track and the presence of fill to the north-east of
the leachate dam (which had not previously been mapped).
Due to these constraints monitoring bores PO34A/B were installed north-west of the leachate
pond and monitoring bores PO35A/B were sited on the southern ‘verge’ of Derril Road. The
rationale was that these bores would monitor potentially impacted groundwater from both the
leachate storage dam and from Area C. Monitoring bores PO34B and PO35B have been
designed so that they can be converted to LIS interception bores if required.
The locations of leachate monitoring bores are shown in Figure 3 and summary details are
presented in Table 5-2.
Table 5-2: Leachate monitoring bore details [Cardno LanePiper (2014b) & Cardno (2015a)]
Bore Year
drilled
Area Location Screened
depth
(m bgl)
Comments
LB01 2012 C Approx. 130m south-west of
Leachate Storage Dam.
4.5-7.5 Operational
LB01A 2015 C Installed in February 2015
Adjacent LB01
1.0-8.9 Operational
May 2016
Page 36
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Bore Year
drilled
Area Location Screened
depth
(m bgl)
Comments
LB02R 2013 B Centre of Landfill. Behind rubbish
stockpile, near transmission tower.
Decommissioned in February 2015.
4.5-7.5 Decommissi
oned
LB02RA 2015 B Installed in February 2015. Centre
of Landfill. Behind rubbish
stockpile, near transmission tower.
1.0-5.1 Operational
LB03 2012 A South of Derril Road, south of
PO07.
1.0-4.5 Operational
The leachate monitoring bore logs and construction details are provided in Cardno (2015b).
LB01A was installed in February 2015 as LB01 did not appear have sufficient depth to monitor
leachate levels in the lower part of the waste mass. LB02 was replaced with LB02R in 2013 as
the original bore had been destroyed. LB02R was decommissioned in February 2015, as the
bore was screened below the waste, and was replaced by LB02RA.
With the exception of the monitoring bores drilled in 2015, all groundwater and leachate
monitoring bores were surveyed to the Australian Height Datum in February 2014.
5.4.2 Geology
Portland is situated close to the northern margin of the Otway Basin, a major sedimentary basin
that extends from near Geelong into South Australia.
Within the local area the Otway Basin includes unconsolidated Quaternary and Tertiary
sediments of marine and non-marine origin. The stratigraphic units beneath the site are
described from oldest to youngest in Table 5-3. The outcropping regional geology is shown in
Figure 6.
Table 5-3: General Stratigraphy, Portland Area
Stratigraphic unit Lithology
Malanganee Sands Formation
(Holocene/Upper Quaternary
Age).
Thin sequence of siliceous sand dune and sheets. This covered most
of the site prior to quarrying. The 2012 and 2013 drilling programs has
found that this formation is absent in some locations.
Bridgewater Formation
(Pleistocene/Lower
Quaternary Age).
Calcareous sand and clay with various amounts of carbonite
cementation forming calcareous dunes (calcarenite) and dune
limestone. This formation ranges in depth below the surface of 9 m in
the central area of the site to about 22 m near the eastern
boundary of the site. AGC Woodward-Clyde (1992) refers to a
marine transgression sequence of clay, limestone and sand followed
by a marine regression with deposition of sand, silt, and clay.
Newer Volcanics Basalt
(Quaternary to late Tertiary
Age).
Residual clay representing weathered basalt with less weathered
basalt at depth. The basalt has occurred in several flows with a
combined thickness below the Bridgewater Formation of 25 m to
40 m.
Whalers Bluff Formation
(Tertiary aged).
This formation, which has not been identified at the site, occurs
along the shoreline cliffs east of the Portland township. It consists of
calcareous clays, silts, and sands with volcanic tuffs and shelly beds.
May 2016
Page 37
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Stratigraphic unit Lithology
Dilwyn Formation The Dilwyn Formation lies below the site at considerable depth
(greater than 1,000 m). It is separated from the above shallow
Tertiary sediments by an extensive thickness of marls.
All of the bores that have intersected the Newer Volcanics Basalt have identified a sandy clay
to clay sequence of 1.0 to 3.5 m thickness at the BFA/NVA interface.
The Cardno (2015b) south-west to north-east cross sections A-A’ and B-B’ are shown in Figure 7
and Figure 8 respectively. The location of these sections are shown in Figure 3.
The lithological logs of the deeper monitoring bores installed in 2013 suggest that the boundary
between the BFA and MSA is indistinct. There are references to cemented and calcareous
sediments to the north up until at least Madeira Packet Road. The depth from the ground
surface to the base if the BFA is approximately 22 m thick near the north-eastern boundary of
the site (at PO31B)
5.4.3 Aquifers
The main aquifers underlying the site and the local area are:
Malanganee Sands Aquifer (MSA);
Bridgewater Formation Aquifer (BFA); and
Newer Volcanics Aquifer (NVA).
The Dilwyn Formation is not considered to be hydraulically connected to the above shallow
aquifers due to the extensive thickness of intervening low permeability marls.
5.4.4 Groundwater levels
Based upon the water level monitoring data from the nested piezometers the MSA and BFA is
acting as a single aquifer system. While the BFA is always saturated the MSA is unsaturated in
some locations.
The interpolated watertable surface within the MSA/BFA as of April 2015 is shown in Figure 9.
The watertable slopes in a north-easterly direction from 45 m AHD in the south-west of the site
to 32.4 m AHD on the Madeira Packet Road to the north-east of the site. The gradient of the
watertable surface increases near IB4 to IB8.
The interpolated watertable level across the Leachate Storage Dam as of April 2015 ranged
from 42.0 m AHD in the south-west to 40.4 m AHD in the north-east. As the water level within the
dam can range from the floor level of 42 m AHD to the freeboard level of 47 m AHD, the
leachate storage dam is likely to recharge the underlying aquifer for most of the year.
Groundwater hydrographs for groundwater monitoring bores PO01to PO24 over the 1991 to
February 2015 period are shown in Figure 10. These hydrographs confirm that the watertable
elevation has not changed significantly over the past twenty five years.
The water level ranges from close to the surface (at monitoring bore PO13) to over 9 m below
ground level at monitoring bore PO25. PO13 is south of the Go Kart track at Yarraman Park,
and PO09 is screened within the Newer Volcanics aquifer just north of the Derril Road entrance
to the landfill.
May 2016
Page 38
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Although the interception bores IB4 to IB7 may have resulted in a minor steepening of the
hydraulic gradient from north to south, the influence is considerably less than the 2 m around
the borefield designed for by AGC Woodward-Clyde (1991 and 1992).
5.4.5 Groundwater movement
Recharge and discharge
Recharge to the MSA is via rainfall infiltration. Groundwater flow from the site is inferred to
ultimately discharge to the coast. There is also likely to be discharge to Fawthrop Lagoon.
Flow
The groundwater flow rate across the site is variable due to lithological heterogeneity in the.
5.4.6 Salinity
The MSA/BFA groundwater salinity (in mg/L TDS) as of April 2015 is presented as a contour plan
in Figure 12. This indicates a background salinity of about 500 mg/L to 1,200 mg/L with elevated
concentrations of up to 9,000 mg/L down-gradient to the north-east of the landfill.
The salinity of the NVA aquifer at PO25 is consistent while previously reported as ranging from
1,100 mg/L to 1,100 mg/L was 2,700 mg/L in April 2015.
Groundwater quality is discussed further in Section 8.4.
5.4.7 Aquifer parameters
Groundwater within the MSA is unconfined. It is unconfined to semi-unconfined in the BSA
becoming more confined with depth.
AGC Woodward-Clyde (1992) estimated the hydraulic conductivity of the MSA/BFA from
recovery tests at monitoring bores PO04 to PO08. The transmissivity ranged from 8m2/day to
23 m2/day with an average hydraulic conductivity of about 1 m/day.
Cardno LanePiper (2014b) undertook slug tests on six bores screened in the MSA only and two
bores were screened in the MSA/BFA on 17th July 2012. The estimated hydraulic conductivity
ranged from 0.11 m/day to 1.76 m/day (with an average of about 0.74 m/day).
Slug tests were also undertaken on monitoring bores PO34B and PO35B, both screened in the
BFA in 2014 (Cardno; 2015a). The estimated mean hydraulic conductivities were 1.87 m/day
(PO34B) and 0.04 m/day (PO34B).
AGC Woodward-Clyde (1992) estimated the storativity to be about 0.3.
5.4.8 Groundwater users
AGC Woodward-Clyde (1992) advised the BFA was the most widely used aquifer adjacent the
site and that Rural Water Corporation (now Southern Rural Water) groundwater bore records
indicate no registered groundwater users (e.g. for irrigation and industrial uses) down the
hydraulic gradient from the site.
Nolan Consulting (2013) undertook a search of the Victorian Water Resource Data Warehouse
for groundwater bores within 3 km of the landfill as part of the 2013 Audit of Landfill Operation.
“Non-groundwater”, “not known”, and “miscellaneous” bores were excluded from the search.
120 bores with known groundwater uses were identified within 3 km and 35 bores with known
groundwater uses were identified within 1 km of the landfill. Uses of these bores, within 1 km
and 3 km of the site are as listed in Table 5-4.
May 2016
Page 39
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Table 5-4: Summary of groundwater bores within 3 km of site (as of November 2012)
Use Within 1 km Within 3 km
Urban 0 6
Irrigation 1 2
Dewatering 0 1
Stock and domestic 7 49
Stock 5 12
Domestic 8 21
Observation 0 4
Groundwater investigation 14 25
Total 35 120
Cardno (2015b) undertook a groundwater database search of the Water Measurement
Information System in January 2015. This search confirmed the information provided in Table
5-4 for bores within 1 km of the site with the exception that the number of investigation bores
had increased from 14 to 26. The location of these bores are shown in Figure 11.
None of the stock and domestic, stock, domestic, and irrigation bores identified in the
database search are located within 1 km to the north-east of the site (in the down-gradient
direction). It should be noted that groundwater may also be utilised by unregistered bores not
appearing on the database.
None of the water supply bores (i.e. those registered for domestic, stock or irrigation use)
identified within 1 km of the site are located hydraulically down-gradient (north-east) of the site
where they may be most vulnerable to contamination from the site.
There are no on-site groundwater supply bores.
Cardno LanePiper (2014a) undertook a telephone survey of property owners with properties
within 500 m of the site boundary. The objective of the survey was to identify any unregistered
private groundwater bores within 500 m of the site boundary. Of the 61 properties included in
the survey, 41 participated. The survey was also used to determine if there are any buildings
basements located within 500m of the site boundary.
Table 5-5 presents a summary of the survey findings.
Table 5-5: Summary of telephone survey findings
Item Yes No Don’t know
Properties with groundwater bores 2 38 1
Properties with basements 0 41(1) 0
(1)Although not actually a basement, the responder from 119 Malings Road indicated that the property
is a two storey building with one room cut into a hill.
Groundwater bores were identified as being present at 119 Malings Road, immediately south
of the landfill and at Oakpark Road (about 900 m west of the site). The Malings Road bore is
used for stock watering and domestic purposes and appears to be identified as Bore 88510 on
the Victorian Water Resource Data Warehouse. The Oakpark Road bore was identified as not
being in use.
May 2016
Page 40
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
5.5 Surface water
All stormwater from the filled landfill areas runs off into an existing surface drainage system
around the property boundary. Refer to Table 3-2 for details.
The major drainage line in the local area is Wattle Hill Creek. It flows in an easterly direction to
Fawthrop Lagoon, which discharges via a canal to the ocean at Portland Harbour. Fawthrop
Lagoon is located approximately 1.7 km to the north of the site. Wattle Hill Creek receives runoff
from the urban catchment.
There are unnamed drainage channels south and east of the site that flow in a south-easterly
direction towards the coast.
5.6 Cultural heritage sites
The EPBC database has not been searched for cultural and spiritual heritage sites.
5.7 Vegetation
In 2011 GSC (2011b) undertook a vegetation survey within the site to identify any vegetation
that was possibly affected by LFG. The survey was undertaken on a 50 m grid.
The survey found that:
although there are some areas or ‘patches’ of affected native vegetation, there was no
vegetation present on the landfill site of any State or National significance, either through
the Catchment and Land Protection Act 1994 or the Flora and Fauna Guarantee Act
1988;
the main native plants affected on-site are acacia longifolia or common name coastal
wattle. There are also some affected coastal tea trees; and
on the north-east fence line there is a large patch of brown and dying gorse. This may or
may not be because of the presence of methane.
GSC (2011b) concluded that there is only a small amount of observable vegetation that is
affected on the site by possible landfill contamination or methane.
GHD has undertaken a native vegetation and fauna survey around the property boundary as
part of the rehabilitation planning process. GSC has advised that the southern brown
bandicoot was identified during the survey.
5.8 Landfill gas
The Portland landfill gas (LFG) monitoring bore network was established by Lane Piper (2010b)
as part of the Landfill Gas Audit. It consisted of 22 monitoring probes installed around the
perimeter of the landfill (i.e. outside of waste mass) and two LFG bores (LFG13 and LFG14)
installed in the landfill cap (i.e. within the waste mass
The depths of these monitoring points range from 1.0 m to 3.1 m. All probes were constructed
with 6 mm Teflon tubing. These soil vapour probes are connected to quick release fittings hence
are not open to the atmosphere. Typically only the very bottom section of each soil vapour
probe is screened. LFG13 and 14 have been constructed as bores with 25 mm PVC screen and
casing.
May 2016
Page 41
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
An additional four LFG monitoring bores (LFG8A, LFG10A, LFG18A and LFG20A) were installed
by GHD in February 2015 to provide comparative results to the corresponding soil vapour
probes. Bore LFG9A was installed to replace the previously destroyed LFG9, and LFG25 was
installed offsite to provide an indication of background or natural carbon dioxide
concentrations.
The location of all LFG monitoring probes and bores are shown in Figure 4.
5.9 Sources, pathways and receptors
5.9.1 Sources
The contamination sources are the waste streams described in Section 3.8.1. These can
generate leachate and LFG. The composition of both the leachate and LFG is dependent
upon the composition of the waste itself.
5.9.2 Migration pathways
LFG through air
Vertically and horizontal LFG migration from the landfill can occur through advective and
diffusive flow mechanisms through the unsaturated zone.
Advective flow of LFG occurs where a pressure gradient is present such as between two soil
layers, soil and a building above, or a service trench and surrounding soil. Diffusive LFG flow
occurs under a concentration gradient as occurs with chemicals mixing in water. The LFG flow
rate under diffusion is much slower than for advective flow.
The unsaturated zone varies in thickness within the landfill and its surrounds. Away from the
landfill the unsaturated zone is predominately comprised of loose sand and silty sand with lesser
silt and clay dominated soils of the MSA.
Vertical migration is restricted by the variable non-engineered cap on Area A, the interim cap
on Areas B and the daily cover in Area C. As the landfill is unlined, the local geology is the only
constraint to lateral LFG migration.
Groundwater
Landfill leachate that percolates through the unlined floor can mix with the groundwater in the
underlying aquifer. Information on landfill history indicates that waste was deposited at levels
close to, and possibly in places, slightly below the watertable. The rate of leachate generation
in the Portland landfill is likely to be much higher than for a landfill constructed with a Type 2
liner and cap (EPA; 2015b).
LFG can migrate by partitioning with leachate or groundwater. This involves methane, as a
volatile organic chemical, dissolving into the liquid phase. There is potential for the methane to
then partition (evolve) out of the water and into the soil gas above the watertable. This may
not be the most significant mechanism due to the low methane solubility in the groundwater
which is estimated to be about 21.5 mg/L2 (Cardno LanePiper; 2011b).
Surface Water
No natural surface water bodies are present at the site. The nearest natural surface water body
to the site is Fawthrop Lagoon, which is located approximately 1.7 km to the north east and its
tributary Wattle Hill Creek. Both groundwater and surface water are potential migration
pathways to Fawthrop Lagoon.
May 2016
Page 42
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Groundwater quality monitoring data indicates that the leachate plume has not migrated as
far as Fawthrop Lagoon.
Underground services and conduits
Underground services, conduits, and pits can transport LFG and leachate. The extent and
location of underground services at the site prior to establishment of the new transfer station
and ancillary facilities are described in Table 5-6.
Table 5-6: Extent and location of services
Service Type Description
Stormwater An underground stormwater drain collects runoff from the weighbridge
area and discharges via the resale centre to the stormwater drainage
system at Derril Road. It is understood that no other underground
stormwater network is present in site.
Telephone A Telstra cable runs southwards to the site office from the property
boundary on Derril Road (near IB4). There also appears to be a Telstra
cable entering the property from the south along Malings Road near
Cape Nelson Road.
Electricity To weighbridge, site office, and compressor house. Information on
subsurface cable location is being sought by GHD as part of the transfer
station design process. Power will be required at the new transfer station.
Compressed air The interception bore pumps are run via a compressed airline from the
bores to the compressor house.
LIS Common connector pipe along Derril Road connecting all IB bores. The
western extent of the LIS system is the compressor house. A header pipe
from around IB8 runs southward then westward to connect into the
eastern side of the Leachate Storage Dam.
Mains water Main pipe line along Cape Nelson Road.
20 mm mains off-take to site office. Route from Cape Nelson Road to site
office is unknown.
Fire water supply A water cart is located towards the southern end of the site. The CFA use
their own hoses and water supply.
Sewerage The site is not sewered.
Septic tank toilet system. Toilet located within site office building. GSC has
been unsuccessful in its search for the septic tank drainage system.
Gas Nil.
GSC has advised that Yarraman Park underground services are likely to be accessed from
McNeillys Road to the north-west.
5.9.3 Receptors
The receptors of potential harm due to the landfill activities that have been considered
relevant include:
people occupying or working at the site and nearby residences, businesses and schools;
flora and fauna on the site and surrounding the site;
the atmosphere as a sink for greenhouse gases;
physical infrastructure on and off-site;
May 2016
Page 43
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
land;
groundwater and potential users; and
surface waters.
The proximity of residences, townships, schools and commercial facilities to the landfill premises
are presented in Table 5-7.
The approximate locations of nearby residences are shown in Figure 3.
Table 5-7: Summary of Portland Landfill development
Type Proximity to landfill
Residences Residence – Malings Road (200 m south of Area A & 70 m south of site).
Residence – On Malings Road near corner with McNeillys Road (120 m
south of Area C and 60 m south-west of site).
Residence - Cnr. Derril and McNeillys Road (250 m north-west of Cell C.
Residence – north of Derril Road (250 m north of Area C from Derril Road).
Multiple residences –about 500 m NE of landfill (north of Madeira Packet
Road).
Townships Portland CBD - about 3 km north-east of the landfill site.
Schools Nil within 1 km.
Commercial facilities Yarraman Park trotting track and go-cart track – on the boundary of the
site to the north-west.
Table 5-7 shows that there are several residences and commercial/industrial buildings within
the recommended buffer distance of 500 m for “buildings or structures” specified in Table 5.2
of EPA (2015a) Landfill BPEM for Type 2 landfills.
GSC has advised that it does not have any planning related restrictions for development within
500 m of the landfill.
The Cardno LanePiper (2014a) telephone survey of 41 participating property owners within
500 m of the landfill site did not identify any building basements. The property owner at 19
Malings Road indicated that their property is a two storey building with one room cut into a hill.
Information on:
flora and fauna;
physical infrastructure on and off-site;
the land;
groundwater and potential users; and
surface waters.
is provided earlier in the audit report.
There are no groundwater or surface water dependent ecosystems including flood plains,
special conservation, heritage, or protected areas or recreational waters within 1 000 m of the
landfill site.
5.9.4 Glenelg Planning Scheme
The nearest Residential Zone is 468m away from the landfill.
May 2016
Page 44
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Planning Clause 19.03-5 in the Glenelg Planning Scheme has the 2004 Waste Management
Policy (Siting, Design and Management of Landfills) as a reference document. It requires a
Type 2 Landfill to have a buffer distance of 500m from all buildings or structures.
Clause 52.10 of the Glenelg Planning Scheme has a recommended setback of 100m for a
transfer Station from Residential Zones (GRZ1).
The only identified Planning Permit issued within the 500 m buffer since 1st July 2015 was issued
for an extension of an existing dwelling extension at 87 Malings Road (approx. 55 m from the
landfill) on the 21st September 2015 (Planning Permit P15117).
May 2016
Page 45
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
6. Risk of landfill operations
The following risk assessment tasks have been undertaken as part of this audit of landfill
operation:
identification of beneficial uses;
review of the Nolan Consulting (2014) risk assessment based upon:
collation of relevant information
update of conceptual model
review of July 2014 to December 2015 monitoring data (see Section 8);
update of the landfill risk assessment register;
update of the landfill compliance risk register; and
summarise the outcomes.
6.1 Beneficial uses
The following Government of Victoria State Environment Protection Policies (SEPPs) have been
reviewed to identify the relevant land, groundwater, and surface water beneficial uses:
SEPP (Variation to Waters of Victoria) – 2003;
SEPP (Groundwaters of Victoria) – 1997;
SEPP (Air Quality Management) - 2001; and
SEPP (Prevention and Management of Contaminated Land) – 2002.
EPA (2011d) “Noise from Industry in Regional Victoria Recommended Maximum Noise Levels
from Commerce, Industry and Trade Premises in regional Victoria” provides guidance on
applicable noise limits.
The beneficial uses for each of these environmental systems are described below.
6.1.1 Surface waters
Under the Variation to SEPP (Waters of Victoria) the site and surrounds is located within the
“Murray and Western Plains” segment. Within this segment, the aquatic ecosystem is
considered to be ”slightly to moderately modified”.
For this segment the rivers and streams are considered potentially suitable for all beneficial uses
including:
primary contact recreation;
aesthetic enjoyment;
indigenous cultural and spiritual values;
non-indigenous cultural and spiritual values;
agriculture and irrigation;
aquaculture;
industrial and commercial use;
human consumption after appropriate treatment; and
fish, crustacea and molluscs for human consumption.
May 2016
Page 46
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
The applicable guidelines for primary contact recreation, agriculture and irrigation, industrial
and commercial use, and human consumption after appropriate treatment are presented in
Table 6-1.
6.1.2 Groundwaters
The SEPP (Groundwaters of Victoria) provides that groundwater is characterised into segments
with each segment having particular beneficial uses. Segments are based on groundwater
salinity, generally reported as Total Dissolved Solids (TDS).
The SEPP (Groundwaters of Victoria) may determine these beneficial uses may not apply
where:
there is insufficient yield;
the background level of water quality indicator other than Total Dissolved Solids (TDS)
precludes a beneficial use;
the soil characteristic precludes a beneficial use; and
a groundwater quality restricted use zone (GRUZ) has been declared.
Away from the leachate plume groundwater within the MSA and BFA aquifers falls within
segment A2, as characterised by the site TDS concentrations. Segment A2 applies to
groundwaters with a salinity range of 500 mg/L to 1,000 mg/L. The segment is consistent to that
determined by Lane Piper (2010a), “Environmental Audit Report (Groundwater - 2010) - 210
Cape Nelson Road, Portland”. (There are isolated instances in which the salinity of monitoring
bores slightly below 500 mg/L. An example is PO14 for which the salinity was 480 mg/L in the
April 2015 monitoring event).
Groundwater within the NVA falls within segment B based upon the records of monitoring bore
PO25. The salinity at this bore ranges between 1,000 mg/L and 1,100 mg/L.
Table 3 of the SEPP (Groundwaters of Victoria) specifies the water quality criteria required to
protect these beneficial uses. The protected beneficial uses and applicable water quality
guideline values for this segment are listed in Table 6-1.
Table 6-1: Water quality criteria for groundwater
Beneficial use category Applicable water quality criteria
Potable water supply
(acceptable)
The NH&MRC (2011) “Australian Drinking Water Guidelines”
replace the former 2004 guidelines. Table 10.5 of the guidelines
include both human health and aesthetic guideline values for
physical and chemical characteristics.
Maintenance of aquatic
ecosystems
Government of Victoria (2003) “SEPP (Variation to Waters of
Victoria)” applies and the water quality guidelines are found in
Chapter 2 of ANZECC (2000), “Australian and New Zealand
Guidelines for Fresh and Marine Water Quality”.
Table A4 of the “SEPP (Variation to Waters of Victoria)” sets the
environmental quality objectives for metal, non-metal, ammonia,
and sulphides within the water column of rivers and streams at
95% of species (level of protection) for the Murray and Western
Plains Segment. This means that the water quality objective
should be met 95% of the time. The environmental quality
objectives for non-metals are 95% in urban areas and 99%
outside of urban areas.
The freshwater trigger values at 95% and 99% are obtained from
Table 3.4.1 of ANZECC (2000) “Australian and New Zealand
Guidelines for Fresh and Marine Water Quality”.
May 2016
Page 47
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Beneficial use category Applicable water quality criteria
Potable mineral water supply Food Standards Australia New Zealand (2014)”Australia New
Zealand Food Standards Code - Standard 2.6.2 - Non-Alcoholic
Beverages and Brewed Soft Drinks”.
Agriculture, parks and gardens ANZECC (2000) “Australian and New Zealand Guidelines for Fresh
and Marine Water Quality Guideline”. Section 4.2 - Water Quality
for Irrigation and General Water Use.
Stock watering ANZECC (2000) “Australian and New Zealand Guidelines for Fresh
and Marine Water Quality Guideline”, Section 4.3 - Livestock
Drinking Water Quality.
Industrial water use ANZECC (1992) “Australian Water Quality Guidelines for Fresh
and Marine Waters”, Chapter 5.
[Note: ANZECC (2000) “Australian and New Zealand Guidelines
for Fresh and Marine Water Quality” does not provide specific
guidance for industrial water use because industrial water
requirements are so varied (both within and between industries)].
Primary contact recreation NHMRC (2008) “Guidelines for Managing Risks in Recreational
Water”, Section 9 - Chemical Hazards.
Buildings and structures Australian Standard (2009) “AS2159-2009 Piling – Design and
Installation”, Table 6.4.2.
The water quality guideline values for indicator parameters are presented in Table 6-2.
Table 6-2: Groundwater environmental quality standards guideline values (triggers)
Indicator Unit AWDG
(2011)
Health
AWDG
(2011)
Aesthetic
ANZECC
(2000)
EcoSystem
Fresh Water
(95%)
ANZECC
(2000)
Agriculture
Parks and
Gardens
ANZECC
(2000)
Stock
watering
NHMRC
(2008)
Recreation
al Waters
pH - - 6.0-8.5 6.0-8.5 6.0-8.5
total dissolved solids mg/L - 600 2,000 2,500
ammonia mg/L - 0.5 0.9 5.0
nitrate (as N) mg/L 11.3 - 0.16 90.3 113
nitrate (as NO3) mg/L 50 - 0.7 400 500
chloride mg/L 250 2,500
sulphate mg/L 500 250 2,000
sodium mg/L 180 1,800
calcium mg/L 1,000
magnesium mg/L 2,000
Arsenic III mg/L 0.01 NA 0.0240(1)
cadmium mg/L 0.002 NA 0.0002
copper mg/L 2 1 0.0013
Lead mg/L 0.01 NA 0.0044
Zinc mg/L NA 3 0.0150
Nickel mg/l 0.02 NA 0.0110
Selenium mg/L 0.01 NA 0.0110
May 2016
Page 48
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
The NHMRC (2008) “Guidelines for Managing Risks in Recreational Water” advise that
environmental quality standards for chemicals in recreational waters should assume that
recreational water makes only a relatively minor contribution of drinking water consumption,
and that 10% is of the correct order. Based upon this advice the NH&MRC (2011) “Australian
Drinking Water Guidelines” guideline concentrations, including aesthetic, are multiplied by 10
times for recreational waters.
The Lane Piper (2010a) Groundwater Audit reviewed monitoring data from 2009 to 2010 and
drew conclusions with respect to whether these applicable beneficial uses are precluded due
to contamination and whether the use is likely. These conclusions have been reviewed based
upon the further development of the conceptual model and more recent monitoring data.
The precluded and likely uses are presented in Table 6-3 together with a commentary.
Where beneficial uses could be realised down-gradient of the site, although the use is
precluded in the immediate vicinity of the landfill, an appropriate management regime is
required to avoid impacts on bores currently operating or potentially installed in the future for
an intended use.
6.1.3 Air quality
The SEPP (Air Quality Management) beneficial uses are as follows:
life, health and wellbeing of humans;
life, health and wellbeing of other forms of life, including the protection of ecosystems
and biodiversity;
local amenity and aesthetic enjoyment;
visibility;
the useful life and aesthetic appearance of buildings, structures, property and materials;
and
climate systems that are consistent with human development, the life, health and
wellbeing of humans, and the protection of ecosystems and biodiversity.
6.1.4 Land
Based upon the site’s zoning and the down-gradient zoning, the SEPP (Prevention and
Management of Contaminated Land) the land segments requiring protection are
recreational/open space and sensitive use. The beneficial uses to be protected are:
modified and highly modified ecosystems;
human health;
buildings and structures; and
aesthetics.
6.1.5 Noise
The EPA (2011d) “Noise from Industry in Regional Victoria Recommended Maximum Noise
Levels from Commerce, Industry and Trade Premises in regional Victoria” provide the methods
to set noise levels for industry in regional Victoria. They provide a balance between protecting
community wellbeing and amenity near industrial premises and supporting the social and
economic value of industry in regional Victoria.
Ma
y 2
01
6
Pa
ge
49
Po
rtla
nd
La
nd
fill
- 2
10 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d
Se
ctio
n 5
3V
Au
dit
No
lan
Co
nsu
ltin
g P
ty L
td
67
14
1-5
_a
.do
cx
Tab
le 6
-3:
Su
mm
ary
of g
rou
nd
wa
ter
be
ne
fic
ial u
se a
sse
ssm
en
t
Be
ne
fic
ial u
se
ca
teg
ory
Pro
tec
ted
Be
ne
fic
ial
Use
s o
f th
is
Gro
un
dw
ate
r
Se
gm
en
t
Precluded
Use
C
om
me
nta
ry
Existing
Likely to be
realised
Unlikely to be
realised
Po
tab
le
wa
ter
sup
ply
–a
cc
ep
tab
le
√
No
√
This
be
ne
fic
ial u
se is
no
t p
rec
lud
ed
aw
ay f
rom
th
e le
ac
ha
te p
lum
e.
The
ba
ckg
rou
nd
wa
ter
qu
alit
y is
ge
ne
rally
with
in t
he
gu
ide
line
va
lue
s fo
r p
ota
ble
wa
ter
sup
ply
(h
ea
lth
).
This
use
is
un
like
ly t
o b
e r
ea
lise
d a
s it is
ass
um
ed
th
at
a r
etic
ula
ted
su
pp
ly is
ava
ilab
le t
o
ne
arb
y r
esi
de
nts
.
Ma
inte
na
nc
e
of
aq
ua
tic
ec
osy
ste
ms
√
Ye
s √
This
be
ne
fic
ial u
se is
pre
clu
de
d.
Ma
ny o
f th
e c
on
tam
ina
nts
in t
he
ba
ckg
rou
nd
gro
un
dw
ate
r e
xc
ee
d m
ain
ten
an
ce
of
aq
ua
tic
ec
osy
ste
m g
uid
elin
e v
alu
es.
Ch
rom
ium
, c
op
pe
r, z
inc
an
d n
itra
te h
ave
be
en
rep
ort
ed
at
co
nc
en
tra
tio
ns
ab
ove
th
e g
uid
elin
e v
alu
es
in o
ne
or
mo
re b
ore
s.
This
is
an
exi
stin
g u
se a
s g
rou
nd
wa
ter
na
tura
lly d
isc
ha
rge
s to
re
ce
ivin
g w
ate
rs.
Po
tab
le
min
era
l w
ate
r
sup
ply
√
Ye
s
√
This
be
ne
fic
ial u
se is
pre
clu
de
d.
Gro
un
dw
ate
r d
oe
s n
ot
co
nfo
rm t
o t
he
po
tab
le m
ine
ral w
ate
r d
efin
itio
n. In
its
na
tura
l sta
te
it d
oe
s n
ot
co
nta
in s
uff
icie
nt
CO
2 a
nd
oth
er
solu
ble
ma
tte
r to
ca
use
eff
erv
esc
en
ce
or
imp
art
a d
istin
ctive
ta
ste
[SEP
P (
Gro
un
dw
ate
rs o
f V
icto
ria
)].
Ag
ric
ultu
re,
pa
rks
an
d
ga
rde
ns
√
No
√
Th
is b
en
efic
ial u
se is
no
t p
rec
lud
ed
.
Mo
st c
on
tam
ina
nt
co
nc
en
tra
tio
ns
are
be
low
th
e g
uid
elin
e c
rite
ria
, w
ith
th
e e
xce
ptio
n o
f
ele
va
ted
sa
linity c
on
ce
ntr
atio
ns
with
in t
he
plu
me
.
This
be
ne
fic
ial u
se c
ou
ld b
e r
ea
lise
d in
th
e v
icin
ity o
f th
e s
ite
.
Sto
ck
wa
terin
g
√
No
√
Th
is b
en
efic
ial u
se is
no
t p
rec
lud
ed
.
Mo
st c
on
tam
ina
nt
co
nc
en
tra
tio
ns
are
be
low
th
e g
uid
elin
e c
rite
ria
, w
ith
th
e e
xce
ptio
n o
f
ele
va
ted
sa
linity a
nd
nitra
te c
on
ce
ntr
atio
ns
with
in t
he
plu
me
.
Ma
y 2
01
6
Pa
ge
50
Po
rtla
nd
La
nd
fill
- 2
10 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d
Se
ctio
n 5
3V
Au
dit
No
lan
Co
nsu
ltin
g P
ty L
td
67
14
1-5
_a
.do
cx
Be
ne
fic
ial u
se
ca
teg
ory
Pro
tec
ted
Be
ne
fic
ial
Use
s o
f th
is
Gro
un
dw
ate
r
Se
gm
en
t
Precluded
Use
C
om
me
nta
ry
Existing
Likely to be
realised
Unlikely to be
realised
This
be
ne
fic
ial u
se c
ou
ld b
e r
ea
lise
d in
th
e v
icin
ity o
f th
e s
ite
, n
ec
ess
ita
tin
g a
n a
pp
rop
ria
te
ma
na
ge
me
nt
reg
ime
to
av
oid
imp
ac
ts o
n n
ea
rby b
ore
s c
urr
en
tly o
pe
ratin
g o
r p
ote
ntia
lly
inst
alle
d in
th
e f
utu
re.
Ind
ust
ria
l
wa
ter
use
√
Ye
s
√
This
be
ne
fic
ial u
se is
pre
clu
de
d.
Gro
un
dw
ate
r is
un
like
ly t
o b
e u
sed
fo
r in
du
stria
l a
s th
e r
eq
uire
d s
alin
ity f
or
mo
st u
ses
is a
t o
r
be
low
th
e b
ac
kg
rou
nd
gro
un
dw
ate
r sa
linity p
urp
ose
s (<
10
0 m
g/L
fo
r th
e t
extile
ind
ust
ry).
This
be
ne
fic
ial u
se is
un
like
ly t
o b
e r
ea
lise
d in
th
e v
icin
ity o
f th
e s
ite
.
Prim
ary
co
nta
ct
rec
rea
tio
n
√
No
√
This
be
ne
fic
ial u
se is
no
t p
rec
lud
ed
aw
ay f
rom
th
e le
ac
ha
te p
lum
e.
This
be
ne
fic
ial u
se r
ela
tes
to t
he
use
of
gro
un
dw
ate
r to
fill
sw
imm
ing
po
ols
, o
r a
wa
ter
bo
dy
wh
ich
is in
pa
rt f
ed
by g
rou
nd
wa
ter
an
d m
ay b
e u
sed
fo
r sw
imm
ing
. R
esi
de
ntia
l pro
pe
rtie
s
are
with
in 1
00
m f
rom
th
e s
ite
to
th
e s
ou
th a
nd
25
0 m
fro
m t
he
site
to
th
e n
ort
h.
Fa
wth
rop
La
go
on
an
d W
att
le H
ill C
ree
k a
re a
bo
ut
1.7
km
fro
m t
he
no
rth
ern
site
bo
un
da
ry
an
d a
bo
ut
1.3
km
fro
m t
he
plu
me
fro
nt.
Am
mo
nia
(N
) c
on
ce
ntr
atio
ns
exc
ee
d t
his
be
ne
fic
ial u
se g
uid
elin
e c
rite
ria
in s
eve
n o
f th
e b
ore
s te
ste
d.
Tho
se b
ore
s re
po
rtin
g t
he
mo
st e
leva
ted
am
mo
nia
(N
) c
on
ce
ntr
atio
ns
(PO
06
an
d P
O0
7)
are
loc
ate
d c
lose
to
lan
dfill.
The
re
alis
atio
n o
f th
is b
en
efic
ial u
se is
un
like
ly b
ut
po
ssib
le.
Bu
ildin
gs
an
d
stru
ctu
res
√
No
√
Th
is b
en
efic
ial u
se is
no
t p
rec
lud
ed
.
The
so
ils a
re c
on
sid
ere
d li
ke
ly t
o b
e m
ild t
o n
on
-ag
gre
ssiv
e w
ith
re
spe
ct
to t
he
ir e
ffe
ct
on
co
nc
rete
pile
s, t
he
pH
is
alw
ays
ab
ove
6.0
, a
nd
th
e c
hlo
rid
e a
nd
su
lph
ate
co
nc
en
tra
tio
ns
are
we
ll b
elo
w 6
,000
mg
/L a
nd
1,0
00
mg
/L r
esp
ec
tive
ly. (S
ee
Ta
ble
9.1
of
Au
stra
lian
Sta
nd
ard
AS2
15
9-2
009
Pili
ng
– D
esi
gn
an
d In
sta
llati
on
).
May 2016
Page 51
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
The guidelines set out recommended maximum noise levels which can be applied to manage
the impacts of noise from the landfill on the community taking into account the landfill and
surrounding land is zoned PPRZ, RCZ1, FZ and PUZ5.
For a Public Use Zone as the generating zone to a Rural Conservation Zone (RCZ) as the most
sensitive receiving zone, the noise levels under EPA (2011d) are:
day 45 dBA (7.00 am to 6.00 pm (Monday to Friday) and to 1.00 pm on Saturday)
evening 37 dBA (6.00 pm to 10.00 pm (Monday to Friday) and from 1.00 pm on Saturday)
night 32 dBA (all other hours)
Day time limits apply at all operation times except from 1.00 pm to 4.30 pm on Saturday when
the evening limits apply and on Sunday when the night lime limits apply. After 1.00 pm on
Saturdays and on Sundays the transfer station is operated with no municipal loads being
received.
6.2 Risk assessment method
The EPA (2011b) Landfill Licensing Guidelines require an environmental risk assessment to be
prepared that identifies and evaluates the potential risks of landfill operations to the
environment. The risk assessment is required to inform the landfill Monitoring Program. The
approach to risk assessment is described in Section 4 of the EPA (2011a) Licence Assessment
Guidelines. It involves the following steps:
establishing the context of the risk assessment;
identifying risks (environmental aspects); and
risk analysis (including development of a risk register).
6.2.1 Risk assessment matrices
Two risk assessment matrices are applied. One is applied to all risks except LFG and the other
to LFG only.
All risks except for LFG
The EPA (2011a) Licence Assessment Guidelines qualitative risk assessment framework is
applied to all risks except for LFG. The level of risk is a combination of the likelihood of a risk
event occurring and the consequence if it does.
The qualitative measure of likelihood is presented in Table 6-4.
Table 6-4: Qualitative measure of likelihood (all hazards except LFG)
Rating Indicator Description Frequency
5 Almost certain Multiple incidents recorded. Expected to occur almost all the time.
4 Likely Several incidents recorded. Is expected to occur most of the time.
3 Possible Some incidents have been
recorded. Might occur.
2 Unlikely Few incidents recorded. Might occur but not expected to.
1 Rare No recorded or known incidents. Only expected to occur under atypical
conditions.
The qualitative measures of consequence are provided in Table 6-5.
May 2016
Page 52
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Table 6-5: Qualitative measure of consequence (all hazards except LFG)
Level Descriptor Description
5 Severe Human deaths, operations cause catastrophic off-site impacts, immense
financial losses.
4 Significant Extensive human injuries, operations cause substantial off-site impacts,
major financial losses.
3 Medium Some health impacts to human, operations cause some external impacts,
large financial loss.
2 Minor First aid treatment, operations cause some minimal off-site impacts, small
financial loss.
1 Negligible Operations cause no injuries, negligible off-site impacts, and negligible
financial loss.
The level of risk is a combination of the likelihood of a risk occurring and the consequence of it
occurring. Using matrices in Table 6-4 and Table 6-5, the level of risk posed is presented in
Table 6-6.
Table 6-6: Qualitative risk assessment matrix (all hazards except LFG)
Likelihood Consequences
Severe (5) Significant (4) Medium (3) Minor (2) Negligible (1)
Almost certain (5) Very High Very High Very High Very High High
Likely (4) Very High Very High Very High High High
Probable (3) Very High High High Medium Medium
Not likely (2) High High Medium Low Low
Rare (1) High Medium Low Low Low
Legend:
Very High - immediate action required.
High risk - management required by senior staff.
Medium - specify required management.
Manage with standard operating procedure.
LFG risks
The UK Environment Agency (2004) “Guidance on the Management of Landfill Gas” LFG risk
assessment method has been adopted in preference to EPA (2011a) Licence Assessment
Guidelines as the UK guidelines recognise that when the likelihood is ‘extremely unlikely’ of ‘very
unlikely’ that the risk may be insignificant or acceptable even if the consequence is
catastrophic.
The LFG severity likelihood matrix is shown in Table 6-7 below.
May 2016
Page 53
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Table 6-7: Severity likelihood matrix for LFG hazards (UK Environment Agency; 2004)
Likelihood Severity of consequences
Minor Noticeable Significant Severe Major Catastrophic
Extremely unlikely 1 2 3 4 5 6
Very unlikely 2 4 6 8 10 12
Unlikely 3 6 9 12 15 18
Somewhat
Unlikely 4 8 12 16 20 24
Fairly probable 5 10 15 20 25 30
Probable 6 12 18 24 30 36
Notes on likelihood:
Extremely unlikely: Incident occurs less than once in a million years.
Very unlikely: Incident occurs between once per million and once every 10,000 years.
Unlikely: Incident occurs between once per 10,000 years and once every 100 years.
Somewhat unlikely: Incident occurs between once hundred years and once every 10 years.
Fairly probable: Incident occurs between once 10 years and once per year.
Probable: Incident occurs at least once per year.
Notes on consequence:
Minor: Nuisance on-site only (no off-site effects), no outside complaint.
Noticeable: Noticeable nuisance off-site e.g. discern odours, minor breach of permitted emission
limits, but no environmental harm. One or two complaints from the public.
Significant: Sustained nuisance, e.g. offensive odours, several breach of permitted emissions limits with
possibility of prosecution, and numerous public complaints.
Severe: Severe and sustained nuisance, e.g. strong offensive odours, major breach of permitted
emissions limits with possibility of prosecution, and numerous public complaints.
Major: Evacuation of local populace, temporary disabling and hospitalisation, serious toxic effect on
beneficial or protected species, widespread but not persistent damage to land.
Catastrophic: Major airborne release with serious off-site effects. Site shutdown.
The magnitude of the risks against the scores presented in Table 6-7 and are shown in Table 6 8.
Table 6-8: LFG Magnitude of risk (UK Environment Agency; 2004)
Magnitude of Risk Score
Insignificant 6 or less
Acceptable 8 to 12
Unacceptable 15 or more
6.2.2 Environmental aspects
The risk register considers aspects and hazards associated with the following elements:
water;
groundwater;
air;
land;
May 2016
Page 54
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
vegetation;
noise; and
aesthetics.
6.2.3 Risk register
For each of the identified aspects/hazards the updated risk register identifies:
environment element;
pathways for risk(factors influencing the likelihood of the risk occurring);
receptors;
location (on-site or off-site);
potential environmental impacts (description of impacts should the risk occur);
existing controls (controls in place to prevent or mitigate the risk);
likelihood of hazard (likelihood of the risk occurring); and
consequence/severity (consequence of the risk occurring including receptor impact).
6.3 Updated landfill register
The Portland Landfill Risk Assessment Register (updated May 2016) is presented in full in
Appendix F and in a comprehensive summary form in Table 6-9 for all non-LFG risks greater than
low and all LFG risk that are greater than insignificant. In updating the register consideration
has been given to the risk assessment undertaken by Cardno (2015b), “Hydrogeological
Assessment for Leachate Level Management - Portland Landfill 210 Cape Nelson Road,
Portland, Vic”.
The risk profile has not changed significantly from that presented in Nolan Consulting (2014).
This reflects only minor refinements to the conceptual site model, and generally consistent
monitoring results.
6.4 Compliance risk register
The Portland Landfill Compliance Risk Assessment Register (updated May 2016) has been
prepared (Appendix G of this audit report) to assess the environmental risks associated with site
operational activities as they relate to licence requirements and the criteria presented
EPA (2015a) Landfill BPEM.
Ma
y 2
01
6
Pa
ge
55
Po
rtla
nd
La
nd
fill
- 2
10 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d
Se
ctio
n 5
3V
Au
dit
No
lan
Co
nsu
ltin
g P
ty L
td
67
14
1-5
_a
.do
cx
Tab
le 6
-9:
Ris
k A
sse
ssm
en
t su
mm
ary
ta
ble
En
viro
nm
en
tal
Ele
me
nt
En
viro
nm
en
tal
Asp
ec
ts /
Ha
zard
s
(So
urc
e)
Pa
thw
ay
s R
ec
ep
tors
P
ote
ntia
l En
viro
nm
en
tal
Imp
ac
ts
Ex
istin
g
Co
ntr
ol
Lik
e
lih
oo
d
Co
nse
qu
en
ce
Ris
k L
eve
l
&Sc
ore
Su
rfa
ce
wa
ter
Su
rfa
ce
wa
ter
Co
nta
min
atio
n
by le
ac
ha
te /
sed
ime
nt.
Su
rfa
ce
ru
n o
ff.
Su
rfa
ce
wa
ters
. D
etr
ime
nt
to s
urf
ac
e
wa
ters
(i.e
. a
qu
atic
ec
osy
ste
ms)
.
No
ne
2
4
M
ed
ium
Gro
un
dw
ate
r.
De
trim
en
t to
su
rfa
ce
wa
ters
(i.e
. a
qu
atic
ec
osy
ste
ms)
.
LIS
2
4
Me
diu
m
Gro
un
dw
ate
r
Gro
un
dw
ate
r C
on
tam
ina
tio
n
by le
ac
ha
te.
Ac
tive
wa
ste
ce
ll.
Gro
un
dw
ate
r.
Co
nta
min
atio
n (
on
-site
&
off
-site
).
No
ne
. 5
4
V
ery
Hig
h
Gro
un
dw
ate
r u
sers
(extr
ac
tive
).
Co
nta
min
atio
n (
off
-site
).
3
4
Hig
h
Inc
rea
sed
lea
ch
ate
le
ve
l
in r
ete
ntio
n
po
nd
s.
Un
satu
rate
d
zon
e.
Gro
un
dw
ate
r.
Co
nta
min
atio
n (
on
-site
).
No
ne
. 2
4
M
ed
ium
Co
nta
min
atio
n
by le
ac
ha
te.
Un
satu
rate
d
zon
e.
Gro
un
dw
ate
r.
Co
nta
min
atio
n (
on
-site
&
off
-site
).
LIS
5
4
Ve
ry H
igh
LFG
mig
ratio
n.
Un
satu
rate
d
zon
e.
Gro
un
dw
ate
r.
Co
nta
min
atio
n (
on
-site
).
No
ne
. 5
3
V
ery
Hig
h
LFG
Air
LFG
mig
ratio
n.
Un
satu
rate
d
Zo
ne
.
Oc
cu
pa
nts
of
bu
ildin
gs
(on
-site
).
De
ath
or
serio
us
inju
ry d
ue
to e
xp
losi
on
.
2
6
A
cc
ep
tab
le
Wo
rke
rs (
e.g
. Sta
ff,
ma
inte
na
nc
e,
etc
.) (
on
sit
e).
Asp
hyxia
tio
n d
ue
to
dis
pla
ce
me
nt
of
oxyg
en
to b
elo
w 1
9.5
% b
y L
FG
.
No
ne
. 3
6
U
na
cc
ep
tab
le
Ma
y 2
01
6
Pa
ge
56
Po
rtla
nd
La
nd
fill
- 2
10 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d
Se
ctio
n 5
3V
Au
dit
No
lan
Co
nsu
ltin
g P
ty L
td
67
14
1-5
_a
.do
cx
En
viro
nm
en
tal
Ele
me
nt
En
viro
nm
en
tal
Asp
ec
ts /
Ha
zard
s
(So
urc
e)
Pa
thw
ay
s R
ec
ep
tors
P
ote
ntia
l En
viro
nm
en
tal
Imp
ac
ts
Ex
istin
g
Co
ntr
ol
Lik
e
lih
oo
d
Co
nse
qu
en
ce
Ris
k L
eve
l
&Sc
ore
De
ath
or
serio
us
inju
ry d
ue
to e
xp
losi
on
.
No
ne
. 3
6
U
na
cc
ep
tab
le
H
um
an
s /
Re
sid
en
ts
(off
site
).
Asp
hyxia
tio
n d
ue
to
dis
pla
ce
me
nt
of
oxyg
en
to b
elo
w 1
9.5
% b
y L
FG
.
No
ne
. 2
6
A
cc
ep
tab
le
M
ain
ten
an
ce
/
co
nst
ruc
tio
n
wo
rke
r in
tre
nc
h /
pits
(off
site
).
Asp
hyxia
tio
n d
ue
to
dis
pla
ce
me
nt
of
oxyg
en
to b
elo
w 1
9.5
% b
y L
FG
.
No
ne
. 2
6
A
cc
ep
tab
le
In
fra
stru
ctu
re (
on
-
site
).
Da
ma
ge
to
in
fra
stru
ctu
re
du
e t
o e
xp
losi
on
or
co
rro
sio
n.
No
ne
. 4
3
A
cc
ep
tab
le
Air
LFG
in
un
de
rgro
un
d
serv
ice
s.
Un
satu
rate
d
zon
e (
serv
ice
tre
nc
he
s).
Oc
cu
pa
nts
of
bu
ildin
gs
(on
site
).
Asp
hyxia
tio
n d
ue
to
dis
pla
ce
me
nt
of
oxyg
en
to b
elo
w 1
9.5
% b
y L
FG
.
No
ne
. 2
6
A
cc
ep
tab
le
De
ath
or
serio
us
inju
ry d
ue
to e
xp
losi
on
.
2
6
Ac
ce
pta
ble
Wo
rke
rs (
e.g
. Sta
ff,
ma
inte
na
nc
e,
etc
.) (
on
sit
e).
Asp
hyxia
tio
n d
ue
to
dis
pla
ce
me
nt
of
oxyg
en
to b
elo
w 1
9.5
% b
y L
FG
.
3
6
Un
ac
ce
pta
ble
De
ath
or
serio
us
inju
ry d
ue
to e
xp
losi
on
.
3
6
Un
ac
ce
pta
ble
Hu
ma
ns
/ R
esi
de
nts
(off
site
).
De
ath
or
serio
us
inju
ry d
ue
to e
xp
losi
on
.
2
6
Ac
ce
pta
ble
Ma
inte
na
nc
e /
co
nst
ruc
tio
n
wo
rke
r in
tre
nc
h /
pits
(off
site
).
Asp
hyxia
tio
n d
ue
to
dis
pla
ce
me
nt
of
oxyg
en
to b
elo
w 1
9.5
% b
y L
FG
.
2
6
Ac
ce
pta
ble
Ma
y 2
01
6
Pa
ge
57
Po
rtla
nd
La
nd
fill
- 2
10 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d
Se
ctio
n 5
3V
Au
dit
No
lan
Co
nsu
ltin
g P
ty L
td
67
14
1-5
_a
.do
cx
En
viro
nm
en
tal
Ele
me
nt
En
viro
nm
en
tal
Asp
ec
ts /
Ha
zard
s
(So
urc
e)
Pa
thw
ay
s R
ec
ep
tors
P
ote
ntia
l En
viro
nm
en
tal
Imp
ac
ts
Ex
istin
g
Co
ntr
ol
Lik
e
lih
oo
d
Co
nse
qu
en
ce
Ris
k L
eve
l
&Sc
ore
Air
Em
issi
on
of
tra
ce
co
mp
on
en
ts –
toxic
ga
ses
(H2S).
Am
bie
nt
air.
Oc
cu
pa
nts
of
bu
ildin
gs
(on
site
).
Ch
ron
ic h
ea
lth
ris
k –
sta
ff,
ma
inte
na
nc
e w
ork
ers
(o
n-
site
).
Co
ntr
ol o
f
wa
ste
stre
am
in
ac
co
rda
nc
e
with
lan
dfill
lice
nc
e.
3
3
Ac
ce
pta
ble
Air
Fu
gitiv
e L
FG
. A
mb
ien
t a
ir.
Infr
ast
ruc
ture
–
tra
nsm
issi
on
to
we
r
(ab
ove
gro
un
d).
(on
-sit
e).
Co
rro
sio
n o
f in
fra
stru
ctu
re.
No
ne
. 5
2
A
cc
ep
tab
le
Lan
d
Un
satu
rate
d
zon
e
(Ad
ve
ctive
or
diffu
sive
flo
w).
Infr
ast
ruc
ture
–
tra
nsm
issi
on
to
we
r
(su
b-s
urf
ac
e)
(on
-
site
).
4
2
Gro
un
dw
ate
r P
art
itio
nin
g o
f
LFG
–
gro
un
dw
ate
r.
Gro
un
dw
ate
r
flo
w t
hro
ug
h
aq
uife
r.
Infr
ast
ruc
ture
–
bu
ildin
gs,
un
de
rgro
un
d
serv
ice
s, f
en
ce
s
(on
sit
e).
Co
rro
sio
n o
f u
nd
erg
rou
nd
infr
ast
ruc
ture
.
No
ne
. 2
6
A
cc
ep
tab
le
Pa
rtitio
nin
g
fro
m le
ac
ha
te
or
gro
un
dw
ate
r
resu
ltin
g in
va
po
ur
intr
usi
on
.
Oc
cu
pa
nts
of
bu
ildin
gs
(on
site
).
De
ath
or
serio
us
inju
ry d
ue
to e
xp
losi
on
.
No
ne
2
6
A
cc
ep
tab
le
Ve
ge
tatio
n
Fu
gitiv
e L
FG
. U
nsa
tura
ted
zon
e (
i.e.
Ad
ve
ctive
or
diffu
sive
flo
w).
Ve
ge
tatio
n (
on
-
site
.).
Da
ma
ge
to
ve
ge
tatio
n.
No
ne
. 4
3
A
cc
ep
tab
le
Ma
y 2
01
6
Pa
ge
58
Po
rtla
nd
La
nd
fill
- 2
10 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d
Se
ctio
n 5
3V
Au
dit
No
lan
Co
nsu
ltin
g P
ty L
td
67
14
1-5
_a
.do
cx
En
viro
nm
en
tal
Ele
me
nt
En
viro
nm
en
tal
Asp
ec
ts /
Ha
zard
s
(So
urc
e)
Pa
thw
ay
s R
ec
ep
tors
P
ote
ntia
l En
viro
nm
en
tal
Imp
ac
ts
Ex
istin
g
Co
ntr
ol
Lik
e
lih
oo
d
Co
nse
qu
en
ce
Ris
k L
eve
l
&Sc
ore
Od
ou
r
Od
ou
r P
rese
nc
e o
f
toxic
ga
ses
(H2S).
Am
bie
nt
air –
od
ou
r
imp
ac
tin
g
bre
ath
ing
spa
ce
s.
Wo
rke
rs (
e.g
. Sta
ff,
ma
inte
na
nc
e,
etc
.) (
on
-sit
e).
Ch
ron
ic h
ea
lth
ris
k –
sta
ff,
ma
inte
na
nc
e w
ork
ers
.
No
ne
. 3
2
M
ed
ium
Lan
d
Lan
d
Co
nta
min
atio
n
by le
ac
ha
te
an
d /
or
LFG
co
nd
en
sate
.
Un
satu
rate
d
zon
e.
Infr
ast
ruc
ture
–
tra
nsm
issi
on
to
we
r
foo
tin
g (
on
-site
).
Co
rro
sio
n o
f in
fra
stru
ctu
re.
No
ne
. 2
4
M
ed
ium
C
on
tam
ina
tio
n
by le
ac
ha
te.
Ove
rfill
ing
of
lea
ch
ate
sto
rag
e d
am
.
Lan
d (
soil)
(o
n-s
ite
).
Co
nta
min
atio
n –
la
nd
. N
on
e.
2
4
Me
diu
m
No
ise
So
un
d
Ma
ch
ine
ry /
Eq
uip
me
nt
/
Tra
ffic
.
Am
bie
nt
air.
Wo
rke
rs,
(e.g
. Sta
ff,
ma
inte
na
nc
e,
etc
.) (
on
-sit
e).
Ae
sth
etic
. P
PE –
sa
fe
wo
rk
pro
ce
du
re.
2
3
Me
diu
m
Litt
er
Ae
sth
etic
s
Ae
sth
etic
s Li
tte
r.
Ac
tive
wa
ste
ce
ll.
Flo
ra &
Fa
un
a
(on
-sit
e).
Ae
sth
etic
s a
nd
vis
ibili
ty;
he
alth
of
fau
na
.
Da
ily c
ove
r.
3
2
Me
diu
m
Ac
tive
wa
ste
ce
ll –
win
db
low
n.
Wo
rke
rs (
e.g
. Sta
ff,
ma
inte
na
nc
e,
etc
.) (
on
-sit
e).
Ae
sth
etic
an
d v
isib
ility
. D
aily
co
ve
r
Re
gu
lar
site
ch
ec
ks.
3
2
Me
diu
m
Ma
y 2
01
6
Pa
ge
59
Po
rtla
nd
La
nd
fill
- 2
10 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d
Se
ctio
n 5
3V
Au
dit
No
lan
Co
nsu
ltin
g P
ty L
td
67
14
1-5
_a
.do
cx
En
viro
nm
en
tal
Ele
me
nt
En
viro
nm
en
tal
Asp
ec
ts /
Ha
zard
s
(So
urc
e)
Pa
thw
ay
s R
ec
ep
tors
P
ote
ntia
l En
viro
nm
en
tal
Imp
ac
ts
Ex
istin
g
Co
ntr
ol
Lik
e
lih
oo
d
Co
nse
qu
en
ce
Ris
k L
eve
l
&Sc
ore
Ae
sth
etic
s – D
ust
Ae
sth
etic
s D
ust
. A
mb
ien
t a
ir –
win
db
low
n.
Wo
rke
rs (
sta
ff,
ma
int.
) (o
n-s
ite
).
Ae
sth
etic
& v
isib
ility
. N
on
e.
3
2
Me
diu
m
Tra
ffic
/ro
ad
s.
Wo
rke
rs (
e.g
. Sta
ff,
ma
inte
na
nc
e,
etc
.) (
on
-sit
e).
3
2
Me
diu
m
Hu
ma
n
He
alth
Du
st.
Am
bie
nt
air –
win
db
low
n.
Hu
ma
ns
(off
-site
).
Ae
sth
etic
& v
isib
ility
. N
on
e.
3
2
Me
diu
m
Hu
ma
ns
(off
-site
).
3
2
Me
diu
m
Wo
rke
rs (
on
-site
).
3
2
Me
diu
m
Tra
ffic
/ro
ad
s.
Wo
rke
rs (
on
-site
).
3
2
Me
diu
m
Ve
rmin
Ae
sth
etic
s V
erm
in (
rats
,
bird
s, e
tc.)
Ac
tive
wa
ste
ce
lls.
Oc
cu
pa
nts
of
bu
ildin
gs
(on
-site
.)
Ve
cto
rs o
f d
ise
ase
. N
on
e.
3
2
Me
diu
m
Hu
ma
ns
at
an
d in
the
vic
inity o
f th
e
lan
dfill
(off
-site
).
3
2
Me
diu
m
Ve
ge
tatio
n
Ve
ge
tatio
n
Fire
. A
ctive
wa
ste
ce
ll.
Flo
ra &
Fa
un
a (
off
-
site
).
Da
ma
ge
to
flo
ra.
Fire
bre
aks.
2
3
M
ed
ium
W
ee
d
ma
na
ge
me
nt.
Site
an
d
ina
ctive
/
clo
sed
wa
ste
ce
lls.
Flo
ra &
fa
un
a in
vic
inity o
f la
nd
fill
(on
-sit
e).
Ae
sth
etic
an
d v
isib
ility
.
Da
ma
ge
to
loc
al f
lora
.
No
ne
. 3
2
M
ed
ium
Site
reh
ab
ilita
tio
n.
Flo
ra &
Fa
un
a (
off
-
site
).
Su
rfa
ce
wa
ter
run
off
.
Ero
sio
n o
f la
nd
fill
ca
p a
nd
exp
osu
re o
f b
urie
d w
ast
e.
No
ne
. 3
2
M
ed
ium
May 2016
Page 60
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
6.4.1 Information sources
The Auditor has inspected the site, undertaken interviews, and selectively reviewed existing
procedures and checklists. These documents include:
Environmental complaints register;
Checklists:
- Routine Inspection Contaminated Water Checklist (Weekly)
- Monitoring and Compliance Daily Checklist
- Monitoring and Compliance Monthly Checklist;
Safe Work Procedures (SWP) for transfer station operation – ventilation of buildings; and
Infrastructure corrosion inspections for May 2015, October 2015 and January 2016.
6.4.2 Monitoring and compliance checklists
The Routine Inspection Contaminated Water Checklist (Weekly) requires inspections of the
Leachate Interception Bores, compressor shed, flow to the leachate storage dam, leachate
storage dam water level and whether further action required.
The Monitoring and Compliance Monthly Checklist includes the following questions:
is there any
- rubbish outside of the boundary perimeter?
- internal windblown rubbish?
- any free laying water on-site?
- asbestos exposed?
- audible noise leaving the site?
- audible noise detectable at any Sensitive Receptor locations?
- vermin visible on-site?
- odour detectable on-site?
- odour at any Sensitive Receptor Locations?
- dust visible on or off-site?
- dust visible at Sensitive Receptor Locations?
is there
- a stock pile of material for daily cover that is sufficient for two weeks?
- ponding of water visible on-site?
- visible leachate anywhere on-site?
is the
- tipping face under 30m long and clear of obstructions?
- lift restricted to 2 m?
Green Waste Stockpiles satisfactory? (Must be under 2m high and 5m apart).
leachate pond in good condition (no cracks/erosion) and at a low depth?
has 300mm of daily cover been applied?
May 2016
Page 61
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
are the groundwater and LFG bores intact and easy to access?
The Monitoring and Compliance Daily Checklist checks whether the following are satisfactory:
perimeter cleanliness;
internal windblown rubbish;
clearance of litter screens;
transfer area / skip condition ;
tip face area under 30 m long and clear of obstructions;
has 300 mm of cover been applied;
asbestos covered;
free laying water on-site;
audible noise, detectable odour, visible dust, visible vermin; and
green waste, concrete, tyre, recyclable steel and timber stockpiles, and recycle shop in
satisfactory condition.
The Facility Maintenance Co-ordinator undertakes the Routine Inspection Contaminated
Water Checklist (Weekly).
Either the Weighbridge Attendant or the Compactor Operator undertakes the daily inspection
and completes the compliance checklist. The Resources Management Officer undertakes the
monthly inspection.
The Auditor witnessed copies of all completed contaminated water checklist, daily and
monthly landfill monitoring and compliance checklists for March, April, June, September and
December 2015.
6.4.3 Observations on landfill practices and procedures
The following observations on landfill practices and procedures were made during the audit.
Environmental complaints
GSC has a procedure for environmental complaints, maintains an environmental complaints
form, and keeps an up to date environmental complaints register.
Complaints received by Customer Services or the Resources Management Officer are
registered in GSC’s ECM data management system.
GSC advised that no complaints were received over the audit period.
Inspections for corrosion
The GSC Resource Management Officer has initiated a quarterly inspection of the site
infrastructure for evidence of corrosion. Photographs are taken at these inspections. A
procedure is now required to report on the findings.
Inspection checklists
The monthly inspections are undertaken at the required frequency. The daily inspections are
generally undertaken from Monday to Friday. There are however gaps. There were only four
daily inspection reports provided for December 2015. This may be related to senior
management staffing changes.
In April 2015 daily inspections were undertaken on one Friday only, and one Saturday only.
May 2016
Page 62
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
The checklists are prepared by the appropriate officer, are submitted to the GSC Resource
Management Officer, are checked, and then scanned and stored.
The checklists are yet to be modified to fully satisfy the Cat A monitoring requirements, and in
particular to identify the locality where observations are made.
Daily cover
The monitoring and compliance daily checklist includes a requirement to advise on whether
300 mm of daily cover has been placed. The inspection for daily cover now occurs at the end
of the day.
There were several occurrences of less than 300 mm of cover being placed due to a lack of
availability. This was noted in the 2014/15 Annual Performance Statement.
Visual inspections
Visual inspection records are not maintained at the weighbridge.
6.4.4 The register
The Portland Landfill Compliance Risk Assessment Register (updated May 2016) has been
prepared (Appendix G of this audit report). It identifies the type of monitoring required for each
licence condition where applicable, the timing and frequency of the monitoring, and the
QA/QC measures.
May 2016
Page 63
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
7. Assessment of monitoring program implementation
This section of the audit assesses progress with implementing the verified environment
Monitoring Program. The assessment draws upon site observations of the location and
installation of monitoring infrastructure and of groundwater, leachate and LFG monitoring, a
review of monitoring infrastructure installation and monitoring reports, and discussions with GSC
and GHD as the contractor engaged to undertaken the monitoring.
7.1 The verified program
The verified Monitoring Program is provided in Section 10 of the Nolan Consulting (2014)
“Section 53V Audit – Landfill Operation, Portland Landfill – 210 Cape Nelson Road Portland”.
The Monitoring Program includes sections on:
roles and responsibilities;
Category A visual monitoring;
Category B monitoring of groundwater, leachate and LFG; and
environment audit program.
Definitions of the Category A and Category B monitoring programs are as follows:
Cat A: Regular or incident driven inspections by trained GSC staff, reporting of visual
inspection observations, and the implementation of mitigation measures where non-
compliances observed.
Cat B: Sampling and testing based programs with on-site and laboratory testing. These
programs also require reporting and adherence to QA/QC procedures.
The category of monitoring required for each environmental element is presented in Table 7-1.
Table 7-1: Status of monitoring types for each environmental element
Environmental Element Type A monitoring Type B Monitoring
Required Regular
frequency
Required Addressed in the
environmental
monitoring
contract
Surface water √ Weekly × NA
Groundwater/leachate × NA √ Generally
Air – LFG √
Quarterly
(Plant stress only) √
Yes, except for
landfill surface
Air – Odour √ Daily × NA
Air - Climate × NA × Covered in LFG
Land × NA × NA
Noise √ Weekly × NA
Aesthetics – Litter √ Daily/Weekly × NA
Aesthetics – Dust √ Weekly × NA
Aesthetics – Vermin √ Fortnightly × NA
Vegetation √ Quarterly × NA
Corrosion √ Quarterly × NA
May 2016
Page 64
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
7.2 Assessment of implementation
The assessment presented below addresses both the Category A and Category B programs
over July 2014 to December 2015audit period.
7.2.1 Cat A monitoring
The required Cat A monitoring activity is observation (visual and olfactory) and must be
undertaken by trained staff. The verified monitoring program requires evidence of the
observations to be reported.
Progress with the implementation of the Cat A monitoring is presented in Table 7-2.
Table 7-2: Progress with implementation of Cat A Monitoring
Aspect Finding Required
frequency
Progress
Training Variable During the audit period staff training has included
asbestos awareness, first aid, and resource
recovery.
Verbal on-site advice is provided by senior
officers.
Formal training of all officers in identification of
environmental issues including ‘calibration’ for
odour monitoring is yet to be undertaken.
Documentation of training needs identification
and records of training undertaken is required.
Observations Surface
water/leachate
Weekly Undertaken as part of the monthly compliance
checklist. Monitoring points not defined.
Air – Odour Daily Within site observations undertaken as part of the
daily compliance checklist. Need to extend this
to the site boundary.
Noise Weekly Off-site observations undertaken as part of the
daily compliance checklist.
Aesthetics – Litter Daily
/Weekly
Daily visual inspections of cover by Compactor
Operator. Daily boundary and on-site inspections
undertaken.
Aesthetics – Vermin Fortnightly Within site observations undertaken as part of the
monthly compliance checklist.
Vegetation Quarterly Plant health monitoring of the cap undertaken
by GHD.
Checklists Compliance checklists addresses most Cat A
monitoring requirements.
Reporting GSC maintains a complaints register.
The daily, weekly, and monthly compliance
checklists are scanned and stored electronically.
The checklists need to identify locations of
observations and follow up actions undertaken
to address any issues.
May 2016
Page 65
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
7.2.2 Cat B monitoring - records reviewed
The Category B program is undertaken by GHD.
The Cat B monitoring undertaken over the audit period is reported in GHD (2015b) “Portland
Landfill Annual Environmental Monitoring Results Report 2014/15” for the 2914/1`5 monitoring
events and in the laboratory results and data files for the 2015/16 monitoring events.
The monitoring events undertaken during the 18 month audit period are presented in Table 7-3.
Table 7-3: Cat B Monitoring undertaken
Element 2014/15 2015/16
22-25/7 28-31/10 02-06/2 28/4-01/5 4-6/8 28-30/10
Groundwater – General √ √ √ √ √ √
Groundwater -VOC and SVOC x x x √ x x
Leachate √ √ √ √ √ √
LFG - Bores and probes √ √ √ √ √ √
LFG - In-building & services √ √ √ √ √ √
LFG – Landfill surface X √ √ √ √ √
Plant stress/dieback survey √ √ √ √ √ √
The GHD (2015b) “Portland Landfill Annual Environmental Monitoring Results Report 2014/15”.
included the following:
groundwater and leachate purging and sampling records;
MGT Eurofins (primary laboratory) analytical results;
ALS (secondary laboratory) analytical results;
chain of custody forms;
tabulation of water quality results;
field water quality analysis calibration certificates;
water quality data QC reviews; and
LFG bore monitoring records.
7.2.3 Cat B Monitoring – Groundwater and leachate
Progress with the implementation of the groundwater monitoring subprogram as developed is
presented in Table 7-4. The assessment has focussed on the 28th April 2015 to 1st May 2015
monitoring events.
May 2016
Page 66
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Table 7-4: Progress with implementing groundwater and leachate monitoring subprogram
(Cat B)
Variables Description Compliance
Installation of
new monitoring
bores
Groundwater
New bores PO34A, PO34B, PO35A and PO35B
installed in September 2015.
Leachate
Bores LB01R and LB02RA installed in February 2015
and LB02R decommissioned.
Compliant
Upgrade of LIS
system
IB6 replaced with IB6R
IB4, IB5, and IB7 redeveloped.
All bores installed with new pumps, pulse counters
and level data loggers except for IB5 which does not
have a data logger.
Cumulative flow meter installed on LIS discharge line
near leachate storage dam.
Gauging board installed in leachate storage dam.
Leachate storage dam floor level and gauging board
datum surveyed.
Generally compliant
Install data logger in IB5.
Works completed by October
2015.
Level survey All bores surveyed to AHD except for new
groundwater bores PO34A, PO34B, PO35A and PO35B
and new leachate monitoring bores LB01R and
LB02RA.
Partially compliant
Survey all new bores.
Bore
maintenance
Bores inspected were locked.
Tree covering monitoring bore PO04 has not been
removed. (PO04 which was also covered by the tree
in the January and April 2015 monitoring events).
Surface casing of monitoring bore PO04 damaged as
of 7th March 2016.
Compliant
Monitoring
occurrence
Frequency
Quarterly monitoring was undertaken. The scheduling
was acceptable although the January 2015
monitoring event was undertaken in early February.
Generally compliant
Groundwater monitoring bores
All required groundwater bores with a sufficient water
volume for sampling was monitored except for PO04
which was covered and PO10, PO32, PO33A, PO33B
which were inundated with surface water on one to
two occasions.
Generally compliant
Leachate monitoring bores
All required leachate monitoring bores with a
sufficient water volume for sampling were monitored
except for leachate monitoring bore IB01 was
thought to be lost. It was found and monitored from
July 2014.
Complaint
Leachate Interception System
Interception bores IB4, IB5, IB6, IB7, and IB8 are
monitored for water quality. Pulse counters (for flow)
and data loggers (for level) installed but not reported
as yet.
Not compliant
Maintain flow meter.
Download data and include in
reporting.
May 2016
Page 67
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Variables Description Compliance
Flow meter on discharge line has failed.
Leachate storage dam level monitored as part of the
Routine Inspection Contaminated Water Checklist
(Weekly) weekly.
parameters Quarterly
(Jan,
Apr, Jul,
Oct)
Quarterly sampling and analysis
undertaken.
Compliant
Annually
Annual testing for SVOC and VOC screens
for all groundwater and leachate was
undertaken in April 2015. These have
been included to address past isolated
events where non-permitted wastes were
accepted.
Compliant
Purging and
sampling
procedure
GHD (2015b) stated that purging and sampling of
groundwater bores was undertaken in accordance
with EPA (2000) “Groundwater Sampling Guidelines”.
Compliant
SWL gauging
procedure
Standing Water Level (SWL) Monitoring undertaking at
commencement of each groundwater monitoring
event.
Compliant
Groundwater
sampling
procedure
Groundwater purging and sampling sheets provide
details on the purge method. The only exceptions
were a few bores for which the water level was low or
the bore was inaccessible to the low flow pump.
The field parameters at most bores had stabilised.
Compliant
Field Records Completed groundwater bore purging and sampling
records provided for each bore including bore/site
details, standing water level, and field parameter
value.
Groundwater bore purging and sampling records did
not identify that metals filtered in the field as stated in
the GHD (2015b) annual report.
The sample containers used were not clearly
identified in the CoC forms, particularly for SVOC and
VOC screens.
Partially compliant
Groundwater bore purging
and sampling records to clarify
which samples are filtered in
site.
CoC forms to identify sample
containers
Calibration
certificates
TPS90-FLMW calibration certificates provided in the
annual monitoring report.
Compliant
Field
Parameters
Groundwater physiochemical parameters are
monitored and recorded during purging.
Compliant
Groundwater
Sample
Collection
Sampling commence once physiochemical
parameters have stabilised and are placed in
containers for delivery to the laboratory under Chain
of Custody documentation.
Compliant
QC Samples See Section 3.4 of the GHD (2015b) “Portland Landfill
Annual Environmental Monitoring Results Report
2014/15”.
The trip blank sample was not collected during the
annual (April) event and analysed for VOC screen
analysis.
Generally compliant
Obtain trip blank sample during
the annual event for VOC
screen analysis.
May 2016
Page 68
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Variables Description Compliance
Trend analysis
plots
Plots should be from 1989 to present day (after pre
2012 data is incorporated into the database).
Partially compliant
Bore
maintenance
observations
The completed groundwater bore purging and
sampling records do not require reporting on bore
condition.
Not compliant
Include statement on bore
conditions.
Records Refer to GHD (2015b) “Portland Landfill Annual
Environmental Monitoring Results Report 2014/15”.
Generally compliant
Contractor GHD had been engaged to undertake the
monitoring and has been assessed by GSC to meet
this criteria.
Compliant
GHD (2014b) reported on the QA/QC results for each of the 2014 /15 monitoring events. The
QA/QC results are reviewed in Table 7-5.
Table 7-5: Groundwater Data Quality Review
Variables Description
Data Validation reporting. GHD (2015b) provides specific data validation reporting.
Holding times Eurofins advised that the samples were extracted within the holding
times.
Blind duplicate testing (Primary
laboratory).
Two April 2015 internal duplicates were analysed. The RPD
exceedances were confined to:
Duplicates 1 – COD (104% compared to 50% acceptable);
Duplicates 1 - TKN and nitrogen (62% compared to 50%
acceptable); and
Duplicates 2 - TKN and nitrogen (98% compared to 50%
acceptable)
Field split testing (Secondary
laboratory).
The April 2015 field split duplicate RPD exceedances are:
Duplicates 1 – VFA (87% compared to 50% acceptable)
Duplicates 1 – Lead (95% compared to 50% acceptable)
Duplicates 1 – COD (125% compared to 50% acceptable)
Duplicates 2 – VFA (151% compared to 50% acceptable)
Duplicates 2 – COD (59% compared to 50% acceptable)
Duplicates 2 –Ammonia (88% compared to 50% acceptable)
Trip Blanks. Not undertaken.
Laboratory Internal QC. Evidence of the laboratories internal QC testing is present and
complete as provided by GHD. Both Eurofins-MGT (Primary) and ALS
(Secondary) performed internal QC with adequate testing and
satisfactory results for matrix spikes and method blanks.
Limit of Reporting. The Limits of Reporting were generally lower than the respective
assessment criteria for each of the analytes.
NATA endorsement of
Laboratory reports.
Laboratory reports were stamped with the NATA endorsement
stamp and signature.
Decontamination and
Equipment Blanks.
One rinsate blank was collected. No analytes were identified
above the limit of detection.
May 2016
Page 69
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Variables Description
Sample Integrity. Field Chain of Custody/Laboratory request forms can be found in
documents provided by GHD.
Validity of Data Set. The data quality review indicates no significant systematic errors in
the data collection process for groundwater and leachate and
therefore the data set used as the basis for assessment is considered
valid and complete.
7.2.4 Cat B Monitoring - LFG
Progress with the implementation of the LFG monitoring subprogram as developed is presented
in Table 7-6. The assessment has focussed on the April 2015 monitoring events.
Table 7-6: Progress with implementing LFG monitoring subprogram (Cat B)
Item Details
Installation of
new monitoring
bores
New bores LFG8A, LFG10A, LFG18A, LFG20A, and
LFG25 installed.
Compliant
Probes and
Bores –
Monitoring sites.
All designated LFG bores/probes are monitored
except for those that are flooded.
The bores have been positioned at approximately
50 m spacing where houses are proximal to filled
areas, and within approx. 250m spacing elsewhere
along the landfill boundary.
The soil vapour probes are connected to a quick
release fitting hence are not open to the atmosphere.
Typically only the very bottom section of each soil
vapour probes is screened.
Compliant
Probes and
Bores -
Monitoring
frequency.
Quarterly LFG monitoring is conducted. Compliant
Weekly monitoring of new LFG monitoring bores for
one month has not been conducted.
Not compliant
Probes and
Bores- sampling
procedures. -
GHD (2015b) advised LFG monitoring was undertaken
in accordance with EPA (2011c) Draft Landfill Gas
Fugitive Emissions Monitoring Guidelines.
GHD has hired all LFG monitoring equipment. Probes
and bore monitoring is undertaken with a GA5000
meter. Evidence of LFG equipment calibration has
been provided.
The Airmet GA5000 calibration sheets has not been
signed.
Compliant
Most LFG monitoring has been undertaken during
falling or low atmospheric pressure on all 2014/15
monitoring events.
Records of CH4, CO2, O2 concentrations during each
bore purge (minimum of six occasions).
Compliant
Monitoring
Procedure –
Surface of
Monitoring commenced in October 2014.
Limited to nine sampling points in Area A and Area B.
Not compliant
May 2016
Page 70
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Item Details
intermediate
cap.
Instrument not identified. Assumed to be an Inspectra
laser. No calibration certificate provided.
Area C that has not been
filled over the past three
months should be
monitored and grid over
the remainder of Area A
and B should be on a 25 m
grid.
Pits and other
enclosed spaces
– monitoring
points and
frequency.
Monitoring is undertaken at locations identified in the
verified monitoring program.
Monitoring has been undertaken on a quarterly basis.
Compliant
Pits and other
enclosed spaces
–equipment.
Services and buildings are monitored with an
Inspectra Laser for methane, and a GA5000/GA2000
for CO2, O2, CO and H2S concentrations (when
measured). CH4 in the services and buildings
monitoring field sheets is in ppm. This is confirmed in
Monitoring Record.
Compliant
Pits and other
enclosed spaces
–measurements.
Monitoring records include peak LFG concentrations
and location details.
Compliant
Monitoring
Procedure –
Indoor Air
Quality.
Within each building monitoring undertaken at one
location only.
As required monitoring is undertaken on a quarterly
basis. Monitoring occurs with an Inspectra Laser for
methane and a GA2000 for CO2 and O2. Inspectra
Laser calibration record not provided.
Partially compliant
Monitoring records do not include location details
(e.g. monitor positions, building conditions, presence
of odour). Would be useful to include description of
any evidence of corrosion, and presence of odours in
the notes.
Non-compliant
Monitoring
Procedure -
Plant Stress of
Die Back.
Plant health at and within 50 m of the landfill is now
monitored.
A more substantive record of the monitoring is
required.
Partially compliant
Monitoring
Procedure –
Infrastructure.
Perimeter fencing, buildings and the bore network,
and any other significant infrastructure are
photographed for signs of corrosion. These
photographs have not been interpreted.
The overhead 500 kV transmission line towers are not
included as they are maintained by AusNet Services.
The bore network is not currently monitored for
corrosion.
Generally compliant
Performance
indicator.
Guideline limits where relevant for the site are
followed.
Compliant
Incorporation of
LFG monitoring
data into
database.
While LFG monitoring data is captured in a data
management system, it is yet to be combined into a
single integrated database including groundwater
monitoring.
Not compliant
May 2016
Page 71
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
7.3 Annual reporting
The annual report is provided in GHD (2015b) “Portland Landfill Annual Environmental
Monitoring Results Report 2014/15”.
The reports requires a declaration that the monitoring program was completely in accordance
with the verified monitoring program and explains any non-conformances, including names of
persons responsible for each component of the monitoring program.
May 2016
Page 72
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
8. Interpretation of monitoring results
The scope of work for an audit of landfill operation includes an interpretation of monitoring
results.
8.1 Scope
The following has been considered in this interpretation of monitoring results:
Nolan Consulting (2014) “Section 53V Audit – Landfill Operation, Portland Landfill – 210
Cape Nelson Road Portland”;
Cardno LanePiper (2014b), “Hydrogeological Assessment - Portland Landfill, 210 Cape
Nelson Road, Portland, VIC”;
GHD (2015b), “Portland Landfill Annual Environmental Monitoring Results Report 2014/15”;
GHD (2015d), “Portland Landfill Annual Performance Statement 2015 Supporting
Information Report”; and
Cardno (2015b), “Hydrogeological Assessment for Leachate Level Management -
Portland Landfill 210 Cape Nelson Road, Portland, Vic”.
Cardno (2015b) presented:
hydrographs of all groundwater monitoring bores from 1991 to February 2015;
groundwater elevation plan (April 2015); and
salinity contours (April 2015).
8.2 Leachate levels
Information on leachate levels obtained from the three operating leachate monitoring bores
is presented in Table 8-1.
Table 8-1: Leachate bore information [after Cardno (2015b)]
Bore ID
Area
Ground
Surface
Base of
Bore
Waste
Thickn
ess
(m)
Waste
base
Bore
Depth
(mbgl)
Leachate Elevation
(m AHD)
(mAHD) (mAHD) (mAHD) Feb
2015
Apr
2015
Oct
2015
LB01 C 50.86 43.36 >7.5 <43.36 7.5 NA NA 43.946
LB01R C 50.9(1) 41.9(1) 8.9 42(1) 9.0 45.69 43.97 44.154
LB02RA B 49.2(1) 44.0(1) 5.2 44(1) 5.1 Dry Dry Dry
LB03 A 46.67 42.22 >4.5 < 42.22 4.5 43.63 Dry 42.856
(1) Estimated level, based on adjacent surveyed bores.
The waste at leachate bore LBO2RA (Area B) is dry. The leachate in Area C is up to 2.2 m above
the base of the waste at LB01R, and the leachate level in Area A (at LB03) fluctuates from dry
conditions to at least 1.4 m above the base.
The interpolated watertable surface at LBO3 as of April 2015 was about 36.0 m AHD. This
suggests the maximum leachate level of 43.63 m is up to 7 m above the watertable surface.
8.3 Groundwater flow direction
The overall groundwater flow direction is to the north-east.
May 2016
Page 73
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Of the nested piezometers separately monitoring the MSA and BFA aquifers, there is no
significant level difference to the south-west of the landfill (at PO26A/B) and there is a
downward gradient of:
0 m to 3.5 m at PO31A/31B at Madeira-Packet Road to the north;
0.17 m at PO34A/B to the north of the north-west corner of the leachate storage dam (as
of the October 2015); and
7.06 m at PO35A/B to the south-east of PO05R (of the October 2015).
The downward gradient is suggestive of local recharge through infiltration.
The mean upward gradient of about 0.3 m at PO33A/B since October 2013, located 140 m
north of IB6/IB7, suggests some impact of the LIS interception bores.
The level within the NVA at PO25 ranges between 7.5 m to 9 m below the level of the
adjacent MSA/BFA bore (PO06). There is a slight increase in the hydraulic gradient towards
the LIS interception bores which indicates a minor beneficial impact.
Over the two years since October 2013 the average change in the watertable surface has
been a marginal fall of 0.1 m. The monitoring bores with a +/- change in level of greater than
0.5 m are PO08R, PO09, PO17, and PO06 which had level falls of 0.6 m to 0.8 m, bore PO18
which had a fall of 1.8 m, and PO02 which had an increase in level of 0.8 m.
The level trends are seasonal and do not appear to reflect any obvious landfill impacts.
8.4 Water quality
8.4.1 Salinity and ammonia
As salinity and ammonia are key groundwater contamination indicators, the analytical results
from March 2010, July 2012, April 2015 and October 2015 are compared in Table 8-2.
Exceedances of water quality guideline values are highlighted. The salinity and ammonia
concentrations of April 2015 are mapped in Figure 12 and 13 respectively.
Table 8-2: Selective salinity and ammonia concentrations at monitoring sites
Site
Beneficial use Salinity as TDS guideline values (mg/L) Ammonia guideline values (mg/L)
Segment A2 1,000 -
Drinking water - Aesthetic 600 0.5
EcoSystem - Fresh Water 2,000 0.9
Stock watering 2,500 -
Salinity as TDS (mg/L) Ammonia (µg/L)
General Location 2/3/10 4/7/12 15/5/14 28/10/15 2/3/10 4/7/12 15/5/14 28/10/15
IB4 Down, local, Cell A NA 2,200 3,200 2,500 NA 25 79 63
IB5 Down, local, Cell A NA 3,000 1,200 2,900 NA 9.6 16 3.1
IB6 Down, local, Cell A NA 2,900 3,000 3,800 NA 9.1 51 1.7
IB7 Down, local, Cell A NA 2,200 2,400 1,800 NA 1.7 27 0.75
IB8 Down, local, Cell A NA NA 2,600 NA NA NA 240 NA
LB01 Cell C NA 5,300 NA 3,400 NA 490 NA 490
LB01R Cell C NA NA NA 3,100 NA NA NA 220
LB02R Cell B NA NA 2100 Decom. NA NA 130 Decom.
May 2016
Page 74
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Site
Beneficial use Salinity as TDS guideline values (mg/L) Ammonia guideline values (mg/L)
Segment A2 1,000 -
Drinking water - Aesthetic 600 0.5
EcoSystem - Fresh Water 2,000 0.9
Stock watering 2,500 -
Salinity as TDS (mg/L) Ammonia (µg/L)
General Location 2/3/10 4/7/12 15/5/14 28/10/15 2/3/10 4/7/12 15/5/14 28/10/15
LB02R Cell B Not installed NA Not installed NA
LB03 Cell A NA 9,500 NA 4,000 NA 800 NA 720
PO1 Down, Local, Cell C 1,100 1,300 1,100 1,200 0.54 2 0.74 0.63
PO4 Down, local, Cell C - 1,100 2,000 NA - 1 0.69 NA
PO05R Down, local, Cell C - 1,800 1,800 1,800 - 0.49 0.40 0.28
PO34A Down, Local, Cell C Not installed 1,800 Not installed 0.22
PO34B Down, local, Cell C Not installed 2,000 Not installed 0.47
PO35A Down, Local, Cell C Not installed 2,000 Not installed 0.09
PO35B Down, local, Cell C Not installed 3,100 Not installed 3.5
PO06 Down, local, Cell C 2,000 2,600 1,900 2,700 210 31 73 42
PO07 Down, local, Cell A 4,700 5,700 4,400 4,000 79 160 200 40
PO08R Down, local, Cell A - 6,800 4,800 6,000 - 1.2 79 28
PO13 Down, local, Cell C 1,300 1,200 930 1,300 0.05 0.10 0.36 0.15
PO19R Down, local, Cell A/B - 3,700 5,100 5,300 - 2.10 0.57 0.33
PO20 Down, local, Cell A/B - 3,200 3,300 3,700 - 1.5 5.6 4.5
PO22 Down, local, Cell A/B 2,400 2,100 3,000 3,000 0.05 0.04 0.06 0.05
PO25 Down, local, Cell A/B (NVA) NA NA 1,100 1,400 NA NA 0.27 0.47
PO33A Down, intermediate, Cell A NA NA 13,000 7,800 NA NA 0.92 0.38
PO33B Down, intermediate, Cell A NA NA 2,500 2,800 NA NA 0.13 0.22
PO12 Down, regional, Cell A - 570 1,100 900 - 0.19 0.06 0.05
PO14 Down, regional, north 560 680 480 790 0.043 0.30 0.43 0.06
PO30 Down, regional, north NA NA 1,200 1,400 NA NA 0.40 0.26
PO31A Down, regional, north NA NA 1,600 1,100 NA NA 0.06 0.1
PO31B Down, regional, north 1,200 1,300 0.27 0.33
PO32 Down, regional, north 1,400 3,200 0.31 0.88
PO3 Lat, local, west - 800 620 590 - 0.39 0.37 0.38
PO17 Lat, local, east - 1,900 1,100 1300 - 120 92 100
PO18R Lat, local, east - 2,100 2,300 1,300 - 42 0.12 2.7
PO21 Lat, local, east 1,100 1,100 930 960 0.34 0.42 0.37 0.32
PO28 Lat, local, east NA NA 1,000 1,100 NA NA 0.63 0.55
PO11R Lat, regional, east - 820 750 1,000 - 0.44 0.31 0.18
PO15R Lat, regional, north - 1,200 680 540 - 0.65 0.65 0.85
PO23 Lat, regional, east 480 410 660 830 0.33 <0.01 0.09 0.6
PO24 Lat, regional, east 330 510 420 470 0.15 <0.01 <0.01 <0.01
May 2016
Page 75
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Site
Beneficial use Salinity as TDS guideline values (mg/L) Ammonia guideline values (mg/L)
Segment A2 1,000 -
Drinking water - Aesthetic 600 0.5
EcoSystem - Fresh Water 2,000 0.9
Stock watering 2,500 -
Salinity as TDS (mg/L) Ammonia (µg/L)
General Location 2/3/10 4/7/12 15/5/14 28/10/15 2/3/10 4/7/12 15/5/14 28/10/15
PO29 Lat, regional, east NA NA 1,000 1,000 NA NA 0.43 0.38
PO2 Up, local, south 540 790 1,100 1,200 0.25 0.06 0.50 0.29
PO09 Up, local, south NA 490 820 570 0.05 0.07 0.08
PO26A Up, south-west corner NA NA 1,800 1,200 NA NA <0.01 <0.01
PO26B Up, south-west corner NA NA 680 650 NA NA 0.05 <0.01
LDam Down, local, Cell C NA NA NA 2,700 NA NA NA 6.5
This salinity monitoring data for April 2015 (Figure 12) indicates the following:
(a) The leachate salinity ranges from 3,100 mg/L in Cell C (LB01R) to 4,000 mg/L in Cell A
(LB03).
(b) Up-gradient groundwater salinity ranges from 300 mg/L to 980 mg/L (with the exception
of PO26A in the MSA which had a concentration of 1,500 mg/L in the April 2015
monitoring event).
(c) The salinity immediately down-gradient of Areas A/B is close to the leachate salinity, and
down-gradient of Area C is elevated above background but less than the leachate
salinity. The exception is monitoring bore PO35B which is screened across low
permeability sediments which contributes to the higher salinity of 3,100 mg/L.
(d) Elevated salinity concentrations extend at least 400 m to the north-east of Derril Road
(at PO32) and possibly 550 m (to Madeira-Packet Road at PO31A/PO31B and PO30). The
latter cannot be confirmed as the salinity is at the upper extent of the background
concentration range.
(e) The elevated salinity concentration plume extends to Cape Nelson Road to the east.
(f) There is a plume of elevated groundwater salinity at PO19, PO20, and PO22 (down-
gradient of Area A/B).
(g) The salinity in the MSA aquifer at the 2.5 m deep monitoring bore PO33A at the July 2013
monitoring event was 2,200 mg/L. This increased to 13,000 mg/L at the April 2015
monitoring event and has subsequently fallen to 7,800 mg/L in October 2015. The wide
fluctuations may reflect perching and/or evapotranspiration). The salinity of the BFA at
the nested piezometer is relatively stable at 2,300 mg/L to 2,800 mg/L.
(h) To the north-east along Madeira-Packet Road the groundwater salinity is generally similar
to the up-gradient salinity, suggesting down-gradient attenuation.
May 2016
Page 76
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
This ammonia concentrations (Figure 13) indicate the following:
(a) Leachate ammonia concentration ranging from 270 mg/L in Area C (LB01R) to 800 mg/L
in Area A (LBO3) with an average of about 480 mg/L. [LBOR2A is not considered as it is
screened below the waste].
(b) Up-gradient concentration is less than 0.20 mg/L (with the exception of PO02 which has
a concentration varying from 0.06 mg/L to 0.50 mg/L and 0.29 mg/L in October 2015).
(c) High levels of contamination immediately down-gradient of Area A (PO07, PO08, and
PO20) and to the east of the site at PO17 (above 5 mg/L).
(d) Moderate levels of contamination, greater than 0.5 mg/L and less than 5 mg/L,
immediately down-gradient of Area C (PO01and PO4), immediately down- gradient of
Area A/B (PO06 and PO19R), down-gradient of Cell A (PO33A), east (PO28), and north-
west of Yarraman Park (PO15R).
(e) The ammonia concentration plume extends to at least 40 m the east of Cape Nelson
Road and attenuates to the north-east.
Based upon the above data the leachate plume extends:
at least 400 m to the north-east of Derril Road (at PO32) and possibly 550 m (to Madeira-
Packet Road at PO31A/PO31B);
to the east of Cape Nelson Road (PO17 and PO18); and possibly
to the north-west of Yarraman Park, (although this may be due to site specific sources of
ammonia).
The 2014 Audit of Landfill Operation reported on an increase in the extent of the leachate
plume from that reported in the 2013 Audit of Landfill Operation. This finding was considered to
be based upon additional data from bores installed in 2013 rather than further plume migration.
This 2016 Audit of Landfill Operation has found that the October 2015 plume extent has
stabilised since June 2014 with reductions in ammonia concentrations observed within the main
plume.
8.4.2 Water quality – other inorganics
Table 6 of GHD (2015b) tabulates bores reporting contaminant concentrations above
beneficial use guideline values for all 2014/15 monitoring events.
Elevated nitrate concentrations above the ANZECC (2000) Ecosystem Fresh water 95%ile of
0.16 mg/L are inconsistent and do not reflect the salinity and ammonia contamination plume.
For example ANZECC (2000) Ecosystem Fresh water 95%ile exceedances from the April 2015
monitoring event are found at PO06 (adjacent IB8), PO08R (between IB6 and IB7), PO18R (on
Cape Nelson Road), and PO26A (up-gradient at south-west corner of the site).
Volatile fatty acids are indicators of leachate contamination. Concentrations of above
20 mg/L were only found in April 2015 at PO32A (300 m north-east of the site entrance).
The Mulvey L/N ratio is an indicator of leachate contamination. It is:
(K +NH4+ NO3)/ (Mg + Ca + Na) x 100
The average leachate monitoring bore L/N ratio is 161. The average groundwater monitoring
bore L/N ratio is 4.3. The only ratios above 10 are at PO18R - 10.7 (along eastern boundary),
PO08R - 28.1 (between IB6 and IB7), PO32 - 40.2 (300 m north-east of the site entrance), PO03 -
42.9 (along western boundary), and PO01 – 101 (south-side of Derril Road).
May 2016
Page 77
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
The exceedances of ANZECC (2000) Ecosystem support 95%ile and the NH&MRC and NRMMC
(2011) AWDG health guideline values for metals are presented in Table 8-3.
Table 8-3: Groundwater bore exceedances of metals beneficial use guideline values
Bore Cd Cu Pb Ni Se Zn
ANZECC (2000) EcoSystem Fresh Water (95%) 0.0002 0.0013 0.0044 0.011 0.011 0.015
NHMRC (2011) Drinking Water - health 0.002 2 0.01 0.02 0.01
Up-gradient bores
PO02 <0.0002 <0.001 <0.001 0.004 <0.001 0.029
PO26B <0.0002 0.001 0.004 0.009 <0.001 0.021
Lateral
PO18R (local, east) 0.0012 0.002 <0.001 0.055 <0.001 3.1
PO21 (local, east) <0.0002 0.009 <0.001 0.006 <0.001 0.01
PO11R (regional, east) <0.0002 <0.001 0.009 0.011 <0.001 0.013
PO15R (regional, north) <0.0002 <0.001 0.001 0.004 0.04 0.011
PO23 (regional, east) <0.0002 0.019 0.003 0.01 <0.001 0.037
Downgradient Area A/B (local)
PO06 <0.0002 0 <0.001 0.01 0.001 0.015
PO08R <0.0002 0.008 <0.001 0.014 0.003 0.029
PO20 <0.0002 <0.001 0.045 0.005 <0.001 0.015
PO22 <0.0002 <0.001 0.014 0.003 <0.001 0.011
Downgradient, intermediate, Cell A
PO33A <0.0002 <0.001 <0.001 0.004 <0.001 0.025
PO33B <0.0002 0.003 <0.001 0.006 0.001 0.008
Downgradient, regional, north
PO14 <0.0002 0.001 <0.001 0.025 <0.001 0.029
PO31A <0.0002 0.002 0.004 0.004 <0.001 0.01
PO31B <0.0002 0.011 0.002 0.001 <0.001 0.03
The metal beneficial use guideline value exceedances are inconclusive in demonstrating a link
with leachate. The most significant exceedance of the guideline values is the zinc
concentration of 3.1 mg/L at monitoring bore PO18R which is immediately east of Area A. Since
April 2013 the zinc concentration at this bore has ranged from 0.41 mg/L to a peak of 3.1 mg/L.
At the October 2015 monitoring event the concentration fell to 1.4 mg/L. At all other monitoring
bores the zinc concentration is within the background range.
8.4.3 Organics
Laboratory analysis was undertaken for BTEXs, monocyclic -aromatic hydrocarbons (MAHs),
organo-chlorine (OC) pesticides, polycyclic-aromatic hydrocarbons (PAHs), phenols, volatile
organic compounds (VOCs), semi-volatile organic compounds (SVOCs), chlorinated
hydrocarbons, explosives, halogenated hydrocarbons, herbicides, nitroaromatics. The only
exceedances of laboratory limits of reporting for the April 2015 monitoring event are presented
in Table 8-4.
ANZECC (2000) Ecosystem support 95%ile and the NH&MRC and NRMMC (2011) AWDG
guideline values are also presented in Table 8-4.
May 2016
Page 78
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Table 8-4: Groundwater bore exceedances of organics LORs
Be
nze
ne
1,2
-dic
hlo
rob
en
zen
e
1,4
-dic
hlo
rob
en
zen
e
Ch
loro
be
nze
ne
Bis
(2-e
thylh
exy
l) p
hth
ala
te
Bore µg/L µg/L µg/L µg/L µg/L
LOR 1 1 1 1 5
ANZECC (2000) Ecosystem Freshwater) 95%ile 950 160 60 NA NA
AWDG health guideline value 1 1500 300 300
PO06 <1 <1 <5 - 3 <1 <5
PO07 3 <5 - 3 <5 - 2 44 <5
PO08R <1 <1 <1 <1 5
PO10 <1 <1 <1 <1 10
PO11R <1 <1 <1 <1 6
PO20 1 <1 <1 17 <5
PO26B <1 <1 <1 <1 8
PO31A <1 <1 <1 <1 5
PO31B <1 <1 <1 <1 5
PO33A <1 <1 <1 <1 6
IB4 5 <1 <1 5 7
IB6 <1 <1 <1 <1 8
IB7A <1 <1 <1 <1 10
lB8 2 <1 <5 - 7 58 <5
LB01 <1 <1 <1 <1 10
LB01A <1 <1 <1 <1 14
Leachate storage dam <1 <1 <1 <1 6
The only exceedances of organic toxicant guideline values are for benzene at monitoring bore
PO07 and interception bores IB4 and IB8 which marginally exceed the ADWG guideline value
of 1 µg/L. Potable water has been identified as a beneficial use that is unlikely to be realised
(Table 6-3).
8.5 LFG monitoring
8.5.1 Subsurface monitoring
GHD monitored the LFG bores/probes for peak and stabilised CH4, CO2, O2 concentrations and
peak H2S and CO concentrations on six occasions over the audit period. The LFG bore steady
state CH4, CO2 and flow rate records are presented in Table 8-5.
Ma
y 2
01
6
Pa
ge
79
Po
rtla
nd
La
nd
fill
- 2
10 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d
Se
ctio
n 5
3V
Au
dit
No
lan
Co
nsu
ltin
g P
ty L
td
67
14
1-5
_a
.do
cx
Tab
le 8
-5:
LFG
bo
re s
tea
dy
sta
te C
H4,
CO
2 a
nd
flo
w r
ate
re
co
rds
Bo
re ID
C
H4
Ste
ad
y s
tate
%v
CO
2 S
tea
dy s
tate
%v
Flo
w r
ate
(L/
hr)
Bo
re ID
23/0
7/1
430/1
0/1
45-6
/02/2
015
30/0
4/1
54-6
/08/1
529/1
0/1
523/0
7/1
430/1
0/1
45-6
/02/2
015
30/0
4/1
54-6
/08/1
529/1
0/1
523/0
7/1
430/1
0/1
45-6
/02/2
015
30/0
4/1
54-6
/08/1
529/1
0/1
5
LFG
01
0.0
0.0
0.0
0.0
0.0
0.1
0.1
0.1
0.1
0.1
0.1
0.3
0.2
0.0
0.0
LFG
02
0.0
0.0
0.0
0.0
0.0
0.0
11.9
16.0
14.8
11.0
12.9
14.1
-0.1
0.4
0.2
0.3
0.0
0.0
LFG
03
0.0
0.0
0.0
0.0
0.0
1.0
0.9
0.9
10.0
0.8
0.4
0.2
0.3
0.0
0.0
LFG
04
0.0
0.1
-0.3
LFG
05
0.0
0.0
0.0
0.0
0.0
0.0
1.6
0.9
1.3
1.3
1.4
0.9
-0.2
0.3
0.1
0.2
0.0
0.0
LFG
06
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.1
3.9
2.5
0.1
3.1
-0.2
0.1
0.2
0.2
0.0
0.0
LFG
07
0.0
0.0
0.0
0.0
0.0
0.0
3.2
0.1
2.8
1.8
2.7
3.1
-0.2
0.2
0.1
0.3
0.0
0.0
LFG
08
0.0
0.0
2.2
1.7
0.2
0.2
LFG
8A
0.0
0.0
0.0
0.0
1.9
2.2
0.4
4.4
0.1
0.2
0.0
0.0
LFG
09
LFG
9A
00
00
1.2
0.9
1.3
2.5
0.1
0.3
00
LF810
0.0
0.0
0.0
0.7
1.3
0.1
0.0
0.2
0.0
LFG
10A
0.0
0.0
0.0
0.0
1.1
1.3
1.0
1.8
0.1
0.2
0.0
0.0
LFG
11
0.0
0.0
0.0
4.7
2.6
6.2
0.2
0.7
0.0
LFG
12
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.1
3.0
6.4
0.1
5.9
0.1
0.5
0.2
0.2
0.0
0.0
LFG
13
75.5
67.1
37.4
38.0
68.2
59.9
18.4
23.3
26.0
19.0
20.1
19.8
-0.2
0.3
0.1
0.2
0.1
0.0
LFG
14
0.0
0.0
0.0
0.0
0.0
5.6
5.4
9.8
7.3
6.5
0.1
0.3
0.2
0.3
0.0
LFG
15
0.0
0.0
0.0
0.0
0.0
0.1
3.0
3.7
0.1
2.2
0.3
0.3
0.4
0.0
0.0
LFG
16
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.1
1.3
1.7
2.8
2.8
0.0
0.3
0.1
0.2
0.0
0.0
LFG
17
0.0
0.0
0.0
0.0
0.0
0.0
1.4
1.6
1.5
1.2
1.5
1.5
-0.1
0.4
0.1
0.4
0.0
0.0
LFG
18
0.0
0.0
0.0
0.0
0.0
0.0
1.4
1.0
1.4
0.9
1.3
1.1
-0.3
0.3
0.2
0.2
0.0
0.0
LFG
18A
0.1
0.0
0.0
0.0
1.3
1.0
1.4
1.0
0.1
0.1
0.0
0.0
LFG
19
0.0
0.0
0.0
0.0
0.0
2.3
2.3
1.7
2.5
2.7
0.3
0.1
0.3
0.0
0.0
LFG
20
0.0
0.0
0.0
0.0
0.0
0.0
0.1
0.1
0.9
0.8
0.1
0.0
0.0
0.3
0.2
0.3
0.0
0.0
LFG
20A
0.0
0.0
0.0
0.0
0.4
0.9
1.1
0.3
0.1
0.2
0.0
0.0
LFG
21
0.0
0.1
4.3
LFG
22
0.0
0.0
0.0
0.0
0.0
0.1
0.1
0.1
10.4
0.1
0.0
0.2
0.1
0.2
0.0
LFG
23
1.1
0.0
0.0
0.0
0.5
0.0
3.3
2.7
2.1
2.8
3.0
2.2
0.1
0.8
0.1
0.2
0.1
0.0
LFG
24
0.0
0.0
0.0
0.0
0.0
0.0
5.3
2.7
3.1
3.0
4.8
3.1
0.0
0.4
0.1
0.2
0.1
0.0
LFG
25
0.0
0.0
0.0
0.0
0.6
0.8
2.5
0.6
0.0
0.3
0.0
0.0
Flo
w r
ate
(L/
hr)
CO
2 S
tea
dy
sta
te %
vC
H4 S
tea
dy
sta
te %
v
May 2016
Page 80
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Findings
The findings for the subsurface LFG monitoring over the audit period are summarised below.
On several occasions LFG probes could not be sampled as the tubing filled with water.
Monitoring bore LFG25 was installed as a background monitoring bore prior to the
February 2015 monitoring event.
Monitoring bore LFG13 is located within the waste mass. The methane concentration
over the monitoring period ranged from 37.4 %v/v to 75.5 % v/v. Monitoring bore LFG14
is also located in the waste mass
All boundary LFG probes recorded methane at concentrations below the EPA (2015a)
Landfill BPEM action level of 1% v/v at all monitoring events except for:
LFG23 at the 23/7/2014 monitoring event (1.0%).
Of the perimeter bores LFG monitoring bores LFG02, LFG07, LFG23 and LFG24 have CO2
concentrations that are consistently greater than 1%v/v above background
concentration. These are located along the eastern boundary except for LFG07 which is
located in the south-west corner.
Isolated CO2 concentrations of greater than 1%v/v above background concentration
have occurred at monitoring bores LFG03, LFG06, LFG11, LFG12, LFG15, LFG19, and
LFG22.
All CO2 concentrations are less than 10 % v/v above background except for LFG02 which
is up to 14.2 % v/v above background.
The maximum gas screening value (GSV) for CO2 is 0.044 L/hr which based upon CIRIA
(2007) represents a very low risk.
Discussion
The Nolan Consulting (2014) audit report recommended that four additional BPEM compliant
LFG monitoring bores be installed adjacent LFG probes LFG07, LFG08, LFG10, and LFG18. The
purpose was to assist in assessing the reliability of the LFG probes in comparison with BPEM
compliant bores.
The need or otherwise for replacement of the LFG probes with EPA (2015a) Landfill BPEM
compliant LFG monitoring bores was to be determined following a review of results from a few
monitoring events.
The CO2 concentrations at LFG08/8A, LFG10/10A, LFG18/18A and LFG20/20A are consistent
between bores and probes. The key exceptions are for LFG10/10A, and LFG20/20A in the
August 2015 monitoring event. In both occasions the probes recorded 0.1% v/v and the bores
recorded 1.0% v/v to 1.1% v/v. As the results are inconclusive ongoing monitoring of the probes
and bores up to the end of 2015/16 year is recommended.
While the reported CO2 exceedances of the EPA (2015a) Landfill BPEM action level are
relatively minor, and it is acknowledged that clayey sediments with organic matter often
record CO2 concentrations with the reported range, the potential for subsurface migration of
CO2 from the landfill cannot be excluded.
8.5.2 Landfill surface
The EPA (2015a) Landfill BPEM require the intermediate cover area of the landfill surface to be
monitored to determine if the 200 ppm methane concentration action level is exceeded.
May 2016
Page 81
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Quarterly monitoring commenced in October 2014. Typically this monitoring has been limited
to nine sampling points in Area A and Area B. Area C has not been monitored.
GHD (2015b) noted that methane concentrations at the landfill surface of greater than the
200 ppm action level have consistently been detected in a bare patch near LFG13, and to the
immediate east of the weighbridge. Up to 17,000 ppm (1.7%) methane has been detected in
this area. Other areas of exceedances have also been noted, and these generally correlate
with bare patches of cap, whereas the remainder is vegetated with grasses.
GHD (2015b) advised that some of the capped areas, particularly to the south, were not
monitored due to various access difficulties. While the recapping of the majority of Area A
and B should reduce methane concentration at the surface to below the final cap action level
of 100 ppm there is a risk of lateral migration around the southern area which will not be
recapped due to the presence of native vegetation
8.5.3 Building, structures and subsurface services
On all monitoring events the methane concentrations within all building, structures and
subsurface services were well below the EPA (2015a) Landfill BPEM action levels.
May 2016
Page 82
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
9. Progress with previous Auditor's recommendations
John Nolan undertook a Section 53V groundwater audit of the Hyland Highway landfill in 2014.
This is referenced as Nolan Consulting (2014) “Section 53V Audit – Landfill Operation, Portland
Landfill – 210 Cape Nelson Road Portland”, Service Order No. 8004179.
The audit report presented twenty four recommendations. Progress on the works associated
with the recommendations is presented in Table 9-1.
Table 9-1: Progress with 2014 Audit of Landfill Operation recommendations
No Recommendation Completion
date
Auditor comment on
implementation progress
Monitoring program
1 Implement updated Monitoring Program including: Ongoing
(a) Install, survey, and monitor additional leachate
monitoring bores.
- near LB02R (to base of waste); and
- adjacent LB01 (to base of waste).
Mar 2015 Completed.
(b) Install, and monitor five additional BPEM
compliant LFG monitoring bores adjacent:
- LFG07, LFG08, LFG10, and LFG18; and
- groundwater monitoring bore PO15R
(background).
Mar 2015 Completed.
(c) Replace all the other soil vapour LFG probes
with new BPEM compliant LFG monitoring bores
(subject to confirmation from monitoring results
at LFG07, LFG08, LFG10, and LFG18 that soil
vapour probes may underestimate subsurface
LFG concentration and flows).
Dec 2015 Not required at this stage.
(d) commence methane monitoring of the interim
cap and the final cap (once installed).
Jan 2015 Partially completed.
Coverage is limited and
does not include Area C
(where filling has not
occurred for a period of
three months or more.
2 Provide all weather 4x4 vehicle access to within 5
m of all bores for all conditions except flooding
events.
Jun 2015 Not completed.
GSC propose to undertake
as part of associated cap
construction activities.
3 Established an integrated database to hold and
enable efficient reporting of all monitoring records
and data from 1989, preferably in ESDAT format in
accordance with the prepared service
specification.
Dec 2014 Not completed.
GHD has data in ESDAT
format from 2011. Earlier
data has been obtained
and now needs to be
entered manually.
Hydrogeology
4 Resolve with the EPA the potential for using the
Groundwater Quality Restricted Use Zone (GQRUZ)
under SEPP Groundwaters of Victoria as a
mechanism to manage this risk.
Mar 2014 Not commenced.
May 2016
Page 83
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
No Recommendation Completion
date
Auditor comment on
implementation progress
Conceptual model
5 Undertake a comprehensive analysis of MSA and
BFA aquifers groundwater quality analysis that
identifies discrete characteristics. This should
include using Stiff and Piper diagrams and Mulvey
L/N ratios.
Jun 2015 Not undertaken.
Cardno (2015b) considered
a single unit for the purpose
of hydrogeological
assessment of leachate
level management.
6 Investigate the hydraulic connection between the
Leachate Storage Dam and the watertable.
Jun 2015 Competed.
Undertaken by Cardno
(2015b).
7 Complete the Hydrogeological Assessment
supporting Post Closure PAN.
Dec 2015 Completed.
Leachate interception system
8 Upgrade the Leachate Interception System in
accordance with Cardno LanePiper (2014c)
recommendations. Specifically:
(a) Redevelop an existing bore, install a new
pump and test over a month to determine if
design pumping rate can be achieved.
Jan 2015 Completed.
(b) If the design pumping rate is achieved at the
redeveloped bore, redevelop the other three
existing bores and replacing the four old
pumps and fittings. If not develop and
implement an alternative leachate control
system that meets the design objectives.
Jun 2015 Completed. The three
existing bores redeveloped
and the old pumps and
fittings replaced.
(c) Install an intermediate sump and transfer pump
at the head of the transfer pipe to maximise
performance (as required).
As
required
Not required.
(d) Install three new bores (IB9 to IB11) to fully
intersect the BFA with new pumps.
Jun 2015 Not commenced.
Addressed in the Cardno
(2015b) Hydrogeological
Assessment
(e) Implement an Operation & Maintenance
manual and program to provide for system
monitoring and optimisation.
Aug 2015 Not commenced.
Infrastructure
9 Investigate the location of on-site electricity supply
pits and Telstra pits and include in LFG monitoring
program. This should consider the proposed
transfer station.
Mar 2015 Completed.
10 Ensure weighbridge office toilet is vented. Sep 2013 Not undertaken.
Vented amenities to be
provided in the new transfer
station facility.
May 2016
Page 84
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
No Recommendation Completion
date
Auditor comment on
implementation progress
LFG Risk Management
11 Extend the Safe Work Procedure - Transfer Station
Operation – Ventilation of building to include the
Resale Centre and the toilet.
Dec 2013 Completed.
12 Review monitoring results from the new LFG
monitoring bores, to determine if any changes to
the risk profile are required.
Dec 2015 Completed.
Reviewed as part of this
audit of landfill operation.
13 Check that the GSC restriction on residential
development within 500 m of the site prevents any
future residential development, particularly of
buildings with unvented basements.
Mar 2015 Checked.
No planning trigger limiting
development within 500 m
buffer. Only one permit
issued within 500 m buffer
since 1st July 2015. It was for
a veranda.
Operational
14 Improve operational management procedures as
per the Landfill Compliance Risk Register
(Appendix F).
Ongoing No change since 2014.
15 Fence off Area A. Upon
completio
n of Area
A final
capping
Awaiting final capping.
16 Include daily checking of the waste height at the
tipping face in the monitoring and compliance
daily checklist (to ensure it does not exceed 2 m).
Ongoing Completed.
In Daily checklist.
Next audit
17 Undertake for period up to 31 December 2015. 31 Mar
2016
Completed through this
audit.
May 2016
Page 85
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
10. Update and reverification of monitoring program
The Monitoring Program has been updated as part of this Audit of Landfill Operation to reflect
the revised CSM, the updated risk assessment, the Verification Auditor’s comment’s, the
assessment of the Monitoring Program over the audit period, and progress with implementing
the 2014 audit recommendations.
The updated monitoring program is presented below for:
roles and responsibilities;
Category A monitoring (visual and olfactory);
Category B monitoring (groundwater and leachate);
Category B monitoring (LFG);
reporting; and
contractor requirements.
In general the changes to the verified Monitoring Program (Nolan Consulting; 2014) are of a
minor nature.
10.1 Updated program
10.1.1 Roles and responsibilities
GSC is responsible for implementing and undertaking the monitoring program. In doing so it
should identify and allocate responsibilities for all monitoring activities to relevant staff and
consultants, and ensure that all responsible officers have adequate training and skills to perform
the tasks.
The Project Planning and Facilities Manager should:
undertake internal audits to ensure the monitoring program is being effectively
implemented; and
review the annual monitoring report and take the necessary actions arising from the
report outcomes.
The Resource Management Officer should facilitate the undertaking of the Category A
monitoring including the completing of the daily, weekly and monthly checklists.
10.1.2 Category A monitoring
Previously separate monitoring sub-programs were prepared for surface water, odour, litter,
vermin, dust, noise. These sub-programs have been brought together into a single Category A
(Cat A) program. This program includes infrastructure (corrosion), dust, and on-site vegetation
health.
The prerequisites for the implementation of the Cat A monitoring are:
the preparation of monitoring checklists at daily, weekly, and quarterly frequencies; and
provision of appropriate staff training.
The updated Cat A monitoring program is presented in Table 10-1.
May 2016
Page 86
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Table 10-1: Updated Category A monitoring program
Variables Description
Monitoring locations Location Hazard Regular
frequency
Landfill cap. Surface water/leachate. Weekly
Weeds. Quarterly
Access roads. Surface water/leachate. Weekly
Transfer and recycling station. Surface water/leachate. Weekly
Corrosion. Quarterly
Leachate storage pond &
immediate surrounds &
stormwater detention ponds
(when constructed - for
overflow & seepage).
Surface water/leachate. Weekly
Odour. Daily
Litter. Daily
Vermin. Weekly
Site boundary. Surface water/leachate. Weekly
Noise. Weekly
Odour. Daily
Litter. Daily
Dust. Weekly
Vermin (fence check). Weekly
On & within 50m of landfill. Plant health. Quarterly
Weighbridge & site office. Corrosion. Quarterly
Bore network. Corrosion. Quarterly
Resale Centre. Corrosion. Quarterly
Compressor shed. Corrosion. Quarterly
Noise. Weekly
Active tipping face. Odour. Daily
Litter. Daily
Cover material. Daily
Dust. Weekly
New works area. Noise. Weekly
Dust. Weekly
Surface water/leachate. Weekly
Site Entry. Dust. Weekly
Other triggers for
inspections
Complaint or notification of a discharge by any GSC staff.
New works area.
Construction of a new cell.
Extreme event (such as very high winds & significant storm).
Placement of odorous material (for odour only).
Following any significant change in site operational procedures.
May 2016
Page 87
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Variables Description
Reporting to include Name of responsible officer, date & time of day.
Environmental conditions (wind direction and strength and
temperature).
Discharge across the site boundary (e.g. stormwater, sediment, litter)
with likely source, direction and characteristics (e.g. colour, odour, and
turbidity for water).
Emissions across site boundary (odour, dust, and noise).
Freeboard in leachate storage dam less than 0.5m (i.e. BEPM threshold).
Extent of any in-site or off-site water ponding.
Cause of any off-site discharge /emissions or significant on-site
generation.
Actions taken to address issue.
Performance
indicators
Generic
No complaints.
Stormwater
No evidence of leachate pond failure, leakage or over filling (i.e.
freeboard to be maintained at >0.5m).
No evidence of significant ponding (i.e. for extended periods after
rainfall.).
Noise
No excessive noise above levels established as normal.
Triggers for sampling
and analysis
Stormwater
Off-site discharges – when significant off-site discharge of odorous
and/or turbid water occur. Sampling and analysis for pH, TDS,
suspended solids, phosphorous, total nitrogen and TOC as a minimum.
Fawthrop Lagoon - if leachate plume is shown to extend within 500 m of
the lagoon. Sampling and analysis as above on a quarterly frequency.
Stormwater sedimentation ponds once constructed - Sampling and
analysis as above on a quarterly frequency.
Dust
More than four dust complaints in any one financial year would trigger
the installation and monitoring of a minimum of three dust gauges
(adjacent the active tipping face, adjacent active traffic area, and on
boundary downwind). See Lane Piper (2010b) for further detail.
Noise
In the event of a future development of the landfill or urban
encroachment from surrounding areas which may result in a change of
risk level to a “High Risk” site, the noise limits may then need to be
monitored to ensure compliance with acceptable noise levels stated in
EPA (2011d) “Noise from Industry in Rural Victoria”.
Records Evidence of staff training for monitoring across all categories. In
particular odour monitoring along boundary should only be taken by
staff that have been calibrated.
Daily log book of key on-site activities, personal on-site, visitors, OHS
incidents, and any key environmental issues.
Daily, weekly, and monthly check list templates.
Completed checklists.
Evidenced of actions taken.
May 2016
Page 88
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Variables Description
Up to date complaints register including, relevant photographs, actions
taken and conclusion of task (i.e. objective achieved) with name of
person responsible.
Associated
procedures
Dust management – to identify dust suppression watering triggers (i.e.
no of dry days, wind direction etc., and watering arrangements.
Responsibility Landfill staff (trained).
The updated Cat A monitoring program includes the requirement to take stormwater samples
once the stormwater sedimentation ponds are constructed. These will be analysed to
determine if any impact from leachate or other known contaminants at the site.
10.1.3 Groundwater and Leachate (Cat B)
The updated Groundwater and Leachate monitoring program (Cat B) is presented in Table
10-2.
Table 10-2: Updated groundwater and leachate monitoring subprogram (Cat B)
Variables Description
Level control IB bores, leachate monitoring bores, and groundwater monitoring bores to top of
casing and ground surface level (mAHD).
As constructed Leachate Storage Dam floor level (mA HD).
Outstanding bores requiring level control are PO34A, PO34B, PO35A and PO35B
and new leachate monitoring bores LB01R and LB02RA
Monitoring
locations and
infrastructure
Groundwater bores
The following groundwater bores shall be monitored for standing water level and
sampled for laboratory analysis:
PO1, PO2, PO3, PO4, PO05R, PO06, PO07, PO08R, PO09, PO10, PO11R, PO12,
PO13, PO14, PO15R, PO17, PO18R, PO19R, PO20, PO21, PO22, PO23, PO24,
PO25, PO26A, PO26B, PO28, PO29, PO30, PO31A, PO31B, PO32, PO33A,
PO33B;PO34, PO34A, PO35, PO35A.
Install new monitoring bore in the wooded area between Area C and the
northern boundary.
Leachate interception bores
The following leachate interception bores (IB bores) shall be monitored for water
quality and cumulative pumped volume.
IB4, IB5, IB6R and IB7.
All leachate interception bores shall be maintained with pulse counters and level
data loggers. The only outstanding item is a level data logger on IB5.
Leachate monitoring bores
The following leachate monitoring bores shall be monitored for standing water
level and water quality.
LB01, LB01A, LB02RA, and LB03.
New bores in centre of Area A and Area B to confirm cell base elevation and
leachate level in the centre of these cells.
Leachate storage dam
A gauge board shall be established and maintained within the leachate storage
dam.
The leachate storage dam shall be monitored for level and quality.
May 2016
Page 89
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Variables Description
A Cumulative flow meter shall be installed and maintained on the LIS discharge
line near the leachate storage dam.
Weather station
Install temporary weather station for on-site rainfall to improve the estimate of net
evaporation loss and support the calculation of the leachate storage dam water
balance.
Guideline values Presented in Table 6-2.
Frequency Weekly Dam level.
LIS bore levels (download quarterly).
Cumulative pump pulse counts.
Flow rate from LIS system to leachate storage dam.
Rainfall and pan evaporation.
Quarterly
(Jan, Apr,
Jul, Oct)
All bores (groundwater and leachate monitoring, and leachate
interception bores) to be tested for:
TDS;
pH;
major ions (sodium, calcium, potassium, magnesium, chloride,
sulphate, carbonate, bicarbonate), including charge balance
error calculations;
nitrogen species (ammonia, nitrate, nitrite, total nitrogen, TKN);
Volatile fatty acids;
Metals (antimony, arsenic, Cd, beryllium, total Cr, copper,
cobalt, lead, mercury, molybdenum, nickel, selenium, tin, zinc);
Methane;
BOD and COD; and
TOC.
To the extent possible analysis should be conducted to method
detection limits compatible with criteria for protection of
groundwater beneficial uses.
Annually
(Jan)
Bores PO1, PO4, PO05R, PO06, PO07, PO08R, PO13, PO19R, and
PO25 to be tested for:
SVOC screen (GC/MS USEPA 8270C); and
VOC screen (P&T GC/MS USEPA 8260B.
Procedures Compliance with EPA (2000) “Groundwater Sampling Guidelines” and EPA (2009)
“Sampling and Analysis of Waters, Wastewaters, Soils and Wastes”.
Standing Water Level (SWL) Monitoring
At the commencement of each groundwater monitoring event, groundwater
level shall be gauged using a water level meter in accordance with methods
specified in EPA Pub 669 Section 4.4.
A water level meter shall be used to measure the depth to groundwater relative
to the ground level and surveyed top of PVC casing in each bore.
Groundwater Sampling Method
In each groundwater monitoring event samples shall be collected for laboratory
analysis using a low flow (minimum purge) methodology in accordance with
methods specified in EPA Pub 669 Section 4.5.2.
Field Records
A completed sampling record is required for each bore including bore/site details,
standing water level, stabilised parameter values and sample containers used.
May 2016
Page 90
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Variables Description
Field Parameters
Groundwater physiochemical parameters (field parameters - temperature,
electrical conductivity, dissolved oxygen, redox potential, pH) to be monitored
and recorded during groundwater removal (purging), prior to collecting
groundwater samples for laboratory analysis.
Groundwater Sample Collection
Sampling shall commence once the physiochemical parameters have stabilised
within ranges stated in EPA Pub 669, Section 4.5.1. Samples shall be collected
directly into new and appropriately preserved laboratory bottles and packed in
chilled containers for delivery under Chain of Custody documentation.
Samples for metals analysis shall be filtered to 0.45 μm in accordance with EPA
Pub 669, Section 4.8.
QC Samples
In each monitoring event the following QC samples shall be collected in
accordance with methods outlined in EPA Pub 669, Section 4.3.2, and
analysed for the suite of analytes applicable to primary groundwater samples.
2 x blind duplicates (for analysis at the primary lab).
2 x field split (for analysis at a secondary lab).
1 x rinsate blank.
In addition to the requirements stated above, one trip blank sample shall be
collected during the annual (Jan) event and analysed for VOC screen analysis.
Maintenance of monitoring infrastructure
In the event bores (groundwater, leachate and interception) and leachate
storage dam monitoring infrastructure are found to not be clearly labelled or
damaged (e.g. locks broken, corrosion of steel standpipe etc.), this information
shall be recorded on field log sheets and GSC notified immediately following
completion of the monitoring event. Arrangements shall be made to rectify these
deficiencies in bore identity and integrity.
In the event that the sample water from bores is turbid, and/or includes sand,
bores should be redeveloped in accordance with methods outlined in EPA Pub
669 Section 3.3, including (but not limited to) actively agitating the water column
prior to the removal of water until water is visibly clean and of constant quality
(meets the criteria for physiochemical properties for sampling). Observations
made during bore development, such as (but not limited to) volumes and water
quality observations, shall be recorded on a bore development log.
Measure LIS bores on a quarterly basis for silt ingress and clean out if there is a
significant build up and leachate pumping is compromised.
Performance
indicator
Groundwater, leachate and LIS monitoring has proceeded in accordance with
requirements outlined in the monitoring program and any subsequent
recommendations provided in future audits of landfill operation.
The leachate bore level, LIS flow, groundwater level, and groundwater chemistry
triggers are not exceeded as described in the Cardno (2015b) Hydrogeological
Assessment.
The monitoring program may need to be revised (i.e. monitoring frequency
decreased and/or bores removed from program):
in consultation with the appointed Environmental Auditor where increasing
contaminant concentration trends are reported; and
in the event contaminant concentrations fall below criteria for protection of
beneficial uses.
May 2016
Page 91
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Variables Description
Bores outside the site boundary maintain water quality levels within the
groundwater segment identified for the area.
10.1.4 Landfill gas (Cat B)
The updated LFG monitoring program (Cat B) is presented in Table 10-3.
Table 10-3: Updated LFG monitoring subprogram (Cat B)
Item Details
Monitoring Procedure
Probes and Bores
The LFG bores/probes to be monitored are:
LFG01, LFG02, LFG03, LFG04, LFG05, LFG06, LFG07, LFG08, LFG09,
LFG10, LFG11, LFG12, LFG15, LFG16, LFG17, LFG18, LFG19, LFG20,
LFG21, LFG22, LFG23 and LFG24 – oil vapour probes with Teflon
tubing (at landfill boundary).
LFG13, LFG14 – 25 mm diameter PVC bores (in landfill cap).
LFG08A, LFG09A, LFG10A, LFG18A, and LFG20A EPA (2015a)
Landfill BPEM compliant bores
LFG25 background EPA (2015a) Landfill BPEM compliant bores.
Replacement of all other soil vapour LFG probes with new BPEM
compliant LFG monitoring bores (subject to confirmation from
monitoring results at LFG08A, LFG10A, LFG18A and LFG20A that soil
vapour probes may underestimate subsurface LFG concentration
and flows (to be determined after last monitoring event in
2015/16).
At all times the bores are to be sealed at the surface from the
atmosphere.
Monitoring Procedure
Probes and Bores
Quarterly (Jan, Apr, Jul, Oct) LFG monitoring.
Weekly monitoring for one month, for new LFG monitoring bores,
following installation.
Monitoring shall (to the extent practicable) be conducted during
falling and/or low atmospheric pressure.
All LFG monitoring equipment shall be operated in accordance with
manufacturer’s instructions and to requirements provided in EPA
(2011c) Landfill Gas Fugitive Emissions Monitoring Guidelines, Publ. No.
1416.
The following LFG monitoring procedure shall be followed at bores /
probes, with
1. Run meter in ambient air and record ambient air readings until
stabilisation.
2. Record bore pressure reading using a manometer (or equivalent).
If reading above 1mmH2O, then also take a pressure reading at
conclusion of monitoring.
3. Record gas flow rate and relative pressure. Ensure the unit has
been “zeroed” prior to taking these readings.
4. Purge LFG probes for a minimum period of one minute and bores
for a minimum period of three minutes. Record CH4, CO2, O2
May 2016
Page 92
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Item Details
concentrations (to 0.5% or lower) on a minimum of six occasions
during each bore purge.
5. If concentrations are fluctuating, continue running pump and
recording concentrations at 1 minute intervals until stable.
6. At completion of monitoring at each bore / probe, purge the
meter in open air until ambient readings are achieved.
Monitoring of monitoring trace elements (volatile organics) at
monitoring bores LFG02, LFG07 and LFG23 over two consecutive
monitoring events.
Monitoring Procedure –
Surface of landfill
Monitor on a 25m square grid over cap and intermediate cover (where
filling will not be undertaken for the next three months) and final cover
areas. This should include the vegetated areas of Areas A and B.
Diversions off the grid pattern to target and monitor any cracks,
odours, stressed vegetation, or infrastructure potentially penetrating
the cap (e.g. bores, posts) is allowed.
Conduct monitoring on a quarterly basis.
Monitor with extendable probe with the specifications recommended
in the EPA (2011c).
The operator should stand still for several seconds and record readings
at ground surface.
Locations (GPS co-ordinates) and concentrations of elevated
methane and carbon dioxide should be recorded along with wind
speed and direction.
This procedure should be modified as required to conform to any
changes between the draft and EPA (2011c) guidelines.
Monitoring Procedure -
Pits and other enclosed
spaces
Monitor:
Leachate Interception pits (IB4 to IB7)
Telstra pits (i) at corner of Cape Nelson Road and Derril Road and
(ii) other on Cape Nelson Road;
water main pit adjacent bore LFG02;
stormwater drains at
- Cape Nelson Road (near cemetery gate)
- 275 Cape Nelson Road
- corner of Derril Road and Cape Nelson Road
- corner Malings Road and Cape Nelson Road
- between recycling shop and weighbridge
following structures
- beneath weighbridge
- shipping container
- weighbridge office
- weighbridge toilet
- shed behind weighbridge
- recycling shop;
new pits and enclosed spaces established with new transfer station
and associated infrastructure; and
May 2016
Page 93
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Item Details
compressor house, compressor electrical box, and beneath
compressor house slab.
Quarterly (Jan, Apr, Jul, Oct) monitoring.
Monitor for CH4, CO2, and O2 concentrations.
Record CH4, CO2, O2 concentrations within pit or enclosed space
immediately upon opening of manhole cover, lid etc.
1. Monitoring records should include LFG concentrations (peak and
stabilised) and location details, evidence of corrosion, and
presence of odours.
2. The program should be modified as required to conform to any
changes in the final version of the EPA (2011c) guidelines.
Within each building monitor at several representative locations to
provide an even coverage of the space while focussing on areas
where gas ingress is most likely (i.e. floor holes or cracks).
Monitoring Procedure –
Indoor air
Conduct monitoring on a quarterly basis.
Monitoring equipment should be operated in accordance with
manufacturer’s instructions.
At each location monitor for several minutes or until readings have
stabilised.
Monitoring records should include LFG concentrations (peak and
stabilised) to an accuracy of ± 0.5% or less and location details (e.g.
monitor positions, building conditions, presence of odours).
This procedure should be modified as required to conform to any
changes between the draft and final EPA (2011c) guidelines.
Action levels as per
Table 10-5 (from Table 6.4 of the BPEM; 2014b).
Performance Indicator All LFG monitoring data and associated information shall be recorded
on standard field record sheets.
Records and Data
Management
LFG monitoring data shall be incorporated into the database
established for groundwater monitoring.
Table 10-4 provides the required details of the LFG monitoring equipment and Table 10-5
provides details of the LFG performance indicators.
Table 10-4: LFG Monitoring Equipment Details
Item Details
LFG bore monitoring An extractive LFG analysers that meets the Performance specification
as per Table 4.1 of EPA (2011c) and is capable of monitoring flow to 0.1
L/hr.
The analyser shall be calibrated to monitor methane (CH4), carbon
dioxide (CO2), oxygen (O2) and flow. Calibration certificates to be
provided by from rental company.
Landfill surface, service
trenches and pits, and
buildings and structures
monitoring
A low-concentration methane detector that meets the Performance
specification as per Table 4.2 of EPA (2011c). An extendable probe to
be used for the landfill surface survey.
May 2016
Page 94
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Item Details
An extractive LFG analyser should be used to monitor CO2 and O2 in
service trenches and pits
The meters shall be calibrated. Calibration certificates to be provided
by the rental company.
Pressure gauge A pressure measure device (i.e. manometer, bi-directional gauge or
equivalent) is required to gauge relative bore pressure prior to and
following sampling of the bore. The pressure gauge should allow for
relatively low pressures (e.g. as low as Pascals rather than mbar or
hectapascals).
Table 10-5: LFG Performance Indicators [from Table 6.4 EPA (2015A) Landfill BPEM]
Location Parameter(s) Action level and unit
Landfill surface final cover
areas.
Methane concentration in air
(50 mm above the landfill
surface).
100 ppm.
Within 50 mm of penetrations
through the final cap.
Methane concentration in air
(50 mm from the point of
discharge).
100 ppm.
Landfill surface intermediate
cover areas (not scheduled to
receive waste during the next
three months).
Methane concentration in air
(50 mm above the landfill
surface).
200 ppm.
Within 50 mm of penetrations
through the intermediate cover.
Methane concentration in air
(50 mm from the point of
discharge).
1,000 ppm.
Biofilters. Methane flux. 1.0 g/m2/hr.
Subsurface geology at the
landfill boundary.
Methane and carbon dioxide
concentrations.
1.0 % v/v methane
or
1.5% v/v CO2 above
background.
Subsurface services on and
adjacent to the landfill site.
Methane concentration. 10,000 ppm.
Buildings/structures on and
adjacent to the landfill site.
Methane concentration in air. 5,000 ppm.
LFG flares. Methane and volatile organic
compounds.
98% destruction efficiency.
LFG flares. Methane and volatile organic
compounds.
98% destruction efficiency.
May 2016
Page 95
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
10.1.5 Annual Reporting (Cat B)
An annual monitoring report is required each completed financial year. The report should
include the following:
A summary of the scope of the monitoring events and methods using tabulations;
A declaration that the monitoring program was completely in accordance with the
verified monitoring program and explains any non-conformances, including names of
persons responsible for each component of the monitoring program;
Identification of any changes to the monitoring points;
A tabulated checklist of all bores at the site noting compliance with the monitoring
specification for each monitoring event, i.e. stating that the bore was sampled or
otherwise noting the reasons for non-compliance;
New field and laboratory groundwater, leachate, and LFG data should be added to a
database holding and enabling efficient reporting of all monitoring records and data
from 1989, preferably in ESDAT compatible format;
A listing of all equipment used by make and model and evidence of any calibration; and
Plans showing the locations of all monitoring locations (i.e. bores, pits, indoor locations)
and general site features;
For water sampling:
- tabulated field parameters and laboratory analytical data, including graphical
presentation of trends for key parameters (including but not limited to reduced
water levels , pH (field), EC (field), dissolved oxygen (field), ammonia (as N), nitrate
(as N), calcium, chloride, magnesium, manganese (filtered), total iron (filtered),
potassium, sodium, sulphate, TDS, and TOC);
- Groundwater flow contour plan;
- Ammonia and TDS iso-concentration maps;
- NATA-stamped laboratory certificates for all results;
- signed chain of custody and laboratory sample receipt records;
- trend analysis for groundwater reduced level, ammonia, nitrate, and TDS;
- Exceedances of beneficial use criteria;
- Equipment calibration certificates; and
- Originals of the groundwater, surface water and leachate field record sheets.
For LFG monitoring:
- tabulated field parameters and laboratory analytical data, including graphical
presentation of trends for key parameters;
- NATA-stamped laboratory certificates for all results;
- signed chain of custody and laboratory sample receipt records;
- trend analysis for groundwater reduced level, ammonia, nitrate, and TDS;
- Exceedances of EPA(2015b) BPEM action levels;
- Equipment calibration certificates; and
- Originals of LFG field record sheets.
An electronic recording device (CD-ROM or USB memory stick) containing the annual
data set as well as a copy of the entire updated database.
An assessment of performance.
May 2016
Page 96
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
An annual licence compliance report should be prepared in support of the Annual
Performance report as well as the QA/QC monitoring requirements listed in the landfill
compliance risk register (Appendix F).
The annual report should also assess performance against the leachate bore level, LIS flow,
groundwater level, and groundwater chemistry triggers as described in the Cardno (2015b)
Hydrogeological Assessment.
10.1.6 Monitoring contractor requirements (Cat B)
The monitoring contractor is required to be to be prequalified, suitably qualified and
experienced to undertake the monitoring in accordance with EPA guidelines and industry
standards of practice. The pre-qualification criteria are:
operates under a quality management system certified under ISO/AS9001, covering the
monitoring activities contained in this specification;
procedures for each of the monitoring activities required by the program;
has written Safe Work Procedures for the required work;
has staff experienced and trained in the requisite monitoring tasks;
operates a suitably qualified NATA certified chemical testing laboratory (able to conduct
tests and issue NATA reports for ALL of the requisite testing) OR has a service agreement
with a suitable NATA certified laboratory;
has a service agreement with a second or quality control laboratory;
owns and operates OR has a service agreement with a provider of all requisite field
equipment and instruments;
has a data validation procedure and system;
operates a data management system using compatible with ESDAT software operated
by the client’s consultants and Auditor;
experienced in reporting monitoring results to EPA and or EPA-appointed Environmental
Auditors; and
documented evidence of all of the above must be submitted to GSC for pre-
qualification.
10.2 Environmental audit program
The next audit of landfill operation is scheduled for 31st October 2017 with the audit period
being up to 30th June 2017. Thereafter, and subject to the outcome of the 2017 audit, the
subsequent audits should be undertaken every two years unless superseded by the yet to be
developed environmental monitoring program which will be required under the Closed Landfill
supporting PAN for aftercare.
10.3 Reverification
This updated Monitoring Program is considered to be complete and is therefore verified as
being adequate for GSC and the EPA to determine compliance with the licence.
May 2016
Page 97
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
11. Conclusions
Risk of landfill operations to beneficial uses identified by the environmental Auditor
1 The Nolan Consulting (2014) risk assessment, including the risk registers, has been
reviewed. The risk register has been updated as part of the audit. No changes to the risk
profile have been required.
2 The following are considered to be very high risks:
groundwater contamination by leachate:
from active cell (on site);
from active cell (off site);
via unsaturated zone (on site); and
via unsaturated zone (off site).
3 The following are considered to be high risks:
LFG migration via unsaturated zone (on-site);
groundwater contamination by leachate from active waste cell impacting on
down gradient groundwater users; and
asphyxiation resulting in death or serious injury of site workers caused by a LFG
explosion via unsaturated zone migration.
4 The following are considered to be medium risks:
corrosion of on-site transmission towers via leachate through the unsaturated zone;
and
litter from active waste cell on the health of flora & fauna and visual amenity;
windblown and traffic generated litter from active waste cell on amenity of on-site
workers;
windblown dust from site activities and traffic on amenity of on-site workers;
windblown dust from site activities on health of on-site workers and humans at
nearby residences and Yarraman Park;
traffic generated on health of on-site workers;
odour from leachate storage dam on amenity of workers;
toxic gases (H2S) on health of maintenance workers;
noise from machinery, equipment, and traffic on amenity of workers;
leachate, via runoff and/or groundwater pathways, on surface water beneficial
uses;
contamination of land by overfilling of leachate storage dam;
on-site groundwater caused by increased level in leachate storage dam
increasing infiltration through unsaturated zone;
vermin from active waste cell on amenity of on-site building occupants and
humans at and in the vicinity of the landfill;
damage to flora due to fire at active waste cell;
May 2016
Page 98
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
poor weed management within the site on amenity and local flora; and
erosion from capped landfill on on-site flora and fauna.
5 The beneficial uses adopted for the atmosphere at the premises, groundwater beneath
the premises, any surface water on the premises and the environment surrounding the
premises are appropriate.
6 The environmental aspects adopted in the updated risk register are comprehensive and
appropriate.
Assessment of implementation of the Monitoring Program
7 The previously verified Monitoring Program (Nolan Consulting; 2014) was structured as
specific sub-programs for individual environmental elements.
8 There are two generic categories of monitoring within the verified environmental
programs. These are Category A for regular or incident driven inspections by trained GSC
staff and Category B for groundwater, leachate, and LFG sampling and testing based
programs.
9 The Category A monitoring activity is observation (visual and olfactory) by trained GSC
staff. The verified Monitoring Program requires evidence of the observations to be
reported.
10 Implementation of the Category A monitoring is progressing. Further improvements are
required in staff training, systematic monitoring and reporting.
11 The Environmental Monitoring contract includes most Category B monitoring
requirements presented in the verified Environmental Monitoring program.
12 The Category B groundwater and leachate monitoring sub-program was implemented
in accordance with the verified monitoring program except for:
a level data logger has not been installed in LIS bore IB5;
new groundwater bores PO34A, PO34B, PO35A and PO35B and new leachate
monitoring bores LB01R and LB02RA are yet to be not surveyed;
flow meter on LIS discharge line has failed;
pulse counters (for flow) and data loggers (for level) installed but are yet to be
reported;
chain of custody forms do not to identify sample containers;
trip blank sample not obtained during the VOC sampling; and
completed groundwater bore purging and sampling records do not report on bore
condition.
13 The LFG monitoring sub-program was implemented in accordance with the verified
monitoring program except for:
monitoring records of pits and other enclosed spaces did not include location
details, evidence of corrosion, and presence of odours;
LFG monitoring in building records do not include location details (e.g. monitor
positions, building conditions, and presence of odours);
monitoring for signs of corrosion at the bore network is not undertaken, and
reporting of corrosion monitoring results needs to be documented ;
May 2016
Page 99
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
LFG surface monitoring is limited to a few (nine) locations on Area A and B and
does not include Area A and B vegetated areas and sections of Area C which has
not been filled within any three month period.
plant health at and within 50 m of the landfill while monitored is not fully reported.
14 LFG monitoring data is not incorporated into the integrated monitoring database.
15 The annual monitoring report requires a declaration that the monitoring program was
completely in accordance with the verified monitoring program and explains any non-
conformances, including names of persons responsible for each component of the
monitoring program.
Interpretation of monitoring results - groundwater
16 The background groundwater is within Segment A2 (less than 1,000 mg/L).
17 The groundwater salinity immediately down-gradient of Areas A and B is close to the
leachate salinity, and the salinity down-gradient of Area C that is elevated above
background but less than the leachate salinity. The salinity plume extends to the north-
east (including to the east of Cape Nelson Road).
18 The background groundwater ammonia concentration is less than 100 µg/L.
19 Elevated ammonia contamination of the groundwater, at concentrations of 5 mg/L and
above, occur immediately down-gradient of Area A and to the east of the landfill site.
There are moderate levels of ammonia contamination immediately down-gradient of
Area C, immediately down-gradient of Area A/B, to the east of Cape Nelson Road, and
north-west of Yarraman Park.
20 The elevated TDS and ammonia concentrations are associated with landfill leachate.
21 Evidence of nitrate concentration above the ANZECC (2000) Ecosystem Freshwater 95th
percentile guideline values are inconsistent and do not reflect the salinity and ammonia
contamination plume.
22 Volatile fatty acids are indicators of leachate contamination. Concentrations of 20 mg/L
or above were only found in April 2015 at PO32A (300 m north-east of the site entrance).
23 The average Mulvey L/N ratios at the leachate monitoring bore L/N ratio is 161. The only
groundwater bores with ratios above 10 that may be indicative of a leachate impact
are at PO18R (along eastern boundary), PO08R (between IB6 and IB7), PO32 (300 m
north-east of the site entrance), PO03 (along western boundary), and PO01 (south-side
of Derril Road).
24 There is negligible evidence of volatile organic and semi-volatile organic compounds in
the groundwater. There were no exceedances of the ANZECC (2000) Ecosystem
Freshwater 95th percentile trigger value and the Australian Drinking Water Guidelines
health guideline values for these compounds except for benzene at PO07 and LIS bores
IB4 and IB8 which marginally exceed the AWDG health guideline value of 1 µg/L.
25 The leachate plume extends at least 400 m to the north-east of Derril Road and possibly
550 m to Madeira-Packet Road as well as to the east of Cape Nelson Road.
26 This 2016 Audit of Landfill Operation has found that the October 2015 plume extent has
stabilised since June 2014 with reductions in ammonia concentrations within the main
leachate plume,
May 2016
Page 100
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Interpretation of monitoring results – landfill gas
27 All boundary LFG probes recorded methane at concentrations below the BPEM
boundary action level of 1% v/v at all monitoring events except for LFG23 at one
monitoring event when 1.0% was recorded.
28 Of the perimeter bores LFG monitoring bores LFG02, LFG07, LFG23 and LFG24 have with
CO2 concentrations that are consistently over 1%v/v above background. These are
located along the eastern boundary except for LFG07 which is located in the south-west
corner.
29 Isolated CO2 concentrations of greater than 1%v/v above background have occurred
at monitoring bores LFG03, LFG06, LFG11, LFG12, LFG15, LFG19, and LFG22.
30 All CO2 concentrations are less than 10 % v/v above background except for LFG02 which
is up to 14.2 % v/v above background concentration.
31 The maximum gas screening value (GSV) for CO2 is 0.044 L/hr which based upon CIRIA
(2007) represents a very low risk.
32 The CO2 concentrations at joint LFG probe/EPA (2015a) Landfill BPEM compliant bores
sites for LFG08/8A, LFG10/10A, LFG18/18A and LFG20/20A are consistent between bores
and probes. The key exceptions are for LFG10/10A, and LFG20/20A in the August 2015
monitoring event. In both occasions the probes recorded 0.1% v/v and the bores
recorded 1.0% v/v to 1.1% v/v. As the results are inconclusive ongoing monitoring of the
probes and bores up to the end of 2015/16 year is recommended.
33 While the reported CO2 exceedances of the EPA (2015a) Landfill BPEM action level are
relatively minor, and are unlikely to be landfill sourced, the potential for subsurface
migration of CO2 from the landfill cannot be excluded.
34 Monitoring of the Area A and Area B landfill surface has found methane concentrations
above the 200 ppm action level at several locations. These are generally in areas with
poor vegetation development.
35 While the recapping of the majority of Area A and B should reduce methane
concentration at the surface to below the final cap action level of 100 ppm there is a risk
of lateral migration within the lower lying areas which will not be recapped due to the
presence of native vegetation.
36 The methane concentrations within all building, structures and subsurface services were
well below the EPA (2015a) Landfill BPEM action levels, except for one instantaneous
methane concentrations of 22.0 ppm found outside the stormwater drain at Cape Nelson
Road near the cemetery gate. This is well below the EPA (2015a) Landfill BPEM action
level of 5,000 ppm.
37 There are no obvious LFG trends based upon the limited set of historical records.
Updated Monitoring Program
38 The Monitoring Program (Nolan Consulting; 2014) has been updated as part of this Audit
of Landfill Operation to reflect the revised CSM, the updated risk assessment, the
verification auditor’s comment’s, the Monitoring Program assessment, and progress with
implementing the 2014 Audit of Landfill Operation recommendations.
May 2016
Page 101
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
39 The updated Monitoring Program includes the following elements:
roles and responsibilities;
Category A monitoring (visual and olfactory);
Category B monitoring (groundwater);
Category B monitoring (LFG);
reporting; and
contractor requirements.
40 In general the updates are of a minor nature. The key changes are the inclusion of one
additional groundwater monitoring bore, two additional leachate monitoring bores, and
the expansion of the methane landfill surface monitoring program.
41 The updated Monitoring Program is verified as meeting the EPA (2011b) Landfill Licensing
Guidelines requirements and being adequate for GSC and the EPA to determine
compliance with the licence.
Implementation of progressive rehabilitation
42 GSC has scheduled the landfill to close following the commissioning of the transfer
station. This is expected to occur in mid-2016.
43 The Rehabilitation Plan has been approved by the EPA. This includes the top of waste
Pre-settlement Contour Plan.
44 The Technical Specification and Construction Quality Assurance Plan for Phase 1
Capping (Stages 1 and 2 cap) have been completed.
45 Phase 1 capping is expected to occur in the 2016/17 financial year. The delay from that
scheduled in the Rehabilitation Plan is due to the need to address native vegetation
management issues as required under the Environment Protection and Biodiversity
Conservation Act 1999 and to consider alternative capping design options.
May 2016
Page 102
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
12. Recommendations
This section of the audit report presents the environmental audit recommendations. The
recommendations are based on risk assessment and are prioritised as defined in Table 12-1.
Table 12-1: Definition of priorities of auditor recommendation
Priority Description
High Requires immediate action to manage high environmental risk or mitigate high
impact
Medium Requires prompt action (within six months) to manage moderate to low impact.
Low Requires action prior to the next Landfill Operation Audit to manage a low
environmental risk, or mitigate a low impact.
The recommended completion dates of several low priority recommendations are in advance
of the next Landfill Operation Audit as it is practical to do and is considered desirable to provide
the information required to monitor changes to the risk profile.
The recommended completion dates of several high priority recommendations are not
immediate as additional monitoring, design or construction is required. For these
recommendations the completion dates are considered that which can be practically
achieved based upon an immediate and prioritised focus.
The recommendations are presented in Table 12-2. These recommendations incorporate the
outstanding recommendations from the Nolan Consulting (2014) “Section 53V Audit – Landfill
Operation, Portland Landfill – 210 Cape Nelson Road Portland”.
Table 12-2: Audit of Portland Landfill operation recommendations
No Recommendation Risk rating Recommended
completion date
Monitoring program
1 Implement updated Monitoring Program including: High Ongoing
a) Install, survey, and monitor additional leachate monitoring
bores.
Centre of Area A (to base of waste); and
Centre of Area B (to base of waste).
High Aug 2016
b) Install, survey and monitor one additional groundwater
monitoring bore in the vegetated area between Area C and
the northern site boundary.
High Aug 2016
c) Install a level data logger in LIS bore IB5. High Aug 2016
d) Install temporary weather station at site to monitor rainfall and
evaporation.
Med Nov 2016
e) Survey new groundwater bores PO34A, PO34B, PO35A and
PO35B, new leachate monitoring bores LB01R and LB02RA, and
the above proposed bores to AHD and location.
Low Dec 2016
f) Maintain the flow meter on the LIS discharge line. High Ongoing
g) Ensure chain of custody forms identify sample containers. Low Ongoing
h) Ensure trip blank sample are obtained during the VOC
sampling.
Low Ongoing
i) Ensure groundwater bore purging and sampling records report
on bore condition.
Low Ongoing
May 2016
Page 103
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
No Recommendation Risk rating Recommended
completion date
j) Undertake methane monitoring of the capped and
intermediate landfill surface, which was not been filled within
the preceding three month period. at a 25 m grid. This should
include the vegetated area of Area A and Area B.
Med First monitoring
event following
Phase 1
capping
k) Identify the location of new service pits associated with the
transfer station and ancillary facilities.
High Upon
commissioning
l) Revise building, structures and service pit LFG monitoring points
to accommodate the new transfer station and ancillary
facilities
High Upon
commissioning
m) Provide a more comprehensive report of plant health at
specific locations on the cap and within 50 m of the landfill.
Low Next audit
2 Provide all weather 4x4 vehicle access to within 5 m of all bores for
all conditions except flooding events.
Low First monitoring
event following
Phase 1
capping.
3 Establish an integrated database to hold and enable efficient
reporting of all monitoring records and data from 1989, preferably
in ESDAT format in accordance with the prepared service
specification.
Low Next audit
Hydrogeology
4 Resolve with the EPA the potential for using the Groundwater
Quality Restricted Use Zone (GQRUZ) under SEPP Groundwaters of
Victoria as a mechanism to manage this risk.
Low Next audit
Conceptual model
5 Undertake a comprehensive analysis of MSA and BFA aquifers
groundwater quality analysis that identifies discrete characteristics.
This should include using Stiff and Piper diagrams and Mulvey L/N
ratios.
Medium Mar 2017
Leachate interception system (LIS)
6 Operate the LIS in accordance with the Cardno (2015b)
“Hydrogeological Assessment for Leachate Level Management -
Portland Landfill 210 Cape Nelson Road, Portland, Vic.”
High Jul 2016
7 Monitor the LIS in accordance with the verified Monitoring Program
(Table 10-2 of this report). This includes reporting of level, flow rate,
and condition at individual LIS bores, leachate level at leachate
storage dam, flow to leachate storage dam and leachate storage
dam water balance.
High Jul 2016
8 Review the LIS monitoring data every six months to determine the
effectiveness of operation whether the leachate bore level, LIS
flow, groundwater level, and groundwater chemistry triggers are
not exceeded as described in Cardno (2015b) “Hydrogeological
Assessment for Leachate Level Management - Portland Landfill 210
Cape Nelson Road, Portland, Vic”..
High Ongoing
9 Implement an Operation & Maintenance manual and program to
provide for system monitoring and optimisation.
Med Sep 2016
Infrastructure
10 Confirm with AusNet Services that they have responsibility for
monitoring structural integrity of the HV transmission line towers
(including corrosion).
Low Next audit
May 2016
Page 104
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
No Recommendation Risk rating Recommended
completion date
LFG Risk Management
11 Review monitoring results from the LFG monitoring probe/bores
monitoring sites, to determine if any changes to the risk profile are
required.
Med Jul 2016
12 Check that the GSC restriction on residential development within
500 m of the site prevents any future residential development,
particularly of buildings with unvented basements.
Med Nov 2016
13 Review the need for LFG control in Areas A and B, particularly
around the eastern part of the site, within a thin corridor along the
southern fringe and the adjoining Malings Road reserve where the
existing cap will not be remediated.
Med First monitoring
event following
Phase 1
capping.
Planning
14 Investigate and implement a mechanism to control proposed
developments within 500 m from the landfill. This would involve a
trigger to identify planning permit applications for such
developments and a process to identify and mitigate risk such as
through an Environmental Significance Overlay or an
Environmental Audit Overlay.
Low Next audit
15 Complete Aftercare Management Plan in accordance with the
Post Closure Supporting PAN.
Med In accordance
with PAN
requirements.
Operational
16 Ensure the stormwater drainage system for the Phase 2 cap is
designed for the whole site and includes adequate stormwater
sedimentation pondage(s) to allow capture and treatment of
stormwater prior to discharge from the site.
Low With Phase 2
cap design
17 Ensure the Phase 2 cap design considers the management of the
shallow fill found to the north-west of the leachate storage dam as
part of the drilling program to install monitoring bore 35A/B.
Med With Phase 2
cap design
18 Remediate the existing perimeter drainage system. Low Next audit
19 Improve operational management procedures as per the Landfill
Compliance Risk Register (Appendix F). These include:
Establish a procedure to report on site infrastructure corrosion
inspection photographs to identify action requirements;
Low
Next audit
Ensure daily inspections are undertaken on all days in which
the landfill is operating;
Low Ongoing
Modify the daily and monthly checklists to identify the locality
where observations are made; and
Low Sep 2016
Maintain a record of visual inspections of loads at the
weighbridge.
Med Sep 2016
20 Ensure at least 300 mm of daily cover is placed on the tipping face
and the intermediate cover within Area C is maintained. This will
require additional cover over parts of Area C where litter is
emerging.
Med Ongoing
21 Fence off Area A. Low Next audit
Auditor activities
22 Review assessment of LIS system performance against triggers and
determine whether the LIS performance meets the design
objective for period from 1st January 2016 to 31st December 2016
High Feb 2017
23 Undertake for period up to 30th June 2017. Medium 31st Oct 2017
May 2016
Page 105
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
13. Applicability
This environmental audit report (“Report”) has been prepared in accordance with Part IXD of
the Environmental Protection Act 1970. The objective of the audit is to identify and, where
possible, quantify the risk of possible harm or detriment to a segment of the environment
caused by the operation of the Portland landfill.
This Report:
1. has been prepared by John Nolan and his team as indicated in the appropriate sections
of this Report (“Nolan Consulting”) for the Glenelg Shire Council (“Council”).
2. may be used and relied on by Council and EPA Victoria.
3. may be provided to other third parties but such third parties’ use of or reliance on the
Report is at their sole risk.
The maximum extent permitted by law, all implied warranties and conditions in relation to the
services provided by Nolan Consulting and the Report are excluded unless they are expressly
stated to apply in this Report.
The services undertaken by the Auditor, his team and Nolan Consulting in connection with
preparing this Report were undertaken in accordance with current professional practice and
by reference to relevant environmental regulatory authority and industry standards in
accordance with Section 53V of the Environment Protection Act 1970.
The opinions, conclusions and any recommendations in this Report are based on assumptions
made by the Auditor, his team and Nolan Consulting when undertaking services and preparing
the Report (“Assumptions”), as specified throughout this Report.
Nolan Consulting and the Auditor expressly disclaim responsibility for any error in, or omission
from, this Report arising from or in connection with any of the Assumptions being incorrect.
Subject to paragraphs in this section of the Report, the opinions, conclusions and any
recommendations in this Report are based on conditions encountered and information
reviewed at the time of preparation of this Report and are relevant until such times as the site
conditions or relevant legislations changes, at which time, Nolan Consulting expressly disclaims
responsibility for any error in, or omission from, this Report arising from or in connection with
those opinions, conclusions and any recommendations.
The Auditor and Nolan Consulting have prepared this Report on the basis of information
provided by Council, which the Auditor and Nolan Consulting have not independently verified
or checked (“Unverified Information”) beyond the agreed scope of work.
Authorised on 26th May 2016 by:
John Nolan
Environmental Auditor
(appointed pursuant to the Environmental Protection Act 1970)
May 2016
Page 106
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
14. References
Legislation and Regulations
Government of Victoria (1970), “Environment Protection Act, 1970”, Act No. 8056/1970).
Government of Victoria (1988), “Flora and Fauna Guarantee Act, 1988”.
Government of Victoria (1994), “Catchment and Land Protection Act, 1994”.
Government of Victoria (1997), “State Environment Protection Policy (Groundwaters of
Victoria)”.
Government of Victoria (1994), “Catchment and Land Protection Act, 1994”.
Government of Victoria (2001), “State Environment Protection Policy (Air Quality
Management)”.
Government of Victoria (2002), “State Environment Protection Policy (Prevention and
Management of Contaminated Land)”.
Government of Victoria (2003), “Variation to State Environment Protection Policy (Waters of
Victoria)”.
Government of Victoria (2004), “Waste Management Policy (Siting, Design and Management
of Landfills)”.
Guidelines
Australian and New Zealand Environment Conservation Council ANZECC (1992), “Australian
Water Quality Guidelines for Fresh and Marine Waters”.
Australian and New Zealand Environment Conservation Council (2000), “Australian and New
Zealand Guidelines for Fresh and Marine Water Quality”.
Australian Standard (2009), “AS2159-2009: Piling – Design and Installation”.
CIRIA (2007), “Assessing Risk Posed by Hazardous Ground Gases to Buildings”, CIRIA
Publication C665.
Food Standards Australia New Zealand (2014), ”Australia New Zealand Food Standards Code
- Standard 2.6.2 - Non-Alcoholic Beverages and Brewed Soft Drinks”.
National Health and Medical Research Council (2008), “Guidelines for Managing Risks in
Recreational Waters”.
National Health and Medical Research Council and Natural Resources Management
Ministerial Council (2011), “National Water Quality Strategy: Australian Drinking Water
Guidelines 6 2011”.
UK Environment Agency (2004), “Guidance on the Management of Landfill Gas”, September
2004
EPA References
EPA (2000), “Groundwater Sampling Guidelines”, Publication 669.
EPA (2009), “Sampling and Analysis of Waters, Wastewaters, Soils and Wastes”, Publication
IWRG701.
May 2016
Page 107
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
EPA (2010), “Clean Up Notice pursuant of Section 62A of the Environment Protection Act 1970”,
2 March 2010.
EPA (2011a), “Licensing Assessment Guidelines – Guidelines for Using a Risk Assessment
Approach to Assess Compliance with Licence Conditions”, Publication No. 1321.2, June 2011.
EPA (2011b), “Landfill Licensing Guidelines”, Publication 1323.2, August 2011.
EPA (2011c),”Draft Landfill Gas Fugitive Emissions Monitoring Guidelines”, Publication 1416,
September 2011.
EPA (2011d), “Noise from Industry in Regional Victoria Recommended Maximum Noise Levels
from Commerce, Industry and Trade Premises in regional Victoria”, Publication No. 1411,
October 2011”.
EPA (2014), “Glenelg Shire Council, EPA Licence”, last amended on 30 June 2014.
EPA (2015a) “Best Practice Environmental Management Siting, Design, Operation and
Rehabilitation of Landfills”, Publication 788.3, August 2015.
EPA (2015b), “Preparation of Environmental Audit Reports on Risk to the Environment”,
Publication 952.5, 21st December 2015.
General information
Government of Victoria (current), “Victorian Water Measurement Information System”, web
based product.
Site Specific References
AGC Woodward-Clyde (1991), “Leachate Interception system borefield design”.
AGC Woodward-Clyde (1992), “Proposal for licence amendment and supporting
documentation for Works Approval in the Matter of AAT Appeal No 1992/11803 & 1991/42675”,
for Portland City Council, June 1992.
Cardno (2015a), “Upgrade to Groundwater & Leachate Monitoring Network Portland Landfill,
210 Cape Nelson Road, Portland, Victoria”, 29th October 2015.
Cardno (2015b), “Hydrogeological Assessment for Leachate Level Management - Portland
Landfill 210 Cape Nelson Road, Portland, Vic.”, 11th December 2015.
Cardno LanePiper (2011a), “Landfill Risk Assessment – 210 Cape Nelson Road, Portland
Victoria”, June 2011.
Cardno LanePiper (2011b), “Landfill Monitoring Program – 210 Cape Nelson Road, Portland
Victoria”, December 2011.
Cardno LanePiper (2014a), “Portland Landfill Telephone Survey 210 Cape Nelson Road,
Portland, Victoria”, 5 March 2014
Cardno LanePiper (2014b), “Hydrogeological Assessment - Portland Landfill, 210 Cape Nelson
Road, Portland, VIC”, April 2014.
Cardno LanePiper (2014c), “Leachate Interception System Upgrade Feasibility, Portland
Landfill – 210 Cape Nelson Road, Portland Victoria”, October 2014.
Geological Survey of Victoria (1978), “Portland 1:63,360 Geological Mapsheet”.
May 2016
Page 108
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
GHD (2011), “Report for Further Investigation of Waste Disposal Options – Stormwater
Management Plan”, report to Glenelg Shire Council, September 2011.
GHD (2013), “Portland Landfill Rehabilitation Plan”, report to Glenelg Shire Council, October
2013.
GHD (2015a), “Portland Landfill Leachate storage dam Liner Geotechnical Report”, report to
Glenelg Shire Council, 27th May 2015.
GHD (2015b), “Portland Landfill Annual Environmental Monitoring Results Report 2014/15”,
report to Glenelg Shire Council, 20th August 2015.
GHD (2015c), “Landfill Leachate Interception Bores Pump Installation”, report to Glenelg Shire
Council, 8th September 2015.
GHD (2015d), “Portland Landfill Annual Performance Statement 2015 Supporting Information
Report”, report to Glenelg Shire Council, 10th September 2015.
GHD (2015e), “Portland Landfill Rehabilitation - Phase 1 Landfill Cap Technical Specification”,
report to Glenelg Shire Council, November 2015
GHD (2015f), “Portland Landfill Rehabilitation - Phase 1 Landfill Cap Design Drawings”, report to
Glenelg Shire Council, November 2015
GHD (2015g), “Portland Landfill Rehabilitation - Phase 1 Landfill Cap CQA Plan”, report to
Glenelg Shire Council, November 2015.
GHD (2015h), “Portland Landfill Stages 1 and 2 Final Cap Design Auditor Assessment”, report to
Glenelg Shire Council, December 2015.
Glenelg Shire Council (2011a), “Portland Landfill Licence HS776 Clean up Plan“, 3rd March 2011.
Glenelg Shire Council (2011b), “Plant Health Survey Portland Landfill”, May 2011.
Glenelg Shire Council (2014), “EPA Annual Performance Statement 2014-2015”.
Glenelg Shire Council (2015), “Portland Transfer Station – Landfill Gas Risk Assessment”.
Lane Piper (2010a), “Environmental Audit Report (Groundwater - 2010) - 210 Cape Nelson
Road, Portland”, 30 July 2010.
Lane Piper (2010b), “Environmental Audit Report (Landfill Gas) - 210 Cape Nelson Road,
Portland”, 3 December 2010.
LMS Generation Pty Ltd (2007), “Landfill Gas Evaluation of the Portland Landfill”, June 2007.
Nolan Consulting (2014) “Section 53V Audit – Landfill Operation, Portland Landfill – 210 Cape
Nelson Road Portland”, CARMS Ref. No. 67141-4, Service Order No. 8004179, November 2014.
Senversa (2013), “Landfill Cap Investigation Portland Landfill”, April 2013.
May 2016
Page 109
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
15. List of abbreviations and units
Chemical Names
BOD Biological Oxygen Demand
BTEX Benzene, Toluene, Ethylbenzene & Xylenes (subset of MAH)
MAH Monocyclic Aromatic Hydrocarbons
OCP Organo Chlorine Pesticides
PAH Polycyclic Aromatic Hydrocarbons
SVOC Semi-Volatile Organic Compounds
TDS Total Dissolved Solids (salinity of water)
TOC Total Organic Carbon
VOC Volatile Organic Compound
Technical Terms
AHD Australian Height Datum
AMG Australian Map Grid
ANZECC Australian and New Zealand Environment and Conservation Council
BFA Bridgewater Formation Aquifer
BGL Below Ground Level
CQAP Construction Quality Assurance Plan
COC Chain of Custody
DO Dissolved Oxygen
EC Electrical Conductivity
EPA Environmental Protection Authority
GCMS Gas Chromatograph - Mass Spectrometer
LFG Landfill Gas
LOR Limit of Reporting
MSA Malanganee Sands Aquifer
NEPM National Environmental Protection Measure
NVA Newer Volcanic Aquifer
N/A Not Applicable
PSCP Pre-settlement Contour Plan
QA Quality Assurance
QC Quality Control
RPD Relative Percentage Difference
May 2016
Page 110
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Units
Ha Hectares
mAHD metres Australian Height Datum
mg/L Milligram per Litre
mTOC Metres below Top of Casing
ppb Part per Billion
ppm Parts per Million
μg/L Microgram per Litre
μS/cm Micro Siemens per Centimetre (Electrical Conductivity - Water)
May 2016
Portland Landfill - 210 Cape Nelson Road, Portland
Section 53V Audit
Nolan Consulting Pty Ltd
67141-5_a.docx
Figures (after Cardno; 2015b)
Figure 1: Site Locality Plan
Figure 2: Landfill Development Sequence
Figure 3: Bore Location Plan
Figure 4: Landfill Gas Bore Location Plan
Figure 5: Leachate Collection System
Figure 6: Regional Geology
Figure 7: Geological Cross-Section A-A’
Figure 8: Geological Cross-Section B-B’
Figure 9: Groundwater Elevation (April 2015)
Figure 10: Groundwater Hydrographs
Figure 11: Groundwater Database Search Results
Figure 12: Groundwater Salinity (April 2015)
Figure 13: Groundwater Ammonia Concentration (April 2015)
Base
image a
fter
Maps(
2010)
PR
OJE
CT:
RE
F: F
igure
1.c
dr
SC
ALE
: S
ee s
cale
bar
DR
AW
N: D
JL
RE
V: 1
FIG
: 1
JOB
No: 209195.8
TIT
LE
:
Site
Loca
lity
Pla
n
N
Site
Loca
tion
DA
TE
: O
ctober
2015
H
ydro
ge
olo
gic
al A
sse
ssm
en
t
P
ort
lan
d L
an
dfil
l
21
0 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d,
Vic
fo
r P
AN
01.0
2.0
km
PR
OJE
CT:
RE
F: F
igure
2.c
dr
SC
ALE
: S
ee s
cale
bar
DR
AW
N: D
JL
RE
V: 1
DA
TE
: N
ove
mber
2015
FIG
: 2
JOB
No: 209195.8
TIT
LE
: La
nd
fill D
eve
lop
me
nt
Se
qu
en
ce
N
SC
AL
E
0100
200m
Malin
gs R
oad
De
rril
Ro
ad
Base
image a
fter
NearM
ap (
2015)
H
ydro
ge
olo
gic
al A
sse
ssm
en
t
P
ort
lan
d L
an
dfil
l
21
0 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d,
Vic
fo
r P
AN
Cap
e N
elso
n R
oad
Are
a A
: F
illin
g c
om
mence
d
in la
te 1
950s-
early
1960s
Rehabili
tate
d 1
983
Lim
est
one q
uarr
ying p
rior
to c
om
mence
ment
of
fillin
g
Are
a A
LE
GE
ND
Are
a C
Are
a B
N
Are
a B
: F
illin
g c
om
mence
d
in 1
983
Curr
ently
act
ive
Are
a C
: F
illin
g c
om
mence
d
in 1
992
Curr
ently
act
ive
Cap
e N
elso
n R
oad
McN
eilly
s R
oad
PR
OJE
CT:
RE
F: F
igure
3.c
dr
SC
ALE
: S
ee s
cale
bar
DR
AW
N: D
JL
RE
V: 1
DA
TE
: O
ctober
2015
FIG
: 3
JOB
No: 209195.8
TIT
LE
:
Bo
re L
oca
tion
Pla
n
N
Se
ctio
n L
ine
LE
GE
ND
A
A’
0100
200m
SC
AL
E
H
ydro
ge
olo
gic
al A
sse
ssm
en
t
P
ort
lan
d L
an
dfil
l
21
0 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d,
Vic
fo
r P
AN
Site
Bo
un
da
ry
Gro
un
dw
ate
r M
on
itorin
g B
ore
Le
ach
ate
In
terc
ep
tion
Bo
re
Lea
cha
te M
on
itorin
g B
ore
IB7
PO
24
LB
03
A’
IB4
IB5
IB6R
IB7
PO
11R
PO
5RP
O3 P
O2
PO
10
PO
9
PO
4
PO
1P
O13
PO
22
PO
19R
PO
6
LB
03
PO
20
PO
8R
PO
23
PO
24
PO
21
PO
18R P
O16
PO
17PO
14
PO
15R
PO
7
LB
01A
LB
02R
A
PO
26A
PO
26B
PO
33B
PO
30
PO
32
PO
28
PO
29
IB8
PO
33A
PO
31A
PO
31B
B’
BM
alin
gs R
oad
Cap
e N
elso
n R
oad
De
rril
Ro
ad
McN
eilly
s R
oad
A
A’
PO
12
PO
25
Ba
se im
age a
fter
Ne
arM
ap (
2015)
PO
34B
PO
34A
PO
35B
PO
35A
Lan
dfil
l Ga
s B
ore
(
ba
ckg
rou
nd
)L
FG
25
LF
G25
LB
01
PR
OJE
CT:
RE
F: F
igure
4.c
dr
SC
ALE
: S
ee s
cale
bar
DR
AW
N: D
JL
RE
V: 1
DA
TE
: N
ove
mber
2015
FIG
: 4
JOB
No: 209195.8
TIT
LE
: La
nd
fill G
as
Bo
re L
oca
tion
Pla
n
N
LE
GE
ND
SC
AL
E
0100
200m
LF
G04
LF
G17
LF
G05
LF
G06
LF
G08
LF
G13
LF
G18
A
LF
G19
LF
G21
LF
G03
LF
G02
LF
G11
LF
G12
LF
G14
LF
G15
LF
G16
LF
G22
LF
G23
LF
G24
LF
G01
Malin
gs R
oad
Cap
e N
elso
n R
oad
McN
eilly
s R
oad
LF
G07
LF
G10
A
LF
G20
De
rril
Ro
ad
LF
G18
LF
G08
A
LF
G20
A
LF
G10
Site
Boundary
LF
G02
La
nd
fill G
as
Bo
re
Ba
se im
age a
fter
Eart
h (
2014)
LFG
09A
H
ydro
ge
olo
gic
al A
sse
ssm
en
t
P
ort
lan
d L
an
dfil
l
21
0 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d,
Vic
fo
r P
AN
PR
OJE
CT:
RE
F:
5F
igure
.cdr
SC
ALE
: S
ee s
cale
bar
DR
AW
N: D
JL
RE
V: 1
DA
TE
: O
ctober
2015
FIG
: 5
JOB
No: 209195.8
TIT
LE
:
Le
ach
ate
Co
llect
ion
Sys
tem
N
LE
GE
ND
Site
Bo
un
da
ry
Le
ach
ate
In
terc
ep
tion
Bo
re
0100
200m
SC
AL
E
Site
Bo
undary
IB4
H
ydro
ge
olo
gic
al A
sse
ssm
en
t
P
ort
lan
d L
an
dfil
l
21
0 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d,
Vic
fo
r P
AN
IB4 IB
8
IB6R
IB7
Leach
ate
Sto
rage D
am
Com
pre
ssor
House
Leach
ate
Pip
elin
eIB5
Ba
se im
age a
fter
NearM
ap (
2015)
PR
OJE
CT:
RE
F: F
igure
6.c
dr
SC
ALE
: S
ee s
cale
bar
DR
AW
N: D
JL
RE
V: 1
DA
TE
: O
ctober
2015
FIG
: 6
JOB
No: 209195.8
TIT
LE
:
Re
gio
na
l Ge
olo
gy
00.5
1.0
km
Hyd
rog
eo
log
ica
l Ass
ess
me
nt
Po
rtla
nd
La
nd
fill
2
10
Ca
pe
Ne
lso
n R
oa
d,
Po
rtla
nd
, V
ic
fo
r P
AN
Aft
er:
Ge
olo
gic
al S
urv
ey
of
Vic
toria
(1
96
7)
LE
GE
ND
Sw
am
p, peat deposi
ts; lim
est
ones
and m
arls
Brid
ge
wa
ter
Fo
rma
tion
A
lluvi
um
, beach
and d
une s
ands
Sili
ceous
sand d
unes
and s
heets
Basa
lt flo
ws
and c
ones
Qu
ate
rnary
R Ma
Ml
Bl
b2
Ne
we
r V
olc
an
ics
Calc
are
ous
dunes
and d
une li
mest
ones
Mala
nganee S
ands
N
PR
OJE
CT:
RE
F: F
igure
7.c
dr
RE
V: 1
DA
TE
: O
ctober
2015
FIG
: 7
JOB
No: 209195.8
Ge
olo
gic
al C
ross
-Se
ctio
n A
-A’
SC
ALE
: As
Show
n
DR
AW
N: D
JL/A
VM
TIT
LE
:
50
40 30 20 10
40
30
20 10
RL
(mA
HD
)
RL
(mA
HD
)
SE
CT
ION
A-A
’
50
Impo
rted
cla
y (le
acha
te d
am)
Silt
y to
cla
yey
sand
Silt
y, c
alca
reou
s sa
nd, c
lay,
lim
esto
ne
Bas
alt
LAND
FILL
MAL
ANG
ANEE
SAN
D
BRID
GEW
ATER
FO
RMAT
ION
NEW
ER V
OLC
ANIC
S
LE
GE
ND
Dril
l hol
e tr
ace
show
ing
bore
scr
een
QU
AT
ER
NA
RY
AG
E
Ro
ad
P0
1P
01
3
Site
Bo
un
da
ry
8.0
m
5.7
m
15.0
m7.0
m
22.0
m
Land
fill w
aste
HO
RIZ
ON
TA
L S
CA
LE
0100
200 m
Sta
ndin
g W
ater
Lev
el
P026B
Le
ach
ate
D
am
Site
Bo
un
da
ry
H
ydro
ge
olo
gic
al A
sse
ssm
en
t
P
ort
lan
d L
an
dfil
l
21
0 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d,
Vic
fo
r P
AN
P026A
(Looki
ng N
ort
h -
West
)
P0
14
LB
01
A
9.0
m
(Apr
il 20
15)
AA
’
PR
OJE
CT:
RE
F: F
igure
8.c
dr
RE
V: 1
DA
TE
: O
ctober
2015
FIG
: 8
JOB
No: 209195.8
Ge
olo
gic
al C
ross
-Se
ctio
n B
-B’
SC
ALE
: S
ee s
cale
bar
DR
AW
N: D
JL/C
FN
TIT
LE
:
50
40 30 20 10
40
30
20 10
1
RL
(mA
HD
)
RL
(mA
HD
)
SE
CT
ION
B-B
’
1
50
HO
RIZ
ON
TA
L S
CA
LE
Land
fill w
aste
Silt
y to
cla
yey
sand
Silt
y, c
alca
reou
s sa
nd, c
lay,
lim
esto
ne
Bas
alt
LAND
FILL
MAL
ANG
ANEE
SAN
D
BRID
GEW
ATER
FO
RMAT
ION
NEW
ER V
OLC
ANIC
S
LE
GE
ND
QU
AT
ER
NA
RY
AG
E
Sta
ndin
g W
ater
Lev
el
Dril
l hol
e tr
ace
show
ing
bore
scr
een
050
100
150
200 m
LB
02R
A
P0
25
P033B
18.0
m
9.0
m
15.0
m
P033A
P032
P031B
P031A
P010
Site
Bo
un
da
ryS
ite B
ou
nd
ary
6.0
m12.0
m2.5
m
5.1
m
5.0
m
8.5
m
P06
H
ydro
ge
olo
gic
al A
sse
ssm
en
t
P
ort
lan
d L
an
dfil
l
21
0 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d,
Vic
fo
r P
AN
BB
’
(Oct
ober
201
4)
(DR
Y)
PR
OJE
CT:
RE
F:
9F
igure
.c
dr
SC
ALE
: S
ee s
cale
bar
DR
AW
N: D
JL
RE
V: 1
DA
TE
: O
ctober
2015
FIG
: 9
JOB
No: 209195.8
TIT
LE
:G
rou
nd
wa
ter
Ele
vatio
n P
lan
(Ap
ril 2
01
5)
N
LE
GE
ND
Site
Bo
un
da
ry
Gro
un
dw
ate
r M
on
itorin
g B
ore
Leach
ate
In
terc
ep
tion
Bo
re
Lea
cha
te M
on
itorin
g B
ore
0100
200m
SC
AL
E
Ba
se im
age a
fter
NearM
ap (
2015)
H
ydro
ge
olo
gic
al A
sse
ssm
en
t
P
ort
lan
d L
an
dfil
l
21
0 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d,
Vic
fo
r P
AN
Gro
un
dw
ate
r E
leva
tion
(m
AH
D)
Mala
ng
an
ee
an
d/o
r B
rid
ge
wa
ter
F
orm
atio
n A
qu
ifers
Gro
un
dw
ate
r E
leva
tion
(m
AH
D)
Ne
we
r V
olc
an
ics
Aq
uife
r
35
.04
29
.52
40
Inte
rpre
ted
Gro
un
dw
ate
r
E
leva
tion
Co
nto
urs
Inte
rpre
ted
Gro
un
dw
ate
r
F
low
Dire
ctio
n
IB7
PO
24
LB
03
A’
IB7
PO
11R
PO
5RP
O3
PO
9
PO
4
PO
1
PO
22
PO
6
PO
20
PO
12
PO
23
PO
24
PO
21
PO
18R P
O16
PO
17PO
14
LB
01A
PO
26A
PO
26B
PO
33B
PO
32P
O30
PO
32
PO
28
PO
29
PO
33A
PO
31A
PO
31B
44
43
42
41
40
39
38
37
36
35
34
33
44
43
4241
40
39
37
36
35
34
33P
O10
PO
15R
PO
25
PO
243.8
3
32
.29
39.9
53
6.0
3
36
.13
33
.11
44.6
944.7
1
40.4
9
42.8
8
37.6
7
33
.77
38.0
3
38.0
3
35
.38
32
.15
36.1
1
33
.62
32
.76
32
.14
32
.17
32
.03
31
.84
31
.85
30
.36
32
.97
32
.76
38
32
32P
O34
BP
O34
AP
O35
BP
O35
A
IB4
PO
13
38.0
4
LB
03
IB8
IB5
IB6
33
.98
PO
7
PO
19R
35
.71
PO
8R
De
rril
Ro
ad
34
.32
33
.35
LB
02R
A
43.9
3
Dry
Dry
PR
OJE
CT:
RE
F:
10
Fig
ure
.cdr
SC
ALE
: N
A
DR
AW
N: D
JL
RE
V: 1
DA
TE
: N
ove
mber
2015
FIG
: 10
JOB
No: 209195.8
TIT
LE
:
Gro
un
dw
ate
r H
ydro
gra
ph
DA
TE
H
ydro
ge
olo
gic
al A
sse
ssm
en
t
P
ort
lan
d L
an
dfil
l
21
0 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d,
Vic
fo
r P
AN
After
GH
D (
2015)
253035404550
Jul-
12A
ug-
12Se
p-1
2O
ct-1
2N
ov-
12D
ec-1
2Ja
n-1
3Fe
b-1
3M
ar-1
3A
pr-
13M
ay-1
3Ju
n-1
3Ju
l-13
Au
g-13
Sep
-13
Oct
-13
No
v-13
Dec
-13
Jan
-14
Feb
-14
Mar
-14
Ap
r-14
May
-14
Jun
-14
Jul-
14A
ug-
14Se
p-1
4O
ct-1
4N
ov-
14D
ec-1
4Ja
n-1
5Fe
b-1
5
Reduced Water Level (m AHD)
PO
1
PO
2
PO
3
PO
4
PO
5R
PO
6
PO
7
PO
8R
PO
9
PO
10
PO
11R
PO
12
PO
13
PO
14
PO
15R
PO
17
PO
18
PO
19R
PO
20
PO
21
PO
22
PO
23
PO
24
PO
25
PO
26A
PO
26B
PO
28
PO
29
PO
30
PO
31A
PO
31B
PO
32
PO
33A
PO
33B
LB0
1
LB0
1A
LB0
2R
LB0
2RA
LB0
3
Leac
hate
Po
nd
RWL mAHD
PR
OJE
CT:
RE
F: F
igure
11.c
dr
SC
ALE
: N
A
DR
AW
N: G
GS
RE
V: 1
DA
TE
: Ja
nuary
2015
FIG
: 11
JOB
No: 209195.8
TIT
LE
: Gro
un
dw
ate
r D
ata
ba
se S
ea
rch
Re
sults
1
km
2 km
N
Ba
se
im
ag
e s
ou
rce
:
Go
og
le E
art
h (
20
14
)
Le
ge
nd
La
nd
fill
Site
Se
arc
h R
ad
ius
Bo
re T
yp
e
Irr
iga
tio
n
Ob
se
rva
tio
n /
In
ve
stig
atio
n
Sto
ck
D
om
estic
S
tock a
nd
Do
me
stic
U
rba
n
De
wa
terin
g
Un
kn
ow
n /
No
n G
rou
nd
wa
ter
H
ydro
ge
olo
gic
al A
sse
ssm
en
t
P
ort
lan
d L
an
dfil
l
21
0 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d,
Vic
fo
r P
AN
N
PR
OJE
CT:
RE
F:
12
Fig
ure
.c
dr
SC
ALE
: S
ee s
cale
bar
DR
AW
N: D
JL
RE
V: 1
DA
TE
: O
ctober
2015
FIG
: 12
JOB
No: 209195.8
TIT
LE
:G
rou
nd
wa
ter
Sa
linity
Pla
n(A
pril 2
015)
N
LE
GE
ND
0100
200m
SC
AL
E
Ba
se im
age a
fter
Ne
arM
ap (
2015)
H
ydro
ge
olo
gic
al A
sse
ssm
en
t
P
ort
lan
d L
an
dfil
l
21
0 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d,
Vic
fo
r P
AN
Site
Bo
un
da
ry
Gro
un
dw
ate
r M
on
itorin
g B
ore
Lea
cha
te I
nte
rce
ptio
n B
ore
Leach
ate
Mo
nito
rin
g B
ore
IB7
PO
24
LB
03
2300
2400
3400
1100
Mala
ng
an
ee
Fo
rma
tion
Brid
ge
wa
ter
Fo
rma
tion
Ma
lan
ga
ne
e &
Brid
ge
wa
ter
Fm
Ne
we
r V
olc
an
ics
TD
S C
on
cen
trat
ion
(m
g/L
) / A
qu
ifer
Mo
nit
ore
d
1000
Salin
ity c
on
tou
r in
terv
al
(mg
/L T
DS
)
3000
4000
2000
1000
IB6
IB7
PO
11R
PO
5RP
O3 P
O2
PO
10PO
4
PO
13
PO
22
PO
19R
PO
6
LB
03
PO
20
PO
12
PO
23
PO
24
PO
21
PO
18R
PO
16PO
14
PO
15R
PO
7L
B01
A
LB
02R
A
PO
26A
PO
26B
PO
32
PO
30
PO
32
PO
28
PO
29
IB8
PO
31A
PO
31B
3200
3100
1300
1300
980
1100
2100
1200
560
1500
600
1100
1200
2700
1600
2300
3400
780
480
540
34
00
860
430
360
1100
920
930
1400
1100
1300
2400
2700
PO
1
3400
PO
25
PO
9
PO
17
3000
4820
IB4
IB5
PO
8R
8800
2400
4500
PO
33B
PO
33A
4000
1000
5000
4000
3000
2000
1000
690
Dry
1000
1000
1000
2000
4000
2700
Lan
dfil
l Le
ach
ate
Dry
PR
OJE
CT:
RE
F:
13
Fig
ure
.c
dr
SC
ALE
: S
ee s
cale
bar
DR
AW
N: D
JL
RE
V: 1
DA
TE
: N
ove
mber
2015
FIG
: 13
JOB
No: 209195.8
TIT
LE
: Am
mo
nia
Co
nce
ntr
atio
n P
lan
N
LE
GE
ND
Site
Bo
un
da
ry
Gro
un
dw
ate
r M
on
itorin
g B
ore
Le
ach
ate
In
terc
ep
tion
Bo
re
Le
ach
ate
Mo
nito
rin
g B
ore
0100
200m
SC
AL
E
Ba
se im
age a
fter
NearM
ap (
2015)
H
ydro
ge
olo
gic
al A
sse
ssm
en
t
P
ort
lan
d L
an
dfil
l
21
0 C
ap
e N
els
on
Ro
ad
, P
ort
lan
d,
Vic
fo
r P
AN
0.5
7
0.2
7IB7
PO
24
LB
03
Am
mo
nia
Co
nce
ntr
atio
n (
mg
/L)
Mala
ng
an
ee
an
d/o
r B
rid
ge
wa
ter
Fo
rma
tion
Aq
uife
rs
Am
mo
nia
Co
nce
ntr
atio
n (
mg
/L)
Ne
we
r V
olc
an
ics
Aq
uife
r
100
In
terp
rete
d A
mm
on
iaC
on
cen
tra
tion
Co
nto
urs
A’
IB4
IB6
IB7
PO
11R
PO
5RP
O3
PO
2
PO
10
PO
9
PO
4
PO
1P
O13
PO
22
PO
19R
PO
6P
O20
PO
8R
PO
12
PO
23
PO
24
PO
21
PO
18R
PO
17
PO
14
PO
15R
PO
7
LB
02R
PO
33B
PO
32
PO
30
PO
28
PO
29
PO
33A
PO
31A
PO
31B
PO
25
0.6
3
0.3
4
0.0
60
.27
0.2
8
0.6
10
.31
0.1
9
0.5
0
0.0
9
0.3
0
0
.04
(Fe
b1
5)
7.1
0.6
5
0.4
10.3
4
0.0
9
0.4
6 0.4
4
0.3
8
2.0
0.1
0(F
eb
15)
190
(Oct1
4)
1.5
00.4
5
0.4
3
80
140
75
0.3
29
7
9.4
10
0
12
100
0.6
5(O
ct1
3) 0
.11
IB5
LB
03
IB8
4
0(F
eb
15
)
20
0
5
70
(Oc
t14
)
LB
01A
PO
26A
PO
26B
<0.0
10.0
3
470
200
400
300
400
300
200
100
500