Sea Port Construction, Project Execution Plan
-
Upload
david-h-moloney -
Category
Engineering
-
view
1.358 -
download
35
Transcript of Sea Port Construction, Project Execution Plan
David H Moloney
14th August 2016
Sea Port Construction, Project Execution PlanDetails of how a Sea Port is constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to ensure that the site is environmentally friendly.
http://www.slideshare.net/DavidHMoloney/sea-port-construction-project-execution-plan
Brief Description
The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a Sea Port .
This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.
Project Execution Plan (PEP) details how a project will be executed, monitored and controlled.
High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)This Video Presentation is innovative and has many beneficial uses.
Video https://www.youtube.com/watch?v=6_Aco_GPO8I
Contents
ⓒ David H Moloney
Introduction
Quay WallQ
uay W
all
Quay WallQ
uay W
all
Brief Description
The quay wall is constructed using precast reinforced concrete hollow blocks that weigh up to 160 tonnes. The blocks were cast in the on-site precast yard and loaded onto barges at the temporary loading jetty that had a 200 tonne capacity gantry crane.
A screeding frame that extended from the sea bet to above water was used to place the bedding layer to the correct level.Up to 22 blocks were placed per day using a barge with a crane.Part of the coping beam was cast in-sit-u in sections using concrete pumps positioned on the reclaimed land behind the quay wall.
Sequence & Methods to Construct Quay WallQ
uay W
all
3D Animation
Quay-wall
ⓒ David H Moloney
Placing Precast Quay Blocks Placing Precast Quay Blocks
Screed Frame for preparing Granular Foundation Placing Precast Quay Blocks
Quay Wall Beam
Screed FrameM
iscella
ne
ous
Brief Description
Duqm, Oman
Mooring Bollards & Marine FendersM
iscella
ne
ous
Marine Equipment ⓒ David H Moloney
Drawing – Quay Wall Cross Section
Breakwater & WavewallB
reakw
ate
r &
Wavew
all
Breakwater & WavewallB
reakw
ate
r &
Wavew
all Brief Description
The breakwater is constructed using core rock, rock armour, precast armour units and geotextile.The core rock is placed using split hopper barges in deep water and by lorry tipping and dozers in shallow water where the risk of slippage is minimal.The precast armour units are placed using crawler cranes fitted with a real-time visual aid system that enabled 70 placements per day.The wave wall is cast in-sit-u in 6 metre long sections.
Sequence & Methods to Construct Breakwater & WavewallB
reakw
ate
r &
Wavew
all
Breakwatersⓒ David H Moloney
Filling Barge with Rock – Temporary Jetty Placing Rock Fill
Breakwater under Construction Placing Rock Armour
Breakwaters
Placing Rock Fill
Breakwater under Construction
Barges for Rock Fill
Geotextile
Precast Sea Armour
Placing Armour
Rock Sea Armour
Placing Armour
Sea Wall
Drawing – Breakwater Cross Section
Quarry Run Rock Fill
Drawing – Breakwater Cross Section
Quarry Run Rock Fill
Wave Wall
Geotextile
Rock Armour 0.5 - 1 ton
Precast Armour
Rock Armour 1 - 3 ton
Precast Yard & Loading JettyP
recast Y
ard
& L
oadin
g J
etty
Precast Yard & Loading JettyP
recast Y
ard
& L
oadin
g J
etty Brief Description
Full-scale sample castings are constructed to demonstrate and document that all the requirements of the concrete and the execution of the work are fulfilled using the actual methods and performed by personnel that will carry out the future castings. One concrete component of each type is produced for approval. The approved castings were retained in a dedicated area for quality assurance purposes.
All works were inspected in accordance with the Inspection & Test Plan on an ongoing basis, in accordance with the site Project Quality Plan. The ITP set out in matrix form the sequence of inspection steps, the governing document (specification, standards), the standard to be achieved, the persons witnessing and the supporting documents to be produced.
Precast Yard & Loading JettyP
recast Y
ard
& L
oadin
g J
etty
Precast Yard & Loading JettyP
recast Y
ard
& L
oadin
g J
etty
Precast Yard & Loading JettyP
recast Y
ard
& L
oadin
g J
etty
Pre-casting Quay Blocks
Precast Sea Armour
Shutters for Precast Sea Armour Shutters for Precast Sea Armour
Quarry & Aggregate Production
3D image to show Sequence, Method & Plant.
ⓒ David H Moloney
Quarry
Concrete Batching Plant David H Moloney
ⓒ David H Moloney
Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks. The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage capacity to match two days concrete production
Concrete Batching Yard
Silos, Ice Flake Plant, Chilled water, Mixer
Storage bays for aggregates
Reinforcement Cutting & Bending Yard David H Moloney
ⓒ David H Moloney
Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine
Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site
Reinforcement Cutting & Bending
ⓒ David H Moloney
Concre
te
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concre
te
Brief Description
The sequence to construct a reinforced concrete wall is as
follows:
Tie the reinforcement.
Erect stop-ends and the wall shutters.
Pour and vibrate the concrete mix.
Remove the shutters after the concrete has hardened.
.
Cycle Time Pour per Day
Reinforced Wall Construction Sequence
ⓒ David H Moloney
Concre
te
Concrete MixG
enera
l Item
s
A concrete mix contains 5 major
elements: cement, water, coarse
aggregates, fine aggregates (sand) and
air in different proportion. Additional
elements such as pozzolanic materials (fly
ash, silica fumes or slag) and chemical
admixtures can also be incorporated to
the mix to increase its properties.
Vibrating Concrete
ⓒ David H Moloney
Concre
te
Dredging & ReclamationD
red
gin
g &
Recla
ma
tion
Dredging & ReclamationD
red
gin
g &
Recla
ma
tion Brief Description
Dredgers are marine vessels used to excavate and fill under water.
Types
1. Cutter Suction Dredgers are used to dredge hard soils by cutting
and breaking up the soil using a rotating head at the end of a pipe
which is lowered onto the sea bed. The fragmented material is
sucked and pumped either into a hopper barge or through a floating
pipeline. During operation the dredger is anchored by a spud that
allows the cutting head to swing in an arc.
2. Trailing Suction Hopper Dredgers are used to dredge soft and
loose soils, gravels and silts. There are two suction drag heads
which are lowered onto the sea bed. These move with the dredger
along the sea bed. The dredged material is sucked and pumped
either into the hopper or through a floating pipeline to a discharge
area.
Dredging & ReclamationD
red
gin
g &
Recla
ma
tion
Dredger - Trailing Suction D
red
gin
g &
Recla
ma
tion
Boskalis Netherlands
Dredger - Cutter Suction D
red
gin
g &
Recla
ma
tion
Boskalis Netherlands
Dredger - Backhoe D
red
gin
g &
Recla
ma
tion
Rock - Excavability
The excavability of rock depends mainly on the rock strength and the layer thickness. This diagram shows excavation methods for rock of various strengths and thicknesses, with a free face.
ⓒ David H Moloney
Vibro Compaction - Fill behind Quay
Vibro Compaction - Fill behind Quay
Ground Improvement using deep vibro-compaction.
Purpose is to provide protection against liquefaction during a seismic
event. Also to provide a specified minimum ground bearing capacity.
Vibro-compaction was use to compact the Dubai man made islands
that were constructed from dredged sand.
Equipment.
Vibroflot with extension tube, hydraulic power pack mounted on crane,
diesel engine driven water jetting pumps, compressors, crawler cranes
60 tonne capacity, water tank, de-watering pump
Vibro Compaction - Fill behind Quay
3D image to show Sequence, Method & Plant.
David H Moloney
ⓒ David H Moloney
Vibro CompactionV
ibro
Com
pa
ction
Surv
eyin
g &
settin
g O
ut
Survey & Setting Out
Surv
eyin
g &
settin
g O
ut
Brief Description
Ope
Survey & Setting Out
Survey Tower
Setting out & Surveying
Setting out & Surveying
Port OperationP
ort
Opera
tio
n
Port OperationP
ort
Opera
tio
n
Port OperationP
ort
Opera
tio
n
Port OperationP
ort
Opera
tio
n
Site Facilities & Temporary WorksS
ite F
acili
tie
s &
tem
pora
ry W
ork
s
Site Facilities & Temporary WorksS
ite F
acili
tie
s &
tem
pora
ry W
ork
s
Welfare Facilities
ⓒ David H Moloney
Genera
l Item
s
Toilets – Washing
Canteen, Drying Room, Toilet & Generator
Site Hoarding examples
ⓒ David H Moloney
Genera
l Item
s
Wheel Wash Drive-through
ⓒ David H Moloney
Genera
l Item
s
Wheel Wash Drive-throughG
enera
l Item
s
Temporary Electricity Supply & Tower Lights
Generators
Genera
l Item
s
Dewatering
ⓒ David H Moloney
Genera
l Item
s
Concrete Batching Yard 3 Nr MixersG
enera
l Item
s
Health, Safety & EnvironmentalH
ealth, safe
ty &
environ
menta
l
Emergency Phone Numbers & Response
HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of
current HSE Issues and historical trends
Site Safety Posters examples
Safety Precautions
Personal Protective Equipment (PPE)H
ealth,
Safe
ty &
Environm
ent
Personal protective equipment (PPE) is protective clothing, helmets, goggles, or other garments or equipment designed to protect the wearer from injury or infection
Safety Training on Site M
iscella
ne
ous
The purpose of safety training is to provide the knowledge necessary to
perform a job safely
Safety Training Matrix M
iscella
ne
ous
The purpose of safety training is to provide the knowledge necessary to
perform a job safely
Emergency Response Drill H
SE
Drills and exercises are used to rehearse anticipated emergency scenarios
Environmentally Friendly Site Air, Noise, Water & Soil Pollution
Hazardous Substances Symbols H
ealth,
Safe
ty &
Environm
ent
COSHH stands for the Control of Substances Hazardous to Health
Shown are the new hazard symbols
Water Pollution PreventionG
enera
l Item
s
Segregation of Waste H
ealth,
Safe
ty &
Environm
ent
Segregation of waste for proper disposal and recycling. Less waste goes to landfill and hazardous waste is treated to make it safe.
Colour Code for Skips & Bins
Putting Waste Concrete to use
ⓒ David H Moloney
Health,
Safe
ty &
Environm
ent
Precast bases for signs and hoarding, Precast blocks for walls.
AdministrationA
dm
inis
tration
Organogram
Brief Description
Shown are the line and
lateral relationships
between the various team
members and their relative
position in the site
organisation.
Staff Responsibility Matrix
Staff Directory
Brief Description
List of staff and their
contact details
Daily Work Record
Brief Description
Daily Work Records showing the
allocation of resources, materials and
work activities carried out daily.
Quotations Comparison Sheet
Filing System
Quality AssuranceQ
ualit
y A
ssura
nce
Quality Assurance Dashboard Dashboard is a single page, graphical representation of
current statistics and historical trends
Laboratory
ⓒ David H Moloney
Asphalt P
avin
g
Programme & Progress MonitoringP
rogra
mm
e &
Pro
gre
ss M
onitori
ng
Progress Monitoring & Reporting - Dashboard
ⓒ David H Moloney
Dashboard is a single page, graphical representation of current progress and historical trends
Histogram Charts for Resources & Outputs
Manpower per Discipline Concrete per Location
Numbers for each month of the Project Quantity for each month of the Project
ⓒ David H Moloney
Plant & Equipment List & Worker’s Job Titles
ⓒ David H Moloney
Other ProjectsO
ther
Pro
jects
Brief Description
Jetty for Kuwait Causeway
Other Projects
Jetty for Kuwait Causeway
Other Projects
Brief Description
Concrete Batching Plant on Barge.
Kuwait Causeway
Other Projects
Kuwait Causeway Offshore Piling
Other Projects
Concrete Batching Plant on Barge. Kuwait Causeway
Other Projects
Pile Driving
Other Projects
Temporary Bridge
Other Projects
Temporary Bridge Piling
Other Projects
Brief Description
Marine Piles
Other Projects
Brief Description
Screed Frame. Morocco
Other Projects
Brief Description
Quay Wall Ruwais UAE
Other Projects
Brief Description
Dubai Palm Island, Rock Armour
Other Projects
Brief Description
Dubai Creek, strengthen
quay wall with sheet piles and
ground anchors
Other Projects
Brief Description
Abu Dhabi Quay Wall
Other Projects
Brief Description
St. Croix Bridge
Other Projects
Brief Description
Cofferdams examples
Other Projects
Jebel Ali DubaiOther Projects
Jebel Ali Dubai
Ports
Muscat Omani
Dublin Cork
Production by David H Moloney
My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ
My Port Construction YouTube link https://www.youtube.com/watch?v=6_Aco_GPO8I