November 1, 2017 1 Completed and ongoing tasks: • Construction trailers setup completed. • Excavation and sheeting/shoring ongoing. • Starting rebar work for footing and foundation. Construction activities next month: • Continuing excavation. • Temporary construction power will be installed. • Below grade waterproofing will be installed. • Tower crane will be erected. • Concrete footings and foundation walls will be installed. Process related activities: • Building Level Planning Committee meeting will be held in early December. • Construction workers parking during excavation and sheeting/ shoring will be on-site. Secondary School @Wilson Community Newsletter (October 2017)
Transcript of Secondary School @Wilson Construction workers parking during excavation and sheeting/ shoring will...
November 1, 2017 1
Completed and ongoing tasks:
• Construction trailers setup completed.
• Excavation and sheeting/shoring ongoing.
• Starting rebar work for footing and foundation.
Construction activities next month:
• Continuing excavation.
• Temporary construction power will be installed.
• Below grade waterproofing will be installed.
• Tower crane will be erected.
• Concrete footings and foundation walls will be installed.
Process related activities:
• Building Level Planning Committee meeting will be held in early December.
• Construction workers parking during excavation and sheeting/ shoring will be on-site.