Secondary Reforming Burners

32

description

History Design Operational Improvements Fabrication Delivery Installation

Transcript of Secondary Reforming Burners

Page 1: Secondary Reforming Burners
Page 2: Secondary Reforming Burners

History Design Operational Improvements Fabrication Delivery Installation

Contents

Page 3: Secondary Reforming Burners

Ring burners have been around for a long time, in fact nearly 25 years

Prior to this shower head types have been used Straight pipes with simple mixers can be used

providing long necks exist

Page 4: Secondary Reforming Burners

In the Secondary Reformer process gas is mixed with air

This provides the nitrogen necessary for ammonia synthesis

The reaction can be described as taking place in two parts: ◦ combustion of hydrogen ◦ reforming of methane

Combustion of hydrogen provides the heat required to achieve a very low exit methane concentration

Page 5: Secondary Reforming Burners

CH4 + 2CO = CO2 + 2H2O

2H2 + O2 = 2H2O

Exothermic - gives out heat

Flame 2500oC mixed gas 1500oC

Page 6: Secondary Reforming Burners

Gas feed very hot > 630oC

Gas feed contains hydrogen

Gas ignites automatically

Autoignition >615oC

No need for spark or pilot

Must maintain gas above 615oC

Page 7: Secondary Reforming Burners

Only 20% of flammable gas is burnt

Excess methane is left

Remaining methane reforms with steam

Oxygen increases temperature

Reverse of normal combustion

Page 8: Secondary Reforming Burners

After combustion gas at 1500oC

Hot enough to react in gas volume

Gas will cool to 1100oC - 1200oC

Substantial amount of methane reacts

Page 9: Secondary Reforming Burners

Steam reforming CH4 + H2O = 3H2 + CO

Endothermic - cools down gas

Water gas shift

CO + H2O = CO2 + H2

Slightly exothermic

Page 10: Secondary Reforming Burners

Catalyst completes reaction to 950oC

Exit methane content approx 0.5% (dry)

Catalyst is Ni on ceramic

Can be ringed or shaped catalyst as for Primary Reformer

Page 11: Secondary Reforming Burners

Bit of black art, originally Now backed up by some science Process calculations are carried out for flows in gas

side, air side ensure pressure drops not too large CFD has improved our designs immensely, but is

expensive Mixing and proportions are important All designs are similar but not Identical Velocity exit nozzles is important

Page 12: Secondary Reforming Burners
Page 13: Secondary Reforming Burners
Page 14: Secondary Reforming Burners

780°C

450°C

2500°C

? ~1500°C

1100-1200°C

950°C

? ~1500°C

1100-1200°C

1300°C

Pipe design

Page 15: Secondary Reforming Burners

Shower Head

Page 16: Secondary Reforming Burners

TI

TITI

Gas from Primary

Gas to Process

Water inlet

Water inlet

Steam vents

Oxygen inlet

Catalyst

Arch

Waterjackets

Burner gun

Refractory

Distributor

Page 17: Secondary Reforming Burners

All materials are Incoloy 800 (UNS 8810) (Alloy 600 is not stronger or more temp resistant at these operating temps, only more expensive)

Oxidation resistance is very important Special Heat treatment ◦ To ensure oxidation resistance is maintained ◦ Improve the grain structure, improve creep resistance

Some components are tightly bent, grains become flattened and weaker. Typically around manifolds and feeders, we correct this.

Page 18: Secondary Reforming Burners
Page 19: Secondary Reforming Burners

Equipment needs to be a good fit to prevent damage

Top hung in the unit, hence why central pipe is thick

Site welding is carried out by customer, we provide weld procedure,Customer provides weld procedure qualification, Consumables

Page 20: Secondary Reforming Burners

Better Mixing Reduced Methane Slip 0.5-0.3% or better Improved Catalyst Performance better bed usage

Page 21: Secondary Reforming Burners

Bending of manifolds is difficult, require skill Welding needs to be well controlled, distortion is an

issue Flow Straighter is Laser cut, SS cannot be flame cut,

plasma cutting needed; this distorts the plates (end up looking like pringles

Page 22: Secondary Reforming Burners

Not the norm around the world, however this has become the norm in FSU

Sufficient detail on the drawing to allow competent operator to install

Welded on site, the unit and lowered in. Take care with dimensions, try to obtain “As Built”

drawings

Page 23: Secondary Reforming Burners
Page 24: Secondary Reforming Burners
Page 25: Secondary Reforming Burners

Proposal 0.2Place order 0.1Process Design 1Mechanical Design 1Client Approval 1Fabrication 9Delivery 2

Weeks 14

Weeks

We try to achieve 10 weeks ! Raw materials are on 6 weeks delivery !!!!!!

Page 26: Secondary Reforming Burners

Delivery usual methods Sea/Road, Air is expensive

Weight approx 1.2 te Packaging:- crated and sealed Need to allow 2 weeks In Europe/FSU ROW 6 weeks Shut downs can be decided in 14 weeks !

Page 27: Secondary Reforming Burners
Page 28: Secondary Reforming Burners
Page 29: Secondary Reforming Burners
Page 30: Secondary Reforming Burners
Page 31: Secondary Reforming Burners
Page 32: Secondary Reforming Burners