SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic...

81
Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS PART 1 - GENERAL 1.1 APPLICABLE DOCUMENTS A. All work under this Section shall comply with the requirements of General Conditions, Supplemental Conditions, Special Conditions and Division 01 - General Requirements, and shall include all Electrical Sections specified herein. 1.2 DESCRIPTION OF WORK A. This Section includes general administrative and procedural requirements for electrical installations. The following administrative and procedural requirements are included in this Section to expand the requirements specified in Division 01. 1.3 DESCRIPTION OF BID DOCUMENTS A. Specifications: 1. Specifications, in general, describe quality and character of materials and equipment. 2. Specifications are of simplified form and include incomplete sentences. B. Drawings: 1. Drawings in general are diagrammatic and indicate sizes, locations, connections to equipment and methods of installation. 2. Conform to scaled and figured dimensions, notify Engineer of any conflicts prior to installation, cutting, drilling, etc. 3. Before proceeding with work check and verify all dimensions. 4. Assume all responsibility for fitting of materials and equipment to other parts of equipment and structure. 5. Make adjustments that may be necessary or requested in order to resolve space problems, preserve headroom, and avoid architectural openings, structural members and work of other trades. 6. Where existing pipes, conduits and/or ducts prevent installation of new work as indicated, relocate, or arrange for relocation, of existing pipes, conduits and/or ducts. Verify exact location and elevation of existing piping prior to any construction. 7. If any part of Specifications or Drawings appears unclear or contradictory, apply to Architect or Engineer for his interpretation and decision as early as possible during bidding period. If answer is not given prior to close of bid time then contractor shall assume the following: a. The scope of work in question is to be included in his bid price. No change orders will be allowed to add to the scope of work.

Transcript of SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic...

Page 1: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 1

SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

PART 1 - GENERAL

1.1 APPLICABLE DOCUMENTS

A. All work under this Section shall comply with the requirements of General Conditions,

Supplemental Conditions, Special Conditions and Division 01 - General Requirements, and shall

include all Electrical Sections specified herein.

1.2 DESCRIPTION OF WORK

A. This Section includes general administrative and procedural requirements for electrical

installations. The following administrative and procedural requirements are included in this

Section to expand the requirements specified in Division 01.

1.3 DESCRIPTION OF BID DOCUMENTS

A. Specifications:

1. Specifications, in general, describe quality and character of materials and equipment.

2. Specifications are of simplified form and include incomplete sentences.

B. Drawings:

1. Drawings in general are diagrammatic and indicate sizes, locations, connections to

equipment and methods of installation.

2. Conform to scaled and figured dimensions, notify Engineer of any conflicts prior to

installation, cutting, drilling, etc.

3. Before proceeding with work check and verify all dimensions.

4. Assume all responsibility for fitting of materials and equipment to other parts of

equipment and structure.

5. Make adjustments that may be necessary or requested in order to resolve space problems,

preserve headroom, and avoid architectural openings, structural members and work of

other trades.

6. Where existing pipes, conduits and/or ducts prevent installation of new work as indicated,

relocate, or arrange for relocation, of existing pipes, conduits and/or ducts. Verify exact

location and elevation of existing piping prior to any construction.

7. If any part of Specifications or Drawings appears unclear or contradictory, apply to

Architect or Engineer for his interpretation and decision as early as possible during

bidding period. If answer is not given prior to close of bid time then contractor shall

assume the following:

a. The scope of work in question is to be included in his bid price. No change orders

will be allowed to add to the scope of work.

Page 2: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 2

b. The greater cost/quality level alternative shall be included in his bid. No change

orders will be allowed for assuming the lesser quality or cost.

c. A separate line item may be included to clarify the bid but the scope of work and/or

cost/quality level in question must be included in the overall bid price.

1.4 DEFINITIONS

A. "Above Grade": Not buried in the ground and not embedded in concrete slab on ground.

B. "Actuating" or "Control" devices: Automatic sensing and switching devices such as thermostats,

pressure, float, electro-pneumatic switches and electrodes controlling operation of equipment.

C. "Below Grade": Buried in the ground or embedded in concrete slab on ground.

D. "Concealed": Embedded in masonry or other construction, installed in furred spaces, within

double partitions or hung ceilings, in trenches, in crawl spaces, or in enclosures. In general, any

item not visible or directly accessible.

E. "Connect": Complete hook-up of item with required service.

F. "Exposed": Not installed underground or "concealed".

G. "Furnish": To supply equipment and products as specified.

H. "Indicated," "Shown" or " "Noted": As indicated, shown or noted on drawings or specifications.

I. "Install": To erect, mount and connect complete with related accessories.

J. "Motor Controllers": Manual or magnetic starters (with or without switches), individual push

buttons or hand-off-automatic (HOA) switches controlling the operation of motors.

K. "Provide": To supply, install and connect as specified for a complete, safe and operationally

ready system.

L. "Reviewed", "Satisfactory," or "Directed": As reviewed, satisfactory, or directed by or to

Architect/Engineer/Owner.

M. "Rough-In": Provide all indicated services in the necessary arrangement suitable for making

final connections to fixture or equipment.

N. "Shall": An exhortation or command to complete the specified task.

O. "Similar": Of base bid manufacture, equal in materials, weight, size, design, and efficiency of

specified products; and as approved by engineer.

P. "Supply": To purchase, procure, acquire and deliver complete with related accessories.

Q. "Will": A desire to complete the specified task. Allows some flexibility in application as

opposed to "shall".

Page 3: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 3

R. "Wiring": Raceway, fittings, wire, boxes and related items.

S. "Work": Labor, materials, equipment, apparatus, controls, accessories, and other items required

for proper and complete installation.

1.5 SHOP DRAWINGS AND EQUIPMENT SUBMITTALS

A. General: Follow the procedures specified in Division 01 Section "SUBMITTALS" except as

expanded for this Division herein. Submittals processed by the Architect/Engineer are not cause

for extra claims nor do they represent a change in the Contract Documents.

B. Purpose: Contractor demonstrates to the Architect/Engineer understanding of the Contract

Documents and design concept by indicating which material intended to be furnished and

installed, and by detailing fabrication and installation methods intended to be used. Intention of

using exactly the materials indicated does not relieve Contractor of obligation of submitting shop

drawings and product literature.

C. Identification: Include project name, both Contractor and electrical Installer names, address,

telephone numbers and contact persons. Clearly mark all submittals to indicate use of the

material.

D. Shop Drawings: Submit on all major pieces of electrical equipment including (but not

necessarily limited to) light fixtures, distribution equipment, starters, circuit breakers, panel

boards, and transformers as identified in the Project Checklist below. Up to 11" x 17" size sheets

must be submitted with product literature below. Over 11" x 17" size submit in accordance with

Architect's requirements.

E. Electronic files shall be submitted in three distinct electronic document processes.

1. Electronic Submittals

2. Equipment Inventory/Document Reference Index

3. Electronic Folders for file management and drawings

4. The GC/Prime shall maintain the master set of record documents to be turned over to the

owner at completion of the project.

5. Product Literature: Submit six copies CD (or DVD) maximum of manufacturer's

descriptive literature and catalog cuts of standard electrical products used including, but

not limited to conductors, connectors, raceway, special raceways, fittings, switches,

outlets, etc.

6. Submit all information described above, except for hardcopies of Shop Drawings, in

electronic format (pdf-files in Adobe Reader 8), on standard Compact Diskettes (CDs).

Electronic files shall be organized in electronic folders on the CD, by the Specification

Section number and the Section name identified in the Project Checklist:

7. Do not mix electronic Product Data Sheets (.pdf-files) with other electronic files, such as

Shop Drawings or files in another format, such as AutoCAD .dwg-files.

8. Each item of equipment shall be a separate, single electronic .pdf-file or xls-file,

containing only pages of manufacturer’s data pertinent to the item. Do not include

literature intended for general sales purposes or for general product information, which

does not pertain the exact item or product to be provided. Individual data files (.pdf-file

and xls-file) for individual items will be arranged in the electronic Section folders named

as indicated in the “CLOSEOUT DOCUMENT FILE NAME” column on the PROJECT

Page 4: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 4

CLOSEOUT DOCUMENT REFERENCE INDEX. The PROJECT CLOSEOUT

REFERENCE INDEX will be furnished by the Owner and include the filenames to be

used.

9. Electronic files for electrical equipment and luminaries shall include the name of item as

indicated on the Electrical Drawings issued “For Construction” (Architect’s IFC Set), will

be the origin of the equipment name (equipment identifier).

F. Product Literature: Submit six copies maximum of manufacturer's descriptive literature and

catalog cuts of standard electrical products used including, but not limited to conductors,

connectors, raceway, special raceways, fittings, switches, outlets, etc.

G. Binders: Three-ring Binders containing loose-leaf pages of Manufacturer’s Product Data sheets

are not required.

H. Marking: Where more than one product is represented, clearly identify those products which the

Contractor intends to furnish on this project. Strike out products which will not be used, or

underline or arrow products on a given product sheet which will be used. Do not use highlighter

pens. Place unspecified items in 260500 and number sequentially.

I. Submittal Review: Submittals not conforming to the aforementioned requirements will not be

accepted by the Engineer and will be returned without review. Such action shall not be cause for

extra claims against the Owner, Architect or Engineer. Consult with the Engineer and obtain

pre-approval of any deviations from the specified electronic format described above, prior to

submission. After necessary approvals are received by the Contractor and revisions made

thereto, the electronic product data files shall be updated to depict equipment items and products

that are installed on the Project. These revised files shall be included as a section of the

Electronic Operation and Maintenance Manuals.

J. Submittal Dates: Submit product data sheet CD’s within 30 calendar days of notice to proceed.

Submit all product literature stragglers and shop drawings within 60 calendar days of notice to

proceed, on separate CD’s. Submit coordination drawings on a separate CD not less than 20

calendar days prior to the beginning of any work affected by the Division 26 work depicted.

After such deadlines, the professional time to consider any submittal shall be paid for by the

contractor. Such payment does not guarantee approval. Costs incurred to the project due to

problems arising from late submittals shall be paid for by the contractor.

1.6 RECORD DOCUMENTS

A. Prepare record documents in accordance with the requirements of Division 01 Section Closeout

and Procedures and Project Record Documents. Providence to receive two hardcopies, full-size

set of Record Drawings and (2) CDs of identical electronic AutoCAD drawing files including

Equipment Installation Manual Programming Manual, System Block Diagrams, Point-to-Point

Wiring Diagrams, Terminal Identification, User Manuals, Parts Lists pertinent to each piece and

type of equipment installed on the Project, at the end of the project. In addition to the

requirements specified in Division 01, Electronic AutoCAD files for Record Drawings shall

indicate, by sheet note, installed conditions for:

1. Major raceway systems, size and location, for both exterior and interior; locations of

control devices; busways; distribution and branch electrical circuitry; and fuse and circuit

breaker size and arrangements.

Page 5: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 5

2. Equipment locations (exposed and concealed), dimensioned from prominent building

lines.

3. Approved substitutions, Contract Modifications, and actual equipment and materials

installed.

B. Prepare electronic files of all approved submittal datasheets for all equipment, items and

products installed in the Project. Update electronic Product Data Sheets to include equipment

specifically utilized on the Project. Follow file format described in Electronic Product Literature,

above. Include electronic Data Sheets from the original submittal CDs, if no modifications were

made to the equipment or item modifications to equipment and hardware to be included here.

Arrange all electronic Product Data Sheets on Record Document CDs by component type, as

listed on the PROJECT CLOSEOUT DOCUMENT REFERENCE INDEX. Document

Reference Index shall be grouped into the Closeout Document Folder under the division

identified in the Project Checklist. Construction and as-installed drawings shall be placed in their

respective folders in the division they belong.

1. After review and approval of RECORD DOCUMENTS by the Engineer and Architect,

Contractor shall make revisions as noted to the Record Documents and provide all Record

Drawings in pdf-format, and include in the electronic Operations and Maintenance

Manual Sub-folder named: RECORD DRAWINGS. Each drawing sheet shall be a

separate pdf-file with sheet name.

C. Provide (1) blue line set, and (1) zip disk containing all ACAD drawing files.

1.7 CODES, STANDARDS, AND REQUIREMENTS OF REGULATORY AGENCIES

A. Execute and inspect all work in accordance with Underwriters Laboratories (UL), and all local

and state codes, rules and regulations applicable to the trade affected as a minimum, but if the

plans and/or specifications call for requirements that exceed these rules and regulations, the more

stringent requirement shall be followed. Follow application sections and requirements and

testing procedures of NFPA, IEEE, NEMA, CBM, ANSI, NECA, ICEA, and NETA.

B. Comply with standards in effect at the date of these Contract Documents, except where a

standard or specific date or edition is indicated.

C. All material used on this project shall be U.L. listed and labeled and be acceptable to the

Authority Having Jurisdiction as suitable for the use intended.

D. After entering into contract, Contractor will be held to complete all work necessary to meet these

requirements without additional expense to the Owner.

1. All equipment to be installed to meet code requirements. Contractor to verify prior to

installation and notify Architect, Owner and Engineer of any conflicts.

2. Clearances for servicing equipment, including space for equipment disassembly required

for periodic maintenance.

3. Exterior wall and foundation penetrations

4. Fire-rated wall and floor penetrations

5. Equipment connections and support details.

6. Sizes and location of required concrete pads and bases

Page 6: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 6

7. Indicate scheduling, sequencing, movement, and positioning of large equipment into the

building during construction.

1.8 GENERAL REQUIREMENTS

A. Examine all existing conditions at building site.

B. Review contract documents and technical specifications for extent of new work to be provided.

C. Provide and pay for all permits, licenses, fees and inspections.

D. Install equipment and materials to provide required access for servicing and maintenance.

Coordinate the final location of concealed equipment and devices requiring access with final

location of required access panels and doors. Allow ample space for removal of all parts that

require replacement or servicing. This work shall include furnishing and installing all access

doors required for mechanical access.

E. Verify final locations for rough-ins with field measurements and with the requirements of the

actual equipment to be connected. Refer to equipment specifications in Divisions 02 through 26

for rough-in requirements.

F. Coordinate electrical equipment and materials installation with other building components.

G. Verify all dimensions by field measurements.

H. Coordinate the installation of required supporting devices and sleeves to be set in poured-in-

place concrete and other structural components, as they are constructed.

I. Sequence, coordinate, and integrate installations of electrical materials and equipment for

efficient flow of the work. Give particular attention to large equipment requiring positioning

prior to closing-in the building.

J. Coordinate the cutting and patching of building components to accommodate the installation of

electrical equipment and materials. Conform to the requirements of Division 01, 02, 03 and 04.

Contractor to provide for all cutting and patching required for installation of his work unless

otherwise noted in Division 01.

K. Where mounting heights are not detailed or dimensioned, install electrical services and overhead

equipment to provide the maximum headroom possible.

L. Install electrical equipment to facilitate maintenance and repair or replacement of equipment

components. As much as practical, connect equipment for ease of disconnecting, with minimum

of interference with other installations. Unless noted otherwise, do not route conduits on floor or

in a manner that prevents access to equipment.

M. Coordinate the installation of electrical materials and equipment above ceilings with ductwork,

piping, conduits, suspension system, light fixtures, cable trays, sprinkler piping and heads,

pneumatic tubes and other installations.

Page 7: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 7

N. Provide all access doors as may be required to maintain electrical equipment and connections

located above ceilings. Access doors shall be fire rated to match ceiling in which they are

installed. Provide in accordance with section 230500.

O. Notify owner when work area is substantially complete, yet not concealed, so he can verify

adequate service accessibility. Equipment requiring service shall be readily accessible.

1.9 INSTRUCTIONS, MAINTENANCE AND O&M MANUALS

A. Prepare electronic Operation and maintenance manuals in .PDF file format accordance with

Division 01 Section Operation and Maintenance Data. In addition to the requirements specified

in Division 01, include the following information for equipment items identified in the Project

Checklists below:

1. Description of function, normal operating characteristics and limitations, performance

curves, engineering data and tests, and complete nomenclature and commercial numbers

of replacement parts.

2. Manufacturer's printed operating procedures to include start-up, break-in, and routine and

normal operating instructions; regulation, control, stopping, shutdown, and emergency

instructions; and summer and winter operating instructions.

3. Maintenance procedures for routine preventative maintenance and troubleshooting;

disassembly, repair, and reassembly; aligning and adjusting instructions.

4. Servicing instructions, lubrication charts and schedules

5. Complete list of parts and wiring diagrams.

6. Names, addresses and telephone numbers of the Contractor, sub-contractors and local

companies responsible for maintenance of each system or piece of equipment.

7. The job name and address and Contractor’s name and address shall be placed on the cover

in a permanent manner. Dymo-tape is not acceptable. The Electronic O & M shall be

sub-divided into specification section divisions by tabs, and shall include copies of

approved shop drawings.

8. Copies of all test reports shall be included in the manuals.

B. Maintenance manuals are to be prepared in accordance with industry standards.

1.10 DELIVERY, STORAGE, AND HANDLING

A. Deliver products to project properly identified with names, model numbers, types, grades,

compliance labels, and similar information needed for distinct identifications; adequately

packaged and protected to prevent damage during shipment, storage, and handling.

B. Store equipment and materials in an environmentally controlled area at the site, unless off-site

storage is authorized in writing. Protect stored equipment and materials from damage.

C. Coordinate deliveries of electrical materials and equipment to minimize construction site

congestion. Limit each shipment of materials and equipment to the items and quantities needed

for the smooth and efficient flow of installations.

Page 8: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 8

1.11 TEMPORARY FACILITIES

A. Provide temporary light, heating, power etc. services as necessary during the construction period

and as required to maintain operation of existing systems.

B. Light, Heat, Power, Etc.

1. Responsibility for providing temporary electricity, heat and other facilities shall be as

specified in Division 01.

C. Building distribution equipment and devices shall not be used without written permission of the

Owner. If used for temporary power, the equipment shall be properly maintained and any

damage resulting from use shall be repaired by the Contractor. The guarantee period for new

equipment shall not begin until the equipment is turned over to the Owner.

1.12 DEMOLITION/REMODEL WORK

A. Refer to Division 01 section on Summary of Work for requirements on working in Owner-

occupied areas of the existing building and Division 02 section on selective demolition. The

following expand the requirements specified in Division 01 and 02.

B. Existing equipment that is removed and not scheduled to be reused shall remain the property of

the Owner unless specifically indicated otherwise and shall be stored in a location designated by

the Owner. Miscellaneous materials that are removed shall become the property of the

Contractor.

C. Existing equipment that is removed and is to be reused shall be cleaned, serviced and operable

before being energized.

D. Revise panelboard schedules to reflect removal or relocation of equipment. Circuit integrity of

equipment shall be left intact.

E. Where remodeling interferes with existing circuits and equipment which is not to be removed,

such circuits and equipment shall be reworked and relocated as required to complete the project.

F. The project involves renovation and remodel of the existing building. On the drawings, certain

renovation symbols are used. These symbols are amplified as follows:

R = Existing items to be removed. Contractor shall remove the existing item and turn over to

the Owner. The existing wiring shall be removed. Where the raceway serving the

equipment is accessible (via removal of suspended ceiling, crawl space, etc.) The raceway

shall also be removed. Where the removal of a raceway leaves visible evidence on an

existing surface which is not being repaired or replace as part of the Work, this Contractor

shall repair the surface. Where the existing raceway is concealed, the outlet box shall be

cleaned, and a blank cover plate installed. Where the concealed raceway is uncovered by

demolition performed as part of the Work, the raceway shall be removed (or extended to

new location if appropriate).

E = Existing item to remain in place. Contractor shall perform the following function based

upon the item to remain:

Luminaries - Clean and re-lamp

Switches - Remove and replace with new in existing box.

Page 9: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 9

Receptacles - Remove and replace with new in existing box.

RL = Existing item to be relocated. Contractor shall remove the existing item, and store in a safe

place. The existing item shall be relocated to the new position as called for on the

drawings. At contractors option, the existing wiring may be extended, or new wiring may

be run from the source. Based upon the item to be relocated, the Contractor shall perform

the following function:

Luminaries - Clean and re-lamp

Switches - Replace.

Receptacles - Replace.

G. The Contractor shall remove all distribution equipment, conductors, etc. which are indicated to

be removed or which must be removed to accommodate demolition. Equipment to be removed

may require reworking conduit and wiring in order to maintain service to other equipment.

H. Where remodeling interferes with circuits serving areas outside of the project or phase limits or

which are remodeled in later phases of the project, circuits shall be reworked or temporary

circuits provided as required.

I. Existing equipment and circuiting shown are based upon field surveys and/or Owner furnished

drawings. The Contractor shall verify conditions as they exist with necessary adjustments being

made to the drawing information.

J. Reuse of existing luminaires, devices, conduits, boxes, or equipment will be permitted only

where specifically indicated within the Contract Documents.

K. Electrical Outages:

1. Contractor shall submit a Method of Procedure (MOP) for each outage to the Owner

detailing the reasons for the outage, areas affected, sequence of procedures to accomplish

work, estimated maximum duration, the date and time of day outage will occur. The

Contractor shall meet with the Owner to set a schedule and date for the outage based upon

the MOP. Due to the critical implications of power outage, the Owner may direct the

Contractor as to the time of day or night and date an outage may take place. A 7 day

notice is required.

1.13 SAFETY AND INDEMNITY

A. The Contractor shall be solely and completely responsible for conditions of the job site including

safety of all persons and property during performance of the work. This requirement will apply

continuously and not be limited to normal hours of work.

B. No act, service, drawing, review, or construction review by the Owner, Architect, the Engineers

or their consultants is intended to include the review of the adequacy of the Contractor's safety

measures, in, on, or near the construction site.

C. The Contractor performing work under this Division of the Specifications shall hold harmless,

indemnify and defend the Owner, the Architect, Engineers and their consultants, and each of the

their officers and employees and agents, from any and all liability claim, losses or damage

arising, or alleged to arise from bodily injury, sickness, or death of a person or persons and for all

damages arising out of injury to or destruction of property arising directly or indirectly out of or

Page 10: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 10

in connection with the performance of the work under the Division of the Specifications, and

from the Contractor's negligence in the performance of the work described in the Construction

Contract Documents, but not including the sole negligence of the Owner, the Architect, the

Engineers, and their consultants or their officers and employees and agents.

1.14 ACCEPTANCE

A. Upon completion of the mechanical systems covered by these specifications, a certificate of

approval and acceptance will be issued for each system. This certificate will in no way relieve

this Contractor from the terms of his guarantee. Refer to Division 01.

1.15 WARRANTIES

A. Refer to the General Conditions and Division 01 for procedures and submittal requirements for

warranties. All equipment shall be provided with a minimum one year warranty to include parts

and labor. Refer to individual equipment specifications for extended or longer term warranty

requirements.

B. Provide complete warranty information for each item, to include product or equipment, and date

of beginning of warranty or bond; duration of warranty or bond; and names, addresses, and

telephone numbers and procedures for filing a claim and obtaining warranty services.

1.16 GUARANTEE

A. The Contractor shall guarantee and service all workmanship and materials to be as represented

by him and shall repair or replace, at no additional cost to the Owner, any part thereof which may

become defective within the period of one (1) year after the Date of Final Acceptance, ordinary

wear and tear excepted.

B. Contractor shall be responsible for and pay for any damages caused by or resulting from defects

in his work.

1.17 PROJECT CHECKLIST

A. In addition to the requirements specified in Division 1 complete the requirements listed below.

B. The contractor shall be responsible for the following Project checklist either by performing

and/or coordinating such items throughout the term of the project and provide all closeout

requirements prior to applying for certification of substantial completion.

1. Refer to “Instructions, Maintenance, O&M Manuals” for Electronic O&M folder

requirements. Include service manuals, programming manuals, sequence of operations,

settings, as-installed software register definitions, block diagrams and point to point wiring

diagrams. Equipment required to have owner-assigned Barcodes are identified in

specification section 017901 and are to be coordinated and included with the owners

“Closeout Document Reference Index.”

Page 11: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 11

2. O&M’s to be submitted at 50% phase of project for review. Include bill of material(s)

under each section tab, in addition to other identified required maintenance information.

Include all test reports required in identified specification sections.

3. Refer to individual specification sections for additional requirements.

4. Spare Parts:

a. Submit master list of spare parts and extra materials as part of submittals. Refer to

individual specification sections for requirements.

b. Turn over spare parts to General Contractor for delivery to Owner, via signed

transmittals.

c. Include spare parts list and transmittals under separate tabs in O&M’s.

5. Refer to Project Close Out Value Schedule for values that will be withheld from the

contractor’s final payment until Project Check List requirements are complete.

6. Submit schedule of values to the Architect and Engineer as part of the submittal process

and as part of the closeout. Include all C.O. etc in the closeout schedule of values.

C. Division 26

SPEC

SECTION ITEM

REQUIREMENTS

SUBMITTALS

SUPPLEMENTAL

INFORMATION

IDENTIFIED IN

SPEC SECTION

FA

CT

OR

Y R

EP

SU

PE

RV

ISIO

N A

T S

ITE

**

TR

AIN

ING

RE

Q'D

AT

SIT

E

SP

AR

E P

AR

TS

/**

EX

TR

A M

AT

ER

IAL

At completion of

project obtain

owners sign off

that the owner has

received the

following:

Include owner

sign off in

O & M’s

SH

OP

DR

AW

ING

PR

OD

UC

T D

AT

A

INC

LU

DE

IN

O&

M

TE

ST

ING

RE

QU

IRE

ME

NT

S

RE

PO

RT

RE

QU

IRE

ME

NT

S

TR

AIN

ING

FO

R

PR

OD

UC

TS

S

PA

RE

PA

RT

S/E

XT

RA

MA

TE

RIA

LS

DO

CU

ME

NT

SCHEDULE OF VALUES X X

260126

ENGINEERING ANALYSIS

AND ELECTRICAL

SYSTEMS TESTING

X X X X

260500 BASIC ELECTRICAL

REQUIREMENTS

260500 CONTRACTOR/EQUIPME

NT WARRANTIES X X X

260500 O&M MANUALS

(ELECTRONIC FILE) X X X

260500 COORDINATION

DRAWINGS X

Page 12: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 12

SPEC

SECTION ITEM

REQUIREMENTS

SUBMITTALS

SUPPLEMENTAL

INFORMATION

IDENTIFIED IN

SPEC SECTION

FA

CT

OR

Y R

EP

SU

PE

RV

ISIO

N A

T S

ITE

**

TR

AIN

ING

RE

Q'D

AT

SIT

E

SP

AR

E P

AR

TS

/**

EX

TR

A M

AT

ER

IAL

At completion of

project obtain

owners sign off

that the owner has

received the

following:

Include owner

sign off in

O & M’s

SH

OP

DR

AW

ING

PR

OD

UC

T D

AT

A

INC

LU

DE

IN

O&

M

TE

ST

ING

RE

QU

IRE

ME

NT

S

RE

PO

RT

RE

QU

IRE

ME

NT

S

TR

AIN

ING

FO

R

PR

OD

UC

TS

S

PA

RE

PA

RT

S/E

XT

RA

MA

TE

RIA

LS

DO

CU

ME

NT

260500

RECORD DRAWINGS

(PAPER AND

ELECTRONIC FILE)

X X X

260519 WIRES AND CABLES X X X X

260526 GROUNDING X X X X

260529 SUPPORTING DEVICES X X X X X

260533 RACEWAYS BOXES AND

CABINETS X

260548 VIBRATION ISOLATION

FOR ELECTRICAL WORK X X X X X

260553 ELECTRICAL

IDENTIFICATION X X

260573 OVERCURRENT

PROTECTIVE DEVICES X X X

262413 SWITCHBOARDS X X X X X X X X X

262416 PANELBOARDS X X X X X X X

262726 WIRING DEVICES X X X X

262813 FUSES X X X X X

262913 CIRCUIT AND MOTOR

DISCONNECTS X X X X

263600 TRANSFER SWITCHES X X X X X X X X

264313 TRANSIENT VOLTAGE

SURGE SUPPRESSORS X X X X X X X

Page 13: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 13

D. Electrical Project Close-out Value Schedule

1. The following values will be withheld from the contractor’s final payment until such time

as satisfactorily delivered to the Owner. (Amounts identified are for each item listed in

the owners “Closeout Document Reference Index” by “Equipment Identifiers.”)

2. Record Drawings (Bond paper prints and Electronic files) $500.00 per sheet

a. Electronic O+M Manuals

1) Electrical

a) Transfer Switches $400.00

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 GENERAL

A. Workmanship shall be performed by licensed journeymen or master mechanics and shall result in

an installation consistent with the best practices of trades.

B. Install work uniform, level and plumb, in relationship to lines of building. Do not install any

diagonal, or otherwise irregular work unless so indicated on Drawings or approved by Architect.

3.2 MANUFACTURER'S DIRECTIONS

A. Follow manufacturers' directions and recommendations in all cases where the manufacturers of

articles used on this Contract furnish directions covering points not shown on the Drawings or

covered in these Specifications

3.3 ROUGH-IN

A. Verify final locations for rough-ins with field measurements and with the requirements of the

actual equipment to be connected.

B. Refer to equipment specifications in Divisions 02 through 26 for rough-in requirements.

3.4 ELECTRICAL INSTALLATIONS

A. General: Sequence, coordinate, and integrate the various elements of electrical systems,

materials, and equipment. Comply with the following requirements:

1. Coordinate electrical systems, equipment, and materials installation with other building

components.

2. Verify all dimensions by field measurements.

Page 14: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 14

3. Arrange for chases, slots, and openings in other building components during progress of

construction, to allow for electrical installations.

4. Coordinate the installation of required supporting devices and sleeves to be set in

poured-in-place concrete and other structural components, as they are constructed.

5. Sequence, coordinate, and integrate installations of electrical materials and equipment for

efficient flow of the Work. Give particular attention to large equipment requiring

positioning prior to closing in the building.

6. Where mounting heights are not detailed or dimensioned, install systems, materials, and

equipment to provide the maximum headroom possible.

7. Coordinate connection of electrical systems with existing utilities and services. Comply

with requirements of governing regulations, franchised service companies, and controlling

agencies. Provide required connection for each service.

8. Install systems, materials, and equipment to conform with approved submittal data,

including coordination drawings, to greatest extent possible. Conform to arrangements

indicated by the Contract Documents, recognizing that portions of the Work are shown

only in diagrammatic form and do not necessarily indicate every required conduit, box,

fitting, etc. Where coordination requirements conflict with individual system

requirements, refer conflict to the Architect and Owner. The Owner reserves the right to

make any changes in outlet, lighting or equipment locations prior to rough-in without

additional cost. Change shall be interpreted as including any change of up to ten feet from

the locations indicated on the drawings.

9. Install systems, materials, and equipment level and plumb, parallel and perpendicular to

other building systems and components, where installed exposed in finished spaces.

10. Install electrical equipment to facilitate servicing, maintenance, and repair or replacement

of equipment components. As much as practical, connect equipment for ease of

disconnecting, with minimum of interference with other installations. Install equipment

and materials to maintain code required clearances and access.

11. Install access panel or doors where units are concealed behind finished surfaces. Access

panels and doors are specified in section 250500 Section "ACCESS DOORS and Access

Panels".

12. Install systems, materials, and equipment giving right of way priority to systems required

to be installed at a specified slope. Coordinate ceiling cavity space carefully with all

trades. In the event of conflict, space for mechanical and electrical systems within the

cavity shall be allocated in the following order:

a. Plumbing waste, vent piping and roof drain mains and leaders.

b. Supply, return and exhaust ductwork.

c. Fire sprinkler mains and leaders

d. Electrical conduit

e. Domestic hot and cold water

f. Pneumatic control piping

g. Fire sprinkler branch piping and sprinkler run outs.

h. Junction boxes shall not be located above grid ceiling tiles containing sprinkler

heads.

Page 15: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 15

3.5 CUTTING AND PATCHING

A. General: Perform cutting and patching in accordance with Division 01 Section "CUTTING

AND PATCHING." In addition to the requirements specified in Division 01, the following

requirements apply:

1. Perform cutting, fitting, and patching of electrical equipment and materials required to:

a. Uncover Work to provide for installation of ill-timed Work.

b. Remove and replace defective Work.

c. Remove and replace Work not conforming to requirements of the Contract

Documents.

d. Remove samples of installed Work as specified for testing.

e. Install equipment and materials in existing structures.

f. Upon written instructions from the Architect and Owner, uncover and restore Work

to provide for Architect and Owner observation of concealed Work.

2. Cut, remove, and legally dispose of selected electrical equipment, components, and

materials as indicated, including but not limited to removal of electrical items indicated to

be removed and items made obsolete by the new Work.

3. Protect the structure, furnishings, finishes, and adjacent materials not indicated or

scheduled to be removed.

4. Provide and maintain temporary partitions or dust barriers adequate to prevent the spread

of dust and dirt to adjacent areas.

5. Protection of Installed Work: During cutting and patching operations, protect adjacent

installations.

6. Patch existing finished surfaces and building components using new materials matching

existing materials and experienced Installers. Installers' qualifications refer to the

materials and methods required for the surface and building components being patched.

a. Refer to Division 01 Section General Requirements for definition of experienced

"Installer."

7. Arrange for repairs required to restore other work, because of damage caused as a result of

electrical installations.

8. No additional compensations will be authorized for cutting and patching Work that is

necessitated by ill-timed, defective, or non-conforming installations.

3.6 TESTING/INSPECTION SUMMARY

A. Following is a list of items requiring inspections and/or testing as part of this contract. It is an

attempt to summarize the requirements from individual Division 26 sections in a single location

for owner and contractor convenience. Failure to list an item here that is included within

individual Division 26 sections does not give the contractor cause to delete that scope of work.

See specific Division 26 sections for more detailed scope requirements.

Page 16: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Basic Electrical Requirements Section 260500 16

B. See section 260126 Engineering Analysis and Electrical Systems testing for additional

requirements

END OF SECTION 260500

Page 17: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

MEDIUM-VOLTAGE CABLES AND ACCESSORIES 260513 - 1

SECTION 260513 - MEDIUM-VOLTAGE CABLES AND ACCESSORIES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary

Conditions and Division 01 Specification Sections, apply to this Section

B. Section 26_08_80_00 - Electrical Testing.

1.2 SUMMARY

A. This Section includes cables and related terminations, and accessories for medium-voltage

(MV) electrical distribution systems.

B. Provide the following termination assemblies:

1. 200A and 600A bolted cable terminations at MV switchgear.

C. Refer to electrical single-line diagrams for additional requirements.

1.3 DEFINITIONS

A. NETA ATS: Acceptance Testing Specification.

B. Cable connector: Where a cable end is field joined to a factory made separable connector

assembly that can be attached and unattached to a mating termination fitting on a piece of

equipment. 600A connectors are dead-break rated and require the system to be shutdown prior

to disconnection. 200A elbows shall be load-break rated.

C. Cable termination: Where a cable end is field joined to a factory made assembly with

compression type lug bolted to a bus bar on the piece of equipment.

D. Termination assembly(ies): Refers to all components associated with cable splices, cable

connectors and cable terminations.

E. Separable connector: A cable is terminated in a factory made assembly unit that can be attached

and unattached to another similar unit without damage to the connection or the cable ends.

Permanent splices are not allowed. All splices shall be made with separable connectors and

shall occur only in vaults and pullboxes.

F. All equipment terminations shall be made via two-hole bolted lugs or separable elbow

connectors, as indicated.

Page 18: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

MEDIUM-VOLTAGE CABLES AND ACCESSORIES 260513 - 2

1.4 ACTION SUBMITTALS

A. Product Data: For each type of cable indicated. Include splices and terminations for cables and

cable accessories.

B. Cable-pulling calculations indicating the maximum pulling tension of the cable will not be

exceeded in PDF, MS Word, or MS Excel format. Provide calcs prior to cable installation.

C. Dynamometer readings recorded during cable pulling in PDF, MS Word or MS Excel format

per submittal schedule.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer.

B. Material Certificates: For each cable and accessory type, signed by manufacturers.

C. Source quality-control test reports.

D. Field quality-control test reports.

1.6 QUALITY ASSURANCE

A. Installer Qualifications: Engage an experienced installer of medium voltage electrical cable to

perform the installation specified in this section. Cable splices, connectors and terminations

shall be made by certified workman with a minimum of 5 years experience in terminating the

specific types of cable and cable accessories specified in this Section.

B. Testing Agency Qualifications: An independent agency, with the experience and capability to

conduct the testing indicated, that is a member company of the InterNational Electrical Testing

Association or is a nationally recognized testing laboratory (NRTL) as defined by OSHA in

29 CFR 1910.7, and that is acceptable to authorities having jurisdiction.

1. Testing Agency's Field Supervisor: Person currently certified by the InterNational

Electrical Testing Association or the National Institute for Certification in Engineering

Technologies to supervise on-site testing specified in Part 3.

C. Source Limitations: Obtain cables and accessories through one source from a single

manufacturer.

D. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,

Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for

intended use.

E. Each reel of cable furnished shall be newly manufactured, no more than 12 months old.

F. Codes and Standards: Conform to the following Standards :

1. NFPA 70.

2. Electrical components and/or systems shall be listed and labeled by a nationally

recognized testing laboratory (NRTL) such as: UL, ETL, CSA, or FM; shall be labeled

Page 19: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

MEDIUM-VOLTAGE CABLES AND ACCESSORIES 260513 - 3

and/or listed as part of a UL-labeled assembly, or shall be evaluated by a third party

acceptable to the authority having jurisdiction (AHJ) as suitable for the use intended. All

labels shall be applied at the manufacturer’s factory or facility prior to shipment.

3. AEIC – Association of Edison Illuminating Companies.

a. AEIC CG5-2005 – Underground Extruded Power Cable Pulling Guide.

b. AEIC CS8-2007 – Specification for Extruded Dielectric Shielded Power Cables

Rated 5 Through 46 kV.

4. IEEE C2-latest – National Electrical Safety Code (NESC) Part 3: Safety Rules for the

Installation and Maintenance of Underground Electric Supply and Communication Lines.

5. ASTM B496-04-2010 – Standard Specification for Compact Round Concentric-Lay-

Stranded Copper Conductors.

6. IEEE

a. IEEE 386™-latest – IEEE Standard for Separable Insulated Connector Systems for

Power Distribution Systems above 600 V.

b. IEEE 576™-latest – Recommended Practice for Installation, Termination, and

Testing of Insulated Power Cable as Used in Industrial and Commercial

Applications.

7. NECA NEIS 600-2003 – Recommended Practice for Installing and Maintaining Medium-

Voltage Cable.

8. NETA – InterNational Electrical Testing Association Inc.

a. NETA ATS-latest – Standard for Acceptance Testing Specifications for Electrical

Power Equipment and Systems.

9. UL

a. UL 1072-latest – UL Standard for Safety, Medium-Voltage Power Cables.

1.7 PROJECT CONDITIONS

A. Interruption of Existing Electric Service: Do not interrupt electric service to facilities occupied

by Owner or others unless permitted under the following conditions and then only after

arranging to provide temporary electric service according to requirements indicated:

1. Notify Owner no fewer than two days in advance of proposed interruption of electric

service.

2. Do not proceed with interruption of electric service without Owner's written permission.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Deliver medium voltage cable on factory reels conforming to NEMA Standard WC 26 - Wire

and Cable Packaging. Reels with unsealed cable ends will be recorded and rejected by the

Owner’s representative.

B. Store cables on reels on elevated platforms in a clean, dry location.

C. On receipt, inspect cable protective covering for evidence of damage during shipment. Report

immediately to carrier if evidence of damage is found.

D. Accomplish unloading without contacting cable surface or protective wrap. If unloading by

crane, use cradle supporting reel flanges or a shaft through arbor hole. If using a forklift, lift the

Page 20: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

MEDIUM-VOLTAGE CABLES AND ACCESSORIES 260513 - 4

reel at 90 degrees to flanges. Use forms long enough to make complete lifting contact with both

reel flanges.

E. If using inclined ramp for unloading, use ramp wide enough to contact both reel flanges

completely. Accomplish stopping of reels at bottom by using the reel flanges and not the surface

of the cable.

F. Do not drop reels from delivering vehicle to ground.

G. Store reels on hard surface to prevent flanges from sinking into the earth and allow the weight

of the reel and cable to rest on the cable surface.

H. Do not store reels in an area where construction equipment, falling or flying objects or other

materials will contact the cable.

I. Store cable where chemicals or petroleum products will not be spilled or sprayed on the cable.

J. Store cable away from open fires or sources of high heat.

K. When a reel of cable is rolled from one point to another, check for and remove objects on

surface that could contact or damage the cable surface or protective wrap. Roll reel in direction

to prevent loosening of the cable on the reel.

L. Store cable according to manufacturer’s recommendations, as a minimum. In addition, store

cable in location protected from vandalism and weather. If cable is stored outside, it must be

covered with opaque plastic or canvas with provisions for ventilation to prevent condensation

and for protection from weather. If air temperature at the cable storage location will be below 5

degrees C, move cable to a heated (10 degrees C minimum) location. If necessary, properly

store cable off site at Contractor’s expense.

M. Seal cut cable ends using properly sized heat shrink cap to prevent moisture ingress to the

internal part of the cable.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering

products that may be incorporated into the Work include, but are not limited to, the following:

1. Cables:

a. Okonite Company (The).

b. Pirelli Cables & Systems NA.

c. Prysmian.

d. Rome Cable Corporation.

e. Southwire Company.

2. Cable Splicing and Terminating Products and Accessories:

a. Raychem: Tyco Electronics.

b. RTE Components; Cooper Power Systems, Inc.

Page 21: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

MEDIUM-VOLTAGE CABLES AND ACCESSORIES 260513 - 5

c. Elastimold: Thomas & Betts Corporation.

d. 3M; Electrical Products Division.

3. Tapes

a. 3M Scotch® 24 – Electrical Shielding Tape.

b. 3M Scotch® 27 – Glass Cloth Electrical Tape.

c. 3M Scotch® 33 – Electrical Tape.

d. 3M Scotch® 69 – Glass Cloth Electrical Tape.

e. 3M Scotch® 77 – Fire Retardant Electric Arc Proofing Tape.

f. 3M Scotch® 130C – Linerless Rubber Splicing Tape.

g. 3M Scotchfil™ - Electrical Insulation Putty.

h. Insulating Materials Inc. (IMI) 202 – Irrathene Film, Class 105C Tape.

i. Plymouth® Bishop® 53 Plyarc® – Arc and Fire Proofing Tape.

4. Conductor and Cable Stripping Tools

a. Acceptable Manufacturers

1) Greenlee.

2) Hi-Line Company

3) Ideal

4) Ripley Company (UtilityTool), BP A, BP 1A, BP 2A, Icon, PIT 1T, TSW

4550, WS 6, WS 7, WS 7A, WS 8, WS 8A, WS 15, WS 64-U, WS 5A, or

WS 66

5) Speed Systems, Inc., 1542-2CL and 1700 Series.

2.2 MV CABLES

A. Cable Type: MV105.

B. Comply with UL 1072, AEIC CS 8, ICEA S-93-639, and ICEA S-97-682.

C. Conductor: Copper.

D. Conductor Stranding: Concentric lay, Class B.

G. Conductor Insulation: Ethylene-propylene rubber.

1. Voltage Rating: 15 kV.

2. Insulation Thickness: 133 percent insulation level.

H. Shielding:

1. 5-mil uncoated Copper shielding tape with minimum 12.5% overlap, helically applied

over semiconducting insulation shield. The copper tape shall meet all of the requirements

of Part 4 of ICEA.

K. Cable Jacket: Black, sunlight-resistant PVC. Use cable jacket meeting the electrical, physical

and sunlight resistant requirements of ICEA S 93 639 / NEMA WC74 and of UL Standard

1072. The average thickness of the jacket shall be as specified in Part 4 of ICEA. Provide

minimum thickness at any point of not less than 80 percent of that specified. CSA listed to

C68.3.

Page 22: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

MEDIUM-VOLTAGE CABLES AND ACCESSORIES 260513 - 6

2.3 SOLID TERMINATIONS

A. Multi-conductor Cable Sheath Seals: Type recommended by seal manufacturer for type of cable

and installation conditions, including orientation.

2. Cold-shrink sheath seal kit with preformed sleeve openings sized for cable and insulated

conductors.

B. Shielded-Cable Terminations: Comply with the following classes of IEEE 48. Insulation class is

equivalent to that of cable. Include shield ground strap for shielded cable terminations.

Terminations without sheds (skirts) are only allowed on indoor applications.

1. Class 1 Terminations, Indoors: Kit with stress-relief tube, nontracking insulator tube,

shield ground strap, compression-type connector, and end seal. Provide slip-on type

insulator with flexible skirted polymer or silicon rubber insulation. Provide hot or cold

shrink type terminator with internal stress relief tube to distribute the electric field over

the entire length of the skirted insulator. Do not use separate parts of copper or copper

alloy used in contact with aluminum or aluminum alloy parts in the construction and

installation of the terminator.

2.4 SEPARABLE INSULATED CONNECTORS

A. Description: Modular system, complying with IEEE 386, with disconnecting, single-pole, cable

terminators and with matching, stationary, plug-in, dead-front terminals designed for cable

voltage and for sealing against moisture.

B. Terminations at Distribution Points: Modular type, consisting of terminators installed on cables

and modular, dead-front, terminal junctions for interconnecting cables.

E. Dead-Front Terminal Junctions: Modular bracket-mounted groups of dead-front stationary

terminals that mate and match with above cable terminators. Two-, three-, or four-terminal units

as indicated, with fully rated, insulated, watertight conductor connection between terminals and

complete with grounding lug, manufacturer's standard accessory stands, stainless-steel

mounting brackets, and attaching hardware.

1. Protective Cap: Insulating, electrostatic-shielding, water-sealing cap with drain wire.

2. Portable Feed-Through Accessory: Two-terminal, dead-front junction arranged for

removable mounting on accessory stand of stationary terminal junction.

3. Grounding Kit: Jumpered elbows, portable feed-through accessory units, protective caps,

test rods suitable for concurrently grounding three phases of feeders, and carrying case.

4. Standoff Insulator: Portable, single dead-front terminal for removable mounting on

accessory stand of stationary terminal junction. Insulators suitable for fully insulated

isolation of energized cable-elbow terminator.

G. Tool Set: Shotgun hot stick with energized terminal indicator, fault-indicator test tool, and

carrying case.

2.5 ARC-PROOFING MATERIALS

A. General: Provide fire taping of all medium voltage cables and termination assemblies inside

vaults, including existing cables if present.

Page 23: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

MEDIUM-VOLTAGE CABLES AND ACCESSORIES 260513 - 7

B. Tape for First Course on Metal Objects: 10-mil- (250-micrometer-) thick, corrosion-protective,

moisture-resistant, PVC pipe-wrapping tape.

C. Arc-Proofing Tape: Fireproof tape, flexible, conformable, intumescent to 0.3 inch (8 mm) thick,

compatible with cable jacket.

D. Glass-Cloth Tape: Pressure-sensitive adhesive type, 1/2 inch (13 mm) wide.

2.6 FAULT INDICATORS

A. Provide automatic reset, in-rush restraint type fault indicators at all splices and at all

terminations. Provide all mounting kits and adapters as required. Manufacturer to recommend

correct trip ratings at each location to be used. Manual reset types are prohibited. Provide a

display that a fault has occurred in cable. Instrument shall not be affected by heat, moisture, and

corrosive conditions and shall be recommended by manufacturer for installation conditions.

B. Mounting: Arranged to clamp to cable sheath on cable terminations or test points on elbow

connectors.

C. Provide cooper power systems, or equal, S.T.A.R. (capacitive test point) fault indicator

D. Provide corrosion resistant, clamp-on current type reset units on terminations without capacitive

test points. Cooper Power Systems, or equal, CRR3PD fault indicator with three-phase remote

display on all solid terminations.

E. Provide one test point testing tool suitable for each type of indicator.

2.7 SOURCE QUALITY CONTROL

A. Test and inspect cables according to ICEA S-94-649 before shipping.

PART 3 - EXECUTION

3.1 INSPECTION

A. Verify that each conduit is ready to receive work. Use properly sized mandrel to determine if

installed conduit is suitable for use.

B. Verify field measurements are as shown on Drawings.

C. Record field-measured lengths of cable and forward to the Contractor.

D. Beginning of installation means Contractor accepts existing conditions.

3.2 PREPARATION

A. Thoroughly swab conduits and pipes to remove foreign material before pulling cables.

Page 24: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

MEDIUM-VOLTAGE CABLES AND ACCESSORIES 260513 - 8

3.3 INSTALLATION

A. Install cable and terminations in accordance with IEEE Standard 576.

B. Install cable and terminations in accordance with manufacturer’s instructions and installation

guidelines.

C. Avoid abrasion and other damage to cables during installation. Install cable as indicated on plan

drawings and cable schedules.

D. Pulling Conductors:

1. Do not exceed manufacturer's recommended bending radius, maximum pulling tensions

and sidewall pressure values.

2. Where necessary, use manufacturer-approved pulling compound or lubricant that will not

deteriorate conductor or insulation.

3. Use pulling means, including fish tape, cable, rope, and basket-weave cable grips that

will not damage cables and raceways. Do not use rope hitches for pulling attachment to

cable.

4. Pull cables using suitable cable-pulling equipment. Do not exceed cable-pulling tensions

or minimum-bending radius recommended by manufacturer.

5. Include approval of cable pull setup by Contractor and Owner prior to each pull.

6. Where pulling equipment is attached to columns, structure, or strut framework, ensure

maximum stress limitations of support and structure systems are not exceeded.

7. During the pulling operation, use dynamometer to record the pulling tension. Give notice

to Owner before cable is pulled so his representative can observe pull. Record

dynamometer readings.

8. Include witnessing of cable pulls by cable manufacturer and certification by manufacturer

that cable was not damaged during installation. Include witnessing of dynamometer

readings and certification that the manufacturer’s allowable pulling tension for each pull

was not exceeded.

9. Install cable using mechanical means with cable pulling equipment, pulleys, sheaves,

wheel, and rollers. Use of hydraulic or electric pulling equipment with smooth, variable

speed control is required. Do not manually pull in cables.

10. Use correctly sized cable pulley (sheave) for each cable-pull. Size sheave diameter per

cable calculations. Use sheave wide enough for cables to properly ride over the sheave.

Do not use narrow sheaves. Set up sheaves for direct reading from dynamometer.

11. Use listed pulling compounds compatible with the cable’s outer jacket, the raceway

involved, and acceptable to the cable manufacturer. If compatible, use Polywater® Type

J or F lubricant.

12. Do not exceed pulling tension of 0.008 pounds per circular mil of conductor cross

sectional area.

13. Pull cable from end resulting in least amount of tension applied to cable. Pull cables

down-grade with the feed-in point at the manhole or building with the highest elevation.

Keep pulling tension to a minimum by liberal application of lubricant, hand turning of

reel and slack feeding of cable into duct entrance. Employ not less than one person at

each reel and one at each manhole during pulling operation. Use 6 personnel minimum

when each phase is on a separate reel.

14. Remove all lashings used for temporary bunching of individual cables before they enter

the raceways.

15. Install cable in manholes along those walls providing the longest route and most spare

cable lengths. Loop cables around the entire inside diameter of manholes where possible.

Page 25: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

MEDIUM-VOLTAGE CABLES AND ACCESSORIES 260513 - 9

Arrange cable to avoid interferences with duct entrances into manhole to allow future

cable installation without relocation of cables.

16. Where required, use pulling eyes and bolts with long barrel ferrules that compress on to

the exposed conductors. Follow cable manufacturer’s instructions for application of

pulling eyes.

17. Do not pull cable into conduit embedded in concrete until after concrete is poured and

has set up.

18. Where cable is pulled under tension over sheaves, conduit bends or other curved surfaces,

select radium that will not result in excessive sidewall pressure and include sheaves,

conduit bends or other curved surfaces in above calculations.

E. Splices, Taps and Terminations

1. Approved splices and taps are indicated on Drawings. Obtain preapproval from the

Engineer or Owner in writing for any additional required splices and taps.

2. Provide terminals and connectors acceptable for the type of conductor used.

3. Follow the manufacturer’s installation instructions for all approved splices, taps and

terminations. For DIN plug-in connections, only factory trained and certified installers

are to be used.

4. Ground/earth cable shield at each splices, taps and terminations.

5. Use tools specified in this Section, for the required task, instead of a standard utility

knife, when cutting the outer jacket, tape-shields, semi-conductor insulation or stripping

insulation from medium-voltage cables.

6. Support cable splices and taps on each side of the splice or tap. Locate splices or taps to

prevent cyclic bending in the spliced sheath. Splices or taps shall not rely on the cable for

support.

7. Provide temporary seal over exposed conductors using tape and heat shrink sleeving

unless splicing and taps are to be completed immediately.

8. For grounding cable shield at each termination and splice, use one- or two-hole

appropriately sized compression connectors on cable shields and join connectors using

properly sized corrosion-resistant bolts, lock-washers and nuts. Install washers on the lug

side of the connection. Torque bolts to recommended values. Split-bolt type connectors

are not approved.

9. Install terminations at ends of conductors and seal multiconductor cable ends with

standard kits.

10. Install separable insulated-connector components as follows:

a. Protective Cap: At each terminal junction, with one on each terminal to which no

feeder is indicated to be connected.

b. Portable Feed-Through Accessory: Three.

c. Standoff Insulator: Three.

F. Other Installation Requirements

1. Locate approved splices and taps in manholes to enable periodic thermal imaging of the

splice or tap to be carried out by Owner.

2. Cable types to be used:

a. Single Conductor Medium-Voltage Cable - Shielded: Use for above and

underground applications (except for Jumper Cable applications – see Jumper

Cable below) and install in conduit or other raceways. Use in cable trays in

dedicated electrical vaults or rooms only.

b. Single Conductor Medium-Voltage Cable - Unshielded (Jumper): Use only

between equipment in the same vicinity, such as between primary switch and

Page 26: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

MEDIUM-VOLTAGE CABLES AND ACCESSORIES 260513 - 10

transformer where adequate through-air clearance can be achieved between

conductors. In general, do not use for installation in metallic raceways.

3. Support cables in manholes and similar locations with cable racks and secure to rack

insulators with self-locking nylon cable ties. Place each cable on a separate insulator.

4. For single-conductor mounting, install all phases from the same circuit on the same rack.

Do not install cables of more than one circuit on the same insulator.

5. Install exposed cables parallel and perpendicular to surfaces of exposed structural

members and follow surface contours where possible.

6. Support cables according to Division 26 Section "Hangers and Supports for Electrical

Systems."

7. Install "buried-cable" warning tape 12 inches (305 mm) above cables per details in the

construction drawings.

8. In manholes, handholes, pull boxes, junction boxes, and cable vaults, train cables around

walls by the longest route from entry to exit and support cables at intervals adequate to

prevent sag.

9. Seal around cables passing through fire-rated elements according to Division 07 Section

"Penetration Firestopping."

10. Install fault indicators on each phase where indicated.

11. Avoiding Cable Strain: Cable shall be trained to final location and secured with

temporary ties prior to any cutting. Terminations installed on the cable shall be oriented

to permit completion of the termination without twisting, or stressing the cable insulation.

12. Bending and Training Cable: The bend radius of any cable shall not be less than fifteen

times the outside diameter of the cable jacket. Cable shall not be twisted.

13. Contractor shall be responsible for the correct phasing out of the conductors of each

circuit at terminations and/or splices.

G. Arc Proofing: After all tests have been performed and accepted, arc-proof medium voltage

cables and termination assemblies within the manhole and at locations not protected by conduit

or termination materials except where indicated. Do not fire tape termination assemblies in

medium voltage switchgear or transformers. Fire tape each individual phase conductor. In

addition to arc-proofing tape manufacturer's written instructions, apply arc proofing as follows:

1. Clean cable sheath.

2. Wrap metallic cable components with 10-mil (250-micrometer) pipe-wrapping tape.

3. Smooth surface contours with electrical insulation putty.

4. Fireproof cables installed in manholes with one layer of one-half-lapped 3M Scotch® 77

or Plymouth-Bishop 53 tape. Apply vinyl side to outside of wrap. Wrap 3M Scotch 27 or

69 tape over fireproofing tape to hold the half-lapped tape in place and prevent

unraveling.

5. Band arc-proofing tape with 1-inch- (25-mm-) wide bands of half-lapped, adhesive,

glass-cloth tape 2 inches (50 mm) o.c.

6. Fireproof all three-phase cables together ending a minimum of 6 feet (1.83 m) from the

splice or connectors, and then individually wrap each phase conductor up to the splice or

connector. This works best if the individual wraps are applied first, and then the triplex-

cables are wrapped afterward to overlap the tape and adequately protect all cable

surfaces.

7. Completely cover each individual and triplex cable with fireproofing tape and hand-taped

splices from duct entrance to duct exit.

8. Extend half-lapped wraps a minimum of 1-inch into all ducts.

9. Extend the fireproofing tape a minimum of 1-inch onto all splice and T-connector bodies.

Page 27: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

MEDIUM-VOLTAGE CABLES AND ACCESSORIES 260513 - 11

H. Causes of Termination Failures: Terminations fail in test or in service for one or more of the

following reasons:

1. Improper crimping, use proper tool for fitting and proper fitting for cable. Check that

correct crimping pressure is applied.

2. Failure to completely cover mating surfaces with silicone lubricant.

3. Dirt or moisture in the termination assembly. Usually introduced by dirty hands, dirty

cleaning cloths, or laying termination material on the ground.

4. Over tightening or under tightening threaded connections. Torque values specified by the

termination manufacturer must be strictly adhered to.

5. Failure to properly assemble the termination. Contractor shall follow the termination

manufacturers specified procedures, strictly, in detail.

I. Site and Work Conditions: The site of the work and working conditions and procedures shall

comply with the following:

1. Clean dry work site a clean dry site shall be provided for constructing all terminations.

Termination work shall be done only in sunny dry weather, unless a heated and lighted

enclosure for the work is provided by the Contractor.

2. Clean drop cloths shall be provided for laying of parts and tools.

3. Hand cleaning supplies packaged cleaning tissues impregnated with an evaporating

cleaning compound and clean dry cotton cloths shall be provided for the termination

workmen to clean and dry their hands.

4. Adequate lighting natural or artificial lighting provided by the Contractor, shall be used

to provide not less than 200 footcandles on the work to be assembled.

5. Manufacturer's instructions work will be permitted at such time as the termination

manufacturers installation and assembly instructions are at work site and easily available

to the termination workmen.

6. Required tool set all tools required for assembly shall be at the work site prior to

beginning termination. The set shall include:

a. Cable shears and hacksaw (or rotating blade cable cutter). Roughing cut may be

made with shears. Final cable cut shall be made with hacksaw or rotating blade

cable cutter.

b. Crimping tool with proper dies for conductors terminated, including grounding

cable and ground leads from ground adapters.

c. Torque wrench (and spanner wrench for 600 amp).

d. Rotary blade insulation cutter and sharp knife.

e. Sand paper and insulation file.

3.4 CABLE GROUNDING:

A. Ground shields of all shielded cable at terminations, splices, and separable insulated connectors.

Ground metal bodies of terminators, splices, cable and separable insulated connector fittings,

and hardware in accordance with manufacturer’s written instructions. Use cable shield adaptor

kits, unless noted otherwise.

B. Connect the primary cable grounding conductors to the ground lug at the transformers and in

turn to the ground rod.

C. The shields of all primary cable terminations shall be bonded to the local ground in each piece

of equipment.

Page 28: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

MEDIUM-VOLTAGE CABLES AND ACCESSORIES 260513 - 12

D. Bare #4/0 AWG, copper 600 volt, equipment ground conductor shall be provided in all medium

voltage cable runs.

E. Ground all cable shields to new #4/0 AWG bare copper ring around interior of each vault. Bond

ring to new ground rods and to new #4/0 bare copper conductors in medium voltage conduit

runs.

F. For grounding cable shield at each termination and splice, use one- or two-hole appropriately

sized compression connectors on cable shields and join connectors using properly sized

corrosion-resistant bolts, lock-washers and nuts. Install washers on the lug side of the

connection. Torque bolts to recommended values. Split-bolt type connectors are not approved.

3.5 INSTALLATION OF CABLE ACCESSORIES

A. Tape for first course on metal objects in contact with cable, such as racks, shall be 10 mil thick,

corrosion protective, moisture resistant PVC pipe wrapping tape.

B. Fault Indicators: Mount remote 3-phase display unit in location noted:

1. Vaults: Point 3-phase display face toward ladder.

2. Switchgear: Flush mounted through housing with 3-phase display on the outside. Provide

label to indicate with circuit is represented.

3.6 IDENTIFICATION

A. Identify cables according to Division 26 Section "Identification for Electrical Systems."

B. Cables shall be identified in two locations:

1. Identify each cable bundle (related A, B and C phase cables) as to manufacturer’s product

number (MV-105), year installed, voltage (15 kV), conductor size, and Owner’s circuit

numbering scheme.

2. Identify each phase cable as to Phase, conductor size, and Owner’s circuit numbering

scheme.

C. Identification shall be carried in plastic embossed letter holder permanently secured with black

nylon ty-wraps where the cable emerges into each and all manholes or switchgear. Identification

shall be applied over the fire tapping where present.

D. The cables shall be identified with a 2” wide band of Scotch 35 colored insulation tape adjacent

to all splices and terminations. The colors shall correspond to the following code.

1. Phase A Two red bands

2. Phase B Two yellow bands

3. Phase C Two blue bands

E. Equipment grounding conductor Green

F. Provide above mentioned identification on all new cables and all existing cables in each

underground vault.

Page 29: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

MEDIUM-VOLTAGE CABLES AND ACCESSORIES 260513 - 13

3.7 FIELD QUALITY CONTROL

B. Testing: Engage a qualified testing and inspecting agency to perform the following field tests

and inspections and prepare test reports:

1. Perform each visual and mechanical inspection and electrical test stated in NETA ATS.

Certify compliance with test parameters.

2. After installing medium-voltage cables and before electrical circuitry has been energized,

test for compliance with requirements.

D. Test medium-voltage cable and accessories in accordance with the requirements of Section

26_08_80_00.

E. Remove and replace malfunctioning items and retest as specified above.

END OF SECTION 260513

Page 30: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Wires and Cables Section 260519 1

SECTION 260519 - WIRES AND CABLES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions

and Division 01 Specification Sections, apply to this Section.

B. Related Sections: The following Sections contain requirements that relate to this section:

1. Division 02 Section “Earthwork” for trenching and backfilling.

2. Division 26 Section “Basic Electrical Requirements.”

3. Division 26 Section “Electrical Identification” for conductor and cable color coding and

identification.

4. Division 26 Section “Electrical Boxes and Fittings” for connectors for Terminating Cables

in boxes and other electrical enclosures

1.2 SUMMARY

A. This Section includes wires, cables, and connectors for power, lighting, control and related

systems rated 600 volts and less.

1.3 SUBMITTALS

A. None required.

1.4 QUALITY ASSURANCE

A. Regulatory Requirements: Comply with provisions of the following code:

B. NFPA 70 “National Electrical Code.”

1. Conform to applicable codes and regulations regarding toxicity of combustion products of

insulating materials.

C. UL Compliance: Provide components which are listed and labeled by UL under the following

standards.

1. UL Std. 4 Armored Cable.

2. UL Std. 83 Thermoplastic-Insulated Wires and Cables.

3. UL Std. 486A Wire Connectors and Soldering Lugs for Use with Copper Conductors.

4. UL Std. 854 Service Entrance Cable.

Page 31: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Wires and Cables Section 260519 2

D. NEMA/ICEA Compliance: Provide components which comply with the following standards:

1. WC-5 Thermoplastic-Insulated Wire and Cable for the Transmission and Distribution of

Electrical Energy.

2. WC-7 Cross Linked Thermosetting Polyethylene-Insulated Wire and Cable for the

Transmission and Distribution of Electrical Energy.

3. WC-8 Ethylene-Propylene-Rubber-Insulated Wire and Cable for the Transmission and

Distribution of Electrical Energy.

E. IEEE Compliance: Provide components which comply with the following standard.

1. Std. 82 Test procedures for Impulse Voltage Tests on Insulated Conductors.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the

following:

1. Wire and Cable:

a. Alflex

b. AFC

c. American Insulated Wire Corp.

d. Rome

e. Southwire Company

2. Connectors for Wires and Cable Conductors:

a. AMP

b. 3M Company

c. O-Z/Gedney Co.

d. Square D Company

2.2 CONDUCTORS AND CABLES

A. General: Provide wire and cable suitable for the temperature, conditions and location where

installed.

B. Conductors: Provide stranded conductors for all power and lighting circuits. Solid conductors

are not acceptable.

C. Conductor Material: Copper for all conductors and cables except where approved by the

Engineer and Owner. When approved in writing it shall be per the aluminum feeder schedule

and only in the feeder sizes noted. Aluminum wiring shall be Stabiloy AA-8830, XHHW-2 type

only.

Page 32: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Wires and Cables Section 260519 3

D. Insulation: Provide THHN/THWN insulation, 90 degrees C as a minimum, for all conductors

size 500 KCMIL and larger, and no. 8 AWG and smaller. For all other sizes provide THW,

THHN/THWN or XHHW insulation as appropriate for the locations where installed. Use low

leakage copper wire (XHHW-2) for all wiring connected to isolation panels, heat trace cable

interconnect wiring, GFCI breakers and other locations and where noted herein.

E. Color Coding for phase identification in accordance with 260553.3.A., Identification.

F. Jackets: Factory-applied nylon or PVC external jacketed wires and cables for pulls in raceways

over 100-feet in length, for pulls in raceways with more than three equivalent 90 deg. bends, for

pulls in conduits underground or under slabs on grade, and where indicated.

2.3 CONNECTORS AND LUGS

A. Provide UL-listed factory-fabricated, solderless metal connectors of sizes, ampacity ratings,

materials, types and classes for applications and for services indicated. Use connectors with

temperature ratings equal to or greater than those of the wires upon which used.

B. Insulated Spring Connectors: Ideal Wire Nut, 3M Scotchlok and Hyflex.

C. Insulated Self Stripping Connectors: 3M 560 and 562.

D. Insulated Crimp Sleeve Connectors: Scotchlok S-31, Panduit VN.

E. Screw Terminal Lugs: Compression tool applied, insulated, flanged or locking fork; Panduit

PN-FF and PN-LF, Burndy, TP and YAE-Z.

F. Crimp Splice Connectors: Circumferential compression tool applied, with 600V heat shrink

insulation; Square D Types VACS with VSS, Kearney, Panduit, Burndy, T&B.

G. Crimp Lug: Circumferential compression tool applied for bolted connection, Panduit Panterm,

Square D Type VCEL, Kearney, T&B. Use long barrel, multiple crimp, two hole lugs wherever

possible. Set-screw type lugs are to be used only where crimp type lugs are not possible.

H. Crimp Tap Connector: Compression tool applied for parallel connections; Square D Type

VACC and VACT, T&B, Panduit.

I. Mechanical Lugs: Set screw, clamp type for 2 AWG and larger; Square D, Burndy, Ilsco. Use

two screw per conductor type lugs wherever possible and where crimp type lugs are not possible.

J. Joint Compound: Burndy Penetrox, Square D Versa-Seal.

K. Exothermically Welded: Erico Cadweld or approved substitute.

L. Vertical Conduit Conductor Clamp Fittings: Burndy or approved substitute.

Page 33: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Wires and Cables Section 260519 4

PART 3 - EXECUTION

3.1 WIRING METHOD

A. Use the following wiring methods as indicated:

1. Conductors: install all conductors in raceway.

B. Install the following minimum sizes of copper conductors for interior wiring of 20-ampere

branch circuits for applications and circuit lengths unless otherwise indicated. For circuit lengths

exceeding the scheduled values install as shown. Refer cases of uncertain applicability to the

Engineer for resolution prior to conduit rough-in and install as directed as part of the Contract

work. Circuits lengths are total current path, device terminal to device terminal. Integral device

and fixture wires are excluded.

Application Circuit

Length (ft.)

Min. Size

(AWG)

277V lighting total of through wiring & home run 0-150

151-250

250-400

12

10

8

277V lighting total of switch tap & switched leg to fixture 0-100

101-200

201-300

12

10

10

120V lighting total of through wiring & home run 0-75

76-125

126-200

12

10

10

120V lighting total of switch tap & switched leg to fixtures 100

101-150

12

10

120V General Purpose receptacle total of through wiring & home

run

0-50

51-125

126-200

12

10

10

120 V General Purpose receptacle total of circuit tap to device 0-50

51-100

101-150

12

10

10

C. The above table is superceded if larger conductor sizes are shown on the drawings or specified

elsewhere such as on site plan drawings.

D. Install copper equipment ground conductor with all branch circuits; see Section 260526

“Grounding.” Increase branch circuit equipment ground conductor sizes in accordance with

NEC for voltage drop.

E. All home runs, through wiring, exposed areas, buried or in-slab conditions, concealed circuits

which become inaccessible in the finished work, feeders, special purpose outlets, special purpose

receptacles and workstation receptacle power circuits must be installed in raceway, unless

otherwise noted.

Page 34: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Wires and Cables Section 260519 5

F. Install cross linked polyethylene insulated hot and neutral conductors with dielectric constant of

3 on load side of ground fault circuit interrupters when one-way circuit length exceeds 50'; 600V

type XLP typical.

G. Portable Cord Type S: For flexible pendant leads to outlets and equipment where permitted by

Code and as indicated.

H. Installation of the following conductor and cable types for permanent wiring is prohibited:

1. Aluminum Conductors: Prohibited.

2. Nonmetallic Sheathed Cable Types NM and NMC: Prohibited.

3. Service Entrance Cable, Types SE and USE: Prohibited.

3.2 INSTALLATION OF POWER WIRES AND CABLES

A. General: Install electrical cables, wires, and connectors in compliance with NEC.

B. Coordinate cable installation with other Work.

C. Pull conductors simultaneously where more than one is being installed in same raceway. Use UL

listed pulling compound or lubricant, where necessary.

D. Use pulling means including, fish tape, cable, rope, and basket weave wire/cable grips which will

not damage cables or raceways. Do not use rope hitches for pulling attachment to wire or cable.

E. Conceal all cable in finished spaces.

F. Install exposed cable parallel and perpendicular to surfaces or exposed structural members, and

follow surface contours, where possible.

G. Provide adequate length of conductors within electrical enclosures and train the conductors to

terminal points with no excess. Bundle multiple conductors, with conductors larger than no. 10

AWG cabled in individual circuits. Make terminations so there is no bare conductor at the

terminal. Identify neutral with correct phase conductor at each j-box and panel.

H. Provide conductor clamp type supports in NEMA enclosures at code required intervals on

vertical conduit runs. Terminations shall not bear the weight of the conductors.

I. MC cable is a) permissible to be used in lieu of EMT conduit and conductors for all power

circuits, except as noted herein. b) MC cable shall only be used for the drops concealed inside

walls inside of a room down to the final branch device or below a raised floor. Do not run MC

cable exposed to normal view. c) Conduit shall be used for all homeruns and “through-wiring”

connections between rooms.

J. All branch circuits shall be provided with separate neutral and shall not share a common neutral.

Branch circuit breakers with tie bars are not acceptable.

Page 35: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Wires and Cables Section 260519 6

3.3 CONNECTORS AND INSULATION

A. Install splices only where such circuits must branch; splice conductors only at outlet boxes,

junction boxes and splice boxes. Keep conductor splices to minimum.

B. Install splice and tap connectors, which possess equivalent or better mechanical strength and

insulation rating than conductors being spliced.

C. Use splice and tap connectors which are compatible with conductor material.

D. Tighten electrical connectors and terminals, including screws and bolts, in accordance with

manufacturer's published torque tightening values. Where manufacturer's torquing requirements

are not indicated, tighten connectors and terminals to comply with tightening torques specified in

UL 486A and UL 486B.

E. Join power limited circuit conductors with insulated crimp sleeve connectors and terminate in

screw terminal lugs, except where otherwise required.

F. Join 8 AWG or larger with crimp compression connectors wherever possible and insulate the

joint equal to the insulation of the conductors. Mechanical connectors are allowed only in

devices such as circuit breakers, where crimp connections are not available.

G. Crimp Required: Install only crimp connectors and crimp lugs for wet locations such as junction

boxes below grade. Install only crimp connectors and crimp lugs for separate grounding

conductors larger than 10 AWG; comply with Section 260526 “Grounding.”

H. Lug Adaptors: Use crimp butt splices and short piece of 10 AWG conductor to adapt oversize

277-volt and 120-volt 20-ampere branch circuit conductors to lugs of devices (branch circuit

breakers, contactors, etc.) labeled for 10 AWG maximum size conductors.

I. Crimp Connections: Use hydraulic compression tools to provide the correct circumferential

pressure for compression connectors. Use tools and dies recommended by the manufacturer of

the connectors. Provide embossing die code or other standard method to make a visible

indication that a connector has been adequately compressed on the ground conductor. Insulate

splices equal to conductor insulation system.

J. Use insulated self-stripping connectors only where specifically indicated; otherwise prohibited.

K. Electrical contractor to provide all lugs inside switchboards, distribution boards, switchgear,

panelboards, on bus bars, etc, except where the lugs are an integral part of a circuit breaker.

Provide specified crimp type lugs wherever possible. This is to prevent mis-coordination issues

between equipment venders, changes in feeder sizes and type of lugs required.

3.4 IDENTIFICATION

A. Refer to specification section 260553.

Page 36: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Wires and Cables Section 260519 7

3.5 FIELD QUALITY CONTROL

A. Prior to energizing, check installed wires and cables with megohm meter to determine insulation

resistance levels to assure requirements are fulfilled.

B. Prior to energizing, test wires and cables for electrical continuity and for short circuits.

C. Subsequent to wire and cable hook-ups, energize circuits and demonstrate proper functioning.

Correct malfunctioning units, and retest to demonstrate compliance.

END OF SECTION 260519

Page 37: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Grounding Section 260526 1

SECTION 260526 – GROUNDING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions

and Division 01 Specification Sections, apply to this Section.

B. Requirements of the following Division 26 Sections apply to this Section:

1. "Basic Electrical Requirements."

1.2 SUMMARY

A. This Section includes solid grounding of electrical systems and equipment. It includes basic

requirements for grounding for protection of life, equipment, circuits, and systems. Grounding

requirements specified in this Section may be supplemented in other sections of these

Specifications.

B. Related Sections: The following sections contain requirements that relate to this Section:

1. Division 26 Section "Wires and Cables."

1.3 SUBMITTALS

A. None required.

1.4 QUALITY ASSURANCE

A. Listing and Labeling: Provide products specified in this Section that are listed and labeled. The

terms "listed" and "labeled" shall be defined as they are in the National Electrical Code, Article

100.

1. Listing and Labeling Agency Qualifications: A "Nationally Recognized Testing

Laboratory" (NRTL) as defined in OSHA Regulation 1910.7.

B. Field-Testing Organization Qualifications: To qualify for acceptance, the independent testing

organization must demonstrate, based on evaluation of organization-submitted criteria

conforming to ASTM E 699, that it has the experience and capability to conduct satisfactorily the

testing indicated.

C. Electrical Component Standard: Components and installation shall comply with NFPA 70,

"National Electrical Code" (NEC).

Page 38: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Grounding Section 260526 2

D. UL Standard: Comply with UL 467, "Grounding and Bonding Equipment."

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by the following:

1. Anixter Bros., Inc.

2. A.B. Chance Co.

3. Engineered Products Co.

4. Erico Products, Inc.

5. GB Electrical, Inc.

6. Ideal Industries, Inc.

7. Kearney-National.

8. O-Z/Gedney Co.

9. Raco, Inc.

10. Thomas & Betts Corp.

2.2 GROUNDING AND BONDING PRODUCTS

A. Products: Of types indicated and of sizes and ratings to comply with NEC. Where types, sizes,

ratings, and quantities indicated are in excess of NEC requirements, the more stringent

requirements and the greater size, rating, and quantity indications govern.

B. Conductor Materials: Copper.

2.3 WIRE AND CABLE CONDUCTORS

A. General: Comply with Division 26 Section "Wires and Cables." Conform to NEC Table 8,

except as otherwise indicated, for conductor properties, including stranding.

B. Equipment Grounding Conductor: Green insulated.

C. Grounding Electrode Conductor: Stranded cable. Do not use conductors with greater than 7-

strands in direct burial applications. Smaller strands do not last as long.

D. Bare Copper Conductors: Conform to the following:

1. Solid Conductors: ASTM B-3.

2. Assembly of Stranded Conductors: ASTM B-8.

3. Tinned Conductors: ASTM B-33.

2.4 MISCELLANEOUS CONDUCTORS

A. Ground Bus: Bare annealed copper bars of rectangular cross section.

Page 39: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Grounding Section 260526 3

B. Braided Bonding Jumpers: Copper tape, braided No. 30 gage bare copper wire, terminated with

copper ferrules.

C. Bonding Strap Conductor/Connectors: Soft copper, 0.05 inch thick and 2 inches wide, except as

indicated.

2.5 CONNECTOR PRODUCTS

A. General: Listed and labeled as grounding connectors for the materials used.

B. Pressure Connectors: High-conductivity-plated units.

C. Bolted Clamps: Heavy-duty units listed for the application.

D. Exothermic Welded Connections: Provided in kit form and selected for the specific types, sizes,

and combinations of conductors and other items to be connected.

E. Aluminum-To-Copper Connections: Bimetallic type, conforming to UL 96, "Lighting Protection

Components," or UL 467.

PART 3 - EXECUTION

3.1 APPLICATION

A. Equipment Grounding Conductor Application: Comply with NEC Article 250 for sizes and

quantities of equipment grounding conductors, except where larger sizes or more conductors are

indicated.

1. Install separate insulated equipment grounding conductors with circuit conductors for the

following in addition to those locations where required by Code:

a. Feeders and branch circuits.

b. Lighting circuits.

c. Receptacle Circuits.

d. Single-phase motor or appliance circuits.

e. Three-phase motor or appliance branch circuits.

2. Busway Circuits: Install separate insulated equipment ground conductor from the ground

bus in the switchgear, switchboard, or distribution panel to the equipment ground bar

terminal on the busway.

3. Data Center Panel Circuits: Install separate insulated equipment ground wire in branch

circuits from data center power panels.

4. Nonmetallic Raceways: Install an insulated equipment ground conductor in nonmetallic

raceways unless they are designated for telephone or data cables.

5. Air Duct Equipment Circuits: Install an insulated equipment grounding conductor to

duct-mounted electrical devices operating at 120-V and above including air cleaners and

heaters. Bond the conductor to each such unit and to the air duct.

Page 40: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Grounding Section 260526 4

6. Water Heater, Heat Tracing, and Anti-Frost Heater Circuits: Install separate insulated

equipment ground conductor to each electric water heater, heat tracing, and surface

anti-frost heating cable. Bond this conductor to heater units, piping, and connected

equipment and components.

B. Signal and Communications: For telephone, alarm, and communication systems, provide a #4

AWG minimum green insulated copper conductor in raceway from the grounding electrode

system to each terminal cabinet or central equipment location.

C. Separately derived systems required by NEC to be grounded shall be grounded in accordance

with NEC paragraph 250-26.

D. Provide code sized grounding conductor bonded to "incoming water pipes" and all other metallic

pipes in addition to the domestic water.

3.2 INSTALLATION

A. General: Ground electrical systems and equipment in accordance with NEC requirements except

where the Drawings or Specifications exceed NEC requirements.

B. Electrical room Ground Bus: Size, location, and arrangement as indicated. Space 1 inch from

wall and support from wall 6 inches above finished floor, except as otherwise indicated.

C. Ground Rods: Locate a minimum of one-rod length from each other and at least the same

distance from any other grounding electrode. Interconnect ground rods with bare conductors

buried at least 24 inches below grade. Connect bare-cable ground conductors to ground rods by

means of exothermic welds except as otherwise indicated. Make these connections without

damaging the copper coating or exposing the steel. Use 3/4-inch by 10-ft. ground rods except as

otherwise indicated. Drive rods until tops are 6 inches below finished floor or final grade except

as otherwise indicated.

D. Metallic Water Service Pipe: Provide insulated copper ground conductors, sized as indicated, in

conduit from the building main service equipment, or the ground bus, to main metallic water

service entrances to the building. Connect ground conductors to the main metallic water service

pipes by means of ground clamps. Where a dielectric main water fitting is installed, connect the

ground conductor to the street side of the fitting. Do not install a grounding jumper around

dielectric fittings. Bond the ground conductor conduit to the conductor at each end.

E. Braided-Type Bonding Jumpers: Install to connect ground clamps on water meter piping to

bypass water meters electrically. Use elsewhere for flexible bonding and grounding connections.

F. Route grounding conductors along the shortest and straightest paths possible without obstructing

access or placing conductors where they may be subjected to strain, impact, or damage, except as

indicated.

G. Bond interior metal piping systems and metal air ducts to equipment ground conductors of

pumps, fans, electric heaters, and air cleaners serving individual systems.

Page 41: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Grounding Section 260526 5

3.3 CONNECTIONS

A. General: Make connections in such a manner as to minimize possibility of galvanic action or

electrolysis. Select connectors, connection hardware, conductors, and connection methods so

metals in direct contact will be galvanically compatible.

1. Use electroplated or hot-tin-coated materials to assure high conductivity and make contact

points closer in order of galvanic series.

2. Make connections with clean bare metal at points of contact.

3. Aluminum to steel connections shall be with stainless steel separators and mechanical

clamps.

4. Aluminum to galvanized steel connections shall be with tin-plated copper jumpers and

mechanical clamps.

5. Coat and seal connections involving dissimilar metals with inert material such as red lead

paint to prevent future penetration of moisture to contact surfaces.

B. Exothermic Welded Connections: Use for connections to structural steel and for underground

connections except those at test wells. Install at connections to ground rods and plate electrodes.

Comply with manufacturer's written recommendations. Welds that are puffed up or that show

convex surfaces indicating improper cleaning are not acceptable.

C. Terminate insulated equipment grounding conductors for feeders and branch circuits with

pressure-type grounding lugs. Where metallic raceways terminate at metallic housings without

mechanical and electrical connection to the housing, terminate each conduit with a grounding

bushing. Connect grounding bushings with a bare grounding conductor to the ground bus in the

housing. Bond electrically non-continuous conduits at both entrances and exits with grounding

bushings and bare grounding conductors.

D. Tighten grounding and bonding connectors and terminals, including screws and bolts, in

accordance with manufacturer's published torque tightening values for connectors and bolts.

Where manufacturer's torquing requirements are not indicated, tighten connections to comply

with torque tightening values specified in UL 486A and UL 486B.

E. Compression-Type Connections: Use hydraulic compression tools to provide the correct

circumferential pressure for compression connectors. Use tools and dies recommended by the

manufacturer of the connectors. Provide embossing die code or other standard method to make a

visible indication that a connector has been adequately compressed on the ground conductor.

F. Moisture Protection: Where insulated ground conductors are connected to ground rods or

ground buses, insulate the entire area of the connection and seal against moisture penetration of

the insulation and cable.

3.4 FIELD QUALITY CONTROL

A. Independent Testing Organization: Arrange and pay for the services of a qualified independent

electrical testing organization to perform tests described below.

B. Tests: Subject the completed grounding system to a megger test at each location where a

maximum ground resistance level is specified, at service disconnect enclosure ground terminal,

and at ground test wells. Measure ground resistance without the soil being moistened by any

Page 42: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Grounding Section 260526 6

means other than natural precipitation or natural drainage or seepage and without chemical

treatment or other artificial means of reducing natural ground resistance. Perform tests by the

2-point method in accordance with Section 9.03 of IEEE 81, "Guide for Measuring Earth

Resistivity, Ground Impedance and Earth Surface Potentials of a Grounding System."

C. Ground/resistance maximum values shall be as follows:

1. Equipment rated 500 kVA and less: 3 Ohms

2. Equipment rated 500 kVA to 1000 kVA: 3 Ohms

3. Equipment rated over 1000 kVA: 3 Ohms

D. Deficiencies: Where ground resistances exceed specified values, and if directed, modify the

grounding system to reduce resistance values. Where measures are directed that exceed those

indicated the provisions of the Contract, covering changes will apply.

E. Report: Prepare test reports, certified by the testing organization, of the ground resistance at

each test location. Include observations of weather and other phenomena that may affect test

results. Describe measures taken to improve test results.

3.5 CLEANING AND ADJUSTING

A. Restore surface features at areas disturbed by excavation and reestablish original grades except as

otherwise indicated. Where sod has been removed, replace it as soon as possible after backfilling

is completed. Restore areas disturbed by trenching, storing of dirt, cable laying, and other Work

to their original condition. Include necessary top soiling, fertilizing, liming, seeding, sodding,

sprigging, or mulching. Perform such Work in accordance with Division 02 Section "Landscape

Work." Maintain disturbed surfaces. Restore vegetation in accordance with Section "Landscape

Work." Restore disturbed paving as indicated.

END OF SECTION 260526

Page 43: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Supporting Devices Section 260529 1

SECTION 260529 - SUPPORTING DEVICES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions

and Division 01 Specification Sections, apply to this Section.

B. Requirements of the following Sections apply to this section:

1. Division 26 “Basic Electrical Requirements.”

2. Division 03 Section “Concrete” for inserts, anchors, and sleeves to be installed in concrete

for use with supporting devices.

3. Division 05 Section “Metal” for requirements for miscellaneous metal items involved in

supports and fastenings.

4. Division 07 Section “Thermal and Moisture Protection” for requirements for Fire stopping

at sleeves through walls and floors that are fire barriers.

5. Refer to other Division 26 sections for additional specific support requirements that may

be applicable to specific items.

1.2 SUMMARY

A. This Section includes secure support from the building structure for electrical items by means of

hangers, supports, anchors, sleeves, inserts, seals, and associated fastenings.

1.3 SUBMITTALS

A. General: Submit the following in accordance with Conditions of Contract and Division 01

Specification Sections.

B. Product data for each type of product specified.

1. Hanger and support schedule showing manufacturer's figure number, size, spacing,

features, and application for each required type of hanger, support, sleeve, seal, and

fastener to be used.

C. Shop drawings indicating details of fabricated products and materials.

1.4 QUALITY ASSURANCE

A. Electrical Component Standard: Components and installation shall comply with NFPA 70

"National Electrical Code."

Page 44: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Supporting Devices Section 260529 2

B. Electrical components shall be listed and labeled by UL, ETL, CSA, or other approved,

nationally recognized testing and listing agency that provides third-party certification follow-up

services.

1.5 SEISMIC ANCHORAGE/RESTRAINT REQUIREMENTS

A. Intent: It is the intent of the seismic portion of this specification to keep all electrical building

system components in place during a seismic event. All such systems must be installed in strict

accordance with seismic codes, component manufacturer's and building construction standards.

Whenever a conflict occurs between the manufacturer's or construction standards, the most

stringent shall apply.

B. This specification is considered to be minimum requirements for seismic consideration and is not

intended as a substitute for legislated, more stringent, national, state or local construction

requirements. Any variance or non-compliance with these specification requirements shall be

corrected by the contractor in an approved manner.

C. Seismic Zone Rating: All equipment and wiring shall be anchored to withstand forces generated

by earthquake motions and certified to meet all applicable seismic requirements of the jobsite

area.

D. Contractor shall engage and pay for the services of a structural engineer, registered in the state of

the project, with a minimum of 5 years experience in the industry, to perform structural design

and submit installation details and calculations for the support of the following items: The

Contractor shall provide assistance and proposed installation sketches to structural engineer as

required.

1. All electrical busway, overhead cable trays and ladder trays.

2. All fire protection equipment and life safety equipment shall be seismically restrained

using the required seismic force levels for life safety equipment.

3. Wall mounted and ceiling hung equipment greater than or equal to 400 lbs.

4. Conduit trapeze racks supporting more than two conduits where any conduit is greater

than 1.25" in diameter.

5. Anchor bolt calculations, signed and stamped by a licensed Structural Engineer in the state

of the project, shall be submitted showing adequacy of the bolt sizing and type. Provide

anchor bolts or drill in anchors that are seismically approved and properly selected, based

on design calculations through the center or gravity. Anchor bolts must be embedded and

spaced in accordance with ICBO standards.

6. Seismic restraint exclusions:

a. All conduit less than 2.5" diameter suspended by individual hanger rods.

b. All conduits suspended by individual hangers 12" or less as measured from the top

of the conduit to the bottom of the support where the hanger is a attached.

However, if the 12" limit is exceeded by any hanger in the run, seismic bracing is

required for the run.

c. The 12" exemption applies for trapeze supported systems if the top of each item

supported by the trapeze qualifies.

Page 45: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Supporting Devices Section 260529 3

E. When the exact location of conduit racks and equipment have been established, the Contractor’s

Structural Engineer shall check the adequacy of the building structure to ensure that the

installation is adequate.

F. Seismic calculations are not required for items not included in the above list, but the Contractor

shall support all equipment and wiring in accordance with recognized seismic restraint design

guidelines such as the "Superstrut: Seismic Restraint System" for conduits, and the "Kin-line:

Seismic Restraint System" for conduits and “Mason Industries Seismic Restrain Guidelines.”

All suspended equipment must be braced against sway and axial motion. Cable braces or solid

braces shall be used. Suspension rods shall include “strongback” bracing to prevent buckling

when subjected to compression stress.

G. Definitions:

1. Life Safety Systems:

a. All systems involved with fire protection including sprinkler piping, fire pumps,

jockey pumps, fire pump control panels, service water supply piping, water tanks,

fire dampers and smoke exhaust systems.

b. All systems involved with and/or connected to emergency power supply including

all generators, transfer switches, transformers and all flow paths to fire protection

and/or emergency lighting systems.

c. Fresh air relief systems on emergency control sequence including air handlers,

conduit, duct, dampers, etc.

2. Positive Attachment: A positive attachment is defined as a cast-in anchor, a drill-in wedge

anchor, a double-sided beam clamp loaded perpendicular to a beam, or a welded or bolted

connection to structure. Single sided "C" type beam clamps for support rods of overhead

piping, ductwork, fire protection, electrical conduit, bus duct, or cable trays, or any other

equipment are not acceptable on this project as seismic anchor points.

3. Transverse Bracing: Restraint(s) applied to limit motion perpendicular to the centerline of

the pipe, duct or conduit.

4. Longitudinal Bracing: Restraint(s) applied to limit motion parallel to the centerline of the

pipe, duct or conduit.

H. Submittal Data Requirements: The manufacturer of vibration isolation and seismic restraints

shall provide submittals for products as follows:

1. Descriptive Data:

a. Catalog cuts or data sheets on vibration isolating pads, anchor bolts and other

specific restraints or supports detailing compliance with the specification.

b. Detailed schedules of flexible and rigidly mounted equipment, showing seismic

restraints by referencing numbered descriptive drawings.

2. Shop Drawings:

a. Submit fabrication details for equipment bases including dimensions, structural

member sizes and support point locations.

b. Provide all details of suspension and support for ceiling hung equipment.

Page 46: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Supporting Devices Section 260529 4

c. Where walls, floors, slabs or supplementary steel work are used for seismic restraint

locations, details of acceptable attachment methods for conduit and equipment must

be included and approved before the condition is accepted for installation.

Restraint manufacturers' submittals must include spacing, static loads and seismic

loads at all attachment and support points.

d. Provide specific details of seismic restraints and anchors; include the number, size,

and type of anchor bolts, support rods/unistrut, cable restraints, etc., for each piece

of equipment.

e. Provide specific structure details and design for housekeeping pad reinforcement

and non-monolithic pad attachment. Housekeeping pads shall be coordinated with

restraint vendor and sized to provide a minimum edge distance of ten (10) bolt

diameters all around the outermost anchor bolt to allow development of full drill-in

wedge anchor ratings. If cast-in anchors are to be used, the housekeeping pads shall

be sized to accommodate the ACI requirements for bolt coverage and embedment.

3. Complete engineering calculations and drawings for all vibration and seismic

requirements for all equipment, piping and ductwork.

4. Seismic Certification and Analysis:

a. Seismic restraint calculations shall be provided for all connections of equipment to

the structure. Calculations must be stamped by a registered professional engineer

with at least five years of seismic design experience, licensed in the state of the job

location.

b. All restraining devices shall have a pre-approval number from California OSHPD

or some other recognized government agency showing maximum restraint ratings.

Pre-approvals based on independent testing are preferred to pre-approvals based on

calculations. Where pre-approved devices are not available, submittals based on

independent testing are preferred. Calculations (including the combining of tensile

and shear loadings) to support seismic restraint designs must be stamped by a

registered professional engineer with at least five years of seismic design experience

and licensed in the state of the job location. Testing and calculations must include

both shear and tensile loads as well as one test or analysis at 45° to the weakest

mode.

c. Analysis must indicate calculated dead loads, static seismic loads and capacity of

materials utilized for connections to equipment and structure. Analysis must detail

anchoring methods, bolt diameter, embedment and/or welded length. All seismic

restraint devices shall be designed to accept, without failure, the forces detailed in

following section acting through the equipment center of gravity. Overturning

moments may exceed forces at ground level.

I. Related Work:

1. Supplementary Support Steel: Contractor shall supply supplementary support steel for all

equipment and wiring, etc., as required or specified.

2. Attachments: Contractor shall supply restraint attachment plates cast into housekeeping

pads, concrete inserts, double sided beam clamps, etc. in accordance with the requirements

of the structural engineer’s calculations.

Page 47: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Supporting Devices Section 260529 5

J. Products:

1. Seismic Cable Restraints shall consist of galvanized steel aircraft cables sized to resist

seismic loads with a minimum safety factor of two and arranged to provide all-directional

restraint. Cables must be prestretched to achieve a certified minimum modulus of

elasticity. Cable end connections shall be steel assemblies that swivel to final installation

angle and utilize two clamping bolts to provide proper cable engagement. Cables must not

be allowed to bend across sharp edges. Cable assemblies shall have an Anchorage Pre-

approval "R" Number from OSHPD in the State of California verifying the maximum

certified load ratings. Cable assemblies shall be Type SCB at the ceiling and at the clevis

bolt, SCBH between the hanger rod nut and the clevis or SCBV if clamped to a beam all

as manufactured by Mason Industries, Inc.

2. Seismic solid braces shall consist of steel angles or channels to resist seismic loads with a

minimum safety factor of 2 and arranged to provide all directional restraint. Seismic solid

brace end connectors shall be steel assemblies that swivel to the final installation angle

and utilize two through bolts to provide proper attachment. Seismic solid brace assembly

shall have anchorage preapproval "R" number from OSHPD in the state of California

verifying the maximum certified load ratings. Solid seismic brace assemblies shall be type

SSB as manufactured by Mason Industries, Inc.

3. Steel angles, sized to prevent buckling, shall be clamped to pipe or equipment rods

utilizing a minimum of three ductile iron clamps at each restraint location when required.

Welding of support rods is not acceptable. Rod clamp assemblies shall have an

Anchorage Preapproval "R" Number from OSHPD in the State of California. Rod clamp

assemblies shall be Type SRC as manufactured by Mason Industries, Inc.

4. Anchor bolts shall be manufactured by Hilti Redtop diameter and penetration depth as

required for each application.

K. Execution:

1. General: All seismic restraint systems must be installed in strict accordance with the

manufacturers written instructions and all certified submittal data.

2. Installation of seismic restraints must not cause any change of position of equipment

resulting in stresses or misalignment.

3. No rigid connections between equipment and the building structure shall be made that

transmits noise or vibration. Provide specified flexible wiring connections and neoprene

isolation pads for transformers and rotating or vibrating machinery. "Building" includes,

but is not limited to, slabs, beams, columns, studs and walls.

4. Coordinate work with other trades to avoid rigid contact with the building.

5. Any conflicts with other trades which will result in rigid contact with equipment or wiring

due to inadequate space or other unforeseen conditions should be brought to the

architects/engineers attention prior to installation. Corrective work necessitated by

conflicts after installation shall be at the responsible contractors expense.

6. Bring to the architects/engineers attention any discrepancies between the specifications

and the field conditions or changes required due to specific equipment selection, prior to

installation. Corrective work necessitated by discrepancies after installation shall be at the

responsible contractors expense.

7. Correct, at no additional cost, all installations, which are deemed defective in

workmanship and materials at the contractor’s expense.

Page 48: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Supporting Devices Section 260529 6

8. Overstressing of the building structure must not occur because of overhead support of

equipment. Contractor must submit loads to the structural engineer of record for approval.

Generally bracing may occur from:

a. Flanges of structural beams.

b. Upper truss cords in bar joist construction.

c. Cast in place inserts or wedge type drill-in concrete anchors.

9. Cable restraints shall be installed slightly slack only where required to not short-circuit the

intent of isolating equipment that may transmit noise or vibration. Cable assemblies shall

be installed taut on non-isolated systems. Seismic solid braces may be used in place of

cables on rigidly attached systems only.

10. Support rods must be braced as required by design guidelines to prevent buckling under

compressive loading condition.

11. Provide drill-in type male concrete anchors for ceiling and wall installation and female

wedge type for floor mounted equipment.

12. Transverse restraints shall occur at 30' intervals or both ends if the electrical run is less

than the specified interval. Transverse restraints shall be installed at each electrical

services turn and at each end of the electric run.

13. Longitudinal restraints shall occur at 60' intervals with at least one restraint per electric

run. Transverse restraints for one electric section may also act as a longitudinal restraint

for a duct for an electric section connected perpendicular to it if the restraints are installed

within 4' of the intersection of the electric run and if the restraints are sized for the larger

electric run.

14. All rigid floor mounted equipment must have a resilient media between the equipment

mounting hole and the anchor bolt. Anchor bolts shall be designed in accordance with

specified seismic forces.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by the following:

1. Slotted Metal Angle and U-Channel Systems:

a. Allied Tube & Conduit

b. B-Line Systems, Inc.

c. GS Metals Corp.

d. Unistrut Diversified Products

2. Conduit Sealing Bushings:

a. Cooper Industries, Inc.

b. GS Metals Corp.

c. Killark Electric Mfg. Co.

d. O-Z/Gedney

e. Raco, Inc.

f. Spring City Electrical Mgf. Co.

Page 49: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Supporting Devices Section 260529 7

g. Thomas & Betts Corp.

2.2 COATINGS

A. Coating: Supports, support hardware, and fasteners shall be protected with zinc coating or with

treatment of equivalent corrosion resistance using approved alternative treatment, finish, or

inherent material characteristic. Products for use outdoors shall be hot-dip galvanized.

2.3 MANUFACTURED SUPPORTING DEVICES

A. Raceway Supports: Clevis hangers, riser clamps, conduit straps, threaded C-clamps with

retainers, ceiling trapeze hangers, wall brackets, and spring steel clamps.

B. Fasteners: Types, materials, and construction features as follows:

1. Expansion Anchors: Carbon steel wedge or sleeve type.

2. Toggle Bolts: All steel springhead type.

3. Powder-Driven Threaded Studs: Heat-treated steel, designed specifically for the intended

service.

4. Steel nail-in fasteners are not acceptable.

C. Conduit Sealing Bushings: Factory-fabricated watertight conduit sealing bushing assemblies

suitable for sealing around conduit, or tubing passing through concrete floors and walls.

Construct seals with steel sleeve, malleable iron body, neoprene sealing grommets or rings, metal

pressure rings, pressure clamps, and cap screws.

D. Cable Supports for Vertical Conduit: Factory-fabricated assembly consisting of threaded body

and insulating wedging plug for non-armored electrical cables in riser conduits. Provide plugs

with number and size of conductor gripping holes as required to suit individual risers. Construct

body of malleable-iron casting with hot-dip galvanized finish.

E. U-Channel Systems: 16-gage steel channels, with 9/16-inch-diameter holes, at a minimum of 8

inches on center, in top surface. Provide fittings and accessories that mate and match with

U-channel and are of the same manufacture.

2.4 FABRICATED SUPPORTING DEVICES

A. General: Shop- or field-fabricated supports or manufactured supports assembled from U-channel

components.

B. Steel Brackets: Fabricated of angles, channels, and other standard structural shapes. Connect

with welds and machine bolts to form rigid supports.

Page 50: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Supporting Devices Section 260529 8

C. Pipe Sleeves: Provide pipe sleeves of one of the following:

1. Sheet Metal: Fabricate from galvanized sheet metal; round tube closed with snaplock

joint, welded spiral seams, or welded longitudinal joint. Fabricate sleeves from the

following gage metal for sleeve diameter noted:

a. 3-inch and smaller: 20-gage.

b. 4-inch to 6-inch: 16-gage.

c. Over 6-inch: 14-gage.

2. Steel Pipe: Fabricate from Schedule 40 galvanized steel pipe.

3. Plastic Pipe: Fabricate from Schedule 80 PVC plastic pipe.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install supporting devices to fasten electrical components securely and permanently in

accordance with NEC requirements.

B. Coordinate with the building structural system and with other electrical installation.

C. Raceway Supports: Comply with the NEC and the following requirements:

1. Conform to manufacturer's recommendations for selection and installation of supports.

2. Strength of each support shall be adequate to carry present and future load multiplied by a

safety factor of at least four. Where this determination results in a safety allowance of less

than 200 lbs, provide additional strength until there is a minimum of 200 lbs safety

allowance in the strength of each support.

3. Install individual and multiple (trapeze) raceway hangers and riser clamps as necessary to

support raceways. Provide U-bolts, clamps, attachments, and other hardware necessary

for hanger assembly and for securing hanger rods and conduits.

4. Support parallel runs of horizontal raceways together on trapeze-type hangers.

5. Support individual horizontal raceways by separate pipe hangers. Spring steel fasteners

may be used in lieu of hangers only for 1-1/2-inch and smaller raceways serving lighting

and receptacle branch circuits above suspended ceilings only. For hanger rods with spring

steel fasteners, use 1/4-inch-diameter or larger threaded steel. Use spring steel fasteners

that are specifically designed for supporting single conduits or tubing.

6. Space supports for raceways in accordance with Table I of this section. Space supports for

raceway types not covered by the above in accordance with NEC.

7. Support exposed and concealed raceway within 1 foot of an unsupported box and access

fittings. In horizontal runs, support at the box and access fittings may be omitted where

box or access fittings are independently supported and raceway terminals are not made

with chase nipples or threadless box connectors.

8. In vertical runs, arrange support so the load produced by the weight of the raceway and the

enclosed conductors is carried entirely by the conduit supports with no weight load on

raceway terminals.

D. Vertical Conductor Supports: Install simultaneously with installation of conductors.

Page 51: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Supporting Devices Section 260529 9

E. Miscellaneous Supports: Support miscellaneous electrical components as required to produce the

same structural safety factors as specified for raceway supports. Install metal channel racks for

mounting cabinets, panelboards, disconnects, control enclosures, pull boxes, junction boxes,

transformers, and other devices.

F. In open overhead spaces, cast boxes threaded to raceways need not be supported separately

except where used for fixture support; support sheet metal boxes directly from the building

structure or by bar hangers. Where bar hangers are used, attach the bar to raceways on opposite

sides of the box and support the raceway with an approved type of fastener not more than 24

inches from the box.

G. Sleeves: Install in concrete slabs and walls and all other fire- rated floors and walls for raceways

and cable installations. For sleeves through fire rated-wall or floor construction, apply UL- listed

firestopping sealant in gaps between sleeves and enclosed conduits and cables in accordance

with "Fire Resistant Joint Sealers" requirement of Division 07 Section "Joint Sealers."

H. Conduit Seals: Install seals for conduit penetrations of slabs on grade and exterior walls below

grade and where indicated. Tighten sleeve seal screws until sealing grommets have expanded to

form watertight seal.

I. Fastening: Unless otherwise indicated, fasten electrical items and their supporting hardware

securely to the building structure, including but not limited to conduits, raceways, cables, cable

trays, busways, cabinets, panelboards, transformers, boxes, disconnect switches, and control

components in accordance with the following:

1. Fasten by means of wood screws or screw-type nails on wood, toggle bolts on hollow

masonry units, concrete inserts or expansion bolts on concrete or solid masonry, and

machine screws, welded threaded studs, or spring-tension clamps on steel. Threaded studs

driven by a powder charge and provided with lock washers and nuts may be used instead

of expansion bolts and machine or wood screws. Do not weld conduit, pipe straps, or

items other than threaded studs to steel structures. In partitions of light steel construction,

use sheet metal screws.

2. Holes cut to depth of more than 1-1/2 inches in reinforced concrete beams or to depth of

more than 3/4 inch in concrete shall not cut the main reinforcing bars. Fill holes that are

not used.

3. Ensure that the load applied to any fastener does not exceed 25 percent of the proof test

load. Use vibration- and shock- resistant fasteners for attachments to concrete slabs.

Page 52: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Supporting Devices Section 260529 10

3.2 TABLE I: SPACING FOR RACEWAY SUPPORTS

HORIZONTAL RUNS

Raceway Size

(Inches)

No. of

Conductors in

Run

Location RMC &

IMC (1)

EMT (1) RNC (1)

1/2,3/4 1 or 2 Flat ceiling or wall. Where

it is difficult to provide

supports except at intervals

fixed by the building

construction.

5 5 3

1/2,3/4 1 or 2 7 7 ---

1/2,3/4 3 or more Any location 7 7 ---

½-1 3 or more Any location 6 6 ---

1 & larger 1 or 2 Flat ceiling or wall. Where

it is difficult to provide

supports except at intervals

fixed by the building

construction

10 10 ---

1 & larger 1 or 2 10 10 ---

VERTICAL RUNS

Raceway Size

(Inches)

No. of

Conductors in

Run

Location RMC &

IMC (1,3)

EMT

(1)

RNS (1)

1/2,3/4 Exposed 7 7

1,1-1/4 Exposed 8 8

1-1/2 and larger Exposed 10 10

Up to 2 Shaftway 14 10

2-1/2 Shaftway 16 10

3 & larger Shaftway 20 10

Any Concealed 10 10

NOTES:

(1) Maximum spacing of supports (feet).

(2) Maximum spacings for IMC above apply to straight runs only. Otherwise the maximums for

EMT apply.

Abbreviations:

EMT Electrical metallic tubing.

IMC Intermediate metallic conduit.

RMC Rigid metallic conduit.

RNC Rigid nonmetallic conduit.

END OF SECTION 260529

Page 53: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Electrical Identification Section 260553 1

SECTION 260553 - ELECTRICAL IDENTIFICATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of Contract, including General and Supplementary Conditions

and Division 01 Specification Sections, apply to this Section.

B. Related Sections: The following Sections contain requirements that relate to this Section:

1. Division 09 Section “Painting and Coatings" for related identification requirements.

2. Division 26 Section “Basic Electrical Requirements.”

C. Refer to other Division 26 sections for additional specific electrical identification associated with

specific items.

1.2 SUMMARY

A. This Section includes identification of electrical materials, equipment, and installations. It

includes requirements for electrical identification components including but not limited to the

following:

1. Equipment labels and signs

2. Device labels

3. Identification labeling for raceways, cables, and conductors

4. Operational instruction signs

5. Warning and caution signs

6. Buried electrical line warnings

1.3 SUBMITTALS

A. None required.

1.4 QUALITY ASSURANCE

A. Electrical Component Standard: Components and installation shall comply with NFPA 70

"National Electrical Code."

B. ANSI Compliance: Comply with requirements of ANSI Standard A13.1, "Scheme for the

Identification of Piping Systems," with regard to type and size of lettering for raceway and cable

labels.

Page 54: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Electrical Identification Section 260553 2

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by the following:

1. Almetek

2. American Labelmark Co.

3. Brother’s Labels

4. Calpico, Inc.

5. Cole-Flex Corp.

6. Emed Co., Inc.

7. George-Ingraham Corp.

8. Ideal Industries, Inc.

9. Kraftbilt

10. LEM Products, Inc.

11. Markal Corp.

12. National Band and Tag Co.

13. Panduit Corp.

14. Radar Engineers Div., EPIC Corp.

15. Seton Name Plate Co.

16. Standard Signs, Inc.

17. W.H.Brady, Co.

2.2 CONDUCTOR AND CABLE IDENTIFICATION

A. Conductor Designation Tape Markers: Vinyl or vinyl-cloth, self- adhesive, wraparound,

conductor markers with preprinted numbers and letters. Handwritten graphics are prohibited.

B. Cable Ties: Fungus-inert, self-extinguishing, one-piece, self- locking nylon cable ties, 0.18-inch

minimum width, 50-lb minimum tensile strength, and suitable for a temperature range from

minus 50 deg F to 350 deg F. Provide ties in specified colors when used for color coding. For

outdoor applications provide black UV resistant ties only; white ties are prohibited.

2.3 NAMEPLATES, LABELS, SIGNS, AND INSTRUCTION PLATES

A. Plasticized Card Stock Tags: Vinyl cloth with preprinted and field-printed legends to suit the

application. Orange background, except as otherwise indicated, with Eyelet for fastener.

B. Aluminum-Faced Card Stock Tags: Weather-resistant, 18-point minimum card stock faced on

both sides with embossable aluminum sheet, 0.002 inches thick, and laminated with

moisture-resistant acrylic adhesive. Pre-print legend to suit the application, and punch for tie

fastener.

C. Brass or Aluminum Tags: Metal tags with stamped legend, punched for fastener. Dimensions: 2

inches by 2 inches by 19 gauge.

Page 55: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Electrical Identification Section 260553 3

D. Engraved, Plastic-Laminated Labels, Signs, and Instruction Plates: Engraving stock melamine

plastic laminate, 1/16-inch minimum thick for signs up to 20 square inches, or 8 inches in length;

1/8-inch thick for larger sizes. All exterior plates shall be punched for mechanical fasteners (pop

rivets). Refer to details on drawings. Use Rowmark "Matt" for indoor use and Rowmark "Ultra-

Matt" for exterior use. Nameplate lettering font shall be Helvetica, with bold or extra-bold

strokes where indicated.

E. Baked-Enamel Warning and Caution Signs for Interior Use: Preprinted aluminum signs, punched

for fasteners, with colors, legend, and size appropriate to the location.

F. Exterior Metal-Backed Butyrate Warning and Caution Signs: Weather-resistant, nonfading,

preprinted cellulose acetate butyrate signs with 20-gage, galvanized steel backing, with colors,

legend, and size appropriate to the location. Provide 1/4-inch grommets in corners for mounting.

G. Legend Plates: Die-stamped metal legend plate with mounting hole and positioning key for

panel mounted operator devices, i.e. motor control pilot devices, hand-off-auto switches, reset

buttons, etc. Stamped characters to be paint-filled.

H. Fasteners for Plastic-Laminated and Metal Signs:

1. Self-tapping stainless steel screws or number 10/32 stainless steel machine screws with

nuts and flat and lock washers.

2. Aluminum pop rivets.

2.4 PANELBOARD, DISTRIBUTION AND MCC IDENTIFICATION

A. Circuit Numbering: Provide factory-supplied permanent self-adhesive labels to identify each

pole of all panelboards.

B. Nameplates: Provide nameplates per above section: “Nameplates, Labels, Signs, and Instruction

Plates.”

C. Schedule Holder: Provide crystal clear, heavy duty, 5 1/8” x 81/2” vinyl, long side open.

Storesmart #STB897 peel and stick 8GA. Vinyl or approved equal

D. Update panel schedules on all existing panels where new work is performed. Update panel

nameplates if they do not comply with the details on the construction drawings.

2.5 DEVICE COVERPLATE LABELS AND PAINT

A. Coverplate material shall be as specified in Section 262726: Coverplates.

B. Embossed metallic or plastic tape (Dymo) is not acceptable for any application.

C. Methods of Inscription: (Unless otherwise noted)

1. Self-adhesive Tape: For Imprinted or thermal transfer characters onto permanent

waterproof tape lettering system. (Brother’s or Kroy). Apply Matte finish spray coating

(Krylon #1311) as required to make lettering waterproof.

Page 56: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Electrical Identification Section 260553 4

D. Paint covers per part 3 below.

PART 3 - EXECUTION

3.1 INSTALLATION - GENERAL

A. Lettering and Graphics: Coordinate names, abbreviations, colors, and other designations used in

electrical identification work with corresponding designations specified or indicated. Use

numbers, lettering, and colors as approved in submittals and as required by code.

B. Sequence of Work: Where identification is to be applied to surfaces that requires finish, install

identification after completion of finish work.

C. Installation:

1. Install identification devices in accordance with manufacturer's written instructions and

requirements of NEC.

2. Clean surface of dust, loose material, and oily films before applying identification.

3. Install identification parallel to equipment lines.

4. Apply using permanent methods and materials (such as tape and nameplate materials) that

is suitable for the environment installed and will not degenerate over time due to UV,

sunlight, humidity, temperature swings, etc.

5. Install labels at locations indicated and at locations for best convenience of viewing

without interference with operation and maintenance of equipment. Do not cover up other

instructions or labels.

3.2 CONDUCTOR AND CABLE IDENTIFICATION

A. Conductor Color Coding: Provide color coding for the following:

1. Secondary service, feeder, and branch circuit conductors throughout the project electrical

system:

208 and 120 Volts Phase 480 and 277 Volts

Black A Brown

Red B Orange

Blue C Yellow

White Neutral White with strip (preferred) or Grey (if allowed

by local inspector)

Green Ground Green

Orange Switch leg Pink

Yellow Traveler Purple

2. Control wiring inside custom electrical equipment and control panels throughout the

project electrical system, refer to mechanical specifications.

3. Use conductors with color factory-applied the entire length of the conductors except as

follows:

Page 57: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Electrical Identification Section 260553 5

a. The following field-applied color-coding methods may be used in lieu of factory-

colored conductor for sizes larger than No. 10 AWG.

b. Apply colored, pressure-sensitive plastic tape in half-lapped turns for a distance of 6

inches from terminal points and in boxes where splices or taps are made. Apply the

last two laps of tape with no tension to prevent possible unwinding. Use

1-inch-wide tape in colors as specified. Do not obliterate cable identification

markings by taping. Tape locations may be adjusted slightly to prevent such

obliteration.

c. In lieu of pressure-sensitive tape, colored cable ties may be used for color

identification. Apply three ties of specified color to each conductor or cable at each

terminal or splice point starting 3 inches from the terminal and spaced 3 inches

apart. Apply with a special tool or pliers, tighten for snug fit, and cut off excess

length.

B. Future Connections: Tag or label conductors indicated to be for future connection or connection

under another contract with identification indicating source and circuit numbers.

C. Multiple Conductors/Circuits: Where multiple branch circuits or control wiring or

communications/signal conductors are present in the same box or enclosure (except for color-

coded, three-circuit, four-wire home runs) and wherever there is possible confusion in identifying

each conductor, label each conductor or cable. Provide label indicating source, voltage, circuit

number, and phase for branch circuit wiring. Phase and voltage of branch circuit wiring may be

indicated by means of color-coded conductor insulation. For control and communications/signal

wiring, use color coding or conductor/cable marking tape at terminations and at intermediate

locations where conductors appear in wiring boxes, troughs, and control cabinets. Use consistent

letter/number conductor designations throughout on conductor/cable marking tapes. Conductor

numbers shall match the manufacturer's shop drawings.

D. Numbering system for all equipment and devices to be coordinate with existing system and the

physical plant manager.

E. Cable and Feeder Identification Tags: Securely fasten identifying tags around cables, feeders,

and power circuits in vaults, pull boxes, junction boxes, manholes, and switchboard rooms with

stamped letters and numbers with legend to correspond with designations on Drawings. If metal

tags are provided, attach them with approximately 55-lb test monofilament line or one-piece

self-locking nylon cable ties.

3.3 NAMEPLATES, LABELS, SIGNS, AND INSTRUCTION PLATES

A. Apply warning, caution, and instruction signs and stencils as follows:

1. Install warning, caution, or instruction signs where required by NEC, where indicated, or

where reasonably required to assure safe operation and maintenance of electrical systems

and of the items to which they connect. Install engraved plastic-laminated instruction

signs with approved legend where instructions or explanations are needed for system or

equipment operation. Install butyrate signs with metal backing for outdoor items.

2. Emergency Operating Signs: Install engraved, laminated signs with white text on red

background with minimum 3/8-inch high lettering for emergency instructions on power

transfer, load shedding, or other emergency operations.

Page 58: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Electrical Identification Section 260553 6

B. Install equipment/system circuit/device identification as follows:

1. Apply equipment identification labels of engraved plastic-laminate on each major unit of

electrical equipment in building, including central or master unit of each electrical system.

This includes communication/ signal/alarm systems, unless the factory supplied labeling

on the unit is acceptable to the Engineer.

2. Refer to drawings for details of signs, if details are not included provide the following

minimum information:

a. Equipment or device designation. (Minimum 3/8" high)

b. Amperage, KVA or horsepower rating, where applicable.

c. Voltage or signal system name.

3. Text shall match terminology and numbering of the Contract Documents and shop

drawings. Apply labels for each unit of the following categories of electrical equipment.

a. Panelboards, electrical cabinets, disconnects, and enclosures.

b. Access doors and panels for concealed electrical items

c. All junction boxes and enclosures larger than 4" square

d. Each circuit breaker or fused switch in distribution boards, switchboards and

switchgear.

e. Electrical switchgear and switchboards

f. Bus duct (10’ intervals)

g. Electrical substations

h. Motor control centers.

i. Motor starters

j. Pushbutton stations

k. Power transfer equipment

l. Contactors

m. Dimmers

n. Control devices

o. Transformers

p. Battery racks

q. Power generating units

r. Telephone switching equipment

s. Clock/program master equipment.

t. Call system master station.

u. Fire alarm master station or control panel.

v. Security monitoring master station or control panel

w. Spare conduits at both ends.

4. Engraved legend using the following color combinations: (Provide alternate color

combinations as shown or noted)

Text Color Background

Color

System Description

White Red Danger and warning signs and devices

such as emergency power off (EPO)

switches.

Black Yellow Instructional and Operational signs.

Page 59: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Electrical Identification Section 260553 7

Text Color Background

Color

System Description

White Black Device Nameplates for controls,

pushbuttons, meters, indicating lights, etc.

White Blue Standby Power systems

White Red Emergency power systems

Black White Normal power systems

Red White Fire alarm device and enclosure

nameplates

C. Apply circuit/control/item designation labels of engraved plastic laminate for disconnect

switches, circuit breakers in distribution, switchboard and switchgear, lights, motor control

centers, and similar items for power distribution, except panelboards and alarm/signal

components, where labeling is specified elsewhere.

D. Provide legends on panel mounted operators devices such as pilot lights, reset buttons,

hand-off-auto switches, pushbuttons and other control components.

3.4 PANELBOARD, DISTRIBUTION AND MCC IDENTIFICATION

A. Circuit Numbering: Starting at the top, odd numbered circuits in sequence down the left hand

side and even numbered circuits down the right hand side.

B. Panelboard Nameplates: Mount nameplates with permanent non-carrier based double-stick tape

in interior locations and pop rivets in exterior locations. In finished public areas, such as in lobby

or corridor walls, mount the nameplate to the top of the inside of the inner door then also provide

an additional 0.75" high, single-line, white nameplate with black 1/4" high panelboard name.

All nameplates that are to be mounted on the outside shall be centered, ½" up from the top on the

inner door on the outside of the outer door.

C. Panelboard Schedule Holder: Mount schedule holder, secured to inside face of inner panel door.

Contractor shall install construction panel schedules in holders during construction and replace

with “as of record” panel schedules in holder at end of project. Final schedules shall include

room numbers and explicit description and identification of items controlled by each individual

breaker.

3.5 DEVICE COVERPLATE LABELS

A. Provide self-adhesive type labels for all receptacles, switches, outlets, plugmold, etc. per the

following:

1. Lettering Type: Helvetica, 12 point or 1/8" high.

2. Text: Label coverplates with identity of source and circuit number serving the device per

the following convention: “Panel Name”- “Circuit Numbers” (except UPS circuits, which

have word UPS as part of the label). Example: “MTE0032-1", “UPS MTE0033-3”.

Page 60: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

Electrical Identification Section 260553 8

3. Color of Characters shall be as follows:

Text Color Background Color System Description

Black White All blue, black, brown power device

coverplates

Black Clear All white, ivory, gray, red, stainless steel

power device coverplates

4. Installation of self-adhesive tape:

a. Imprinted tape shall be coated with a permanent, non-gloss protective finish. Spray

coating shall be applied prior to installation or simultaneously as with Brother’s

unit.

b. Tape shall be applied to coverplate there is no need to wrap label and label should

be at bottom of plate. Top of plate for special equipment designations.

c. Inscription shall be centered and square with coverplate.

B. Provide engraved coverplates for switches, dimmers, etc. as follows: (in addition to panel-circuit

number labels)

1. All multi-ganged (three or more) switches or dimmers.

2. All special purpose switches or controls, i.e. - fan, projector screen, etc. where it is not

obvious what it controls.

3. Engraving shall indicate fixtures or devices controlled (i.e. "Down Lights", "Cove Lights",

etc.)

C. Identify Junction, Pull, and Connection Boxes:

1. Identify Junction, Pull, and Connection Boxes above accessible ceilings, exposed in

mechanical and electrical rooms and other non-finished areas such as tunnels, loading

docks, etc. by neatly spray painting the box and cover plate. Conform to site’s standard

colors for each system type. The boxes and covers shall be painted prior to installation. It

is unacceptable to paint the boxes after installation where the overspray paints the conduits

and other surrounding items. It is the electrician's responsibility to ensure that the boxes

are not painted over by the architectural painting contractor. Refer to detail drawings for

color code of conduits and J-boxes.

END OF SECTION 260553

Page 61: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 1

SECTION 16940 - ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING

PART 1 GENERAL

1.1 SECTION INCLUDES

A. Provide all engineering, labor, materials, apparatus, tools, equipment, transportation,

temporary construction and special or occasional services as required to perform the following

items specified, including but not limited to:

1. Verify Operation of all Low Voltage Circuit Breaker Functions and Accessories with

primary injection test equipment.

2. Inspect and Test Building Electrical Grounding System.

3. Inspect and Test Metering and Instrumentation.

4. Inspect and Test Medium Voltage Cables.

5. Inspect and Test Protective Relays.

6. Inspect and Test Instrument Transformers.

7. Inspect and Test Liquid Filled Transformers.

8. Inspect and Test Automatic Transfer Switches.

9. Testing Procedures and Testing Schedules.

1.2 RELATED SECTIONS AND INFORMATION

A. Consult all related sections of the Division 26 specifications and drawings to determine the

extent and character of the installed work and to properly coordinate the testing work specified

herein with that specified elsewhere.

B. All inspections and tests shall utilize the following references:

1. Project Design Specifications

2. Project Design Drawings

3. Manufacturer's instruction manuals applicable to each particular apparatus

1.3 GENERAL SCOPE OF WORK

A. The Electrical Contractor Owner shall engage and pay for the services of a recognized

independent testing firm for the purpose of performing inspections and tests as herein

specified.

B. The testing firm shall provide all material, equipment, labor, and technical supervision to

perform such tests and inspections.

1.4 FIELD TESTING AND OPERATIONAL CHECK

A. General Scope:

1. Perform field testing and operational checks to assure that all electrical equipment, both

contractor and Owner supplied, is operational within industry and manufacturer's

tolerances and is installed in accordance with Contract Documents.

2. The tests and operational check shall determine the suitability for energization.

3. Schedule tests and give a minimum of 30 working days advance notice to the

Architect/Owner.

Page 62: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 2

4. Reports: Prepare written reports of test results and observations. Report defective

materials and workmanship. Include complete records of repairs and adjustments.

5. Labeling: Upon satisfactory completion of tests and related effort, apply a label to tested

components indicating test results, date, and responsible person and organization.

1.5 QUALITY ASSURANCE

A. Reference to codes, standards, specifications and recommendations of technical societies, trade

organizations and governmental agencies shall mean that latest edition of such publications

adopted and published prior to submittal of the bid. Such codes or standards shall be

considered a part of this Specification as though fully repeated herein.

B. Work shall be performed in accordance with all applicable requirements of the latest edition of

all governing codes, rules and regulations including but not limited to the following minimum

standards, whether statutory or not:

1. National Electrical Code - NEC

2. National Electrical Manufacturer's Association - NEMA

3. American Society for Testing and Materials - ASTM

4. Institute of Electrical and Electronic Engineers - IEEE

5. International Electrical Testing Association - NETA

6. American National Standards Institute - ANSI

a. ANSI C2: National Electrical Safety Code

b. ANSI Z244-1: American National Standard for Personnel Protection

7. State and Local Codes and Ordinances

8. Insulated Cable Engineers Association - ICEA

9. Association of Edison Illuminating Companies - AEIC

10. Occupational Safety and Health Administration

a. OSHA Part 1910: Subpart S, 1910.308

b. OSHA Part 1926: Subpart V, 1926.950 through 1926.960

11. National Fire Protection Association - NFPA

a. ANSI/NFPA 70B: Electrical Equipment Maintenance

b. NFPA 70E: Electrical Safety Requirements for Employee Workplaces

c. ANSI/NFPA 70: National Electrical Code

d. ANSI/NFPA 78: Lightning Protection Code

e. ANSI/NFPA 101: Life Safety Code

1.6 QUALIFICATIONS OF TESTING AGENCY

A. The testing firm shall be a corporately independent testing organization which can function as

an unbiased testing authority, professionally independent of the manufacturers, suppliers, and

installers of equipment or systems evaluated by the testing firm.

B. The testing firm shall be regularly engaged in the testing of electrical equipment devices,

installations, and systems.

C. The testing firm shall have been engaged in such practices for a minimum of five years.

D. The testing firm shall meet federal OSHA criteria for accreditation of testing laboratories, Title

29, Parts 1907, 1910, and 1936. Full membership in the International Electrical Testing

Association (NETA) constitutes proof of such criteria.

Page 63: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 3

E. The lead, on site, technical person shall be currently certified by the International Electrical

Testing Association (NETA) in Electrical Power Distribution System Testing.

F. Testing firm shall utilize only full-time technicians who are regularly employed by the firm for

testing services. Electrically unskilled employees are not permitted to perform testing or

assistance of any kind. Electricians and/or linemen may assist, but may not perform testing

and/or inspection services.

G. The testing firm shall submit proof of the above qualifications with bid documents when

requested.

H. All instruments used by the testing firm to evaluate electrical performance shall meet NETA's

Specifications for Test Instruments. (See Section 3 of this specification.)

I. The terms used here within such as Test Agency, Test Contractor, Testing Laboratory, or

Contractor Test Company, shall be construed to mean testing firm.

J. Each on-site crew leader shall hold a current registered certification in electrical testing

applicable to each type of apparatus to be inspected or tested. The certification in electrical

testing shall be issued by an independent, nationally-recognized, technician certification

agency. The following entities shall qualify as independent, nationally-recognized, technician

certification agencies:

1. InterNational Electrical Testing Association (NETA) Accepted certifications:

a. Certified Technician/Level III

b. Certified Senior Technician/Level IV

2. National Institute of Certification in Engineering Technologies (NICET) Accepted

certifications specifically in Electrical Testing Engineering Technology:

a. Engineering Technician/Level III

b. Senior Engineering Technician/Level IV

1.7 DIVISION OF RESPONSIBILITY

A. The following items of work will have been provided under by the Division 16 contractor for

all distribution and utilization equipment prior to and in addition to tests performed by the

testing firm specified herein.

1. Insulation Resistance: 1000-volt DC tests for one minute on all 600 volt and lower rated

equipment, feeder and branch circuit conductors, including the neutral. Review the

electrical contractor's typed record of all readings that are to be included in the

maintenance instructions. Circuits showing less than 10 megohms resistance to ground

were repaired or replaced.

2. Circuit Continuity: All feeders and branch circuits were tested for continuity. All neutrals

were tested for improper grounds.

3. Equipment Operation: Motors were tested for correct operation and rotation.

B. The electrical contractor shall supply a suitable and stable source of electrical power to each

test site. The testing firm shall specify the specific power requirements.

C. The electrical contractor shall notify the testing firm when equipment becomes available for

acceptance tests. Work shall be coordinated to expedite project scheduling.

Page 64: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 4

D. The project architect shall supply a complete set of electrical plans, specifications and any

pertinent change orders to the testing firm prior to commencement of testing.

E. The testing firm shall notify the PSU engineer prior to commencement of any testing.

F. Any system, material or workmanship which is found defective on the basis of acceptance

tests shall be reported.

G. The testing firm shall maintain a written record of all tests and upon completion of project,

assemble and certify a final test report. Refer to section 3 for further information on test

reports.

1.8 SAFETY AND PRECAUTIONS

A. This document does not include any procedures, including specific safety procedures. It is

recognized that an overwhelming majority of the tests and inspections recommended in these

specifications are potentially hazardous. Inherent in this determination is the prerequisite that

individuals performing these tests be capable of conducting the tests in a safe manner and with

complete knowledge of the hazards involved.

B. Safety practices shall include, but are not limited to, the following requirements:

1. Occupational Safety and Health Act.

2. Accident Prevention Manual for Industrial Operations, National Safety Council.

3. Applicable State and Local safety operating procedures.

4. NETA Safety/Accident Prevention Program.

5. Owner's safety practices.

6. ANSI/NFPA 70E, Electrical Safety Requirements for Employee Workplaces.

7. ANSI Z244.1 American National Standards for Personnel Protection.

C. All tests shall be performed with apparatus de-energized except where otherwise specifically

required.

D. The testing firm shall have a designated safety representative on the project to supervise

operations with respect to safety.

1.9 JOB CONDITIONS

A. Examination of Site: The Contractor shall visit the site and thoroughly review the locale,

working conditions, conflicting utilities and the conditions in which the electrical testing work

will take place. Verify all existing conditions in the field. No allowances will be made

subsequently for any costs which may be incurred because of any error or omission due to

failure to examine the site.

B. Supervision: Contractor shall personally or through an authorized and competent

representative constantly supervise the work from beginning to completion and, within reason,

keep the same foreman and workmen on the project throughout the project duration.

1.10 LOW VOLTAGE INSULATED CASE CIRCUIT BREAKER TESTING

A. General: Perform and document the following tests, as applicable, on the following circuit

breakers (C.B.):

Page 65: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 5

1. All drawout C.B.'s including the spare C.B.'s.

2. All 100 amp frame and larger C.B.'s, including the spare C.B.'s.

3. 100% of all the C.B.'s that serve mechanical equipment.

B. Visual and Mechanical Inspection:

1. Circuit breaker shall be checked for proper mounting.

2. Operate circuit breaker to ensure smooth operation.

3. Inspect case for cracks or other defects.

4. Check tightness of connections with calibrated torque wrench. Refer to manufacturer's

instruction or NETA Table 11.1 for proper torque levels.

5. Check internals on unsealed units.

6. Check for proper conductor and conduit size per the feeder schedule in the construction

documents and proper nameplates and feeder designations.

C. Electrical Tests:

1. Perform a contact resistance test or measure millivolt drop at rated current.

2. Perform an insulation resistance test at 1000 volts dc for one (1) minute from pole-to-pole

and from each pole-to-ground with breaker closed and across open contacts of each phase.

3. Adjustable trip breakers shall have minimum pickup current determined by primary

current injection where applicable.

4. Perform long time delay time-current characteristic tests by passing three hundred percent

(300%) rated current through each pole separately. Determine trip time.

5. Determine short time pickup and delay by primary current injection if applicable to the

particular breaker.

6. Determine ground fault pickup and time delay by primary current injection if applicable to

the particular breaker.

7. Determine instantaneous pickup current by primary injection using run-up or pulse

method. Clearing times shall be within four (4) cycles.

8. Verify trip unit reset characteristics.

9. Perform adjustments for final settings in accordance based on the data generated from the

short circuit/coordination studies if applicable to the particular breaker.

10. Verify correct operation of all accessories; shunt trips, electric operators, status indicating

lights, etc.

D. Test Values:

1. Compare contact resistance or millivolt drop values to adjacent poles and similar breakers.

Investigate deviations of more than fifty percent (50%). Investigate any value exceeding

manufacturer's recommendations.

2. Insulation resistance shall not be less than 100 megohms.

3. Trip characteristic of adjustable trip breakers shall fall within manufacturer's published

time-current characteristic tolerance band.

4. All trip times shall fall within NETA Table 8.6.1.1. Circuit breakers exceeding maximum

three hundred percent (300%) time shall be replaced. (Reference Table 201 NEMA Std.

AB-2.)

5. Instantaneous pickup values shall be within values shown on Table 8.6.1.2. (Reference

Table 2-1 NEMA Std. AB-2.)

1.11 MOLDED CASE CIRCUIT BREAKER TESTING

Page 66: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 6

A. General: Perform and document the following tests, as applicable, on the following circuit

breakers (C.B.):

1. All C.B.'s including the spare C.B.'s.

2. All 100 amp frame and larger C.B.'s, including the spare C.B.'s.

3. 100% of all the C.B.'s that serve mechanical equipment.

B. Visual and mechanical inspection: Include the following inspections and related work.

1. Overcurrent-Protective-Device Ratings and Settings: Verify indicated ratings and settings

to be appropriate for final system arrangement and parameters. Where discrepancies are

found, test organization shall recommend final protective device ratings and settings. Use

accepted revised ratings or settings to make the final system adjustments.

2. Inspect for defects and physical damage, NRTL labeling, and nameplate compliance with

current single line diagram.

3. Exercise and perform operational tests of all mechanical components and other operable

devices in accordance with manufacturer's instruction manual.

4. Check tightness of electrical connections of OCPDs with calibrated torque wrench. Refer

to manufacturer's instructions for proper torque values.

5. Clean OCPDs using manufacturer's approved methods and materials.

6. Verify installation of proper fuse types and ratings in fusible OCPDs.

C. Electrical Tests: Include the following items performed in accordance with manufacturer's

instructions:

1. Insulation resistance test of OCPD conducting parts. Insulation resistance less than 100

megohms is not acceptable.

2. Contact resistance test or measurement of millivolt drop across contacts of drawout circuit

breakers and fused power circuit devices at rated current. Compare contact resistance or

millivolt drop values of adjacent poles and of similar breakers. Deviations of more than

50 percent are not acceptable.

3. Insulation resistance test of fused power circuit devices and insulated-case and

molded-case circuit breakers over 600-ampere frame size at 1000 V d.c. for one minute

from pole to pole and from each pole to ground with breaker closed and across open

contacts of each phase. Insulation resistance less than 100 megohms is not acceptable.

4. Use primary current injection to check performance characteristics of trip units of

insulated-case circuit breakers and molded-case breakers over 600-ampere frame size.

Trip characteristics not falling within manufacturer's published time-current characteristic

tolerance bands when adjusted to approved parameters are not acceptable. Perform the

following tests:

a. Determine minimum pickup current acceptable per manufacturer's instructions.

b. Determine long-time delay at 300 percent pickup current.

c. Determine short-time-pickup current and corresponding delay time.

d. Determine ground-fault current pickup and corresponding delay time.

e. Determine instantaneous pickup current value.

5. Verify trip unit reset characteristics for insulated-case circuit breakers.

6. Make adjustments for final settings of adjustable-trip devices.

7. Activate auxiliary protective devices such as ground fault or undervoltage relays, to verify

operation of shunt-trip devices.

8. Check key and other interlock and safety devices for operation and sequence. Make

closing attempts on locked-open and opening attempts on locked-closed devices including

moveable barriers and shutters.

Page 67: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 7

1.12 DRY TYPE TRANSFORMER TESTING

A. General: Perform and document the following tests:

B. Visual and Mechanical Inspection:

1. Inspect for physical damage, proper anchorage and grounding, and proper installation in

compliance with the manufacturer's instructions.

2. Thoroughly clean unit prior to making any tests. Check for cleanliness of interior and

insulator surfaces.

3. Inspect for code violations.

4. Inspect for proper identification of protective devices and switches.

5. Check tightness of bolted terminations, with calibrated torque wrench, in accordance with

manufacturer's recommended torque levels or NETA Table 11.1.

C. Electrical Tests:

1. Perform insulation resistance test. Calculate dielectric absorption ratio. Measurements

shall be made from winding-to-winding and winding-to-ground. Test voltages and

minimum resistances shall be made in accordance with NETA Table 8.2.3. Results to be

temperature corrected in accordance with NETA Table 8.2.4.

2. Verify taps if applicable and connect transformer to desired tap.

1.13 ELECTRICAL GROUNDING SYSTEM TESTING

A. General: Perform and document the following tests, as applicable, on all distribution and

grounding equipment:

B. Visual and Mechanical Inspection:

1. Inspect ground system for compliance with plans and specifications.

C. Electrical Tests:

1. Perform three (3) point fall-of-potential test per IEEE Standard No. 81, Section 9.04 on

the main grounding electrode or system.

2. Perform the two (2) point method test per IEEE No. 81, Section 9.03 to determine the

ground resistance between the main grounding system and all major electrical equipment

frames, system neutral and/or derived neutral points.

D. Test Values:

1. The main ground electrode system resistance to ground should be no greater than five (5)

ohms for commercial or industrial systems and one (1) ohm or less for generating or

transmission station grounds unless otherwise specified by the project electrical engineer.

1.14 INSTRUMENT TRANSFORMERS

A. General: Perform and document the following tests on all instrument transformers (PT's and

CT's):

B. Visual and Mechanical Inspection:

1. Inspect for physical damage, cracked insulation, broken leads, tightness of connections,

defective wiring, overall general condition and nameplate information for compliance with

instructions and specification requirements.

2. Verify phase rotation and phasing.

Page 68: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 8

3. Verify proper connection of transformers with system requirements.

4. Verify proper primary and secondary fuse sizes as indicated on potential transformers.

5. Verify proper interlock function, and contact operation.

6. Verify tightness of all bolted connections and assure adequate clearances exist between

primary circuits to secondary circuit wiring.

7. Verify that all required grounding and shorting connections provide good contact.

8. Test proper operation of transformer withdrawal mechanism (tip out) and grounding

operation when applicable.

C. Electrical Tests - Current Transformers:

1. Perform insulation resistance test of the current transformer and current transformer wiring

to ground at 500 volts dc for 30 seconds. Disconnect ground connection at ground

connection point in the circuit for this test. Do not perform this test on solid state devices.

2. Perform a polarity test of each current transformer.

3. Perform a ratio verification test of each current transformer. This shall be performed using

the voltage method or current method in accordance with ANSI C57.13.1.

4. Perform an excitation test on transformers used for relaying applications in accordance

with ANSI C57.13.1.

5. Measure relaying circuit burdens at current transformer terminals and determine the total

burden in ohms at 60 hertz.

6. Perform a dc dielectric withstandability test on the primary windings with the secondary

windings connected to ground. The dc dielectric voltage should be in accordance with

NETA Table 8.10.1.

D. Electrical Tests - Potential Transformers:

1. Perform insulation resistance tests on voltage transformers, winding-to-winding and

windings-to-ground. Test voltages and minimum resistances shall be in accordance with

NETA Table 8.2.1. Results to be temperature corrected in accordance with NETA Table

8.2.2. Do not perform this test on solid state devices.

2. Perform a polarity test on each transformer to verify the polarity marks or H1-X1

relationship as applicable. The test may be performed with a TTR type ratio set or by the

inductive kick method in accordance with ANSI C-57.13.

3. Perform a ratio test using a transformer-turns-ratio test set or by the voltage comparison

method.

4. Perform a dc dielectric withstandability test on the primary windings with the secondary

windings connected to ground. The dc dielectric voltage shall be in accordance with

NETA Table 8.10.1.

5. Verify secondary voltage by energizing primary winding with system voltage. Measure

secondary voltage with the secondary wiring disconnected.

6. Perform secondary wiring integrity test. Disconnect transformer at secondary terminals

and connect secondary wiring to proper secondary voltage. Check for proper potential at

all devices.

E. Test Values:

1. Insulation resistance measurement on any instrument transformer comparison or wiring

shall be not less than that shown in NETA Table 8.1.1.

2. Excitation current on current transformers shall not deviate from the manufacturer's

published excitation value or from each adjacent current transformer by more than fifty

percent (50%).

Page 69: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 9

3. Perform a burden/saturation calculation on current transformers supplying relaying

circuits.

1.15 METERING AND INSTRUMENTATION TESTING

A. General: Perform and document the following tests on all meters and other control or

annunciation devices:

B. Visual and Mechanical Inspection:

1. Examine all devices for broken parts, indication of shipping damage and wire connection

tightness.

2. Verify that meter connections are in accordance with appropriate wiring diagrams.

C. Electrical Tests:

1. Check calibration of meters at all cardinal points.

2. Verify all instrument multipliers.

1.16 AUTOMATIC TRANSFER SWITCHES (ATS)

A. General: Perform and document the following tests on all ATS's:

B. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Verify that manual transfer warnings are attached and visible.

5. Verify tightness of all control connections.

6. Inspect all bolted electrical connections for high resistance using one of the following

methods:

a. Use of low-resistance ohmmeter in accordance with Electrical Tests.

b. Verify tightness of accessible bolted electrical connections by calibrated torque-

wrench method in accordance with manufacturer’s published data or NETA Table

10.12.

c. Perform thermographic survey in accordance with NETA Section 9.

7. Perform manual transfer operation.

8. Verify positive mechanical interlocking between normal and alternate sources.

C. Electrical Tests

1. Perform a contact-resistance test.

2. Perform resistance measurements through all bolted connections with low-resistance

ohmmeter, if applicable, in accordance with Visual and Mechanical Inspection.

3. Perform insulation-resistance on each pole, phase-to-phase and phase-to-ground with

switch closed and across each open pole for one minute. Perform tests in both source

positions. Test voltage shall be in accordance with manufacturer’s published data or Table

NETA 10.1.

4. Calculate polarization index.

5. Verify settings and operation of control devices.

6. Calibrate and set all relays and timers in accordance with NETA Section 7.9.

7. Perform automatic transfer tests:

a. Simulate loss of normal power.

Page 70: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 10

b. Return to normal power.

c. Simulate loss of emergency power.

d. Simulate all forms of single-phase conditions.

8. Verify correct operation and timing of the following functions:

a. Normal source voltage-sensing relays.

b. Engine start sequence.

c. Time delay upon transfer.

d. Alternate source voltage-sensing relays.

e. Automatic transfer operation.

f. Interlocks and limit switch function.

g. Time delay and retransfer upon normal power restoration.

h. Engine cooldown and shutdown feature.

D. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by

manufacturer.

3. Minimum insulation-resistance shall be in accordance with manufacturer’s published data

or NETA Table 10.1.

4. Microhm or millivolt drop values shall not exceed the high levels of the normal range as

indicated in the manufacturer’s published data. If manufacturer’s data is not available,

investigate any values which deviate from similar connections by more than 50 percent of

the lowest value.

1.17 LIQUID FILLED TRANSFORMERS

A. General: Perform and document the following tests:

B. Visual and Manual Inspection:

1. Inspect for physical damage, cracked insulators, leaks, tightness of connections, and

general mechanical and electrical conditions.

2. Inspect impact recorder prior to unloading transformer if applicable.

3. Verify removal of any shipping bracing after final placement.

4. Compare equipment nameplate information with latest single line diagram.

5. Verify proper auxiliary device operation.

6. Check tightness of accessible bolted electrical connections in accordance with NETA

Table 11.1.

7. Verify proper liquid level in all tanks and bushings.

8. Perform specific inspections and mechanical tests as recommended by manufacturer.

9. Verify proper equipment grounding.

C. Electrical Tests:

1. Perform insulation resistance tests, winding-to-winding and windings-to-ground, utilizing

a megohmmeter with test voltage output as shown in NETA Table 8.2.1.

a. Test duration shall be for 10 minutes with resistances tabulated at 30 seconds, 1

minute, and 10 minutes. Calculate dielectric absorption ratio and polarization index.

2. Perform a turns ratio test between windings for all tap positions. The final tap setting is to

be determined by the project electrical engineer and set by the testing laboratory. Test

results shall be in accordance with paragraph D2 of this section.

Page 71: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 11

3. Insulating liquid shall be sampled in accordance with ASTM D-923. Sample shall be

laboratory tested for:

a. Dielectric breakdown voltage: ASTM D-877 or ASTM D-1816

b. Acid neutralization number: ASTM D-974

c. Specific gravity: ASTM D-1298

d. Interfacial tension: ASTM D-971 or ASTM D-2285

e. Color: ASTM D-1500

f. Visual Condition: ASTM D-1524

g. PPM water: ASTM D-1533. Required on 25 kV or higher voltages and on all

silicone filled units. Acceptable values shall be in accordance with paragraph D7 of

this Section.

h. Perform insulation power factor tests or dissipation factor tests on all windings and

bushings. Overall dielectric-loss and power factor (CH, CL, CHL) shall be determined.

Test voltages should be limited to the line to ground voltage rating of the transformer

winding.

i. Perform winding resistance tests on each winding at nominal tap position.

Acceptance values shall be in accordance with paragraph D6 of this Section.

j. Verify proper core grounding if accessible.

D. Test Values:

1. Insulation resistance and absorption test. Test voltages to be in accordance with NETA

Table 8.2.1. Resistance values to be temperature corrected in accordance with NETA

Table 8.2.4.

2. The dielectric absorption ratio and polarization index should be above 1.5 unless an

extremely high value is obtained initially, such that when doubled will not yield a

meaningful value.

3. Turns ratio test results shall not deviate more than one half percent (0.5%) from either the

adjacent coils or the calculated ratio.

4. Maximum power factor of liquid filled transformers corrected to 20oC shall be in

accordance with NETA Table 8.2.1.

5. Bushing power factors and capacitances should not vary from nameplate values by more

than ten percent (10%).

6. Excitation current test data pattern: Two similar current readings for outside coils and a

dissimilar current reading for the center coil of a three phase unit.

7. Dielectric fluid should comply with NETA Table 8.2.2.

1.18 DRY TYPE SERVICE TRANSFORMERS

A. General: Perform and document the following tests:

B. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical, electrical, and mechanical condition.

3. Verify that control and alarm settings on temperature indicators are as specified.

4. Verify that cooling fans operate and that fan motors have correct overcurrent protection.

5. Inspect all bolted electrical connections for high resistance using one of the following

methods:

a. Use of low-resistance ohmmeter in accordance with Section 7.2.1.2.2 (Electrical

Tests).

Page 72: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 12

b. Verify tightness of accessible bolted electrical connections by calibrated torque-

wrench method in accordance with manufacturer’s published data or Table 10.12.

c. Perform thermographic survey in accordance with Section 9.

6. Perform specific inspections and mechanical tests as recommended by manufacturer.

7. Verify that resilient mounts are free and that any shipping brackets have been removed.

8. Verify that the core, frame, and enclosure groundings are correct.

9. Verify the presence of transformer surge arresters.Verify that as-left tap connections are as

specified.

C. Electrical Tests

1. Perform insulation-resistance tests winding-to-winding and each winding-to-ground with

test voltage in accordance with Table 10.5.

2. Calculate polarization index.

3. Perform resistance measurements through all bolted connections with low-resistance

ohmmeter, if applicable, in accordance with Section 7.2.1.2.1 (Visual and Mechanical

inspection).

4. Perform power-factor or dissipation-factor tests in accordance with the test equipment

manufacturer’s published data.

5. Perform a turns-ratio test on all tap connections. Verify that winding polarities are in

accordance with nameplate.

6. **Perform an excitation-current test on each phase.

7. **Measure the resistance of each winding at each tap connection.

8. Measure core insulation resistance at 500 volts dc if core is insulated and if the core

ground strap is removable.

9. **Perform an overpotential test on all high- and low-voltage windings-to-ground.

10. Verify correct secondary voltage phase-to-phase and phase-to-neutral after energization

and prior to loading.

D. Test Values

1. Compare bolted connection resistances to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by

manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as

indicated in the manufacturer’s published data. If manufacturer’s data is not available,

investigate any values which deviate from similar connections by more than 50 percent of

the lowest value.

4. Insulation-resistance test values at one minute should not be less than the values calculated

in accordance with the formula in Table 10.5. Results shall be temperature corrected in

accordance with Table 10.14.

5. The polarization index shall be greater than 1.0 and shall be recorded for future reference.

6. Turns-ratio test results shall not deviate more than one-half percent from either the

adjacent coils or the calculated ratio.

7. CH and CL dissipation-factor/power-factor values will vary due to support insulators and

bus work utilized on dry transformers. The following is expected on CHL power factors:

a. Power Transformers: one percent or less

b. Distribution Transformers: three percent or less

c. Consult transformer manufacturer’s or test equipment manufacturer’s data for

additional information.

Page 73: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 13

8. Winding resistance test results, after factoring in temperature corrections, should compare

within one percent of factory obtained results except in instances of extremely low

resistance values.

9. Typical excitation current test data pattern for a three-legged core transformer is two

similar current readings and one lower current reading.

10. Core insulation resistance values should be comparable to factory obtained results but not

less than one megohm at 500 volts dc.

11. AC overpotential test shall not exceed 75 percent of factory test voltage for one minute

duration. DC overpotential test shall not exceed 100 percent of the factory RMS test

voltage for one minute duration. The insulation shall withstand the overpotential test

voltage applied.

1.19 MEDIUM VOLTAGE CABLES

A. General: Perform and document the following tests on all medium voltage cables:

B. Visual and Mechanical Inspection

1. Compare cable data with drawings and specifications.

2. Inspect exposed sections of cables for physical damage.

3. Inspect all bolted electrical connections for high resistance using one of the following

methods:

a. Use of low-resistance ohmmeter in accordance with Electrical Tests.

b. Verify tightness of accessible bolted electrical connections by calibrated torque-

wrench method in accordance with manufacturer’s published data or Table 10.12.

c. Perform thermographic survey in accordance with Section 9.

4. Inspect compression-applied connectors for correct cable match and indention.

5. Inspect for shield grounding, cable support, and termination.

6. Verify that visible cable bends meet or exceed ICEA and/or manufacturer’s minimum

allowable bending radius.

7. Inspect fireproofing in common cable areas, if specified.

8. If cables are terminated through window-type current transformers, make an inspection to

verify that neutral and ground conductors are correctly placed and that shields are

correctly terminated for operation of protective devices.

9. Visually inspect jacket and insulation condition.

10. Inspect for correct identification and arrangements.

C. Electrical Tests

1. Perform a shield-continuity test on each power cable by ohmmeter method.

2. Perform an insulation-resistance test utilizing a megohmmeter with a voltage output of at

least 2500 volts. Individually test each conductor with all other conductors and shields

grounded. Test duration shall be one minute.

3. Perform resistance measurements through all bolted connections with low-resistance

ohmmeter, if applicable, in accordance with Visual and Mechanical Inspection.

4. Perform a dc high-potential test on all cables. Adhere to all precautions and limits as

specified in the applicable NEMA/ICEA Standard for the specific cable. Perform tests in

accordance with ANSI/IEEE Standard 400. Test procedure shall be as follows, and the

results for each cable test shall be recorded as specified herein. Test voltages shall not

exceed 80 percent of cable manufacturer’s factory test value or the maximum test voltage

in NETA Table 10.6.

a. Insure that the input voltage to the test set is regulated.

Page 74: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 14

b. Current-sensing circuits in test equipment shall measure only the leakage current

associated with the cable under test and shall not include internal leakage of the test

equipment.

c. Record wet- and dry-bulb temperatures or relative humidity and temperature.

d. Test each section of cable individually.

e. Individually test each conductor with all other conductors grounded. Ground all

shields.

f. Terminations shall be adequately corona-suppressed by guard ring, field reduction

sphere, or other suitable methods as necessary.

g. Insure that the maximum test voltage does not exceed the limits for terminators

specified in ANSI/IEEE Standard 48, IEEE 386, or manufacturer’s specifications.

h. Apply a dc high-potential test in at least five equal increments until maximum test

voltage is reached. No increment shall exceed the voltage rating of the cable. Record

dc leakage current at each step after a constant stabilization time consistent with

system charging current.

i. Raise the conductor to the specified maximum test voltage and hold for 15 minutes on

shielded cable and five minutes on nonshielded cable. Record readings of leakage

current at 30 seconds and one minute and at one minute intervals thereafter.

j. Reduce the conductor test potential to zero and measure residual voltage at discrete

intervals.

k. Apply grounds for a time period adequate to drain all insulation stored charge.

l. When new cables are spliced into existing cables, the dc high-potential test shall be

performed on the new cable prior to splicing in accordance with Section 7.3.2. After

test results are approved for new cable and the splice is completed, an insulation-

resistance test and a shield-continuity test shall be performed on the length of new and

existing cable including the splice. After a satisfactory insulation-resistance test, a dc

high-potential test shall be performed on the cable utilizing a test voltage acceptable to

owner and not exceeding 60 percent of factory test value.

D. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with Table 10.12 unless otherwise specified by

manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as

indicated in the manufacturer’s published data. If manufacturer’s data is not available,

investigate any values which deviate from similar connections by more than 50 percent of

the lowest value.

4. Shielding shall exhibit continuity. Investigate resistance values in excess of ten ohms per

1000 feet of cable.

5. **Graphic plots may be made of leakage current versus step voltage at each increment and

leakage current versus time at final test voltages.

a. The step voltage slope should be reasonably linear.

b. Capacitive and absorption current should decrease continually until steady state

leakage is approached.

E. Product, Installation and Testing Failures:

1. If any primary cable fails, or tests, in the opinion of the testing agency, show unacceptable

cable defects, all cables in that conduit between the nearest pulling points on each side of

the failure shall be withdrawn. If, in the opinion of the testing agency, other cables that

Page 75: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 15

may have been installed in the same duct are not damaged, they may be reinstalled, but the

failed cable shall be replaced with new cable without additional cost by the Owner.

2. After replacement of the faulty cable, and any other damaged cables and cables of the

circuit in that conduit shall be retested. If the cable fails again, or if tests, in the opinion of

the testing agency, show unacceptable cable defects, all cables shall be replaced without

cost and this procedure shall be repeated until tests prove satisfactory.

3. Report all unacceptable cables to the Engineer.

1.20 METAL ENCLOSED - MEDIUM VOLTAGE AIR SWITCHES - MEDIUM VOLTAGE

SECTIONALIZING SWITCHES

A. General: Perform and document the following tests on all medium voltage equipment:

B. Visual and Mechanical Inspection:

1. Inspect for physical and mechanical condition.

2. Compare equipment nameplate information with latest single line diagram and report

discrepancies.

3. Check for proper anchorage and required area clearances.

4. Inspect all doors, panels, and sections for paint, dents, scratches, and fit.

5. Verify that fuse sizes and types correspond to drawings.

6. Perform mechanical operator tests in accordance with manufacturer's instructions.

7. Check blade pressure, alignment, and arc interrupter operation.

8. Check fuse link or element and holder for proper current rating.

9. Verify that condensers are in place on all holders having expulsion type elements.

10. Check each fuse holder for adequate mechanical support for each fuse.

11. Inspect all bus connections for tightness of bolted bus joints by calibrated torque wrench

method. Refer to manufacturer's instructions or NETA Table 11.1 for proper torque

levels.

12. Test all electrical and mechanical interlock systems for proper operation and sequencing.

a. Make closure attempt on locked open devices and opening attempt on locked closed

devices.

b. Make key exchange with devices operated in offnormal positions.

13. Clean entire switch using manufacturer's approved methods and materials.

14. Verify proper phase barrier materials and installation.

15. Lubricate as required.

a. Lightly apply contact lubricant on moving current carrying parts.

b. Apply appropriate lubrication on moving and sliding surfaces.

16. Check open and closed switch blade clearances with manufacturer's published data.

17. Exercise all active components.

18. Inspect all indicating devices for proper operation.

C. Electrical Tests:

1. Perform insulation resistance tests on each pole, phase-to-phase and phase-to-ground for

one (1) minute. Test voltage and minimum resistances should be in accordance with

NETA Table 11.2.

2. Perform a dc overpotential test on each pole with switch closed. Test each pole-to-ground

with all other poles grounded for five (5) minutes at values indicated in NETA Table 8.1.2

or manufacturer's recommended potential. Refer to Section 8.5.1.2.3.2 before performing

test.

3. Perform contact resistance test across each switch blade and fuse holder.

Page 76: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 16

D. Test Values:

1. Bolt torque levels shall be in accordance with NETA Table 11.1 unless otherwise

specified by manufacturer.

2. Perform insulation resistance test in accordance with NETA Table 8.1.1. Investigate

values of insulation resistance less than this table or manufacturer's minimum.

Overpotential tests should not proceed until insulation resistance levels are raised to said

minimum.

3. Determine contact resistance in micro-ohms. Investigate any value exceeding 100

microohms or any values which deviate from adjacent poles or similar switches by more

than fifty percent (50%).

1.21 MEDIUM VOLTAGE VACUUM CIRCUIT BREAKER AND VACUUM FAULT

INTERRUPTER SWITCHGEAR

A. General: Perform and document the following tests on all medium voltage breakers:

B. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Confirm correct application of manufacturer’s recommended lubricants.

4. Inspect anchorage, alignment, and grounding.

5. Perform all mechanical operational tests on both the circuit breaker and its operating

mechanism.

6. Measure critical distances such as contact gap as recommended by manufacturer.

7. Inspect all bolted electrical connections for high resistance using one of the following

methods:

a. Use of low-resistance ohmmeter in accordance with Section 7.6.2.3.2 (Electrical

Tests).

b. Verify tightness of accessible bolted electrical connections by calibrated torque-

wrench method in accordance with manufacturer’s published data or NETA Table

10.12.

c. Perform thermographic survey in accordance with NETA Section 9.

8. Perform timing tests.

9. Record as-found and as-left operation counter readings.

C. Electrical Tests

1. Perform a contact-resistance test.

2. **Perform minimum pickup voltage tests on trip and close coils.

3. Verify trip, close, trip-free, and antipump function.

4. Trip circuit breaker by operation of each protective device.

5. Perform resistance measurements through all bolted connections with low-resistance

ohmmeter, if applicable, in accordance with Section 7.6.2.3.1 (Visual and Mechanical

Inspection).

6. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles at

2500 volts minimum

7. Perform vacuum bottle integrity (overpotential) test across each vacuum bottle with the

breaker in the open position in strict accordance with manufacturer’s instructions.

8. **Perform insulation-resistance tests at 1000 volts on all control wiring dc. For units with

solid-state components, follow manufacturer’s recommendations.

Page 77: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 17

9. **Perform dissipation-factor/power-factor tests on each pole with the breaker open and

each phase with the breaker closed.

10. **Perform dissipation-factor/power-factor tests on each bushing. Use conductive straps

and hot collar procedures if bushings are not equipped with a power factor tap.

11. **Perform an overpotential test in accordance with manufacturer’s instructions.

D. Test Values

1. Compare bolted connection resistance to values of similar connections.

2. Bolt-torque levels should be in accordance with NETA Table 10.12 unless otherwise

specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as

indicated in the manufacturer’s published data. If manufacturer’s data is not available,

investigate any values which deviate from similar connections by more than 50 percent of

the lowest value.

4. Circuit breaker insulation resistance should be in accordance with NETA Table 10.1.

5. Contact displacement shall be in accordance with factory recorded data marked on the

nameplate of each vacuum breaker or bottle.

6. The interrupter shall withstand the overpotential voltage applied.

7. Compare circuit breaker timing values to manufacturer’s published data.

8. Control wiring insulation resistance should be a minimum of two megohms.

9. Dissipation-factor/power-factor test results shall be compared to manufacturer’s published

data. In the absence of manufacturer’s published data the comparison shall be made to

similar breakers.

10. Dissipation-factor/power-factor and capacitance test results should be within ten percent

of nameplate rating for bushings.

11. The insulation shall withstand the overpotential test voltage applied.

1.22 MEDIUM-VOLTAGE VACUUM SWITCHES:

A. Visual and Mechanical Inspection

1. Compare equipment nameplate data with drawings and specifications.

2. Inspect physical and mechanical condition.

3. Inspect anchorage, alignment, and grounding.

4. Perform all mechanical operation and contact alignment tests on both the switch and its

operating mechanism.

5. Check each fuse holder for adequate support and contact.

6. Verify that fuse sizes and types correspond to drawings.

7. Test all electrical and mechanical interlock systems for correct operation and sequencing.

8. Inspect all bolted electrical connections for high resistance using one of the following

methods:

a. Use of low-resistance ohmmeter in accordance with Electrical Tests.

b. Verify tightness of accessible bolted electrical connections by calibrated torque-

wrench method in accordance with manufacturer’s published data or NETA Table

10.12.

c. Perform thermographic survey in accordance with NETA Section 9.

9. Verify that insulating oil level is correct, if applicable.

B. Electrical Tests

1. Perform resistance measurements through all bolted electrical connections with a low-

resistance ohmmeter, if applicable. See Visual and Mechanical Inspection.

Page 78: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 18

2. Perform a contact-resistance test.

3. Verify open and close operation from control devices, if applicable.

4. Perform insulation-resistance tests pole-to-pole, pole-to-ground, and across open poles at

2500 volts minimum.

5. Perform vacuum bottle integrity (overpotential) test across each vacuum bottle with the

switch in the open position in strict accordance with manufacturer’s published data. Do

not exceed maximum voltage stipulated for this test. Provide adequate barriers and

protection against x-radiation during this test. Do not perform this test unless the contact

displacement of each interrupter is within manufacturer’s tolerance. (Be aware that some

dc high-potential test sets are half-wave rectified and may produce peak voltages in excess

of the switch manufacturer’s recommended maximum.)

6. Remove a sample of insulating liquid, if applicable, in accordance with ASTM D-923.

Sample shall be tested in accordance with the referenced standard.

a. Dielectric breakdown voltage: ASTM D-877

b. Color: ASTM D-1500

c. Visual condition: ASTM D-1524

7. **Perform insulation-resistance tests on all control wiring at 1000 volts dc. For units with

solid-state components, follow manufacturer’s recommendations.

8. **Perform an overpotential test in accordance with manufacturer’s published data.

C. Test Values

1. Compare bolted connection resistances to values of similar connections.

2. Bolt-torque levels should be in accordance with NETA Table 10.12 unless otherwise

specified by manufacturer.

3. Microhm or millivolt drop values shall not exceed the high levels of the normal range as

indicated in the manufacturer’s published data. If manufacturer’s data is not available,

investigate any values which deviate from adjacent poles or similar switches by more than

50 percent of the lowest value.

4. Contact displacement shall be in accordance with factory recorded data marked on the

nameplate of each vacuum switch or bottle.

5. The vacuum bottles shall withstand the overpotential voltage applied.

6. Control wiring insulation resistance should be a minimum of two megohms.

7. The insulation shall withstand the overpotential test voltage applied.

8. Insulating liquid test results shall be in accordance with NETA Table 10.4.

1.23 PROTECTIVE RELAYS

A. General: Perform and document the following tests on all protective relays:

B. Visual and Mechanical Inspection:

1. Inspect relays for physical damage and compliance with specifications.

2. Inspect cover gasket, cover glass, presence of foreign material, moisture, condition of

spiral spring, disc clearance, rust, contacts, and case shorting contacts if present.

3. Check mechanically for freedom of movement, proper travel and alignment, and tightness

of mounting hardware and tap screws.

4. Perform adjustments for final settings in accordance with the data generated from the short

circuit/coordination studies, if applicable to the particular relay.

C. Electrical Tests:

Page 79: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 19

1. Perform insulation resistance test on each circuit to frame. Do not perform this test on

solid state devices.

2. Perform the following tests on the nominal settings specified by the project electrical

engineer:

a. Pickup parameters on each operating element.

b. Perform timing test at two (2) points on time dial curve.

c. Pickup target and seal-in units.

d. Special tests as required to check operation of restraint, directional and other elements

per manufacturer's instruction manual.

3. Perform phase angle and magnitude contribution tests on all differential and directional

type relays after energization to vectorially prove proper polarity and connection.

1.24 TESTING PROCEDURES AND SCHEDULES

A. Test Procedures: Type written recommended test procedures for each type of test shall be

submitted along with the system studies for approval by the Engineer prior to commencement

of the testing of the system components. Test procedures shall indicate the type of test

equipment that will be used during the testing.

B. Test Schedule: A type written schedule listing the number of workman that will be present,

the time and the date for each testing of each of the system's components shall be submitted

for approval by the Engineer prior to commencement of the testing.

PART 2 PRODUCTS (Not applicable)

PART 3 EXECUTION

3.1 FIELD QUALITY CONTROL

A. General: Perform tests to prove installation is in accordance with contract requirements.

Perform tests in presence of the Owner's representative and furnish test equipment, facilities

and technical personnel required to perform tests. Tests shall be conducted during the

construction period and at completion to determine conformity with applicable codes and with

the related Specifications.

B. Product, Installation and Testing Failures: Any installation or products or workmanship

which fail during the tests or are ruled unsatisfactory as a result of this testing shall be

replaced, repaired or corrected as prescribed by the Owner's representative at the expense of

the installing Electrical Contractor. Tests shall be performed again after repairs, replacements

or corrections are completed until satisfactory performance is demonstrated, without additional

cost to the Owner. Any system material which is found defective on the basis of performance

tests shall be reported directly to the Architect.

C. All devices and materials to perform the inspection and maintenance must be obtained prior to

commencing the work.

D. All instruments required must be available and in proper operating condition.

E. All disposable materials such as solvents, rags, and brushes required must be provided.

Page 80: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 20

F. All equipment handling devices such as cranes, vehicles, chain falls, and other lifting

equipment must be available or scheduled.

G. All instruction books, calibration curves, or other printed material to cover the electric devices

must be available.

H. Data sheets to record all test results must be available before the work is started.

3.2 TEST INSTRUMENT CALIBRATION

A. The testing firm shall have a calibration program which assures that all applicable test

instrumentation are maintained within rated accuracy.

B. The accuracy shall be directly traceable to the National Bureau of Standards in an unbroken

chain.

C. Instruments shall be calibrated in accordance with the following frequency schedule:

1. Field instruments: Analog - 6 months maximum

2. Digital - 12 months maximum

3. Laboratory instruments: 12 months

4. Leased specialty equipment: 12 months (Where accuracy is guaranteed by lessor)

D. Dated calibration labels shall be visible on all test equipment.

E. Records must be kept up-to-date which show date and results of instruments calibrated or

tested.

F. An up-to-date instrument calibration instruction and procedure will be maintained for each test

instrument.

G. Calibrating standard shall be of higher accuracy than that of the instrument tested.

3.3 CLEANING

A. Cleaning: After all work has been completed, clean panelboards, switchboards and other

electrical equipment to remove dust, dirt, grease or other marks. Leave work in clean

condition.

3.4 TEST REPORTS

A. General: Submit three typed copies of the completed test reports on 8- 1/2" x 11" paper in a

neatly bound folders to the Architect no later than 10 working days after completion of test

unless directed otherwise. The test reports shall be bound and it contents certified. Failure to

comply with this will result in a delay of final testing and acceptance. Upon approval by the

Engineer and after all review comments from the Engineer have incorporated, if any, submit

four copies to the owner.

B. Short Circuit and Ground Fault System Studies: Provide a complete set of reports per section

1.06.

Page 81: SECTION 260500 - BASIC ELECTRICAL …...Medium Voltage Testing and Maintenance Project Basic Electrical Requirements Section 260500 1 SECTION 260500 - BASIC ELECTRICAL REQUIREMENTS

Medium Voltage Testing and Maintenance Project

ENGINEERING ANALYSIS & ELECTRICAL SYSTEMS TESTING 16940 - 21

C. Equipment Test Reports: Provide a complete report listing every device, the date it was tested,

the procedures performed, the results and the date retested (if failure occurred during the

previous test). The test report shall indicate that every device tested successfully.

D. Test Report shall also include the following:

1. Summary of project.

2. Description of equipment tested.

3. Description of test.

4. Test results.

5. Conclusions and recommendations.

6. Appendix, including appropriate test forms.

7. Identification of test equipment used and their calibration date.

8. Signature of responsible test organization authority.

E. Set transformer taps to obtain the nominal secondary voltage rating indicated on drawings.

END OF SECTION