Second Narrows Water Supply Tunnel - Metro Vancouver

2
APRIL 2021 Second Narrows Water Supply Tunnel Burrard Inlet Harbour Rd Harbour Rd Railway St Railway St Riverside Dr Riverside Dr Amherst Ave Amherst Ave Spicer Rd Spicer Rd D D o ol ll la a r rt t o o n n H Hw w y y Main St Main St T T r ra an ns s C Ca an na ad d a a H H w w y y Ironworkers Memorial Bridge Ironworkers Memorial Bridge Edinburgh St Edinburgh St Columbia St Columbia St Harbour Rd Railway St Riverside Dr Amherst Ave Spicer Rd D olla rt o n Hwy Main St Trans Canad a H w y Ironworkers Memorial Bridge Edinburgh St Columbia St Second Narrows Park Metro Vancouver Works Yard North Shore Recycling and Waste Centre CITY OF BURNABY DISTRICT OF NORTH VANCOUVER SECOND NARROWS WATER SUPPLY TUNNEL ALIGNMENT North (Entry) Shaft Construction Early 2019 – Mid 2023 Connection to existing system and restoration Fall 2023 – Spring 2025 South (Exit) Shaft Tunnel alignment for the Second Narrows Water Supply Tunnel Site preparation and shaft construction Early 2019 – Mid 2021 Valve chamber construction and water main installation Mid 2021 – Mid 2023 Connection to existing system and restoration Fall 2023 – Spring 2025 To help ensure the continued delivery of clean, safe drinking water for the region’s growing population. long‑term needs of the growing population. The new water supply tunnel will be excavated deep underground using a tunnel boring machine. The tunnel boring machine will launch from a vertical entry shaft on the North Vancouver side and progress south under Burrard Inlet to the vertical exit shaft on the Burnaby side. Please see the map for the alignment of the tunnel and locations of work. Once the tunnel is excavated, three steel water mains will be installed inside the new tunnel and connected to the new valve chambers at each shaft site, and into the region’s drinking water system. Construction Schedule Construction of this project is underway, with completion expected in 2025. While the duration of this project spans over six years, work at the south shaft site in Second Narrows Park will take place intermittently with some breaks between different construction activities. Upcoming Activities Activities associated with this project include shaft excavation and shoring, valve chamber and pipe installation, welding, backfilling and restoration. Construction equipment will include a large crane, excavators, pumps and ventilation fans. Site Selection When selecting the location of the tunnel, Metro Vancouver, in conjunction with the District of North Vancouver and the City of Burnaby, considered geotechnical, bio‑environmental, socio‑economic and archaeological factors, along with the need to connect the tunnel to existing infrastructure in Second Narrows Park. The selected site has the least impact to the park of the options considered, utilizes an existing access road and will allow maintenance workers to access the new infrastructure without impacting nearby residents. Project Overview Metro Vancouver is constructing a new water supply tunnel deep under Burrard Inlet, east of the Ironworkers Memorial Bridge between the District of North Vancouver and the City of Burnaby. This project is one of five new regional water supply tunnels that are being designed to meet current seismic standards to ensure the reliable delivery of drinking water in the region in the event of a major earthquake. When complete, the tunnel will also increase the capacity of the existing system to meet the WATER

Transcript of Second Narrows Water Supply Tunnel - Metro Vancouver

Page 1: Second Narrows Water Supply Tunnel - Metro Vancouver

APRIL 2021

Second Narrows Water Supply Tunnel

Burrard Inlet

Harbour RdHarbour Rd

Railway St

Railway St

Rive

rsid

e D

r

Rive

rsid

e D

r

Am

herst Ave

Am

herst Ave

Spicer RdSpicer Rd

DDoollllaarrttoonn HHwwyy

Main StMain St

TTrraannss CCaannaaddaa HH

wwyy

Ironw

orkers M

emo

rial Brid

ge

Ironw

orkers M

emo

rial Brid

ge

Edinburgh StEdinburgh St

N B

ound

ary Rd

N B

ound

ary Rd

Columbia St

Columbia StHarbour Rd

Railway St

Rive

rsid

e D

r

Am

herst Ave

Spicer Rd

Dollarton Hwy

Main St

TransC

anadaH

wy

Ironw

orkers M

emo

rial Brid

ge

Edinburgh St

N B

ound

ary Rd

Columbia St

Second Narrows

Park

Metro Vancouver

Works Yard

North Shore

Recycling and Waste

Centre

Bates Park

CITY OF BURNABY

DISTRICT OF NORTH

VANCOUVER

SECOND NARROWS WATER SUPPLY TUNNEL ALIGNMENT

North (Entry) Shaft

ConstructionEarly 2019 – Mid 2023

Connection to existing system and restoration Fall 2023 – Spring 2025

South (Exit) Shaft

Tunnel alignment for the Second Narrows Water Supply Tunnel

Site preparation and shaft construction

Early 2019 – Mid 2021

Valve chamber construction and water main installationMid 2021 – Mid 2023

Connection to existing system and restoration

Fall 2023 – Spring 2025

To help ensure the continued delivery of clean, safe drinking water for the region’s growing population.

long‑term needs of the growing population.

The new water supply tunnel will be excavated deep underground using a tunnel boring machine. The tunnel boring machine will launch from a vertical entry shaft on the North Vancouver side and progress south under Burrard Inlet to the vertical exit shaft on the Burnaby side. Please see the map for the alignment of the tunnel and locations of work. Once the tunnel is excavated, three steel water mains will be installed inside the new tunnel and connected to the new valve chambers at each shaft site, and into the region’s drinking water system.

Construction ScheduleConstruction of this project is underway, with completion expected in 2025. While the duration of this project spans over six years, work at the south shaft site in Second Narrows Park will take place intermittently with some breaks between different construction activities.

Upcoming ActivitiesActivities associated with this project include shaft excavation and shoring, valve chamber and pipe installation, welding, backfilling and restoration. Construction equipment will include a large crane, excavators, pumps and ventilation fans.

Site SelectionWhen selecting the location of the tunnel, Metro Vancouver, in conjunction with the District of North Vancouver and the City of Burnaby, considered geotechnical, bio‑environmental, socio‑economic and archaeological factors, along with the need to connect the tunnel to existing infrastructure in Second Narrows Park.

The selected site has the least impact to the park of the options considered, utilizes an existing access road and will allow maintenance workers to access the new infrastructure without impacting nearby residents.

Project OverviewMetro Vancouver is constructing a new water supply tunnel deep under Burrard Inlet, east of the Ironworkers Memorial Bridge between the District of North Vancouver and the City of Burnaby. This project is one of five new regional water supply tunnels that are being designed to meet current seismic standards to ensure the reliable delivery of drinking water in the region in the event of a major earthquake. When complete, the tunnel will also increase the capacity of the existing system to meet the

WATER

Page 2: Second Narrows Water Supply Tunnel - Metro Vancouver

Contact Metro VancouverMetro Vancouver Information Centre: 604-432-6200 (Monday to Friday from 8 AM to 4:30 PM)

[email protected] (Please include ‘Second Narrows Water Supply Project’ in the subject line)

COVID‑19 and Delivery of Essential Services Metro Vancouver continues to closely monitor developments regarding COVID‑19 and our paramount commitment is to maintain essential services to the region while protecting the health and safety of our employees, contractors, residents and businesses. Metro Vancouver’s construction projects are key components in ensuring the ongoing delivery of essential services as defined by the Province of BC. Metro Vancouver follows the guidance of the Provincial Health Officer and is taking all necessary measures to ensure our work sites remain safe and healthy.

Reducing Impacts to the Park The new valve chamber in Second Narrows Park has been designed to fit into the park as seamlessly as possible; this includes the valve chamber being set into the existing landscape and the installation of a sloping green roof.

Tree removal will be required to accommodate construction. The majority of vegetation removal required for this project consists of shrubs and invasive species such as blackberry bushes and knotweed.

Once construction is complete, this site will undergo a full restoration. This includes the implementation of a re‑planting program and landscaping of any disturbed areas with native plants and species.

Trans Canada TrailThe Trans Canada Trail will remain open for the duration of construction.

The existing access road that is used for utility maintenance, sometimes known as the Upper Trail, will be closed for the entire construction period. This road was initially built to conduct maintenance on the existing water and sewer infrastructure that is located in and around the park.

Metro Vancouver recognizes the current recreational use of the access road and will ensure that it is restored to similar or better condition after construction.

Traffic Impacts & NoiseThe entry shaft will be located in an industrial area in the District of North Vancouver; this is where the majority of construction, including the removal of excavated ground material, will take place. In an effort to reduce truck traffic, ground material excavated from this entry shaft will be transported to a disposal facility by barge.

In meeting with local residents, Metro Vancouver heard that noise was a concern and will ensure that noise mitigation measures will be in place during construction. In addition, noise studies have been completed to ensure that all work will comply with City of Burnaby’s bylaws or granted bylaw variances.

Hours of Work Work will take place Monday to Friday between 7 AM and 8 PM and Saturdays between 9 AM and 8 PM. Crews may occasionally be required to work outside of bylaw hours; in these cases, advanced notice will be provided to residents. All work will comply with City of Burnaby’s bylaws or granted bylaw variances.

Working with the CommunityMetro Vancouver is committed to minimizing the impacts of construction on the community. Local residents and businesses will receive ongoing notifications through newsletters, web updates, email and on‑site signage.

A Community Liaison Officer has been assigned to this project and is available to address any public questions or concerns.

RETAINING WALLVALVE CHAMBER

NATIVE SPECIES SHRUBSOVER VALVE CHAMBER

RETAINING WALLWITH GUARDRAIL

UNDISTURBEDFOREST

ACCESS ROAD

LARGE TREESAND SHRUBS

LANEPRIVATE

RESIDENCE

CROSS-SECTION OF THE COMPLETED VALVE CHAMBER AND RESTORATION IN SECOND NARROWS PARK

35 to 45 metres deep

Water Supply Tunnel (1.1 km long and 30 m below the bottom of Burrard Inlet)

North (Entry) Shaft(60 m deep)

South (Exit) Shaft(110 m deep)

Burrard InletMetro Vancouver

Works Yard

Second Narrows

Park

RockSoil

BURNABYNORTH VANCOUVER

CROSS-SECTION OF THE SECOND NARROWS WATER SUPPLY TUNNEL