Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to...

25

Click here to load reader

Transcript of Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to...

Page 1: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 1

Terms of Reference

for

SUPERVISION CONSULTANCY SERVICES FOR “DESIGN, SUPPLY AND INSTALLATION OF GAS STORAGE

EXPANSION PROJECT”

1. Background

The Client, that is the Pipeline Corporation of Turkey (BOTAŞ), intends to expand the capacity of the existing Tuz Gölü underground gas storage (UGS) facility from 1.2 Bcm to 5.4 Bcm daily withdrawal capacity from 40 Million Sm3 to 80 Million Sm3 and injection capacity from 30 Million Sm3 to 60 Million Sm3. Project site is located approximately 200 km. south of Ankara in the central part of Turkey, approximately 40 km south of Tuz Gölü.

The objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed gas storage capacity and deliverability for the national gas transmission and distribution network. Gas Storage Expansion Project will support the nation’s natural gas infrastructure to prevent any delivery constraints relating to the potential forthcoming peak customer demand.

The existing Tuz Gölü Underground Gas Storage Facility Contract, signed on 15 June 2011 following an International Competitive Bidding (ICB) process under a World Bank loan, is currently under implementation.

The Tuz Gölü UGS Project, well drilling has been completed for 12 wells, and the solution mining is ongoing for the Phase 2 caverns. First gas filling operation is completed in three caverns. These three caverns have been commissioned and in operation since December 2017, and all 12 caverns will be prepared for storage service by October 2021 with 1.2 Bcm of working gas capacity.

Gas Storage Expansion Project construction is set to begin in 2018 and involves drilling up to 40 wells and 8 additional (spare) wells, which would raise total storage working gas capacity to approximately 5.4 Bcm, the daily maximum withdrawal capacity to 80 million Sm3and daily gas injection capacity to 60 million Sm3.

The expansion project is planned to be constructed in an extension of the salt formation identified for the Tuz Gölü UGS. As in the current Tuz Gölü UGS project, the fresh water will be injected into the salt formation from the depth of 900 m to the depth of 1,500 m from the surface through wells constructed for that purpose. The caverns will be solution mined within the salt formation, each with net usable physical volume of 630,000 m³ to 870,000 m³. The brine generated during mining process will be discharged to the Tuz Gölü through a gravity pipeline. The natural gas will be taken from and returned to the main transmission line by a 40” diameter connection (header) pipeline 23 km in length. Natural gas will be stored in caverns under a maximum pressure of approximately 200 bars and will be withdrawn during times of peak demand in excess of contractual pipeline supplies or supply shortfalls.

Page 2: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 2

A detailed environmental impact assessment (EIA) study was conducted to satisfy Turkish Environmental regulatory requirements and EIA Report was approved by the Turkish Ministry of Environment and Forestry (MoEF) on 10.03.2017. An Environmental and Social Impact Assessment (ESIA) Report and a Resettlement Policy Framework (RPF) Report were also prepared to meet the World Bank requirements. (See Section 8.1. Data/Reports for the links to ESIA and RPF reports.)

In parallel with the Supervision Consultant selection process, the Client will also initiate the procurement process regarding ESIA and RAP Monitoring Consultancy Services for the Gas Storage Expansion Project.

2. Objectives

The Gas Storage Expansion Project intends to construct a new facility capable of storing nearly 4.2 Bcm (working gas capacity) of natural gas, which will include the following activities as the task of the Contractor:

• Surface Facilities: This work component includes review of basic designs, preparation of detailed engineering and design of surface facilities that include; , pig stations, all necessary injection and withdrawal units, i.e. the compressor facility, with turbo compressor units and reciprocating compressor units, the gas treatment facility, with pressure reduction units, water separators, heating and tri-ethylene glycol (TEG) units, all auxiliaries, filters, fuel gas skid and vent stack, fiscal metering units, a control room, a utility building, worker’s camps and access roads.

• Subsurface Facilities: Under the expansion project, it is planned to drill and leach 40 wells with solution mining of 4.2 Bcm working gas within the licensed area. This work component includes review of basic designs prepared by BOTAS and , preparation of detail engineering and design, drilling of wells with adequate subsurface installation, solution mining of salt cavern space for gas storage purposes (each cavern with a free geometrical volume approximately 630,000 – 870,000 m³), first gas fill for each cavern, snubbing (removal of the de-brining string and installation of the production string) for each cavern, commissioning of each cavern and operation of all caverns until handover.

• Field Gas Pipeline System, Fresh Water Field Pipelines and Brine Field Pipelines: This component will involve design and construction of all field pipelines that transport natural gas from the gas facilities to and from the cavern sites, as well as field pipelines for fresh water and brine from the central pumping station to the cavern sites. • Fresh Water Supply and Brine Discharge Pipelines: This component will involve design and construction of a 117-km fresh water supply line (52-60” in pipe diameter) from Hirfanlı Reservoir to project site and a 31-km brine discharge line (64” in pipe diameter) from the solution mining plant to Tuz Gölü. The Fresh Water Supply Pipeline

Page 3: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 3

involves construction of several pumping stations and storage reservoirs between the intake structure from Hirfanlı Dam reservoir and the Project Site.

• Electricity Supply: Project includes electricity transmission lines for the fresh water pumping stations, surface and sub-surface facilities.

• Natural Gas Pipeline: Gas pipeline interconnection (header) between Kayseri–Konya–Seydişehir section (approximately 23 km north of the Project Site) of the existing Eastern Anatolia Natural Gas Main Transmission Line (40” in pipe diameter) to the Expansion Project Site.

3. Project Implementation and Construction Process

Gas Storage Expansion Project is composed of two main components; (i) construction of all surface facilities related to gas transport, including gas compression, drying, metering and gas field pipelines; and (ii) construction of all surface and subsurface facilities related to transport of fresh water and brine, pumping stations, field pipelines and the drilling, leaching of 40 (plus 8 spare) caverns.

Surface facilities construction will be relatively conventional for gas storage, but with that of a compressor station with rather greater gas pressures than is normal in the pipeline industry. Be-cause of the many concurrent activities, construction, drilling, leaching, first gas fill and normal operations, the interaction between work activities on subsurface and the surface facilities does require specialized knowledge with high level of coordination.

Subsurface construction (drilling, leaching and first gas fill) of a cavern gas storage facility is a worldwide well-established activity; with experience of well drilling, brine and gas tubing in-stallation and circulation of large volumes of water. However, the expansion works are likely to be complex, especially because it will be adjacent to a fully functional storage plant in operation which will create ‘brown field’ complexity. Moreover, the subsurface construction peak periods will cover the simultaneous drilling of several wells with likely six drilling rigs operating in par-allel while the leaching of multiple caverns (up to 28) will take place simultaneously, with ap-proximately three-year solution mining period anticipated for each cavern. Therefore, contract-ing and managing the activities of all crews during the drilling and cavern completion process, with delivery and installation of well tubulars, proper installation of wellheads and solution mining strings, blanket equipment and control, sonar surveys, and management of solution min-ing string movements for up to 40 wells in various stages of construction activity will require a qualified construction management team with extensive experience in this area of construction. Finally, recognition that the critical first gas filling for several caverns are expected to overlap adding a layer of complexity that requires substantial material and personnel logistical support.

Hence, the Supervision Consultant’s planning and management contribution to the above given activities is critical for the proper and timely completion of the Gas Storage Expansion Project.

Page 4: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 4

4. Project Management Unit

The Client’s Gas Storage Department acts as a Project Management Unit (PMU), with authority and responsibility for the implementation and coordination of the Project in Ankara as well as related staff and resources at the Project Site.

The Consultant will support the Project Management Unit and train Client staff on-site to per-form the duties assigned to them to implement the Project.

5. Implementation Schedule

The Gas Storage Expansion Project implementation period is between 6 to 7 years including defect liability period. The Project will be implemented as described below.

No Activity Days from the Effective Date

1

Phase 0: Mobilization, Completion of Detailed Engineering, Procurement and Installation of Fresh Water Pipeline, Brine Discharge Pipelines and Energy Transmission Lines

548

2 Mobilization, Completion of Detailed Engineering, Procurement and Drilling of Wells

577

3 Phase 3: Finishing of first 12 Caverns for Gas Operation 1.644

4 Phase 4: Finishing of all 40 Caverns for Gas Operation 2.000

First set of 12 Caverns (Phase3): This includes construction of field pipelines, drilling of wells, solution mining of the first 12 caverns, construction of surface facilities, and first filling of 12 caverns. Leaching will start in fourth quarter of 2019 and 12 wells will be ready for operation at the second quarter of 2022.

Third set of 28 Caverns (Phase 4): This includes, drilling of wells, leaching of the third set with 28 caverns, and first filling of 28 caverns. Solution mining will start earliest in last quarter of 2019 and 28 wells will be ready for operation at the last quarter of 2023.

Each cavern will be put into operation individually when completed. Consultant will remain with the project through final hand over and during the Defects Liability Period.

Page 5: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 5

6. Scope of Services

The Consultancy services are required for approximately 7 years in line with the expected project implementation schedule, including the Defects Liability Period. The Client shall review the status of project at the end of each phase and may revise the implementation schedule, accordingly.

The Client will hold the overall project management responsibility through construction supervision, and retain control and financial responsibility for the Expansion Project. The Consultant shall assist and advice the Client as defined below and specifically when requested by the Client.

The Consultant shall support BOTAS in all aspects while BOTAS Gas Storage Department acts as “the Project Manager” (see definition in the World Bank’s Standard Procurement Document - Request for Bids - Plant Design, Supply and Installation) and shall be responsible to carry out all duties envisaged in the Contractors’ contract document.

The duties and responsibility of the Consultant can be defined as but not limited to:

A. SERVICES DURING CONSTRUCTION AND INSTALLATION

A1. GENERAL SERVICES

i. The Consultant shall review, verify and approve the detailed engineering documents and drawings prepared by the Contractor to ensure compliance with specification, performance criteria, operations and maintenance utility, and good industry practice during construction.

ii. The Consultant shall be responsible to check all the information required for accurate setting-out of the Facilities and obtain additional information from the related authorities before the Contractors set out the works and supervise all the setting-out studies by the Contractors.

iii. The Consultant shall supervise and oversee all aspects of the design, construction and installation, operation of the various components of the Project to ensure strict compliance with the drawings and contract documents, subject to any express or implied term contained in any Conditions of Contract entered into between the Employer (Client) and the Contractors.

iv. The Consultant shall supervise to control the implementation of the overall project quality assurance and quality control program prepared by the Contractor. During supervision, the Consultant will immediately inform the Client and if needed, recommend to stop the work,in case of any non-compliance with regards to project’s technical, safeguards, health and safety related commitments.

v. The Consultant shall supervise timely expedition of all materials and equipment to ensure undamaged delivery and – if need be – storage of goods to the site.

Page 6: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 6

vi. The Consultant shall provide sufficient, qualified and experienced staff to ensure proper site supervision of all of the Facilities, surface and subsurface and engineering services both during the installation/construction period and during the Defects Liability Period.

vii. The Consultants will be responsible for supervising the construction and installation of the Facilities as well as for the inspection and conduct testing of all materials, plant and equipment both during the construction and installation of the facilities and for any works that have to be completed during the Defects Liability Period. The Consultant shall maintain effective liaison with the Client on all aspects of the installation services including the performance of the Contractors and shall submit reports specified later in Section 7 of these terms of reference and envisaged in the Contractors contracts in a timely manner and to the required details.

viii. The Consultant will be responsible from any and all adverse consequences which arise as a result of their slow action, delay, omission, etc. The Consultant shall not delay any action required to be taken by the Consultant during the installation/construction/operation services for the Expansion Project. In any case, all the correspondences received from the Contractors shall be reviewed evaluated and responded latest within one week. Any claim from the Contractors shall be evaluated by the Consultant and necessary recommendations shall be made the latest within one week as well.

ix. The Consultant shall fully inform the Client about the cost and time impact and any other consequences of his any sort of proposals (such as revisions, recommendations, etc). Client shall not be responsible for or from the consequences of the fact(s) of which the Client is not informed in advance.

x. It is the duty of the Consultant to interpret the drawings and specifications and to consult with the Contractors as required to ensure compliance with the Contract Documents and the installation program.

xi. iv. The Consultant shall support the Client in the management of the construction contract for the storage facility throughout its duration as to progress against the Contract Management Plan. The Consultant shall monitor the key performance indicators and report to the Client successful compliance of both contracting parties with contractual provisions and progress. The Consultant’s report shall identify the potential risks that may cause time and cost overruns of the works contract and determine their mitigation measures.

xii. v. The Consultant shall control and monitor the Seismic Network installed by the Contractor as well as evaluate data obtained from Seismic Network.

xiii. The Consultant shall control and monitor GPS Monitoring System installed by the contractor. This service shall be performed beginning with the first fill of the First Set of 12 caverns.

xiv. The Consultant shall develop communication procedures with the ESIA and RAP monitoring consultant, coordinate with them at all times and inform them of the progress in civil works so as to ensure no civil works would start causing impact that triggers OP 4.12 as defined in the project RPF prior to the payment of compensation or implementation other mitigation measures provided in the RAP.

Page 7: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 7

xv. The Consultant shall review the ESIA and RAP monitoring consultant’s reports and discuss their findings with both the monitoring consultant and the Client, and recommend the Client to ensure that the recommended mitigation measures and corrective actions have been suitably embedded in design material, work planning and execution by the Contractor.

Performance of Tests/Inspections:

xvi. The Consultant shall stipulate the appropriate criteria, the planning and the procedure for all tests and inspections necessary for the materials, equipment, plants, workmanship and the commissioning of the Facilities and shall provide supervision and inspection for these tests. The Consultant shall compile the records of all such tests and compare the results with the specifications, standards or with the performance criteria that has been guaranteed by the Contractor.

xvii. Where necessary, tests and inspections may be carried out at the place of manufacture during fabrication and/or prior to shipment. The Consultant shall inform the Client well in advance about any such performance test foreseen, to enable the Client to participate in these tests if he so wishes.

xviii. The Consultant’s specifications shall stipulate the testing and inspection procedure and criteria required for the various elements of the works including the number of tests required, the test procedure, the criteria for acceptance or rejection of the items tested and the actions to be taken in the event of test failure.

xix. The Consultant shall approve an appropriate testing laboratory for all tests required and discuss the various testing requirements stipulated in its documents with the personnel of the laboratory. The Consultant shall give at least 24 hours prior notice to the laboratory for all tests, which are required to be undertaken by the latter. All samples shall be properly labeled in accordance with the requirements of the laboratory and the Consultant shall be responsible for the delivery of all samples for testing and for the collection of all test reports. All tests shall be performed at laboratory acceptable to the Consultant and Client.

xx. The involvement of the approved Materials Testing Laboratory is limited to the actual performance of the tests in accordance with the Consultant’s written procedures and/or the standards specified in the Contract. The Consultants shall be responsible for interpreting the results received, instructing the repetition or the implementation of additional tests and taking whatever action necessary to ensure compliance with the contract requirements. The Laboratory staff may from time to time offer advice to the Consultant on any matter within the scope of their competence but it is up to the Consultant whether to accept or reject such advice or suggestion. If any advice or suggestion is accepted by the Consultant, they shall become completely responsible for it as if the advice or suggestion has been of its own initiative.

Accounts, Claims:

xxi. The Consultant shall confirm the Contractor’s valuations for payment on account (progress payment reports) and approve such reports according to the Conditions of Contract used and shall also be responsible for agreeing with the Client on each payment certificate in payable amount. The actual procedure and presentation of the certificates, supporting documents etc., shall be discussed and agreed with the Client.

Page 8: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 8

xxii. The Consultant shall review and report on any financial claims submitted by the Contractor within 1 week of receipt of such claims submission.

xxiii. Disputes. The Consultant shall assist in setting out and clarifying all disputes or differences, which may arise between the Client and the Contractors in a timely manner. In the case of litigation and arbitration, the Consultant shall assist the Client in the preparation of the documents needed by the Client. The costs related with such services of the Consultants are deemed to be included in the fee proposal of the Consultants during the life of the primary consulting Contract. Records and Operating Instructions:

xxiv. After completion of the facilities, the Consultant shall prepare and submit to the Client a report giving all information about the "as-built conditions” including, but not limited to, calculations, drawings, specifications, test reports and final cost analysis.

xxv. The Consultant shall review, approve and supply to the Client a complete set of records drawings prepared by the Contractor(s) of the facilities “as-built” as soon as possible after the Completion Certificate is issued and in any case within 28 days of the date of this Certificate.

xxvi. The Consultant shall also review, approve and supply to the Client a comprehensive set of the operating and maintenance manuals, procedures and specifications for the whole system prepared by the Contractor(s). Consultant shall review and finalize the operation and maintenance manuals provided by the related suppliers for each equipment and plant through Contractor(s) to safely operate and maintain the system and its components. This task shall also be completed within a similar time period as specified immediately above.

xxvii. These manuals shall include quality assurance (QA) programs to measure and monitor performance. The programs shall include critical path (CP) monitoring schedules, leak detection surveys and patrols, valve maintenance and inspection, regulator station maintenance, inspection and meter measurement certification.

xxviii. The Consultant shall develop and provide copies of an Emergency Plan Manual and Contingency Plan Manual documenting the procedures to be adopted to mitigate the effects of pipeline emergencies and contingency modes of operation to prevent or minimize the interruption of supply and damage to the Facilities.

xxix. These reports and manuals shall be subject to the Client’s approval. The format and number of copies shall be as stated in Paragraph 7 herewith.

Defects Liability Period:xxx. The Consultant shall continue to be responsible for the supervision, inspection of the installation and completion of the Facilities during the Defects Liability Period as defined in the Installation Contracts. The level of supervision shall be appropriate to the scale of the works being carried out. These inspections and supervision are to ensure that works agreed to be carried out by the Contractors have been completed during the Defects Liability Period have been properly carried out and completed and that any failure of any part of the work has been rectified. If any defect is discovered during this period, the Consultant shall promptly investigate the reason for it, report to the Client and take required actions to rectify the defect.

Page 9: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 9

xxxi. Reports of these inspections shall be submitted to the Client which shall include all details of any defects, faults deficiencies, accidents or breakdowns, which have occurred together with the estimated costs of repair and the time scales within which they will be completed. Moreover, the Consultant shall submit quarterly reports summarizing all the activities during subject quarter. A final report shall be submitted at the end of the Defects Liability Period giving full details of all works carried out during that period. This report shall be submitted to the Client at least 30 (thirty) days prior to the Consultants issuing its Defects Liability Certificate for the Completed Facilities.

xxxii. The Consultant shall assist the staff of Client for operation of the first 12 caverns during the Defects Liability Period.

Environmental and Social Safeguards

xxxiii. The Consultant shall ensure the integration into the design, planning and project execution of the requirements of the Environmental and Social Impact Assessment (ESIA) Report, Environmental and Social Management Plan (ESMP) and other supporting documents, Resettlement Action Plan (RAP) during the supply and the installation of Facilities and instruct the Contractor to comply with all requirements. The Client will separately employ a consultant responsible to monitor and report the environmental and social issues (namely the ESIA and RAP Monitoring Consultant). The Consultant shall work closely with the ESIA and RAP Monitoring Consultant to ensure that (i) ESIA and supporting documents, including but not limited to ESMP, Stakeholder Engagement Plan, Occupational Health & Safety Plan, sub-management plans; and (ii) RAPs and supporting documents including but not limited to RAP Monitoring Plan(s) are being complied with and all services are in full conformity with the environmental and social safeguard documents developed by Client.

xxxiv. The Consultant will review the weekly workplan with the Contractor and ensure all required environmental (including occupational health and safety), social (including RAP), health and safety planning measures have been taken before execution. The Consultant will compile health and safety Key Performance Indicators to be analyzed in concurrence with other indicators and presented in an integrated manner to support the Client’s decision-making process. The Consultant will also lead the root cause analysis and sign-off on corrective actions to address health and safety non-compliances with the applicable standards.

xxxv. Review the As-Built drawings of the Project and request any revision(s).

xxxvi. The Consultant shall prepare Monthly Progress Report and all other reports mentioned in Section 7.

A2. SURFACE FACILITIES SERVICES

i. Supervise/inspect the site activities and approve daily reports.

ii. Supervise installation of surface facilities including piping, instrumentation, mechanical, equipment, electrical, control systems, cathodic protection, etc.,

A3. SUBSURFACE FACILITIES SERVICES

A3-1. Well Drilling Services

Page 10: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 10

i. Supervise/inspect the site activities during operation and approve daily drilling reports,

ii. Supervise the installation of casing, all wellhead related equipment and relevant auxiliary services,

iii. Prepare weekly reports and approve the final Well Acceptance Report for each individual well prepared by Contractor,

iv. Supervise the relevant wireline logging operations and requested tests (mini fracture tests),

v. Supervise safe completion of the wells (including cementation) and preparation for further cavern operations.

A3-2. Services During Cavern Solution Mining

The Consultant shall supervise the solution mining process of the caverns according the program to be prepared by the Contractor as follows but not limited to:

i. Supervise/check the field activities and reports.

ii. Examine and test all Contractor reports, data and information for accuracy and reasonability as defined in the installation Contract.

iii. Take remedial actions immediately in case of any unforeseen construction development.

iv. Supervise the regular and any additional cavern sonar surveys to intervene in case of interpretation doubts, and attend all sonar analysis meetings at the Site.

v. Perform computer simulations, history matches/predictions for adjusting the solution mining program to overcome cavern development irregularities and provide all necessary raw data files to the Client.

vi. Prepare monthly progress reports and the final reports on each individual cavern development.

vii. Prepare 2D and 3D geo-mechanical analysis, predicting cavern behavior separately and as as a part of a gallery.

viii. Supervise installation of solution mining strings and all equipment relevant to wellhead.

ix. Supervise installation of the leaching wellhead.

x. Supervise Mechanical Integrity Test (MIT), report and assert readiness of the cavern for leaching.

A3-3. Services for First Gas Filling

The Consultant shall supervise the first gas filling of the caverns with gas as given here below but not limited to:

Page 11: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 11

i. Supervise/oversee the field activities and reports,

ii. Prove that all reported data and information have the accuracy and reasonability defined in the construction contract,

iii. Develop remedial action immediately in case of any unforeseen development,

iv. Compare brine levels after interface measurements with predicted value,

v. Require interface measurements if necessary, particularly before the end of the first fill to avoid overfilling with subsequent gas break through,

vi. Prepare monthly reports and the final reports for each individual cavern,

vii. Supervise the snubbing out of the temporary brine displacement tubing,

viii. Supervise the installation of the subsurface safety valves,

ix. Supervise the dismantling of the temporary first fill equipment and the mounting of the final cavern wellhead and its connections to the gas plant,

x. Supervise commissioning and transfer of each cavern and surface facility for storage operation,

xi. Supervise installation of gas production strings and all wellhead related equipment.

xii. Supervise Gas Tightness Test (GTT), Cavern Acceptance Test (CAT), report and assert readiness of the cavern for gas operation.

A3-4. Assistance during Gas Operation of the Facilities

The Consultant shall assist and train staff of the Client during the operation of the Facilities covering all caverns completed.

A4. PIPELINES AND ELECTRICITY TRANSMISSION LINES SERVICES

i. Supervise/inspect the site activities and approve daily reports,

ii. Supervise installation for the water supply pipeline, and all stationary facilities such as water intake structure, storage tanks, pumping stations, drain/air relief valve chambers, etc. pertaining to pipelines,

iii.Supervise installation for the brine discharge pipeline and all associated stationary facilities such as diffuser, drain/air relief valve chambers, etc. pertaining to brine discharge pipeline,

iv. Supervise installation for the natural gas connection pipeline, and all associated stationary facilities such as valve chambers, etc. pertaining to natural gas pipeline,

v. Supervise installation for the energy transmission lines for the Project.

Page 12: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 12

B. Training

The Consultant shall train the staff of Client for the detailed design of natural gas storage facilities in addition to supervision of installation of subsurface and surface facilities during construction. These trainings shall be conducted mainly at the Site as “on the job training” for the operations, maintenance and safety requirements of the Facilities during implementation. In addition, it is also envisaged that the Consultant shall train the Client’s staff responsible for the gas storage operation including the operation cycles, thermodynamic analysis and critical operation parameters comparing with the history matches/predictions by the Client´s own crew.

The Consultant shall be in close coordination with the Client and shall help to realize transfer of technology to the maximum extent. This shall cover the transfer of all software to the Client (including geological and geomechanical modelling, thermodynamic analysis, leaching, dewatering and gas operation) used during the design, execution and operation of the Facilities, under the Service Contract, at no cost to the Client.

7. Submission of Reports, Drawings and Documents

The Consultant shall supervise the activities of the contractor(s) daily. The Consultant shall inspect the Sites, review the performance of contractor(s) and their sub-consultants, sub-contractors and suppliers, carry out control analyses and data collection, and report the findings both to the contractor(s) and to the Client. The Consultant shall organize weekly meetings with the contractor(s) to discuss the progress of installation with anticipated problems and their solutions. The Consultant shall keep the minutes of meeting and distribute it to the contractor(s) and Client.

The Consultant shall submit a copy of all correspondences with the contractor(s) simultaneously to the home and site offices of the Client.

The Consultant shall prepare and submit to the Client various reports, drawings and documents that are specified in or that are implied from these Terms of Reference in respect of various components of the Projects as described in the Terms of Reference.

The Consultant shall prepare and submit a report satisfactory to the Project Manager on weekly basis for the services stipulated in A2, A3 and A4 sections of Scope of Services above.

The Consultant shall prepare and submit a report (including the reference made to the Contract Management Plan in Paragraph A1 (iv) above) satisfactory to the Client each calendar month, including progress charts and photographs in colors giving all information regarding the progress of the Facilities, actual extent and nature of the Facilities completed as well as details of any delay in the Facilities substantiating documentation if required. The Consultants shall also clearly indicate in the report whether the delay (if any) of any part of the works will cause any delay in the completion of the Expansion Facility.

Page 13: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 13

The report shall also include the percentages of the work items completed and planned, and also the actual and planned cash flows for each work item as of the reporting period.

The report shall also include test records of materials, equipment and plant tested with copies of the test results. Action taken with regard to poor results shall be highlighted and expressly stated.

The report shall give a detailed review of the activities to be performed during the following month and a general listing of the works to be performed during the following two months.

The report shall be submitted to the Client by the fifth day of the following month. Any comment by the Client on the report shall be reviewed and the report shall be modified and re-submitted to the Client within a week.

In addition, the Consultant shall record views (photos or videos) from at least 5 different points from site, on weekly base, showing the progress on the site with dates and record them with acceptable format on CD and submit to the Client.

The requirements for the submission of reports, drawings and other documentation are given below. Reports shall be prepared in English. The metric system of weights and measures shall be used.

Submission shall be as follows:

i. General

Format of Reports : A4 or A3, including where appropriate drawings reduced to A3 size.Format of Drawings: A1 and/or A0 size.

A draft copy of all reports shall be submitted to the Client in advance for discussion purposes following which the Consultant shall be required to prepare the final copy, incorporating any amendments arising from such discussions.

ii. Installation Stage

Number of copies of Weekly Report 3Number of copies of Monthly Report 3Number of copies of Quarterly Report 3

iii. Completion and Defects Liability Period

Number of copies of Quarterly Report 3Number of copies of Defects Liability Period Report(s) 3Number of copies of Final Report 3

Original of the drawings that shall be submitted to the Client are not included in the above number of copies.

Those of the documents and reports not mentioned above but either specified or implied in the contract shall be submitted in 3 copies in English.

Page 14: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 14

In relation to the ongoing stages of the Consultants Services, the submission requirements given above should be allowed by the Consultant as a guideline for the extent and type of documentation that will be required by the Client during the performance of the Services. However, the Consultant shall allow in its fee for the submission of all reports, drawings, documents, etc. either specifically requested in these Terms of Reference or those which may be implied there from and the Contractors' contracts. The Client may however vary such requirements during the course of the Services to be performed.

Should additional copies be required over to those stated above or specified in these Terms of Reference, these shall be supplied by the Consultant at the cost of reproduction of such documents, reports or drawing.

Additionally, after finalizing the documents and reports, these shall be submitted to the Client on one (1) set of CD and in the software format acceptable by the Client.

Upon the completion of Works, the Consultant shall submit all the original copies of correspondences, documents, test results and drawings relating to the services and the Expansion Facilities, to the Client together with indices in an acceptable files and forms by the Client and as archived. The Consultant shall keep the copies of the documents.

8. Data, Local Services, Personnel, and Facilities to be Provided by the Client

8.1. Data/Reports

One copy of the consequent reports defined below is going to be provided by the Client.

Complete set of Bidding Documents of Design, Supply and Installation of Tuz Gölü Underground Gas Storage Expansion Project,

Complete set of Contract Documents of Design, Supply and Installation of Tuz Gölü Underground Gas Storage Expansion Project,

3D Seismic Report, Preliminary well location determination report for new 40 wells, Drilling and Well Evaluation Reports for the 2 test wells and 12 cavern wells of the

existing Tuz Gölü UGS Project, Geological and Drilling Design Documents for the existing 12 cavern wells, Well Completion Reports & Log Interpretation Reports for the existing 12 wells, Core and Laboratory Tests Reports for the existing cavern wells, The Final ESIA Report (

http://www.botas.gov.tr/docs/duyurular/2018/duyuru_26032018_1/Gas_Storage_Expansion_Project_Final_ESIA_Report_Rev.0_EN.zip,

RPF (approved by the World Bank) (http://www.botas.gov.tr/docs/duyurular/2018/duyuru_26032018_1/Resettlement_Policy_Framework_Rev.H_EN.pdf ), and

the supporting documents (including Environmental and Social Management Plan, other sub-management plans and Occupational Health & Safety Plan)

8.2. Local Services, Facilities

Page 15: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference 15

The Client shall provide a 50 m2 (net) office at pipeline site camp areas with office furniture (excluding office equipment such as computer, printer, copy machine, etc.) and 2 rooms for 4 personnel for accommodation at the water supply and brine disposal pipeline and gas pipeline construction site near Aksaray until the completion of the Expansion Project. All communication costs shall be borne by the Consultant. The Consultant shall be responsible for the supply of office equipment and operational cost of his office and accommodation rooms except heating, electricity, water and wastewater services.

In the same manner, the Client shall provide a total 100 m2 (net) office with office furniture (excluding office equipment), accommodation rooms for 8 personnel and four phone lines to the Consultant through the Contractor at the Site. The Consultant shall be responsible for the supply of office equipment and the operational cost of his office and accommodation rooms except heating, electricity, water and wastewater services.

8.3. Personnel

The Client will provide no counterpart personnel.

9. Personnel to be Assigned by the Consultant

The Consultant shall employ personnel fully qualified and capable of performing all aspects of the Client’s specific needs and requirements for the Services as outlined herein to the satisfaction of the Client during the entire period of the Services. The Consultant shall clearly indicate the location (Home Office/Site/etc) of proposed key staff in his proposal. The Project Manager (Team Leader) or his substitute is required to be on Site during the implementation of Services.

For the effective use of Consultant’s resources, the Client and the Consultant shall review the key and non-key expert input required for the next 6 months of the Services starting from the effectiveness date of the Contract and based on the agreed staff plan, and the Consultant shall mobilize its personnel and be paid accordingly. This review shall be done every 6 months throughout the duration of the Consultation Services. Depending on the implementation period of the facility and satisfactory performance of the Consultant as determined by the Client, the Consultants may be requested to perform additional services downstream based on the terms and unit prices of the original Contract.

The years of experience required for various staff is given in Table 1 below.

Page 16: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference

Table 1. Consultant Personnel, Number of Assignments and Years of Experience.

POSITION Number of Assignment

General Experience

Specific Experience

1 Project Manager (Team Leader) 1 20 15

2 Chief Design Engineer 1 15 10

3 Specialist Engineer for Geology 2 15 10

4 Specialist Engineer for UGS Geomechanics 1 15 10

5 Specialist Engineer for Pipelines 2 10 5

6 Supervisor for Drilling*, ** 1 10 5

7 Specialist Engineer for Drilling* 6 10 5

Specialist Engineer for Well Cementing** 1 10 5

Specialist Engineer for Well Logging** 1 10 5

8 Process System Engineer for Leaching 4 15 10

9 Process System Engineer for Surface Facilities 2 15 10

10 Instrumentation Engineer 1 10 5

11 Specialist Engineer for Geophysics 1 10 5

12 Specialist Engineer for Snubbing and First Filling Operation 2 15 10

13 Specialist Engineer for Gas Injection/Withdrawal Operations 2 15 10

14 Specialist Engineer for SCADA and Telecom 1 15 10

15 Specialist Engineer for Electrical 1 15 10

16 Specialist Engineer for Mechanical Works 2 15 10

17 Quality Control Engineer 1 10 5

18 Contract Engineer 1 15 10

19 Environmental and Social Specialist 1 10 5

20 Specialist Engineer for Civil Works 2 10 5

21 Specialist Architect for Civil Works 1 10 5

16

Page 17: Section 5 Terms of Reference · Web viewThe objective of Gas Storage Expansion Project is to provide reliability and security of the natural gas supply by expanding the urgently needed

Terms of Reference

22 Occupational Health and Safety Specialist** 2 10 5

*at least two having IWCF/WellCAP certification.

**during critical phases of drilling, completion, snubbing and first fill, consider expanding these specialist functions temporarily to be able to cover 24/7 coverage with day and night shift crews

17