SDR by ZTE

45
SDR Site Installation Standards For Telenor Vega Swap Project(V1.0) Zhongxing Telecom Pakistan(Pvt.) LTD 20120912 QA Team

description

SDR installation by ZTE

Transcript of SDR by ZTE

Page 1: SDR by ZTE

SDR Site Installation Standards For Telenor Vega Swap Project(V1.0)

Zhongxing Telecom Pakistan(Pvt.) LTD

20120912

QA Team

Page 2: SDR by ZTE

Telenor Vega Project

Contents

• Installation of SDR, Rectifier, Battery and IDU

• Fixing of brackets, ODU, RRU with PIMDC

• Cabling, grounding and labeling

• View and neatness of site

Page 3: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Installation of new U steel

3

• All new U steels should be installed firmly on old U steel as per design drawings.

• Base angle should be connected to inner side of new U steel with two bolts, and clipped old U steel with one bolt tightly.

Page 4: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Installation of SDR and Rectifier Cabinets

4

• Installation of SDR and rectifier cabinets as per design drawings.

• Length of GI flexible pipe for the cable should be at least 6 inch under the SDR/Rectifier cabinet

Page 5: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Installation of SDR, Rectifier, Battery for macro site

5

• All ancient equipments should be swapped by SDR, rectifier and battery for macro site,

• All equipment bases should be installed on new U steel in line.

• Each rack of equipment shall be installed firmly and reliably in position as per design drawings.

• Ensure equipment door can be opened/closed freely after neighbor rack installation.

Page 6: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Installation of SDR for distributed site

6

• Ancient BTS should be swapped by SDR for distributed site.

• SDR base should be installed on new U steel in line with old equipment.

• Rack of SDR shall be installed firmly and reliably in position as per design drawings.

• Ensure SDR door can be opened/closed freely after the rack installation .

Page 7: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Installation of MW IDU

7

• IDU of NEC should be fixed firmly with 4 screws in old rectifier cabinet for distributed site.

• IDU of NEC should be fixed firmly with 4 screws in ZTE rectifier cabinet for macro site.

Page 8: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Contents

• Installation of SDR, Rectifier, Battery and IDU

• Fixing of brackets, ODU, RRU with PIMDC

• Cabling, grounding and labeling

• View and neatness of site

Page 9: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Fixing of ODU brackets, ODU

9

• ODU brackets should be fixed firmly with 4 U bolts on main material of tower in position as per design drawings.

• ODU of NEC should be fixed firmly on the ODU brackets in position as per design drawings.

• Plain washer, spring washer, nuts can not be missing.

Page 10: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Fixing of ODU brackets, ODU

10

• The brackets of ODUs on the tower should be mounted reliably and fully with flat washer, spring washer and twin nuts orderly according to engineering design drawing.

Page 11: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Fixing of ODU Side strut at Tower

11

• Horizontal suspension support should be installed for MW an antenna over 1.2m. This horizontal suspension support must be installed along the antenna.

Page 12: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Fixing of RRU brackets, RRU with PIMDC

12

• RRU brackets should be fixed firmly with 4 U bolts on main material of tower in position as per design drawings.

• RRU with PIMDC should be fixed firmly on the RRU brackets in position as per design drawings.

• Plain washer, spring washer, nuts can not be missing.

Page 13: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Fixing of RRU brackets, RRU with PIMDC

13

• RRU brackets should be fixed firmly with 4 U bolts on main material of tower in position as per design drawings.

• RRU with PIMDC should be fixed firmly on the RRU brackets in position as per design drawings.

• Plain washer, spring washer, nuts can not be missing.

Page 14: SDR by ZTE

Telenor Vega Project

Contents

• Installation of SDR, Rectifier, Battery and IDU

• Fixing of brackets, ODU, RRU with PIMDC

• Cabling, grounding and labeling

• View and neatness of site

Page 15: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Cabling of RRU, PIMDC

15

• Ground cable of RRU/MW dish should be separately connected to bus bar, if no bus bar is available within 5m then should be grounded reliably with main brace of tower through c-clamp for angular tower.

• For tubular tower, C- clamp should be connected to the RRU/MW mount.

• Grounding cable should be connected from RRU to PIMDC ,then from PIMDC to tower via C-clamp

Page 16: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Cabling, grounding and labeling of RRU

16

• All connectors of RRU should be wrapped from the bottom up as per 1 layer of insulating tape + 3 layers of waterproof insulating plaster + 3 layer of insulating tape.

• Ground cable of RRU/PIMDC/MW dish should be separately connected to bus bar, if no bus bar is available within 5m then should be grounded with main material of tower through c-clamp.

• All labels for outdoor site must be ZTE private outdoor plastic labels, with the labels 200mm away from the RRU.

R8860E

Page 17: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Cabling, grounding and labeling of RRU, PIMDC

17

PIMDC R8882 • All connectors of RRU should be wrapped from the bottom up as per 1 layer of insulating tape + 3 layers of waterproof insulating plaster + 3 layer of insulating tape.

• Ground cable of RRU/PIMDC/MW dish should be separately connected to bus bar, if no bus bar is available within 5m then should be grounded reliably with main brace of tower through C-clamp.

• All labels for outdoor site must be ZTE private outdoor plastic labels, with the labels 200mm away from the RRU.

Page 18: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Connecting power & dry contact cables in RRU with PIMDC

18

• Connect the A-end of the power cable to the Device Side on the PIMDC: connect the blue cable to -48V port and connect the black cable to -48VRTN port. Connect the white and blue dry contact cables to the Alarm ports.

• Connect the B-end of the power cable to the PWR port of the RRU, and then tighten it fully.

Page 19: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Waterproofing of Outdoor Jumper Cable

19

• Spiral-wrap one layer of insulating adhesive tape: After the feeder is connected, spiral-wrap one-layer insulating adhesive tape around the connector with 50% overlapping, ensuring that an excess of 10 mm insulating adhesive tape is reserved at the tail of the connector. Remember that you must apply proper force while spiral-wrapping the insulating tape.

• Spiral-wrap three layers of waterproof adhesive tape: Stretch the waterproof adhesive tape two times as long as its original length. Use approximately 50 cm waterproof adhesive tape for each connector. Spiral-wrap three-layer waterproof adhesive tape around the connector in the direction that you tighten the feeder. This can protect the feeder from being loosened during the spiral-wrapping process. Smooth over the waterproof adhesive tape by applying proper force to secure it on the feeder.

Page 20: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Cabling and labeling of jumper connected to GSM antenna

20

• The jumper connector to GSM antenna should be wrapped from the bottom up as per 1 layer of insulating tape + 3 layers of waterproof insulating plaster + 3 layer of insulating tape.

• Near the connector of a jumper and an antenna, the jumper should keep straight for 300mm.

• Extra jumper should be routed in S shape • All labels for outdoor site must be ZTE

private outdoor plastic labels, with the labels 200mm away from the bottom of antenna.

Page 21: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Cabling of optical fibers

21

• The power cable is bundled and laid separately from signal cables and tail fibers with a spacing of more than 3cm in between. No crossing or overlapping or inter-twist is allowed.

• Extra Optical fiber to be coiled properly for each sector and placed on top of horizontal ladder in series sector wise.

• For Optical fiber connectivity from FS to RSU use the rack specified channel for routing between 2 racks

Lack of blue cable

Fiber routing hole

Page 22: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Cabling of optical fibers

22

• The power cable is bundled and laid separately from signal cables and tail fibers with a spacing of more than 3cm in between. No crossing or overlapping or inter-twist is allowed.

• For ZXSDR BS8700 use right side of rack to route the Optical fibers as on left side there is main power and main grounding path

• All the cables should be properly tie up on cable tray inside cabinet

Page 23: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Cabling of optical fibers

23

• The optical fibers are connected to the correct sectors.

• The bends of optical fibers should be smooth and consistent, with the bending radius at least 20 times that of the fiber external diameter.

• Optical fibers should not inter-twist or wring when they are laid.

• Outdoor optical fibers should be bundled with a proper tightness to prevent the cables moving flexibly in the ties.

• Fiber in the cabinet should be laid and covered with protective flexible pipe.

• All labels for must be ZTE private outdoor plastic labels.

Page 24: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Cabling of optical fibers

24

• The power cable is bundled and laid separately from signal cables and tail fibers with a spacing of more than 3cm in between. No crossing or overlapping or inter-twist is allowed.

• Extra Optical fiber to be coiled properly for each sector and placed on top of horizontal ladder in series sector wise.

• Outdoor optical fibers should be bundled with a proper tightness to prevent the cables moving flexibly in the ties.

S1-OPR

S2-OPR

S3-OPR

Page 25: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Outdoor Labeling of ODU,Dish IF and Grounding Cables

25

• The connectors of each IF cable should be labeled to indicate the IF cable length and the Tx/Rx routing direction.

• ODU, Dish,Groundig and IF cables should be labeled at both end at 20mm

• Metallic label should be used on outdoor IF cable

Page 26: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

IF Cable Laying

26

• Before connecting ODU, leave more than 5m IF cable as the margin. The IF cable should be wired orderly and good-looking, without intersection, bending, or damage, and fastened with fixing ties at regular intervals of 1-1.5m.

Page 27: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

IF, Power ,grounding cable ,IDU and circuit breaker labeling

27

• Proper labeling should be done on IF, Grounding, Power Cables, IDU, Modems and Circuit Breakers as per approved standards

• Proper Sleeve/Tapping should be done on IF connectors , Grounding connectors and Power cables.

• Link Budget should be installed for each link in proper position and standard size.

Page 28: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Routing and colors of power cable & grounding cable

28

• New AC cable should be properly routed to the intake box. The buried portion should be at least 9” below ground in PVC conduit.

AC cable without PVC

Page 29: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Cabling & labeling of DC cables between SDR and REC

29

• The power cable should be connected by copper lug to the connecting terminal of rectifier and SDR, and then fixed with nuts to ensure sound contact.

• DC cable of cabinet should be pasted printing label at 20mm away from the ends.

SDR REC No Label No Label

Page 30: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Breaker distribution of SDR cabinet

30

• Connections to DCDB in SDR cabinet should be according to numbering 1, 2, …8, from left to right is defined as following.

a. Breaker slot 1, 2, 3… 6 : RRUs accordingly.

b. Breaker slot 7: BBU c. Breaker slot 8: Fan • DC cable of cabinet should be

pasted printing label at 20mm away from the ends.

• All the modules and cables without manufacture labels should be labeled.

Page 31: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Cabling & labeling of DC cables between SDR and PIMDC

31

• DC cable between SDR cabinet and PIMDC should be fixed private outdoor plastic labels at the end.

• The power cable layout should be in order and the turning points should be arc-shaped, with consistent bending radius over 50mm (no less than 20 times of the cable’s external diameter).

SDR REC PIMDC

Page 32: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Grounding of DC cables between SDR and PIMDC

32

• DC cable between SDR cabinet and PIMDC should be fixed with private outdoor plastic labels at the end.

• DC cable between SDR cabinet and PIMDC should be grounded with ground clip to old bus bar the same as dismantled feeder cable grounding requirements.

• DC Ground clips should be wrapped from the bottom up as per 1 layer of insulating tape + 3 layers of waterproof insulating plaster + 3 layer of insulating tape with proper shape.

Page 33: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Grounding of IF Cables and BTS

33

• There should be no doubling on bus bar. If no space available then 2nd cable can be connected to other side of bolt only.

• Upon completion of work, all connections shall be checked for a firm and tight contact. Checking shall be done on bolts, screws, clamps, sleeve connectors, and all hardware pertaining to the bonding of various elements of the grounding network.

SDR

Page 34: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Fiber and DC cables routing

34

• The power cable is bundled and laid separately from signal cables and tail fibers with a spacing of more than 3cm in between. No crossing or overlapping or inter-twist is allowed.

• The wiring is neat and uniform, cable outside of the cabinet is permitted to cross within 1m without winding and twisting.

Page 35: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Outdoor cables near cabinet

35

• Outdoor cables on equipment pad have G.I flexible pipe and clamps with proper distance of 200mm.

• GI Flexible pipe should be in accordance to the size of the cable

• Length of GI Flexible pipe should be at least 6 inch under the BTS/REC cabinet.

Page 36: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Outdoor cables near cabinet

36

• The protection GI Flexible should be tied with anti-cut protection.

• Silicon filling should be done at both the end of GI Flexible.

Page 37: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Cables Inlet and Outlet

37

• The cable-through holes of cabinet should be sealed properly.

• Use proper slot of Roxtec in accordance with the external diameter of cables

REC

SDR

Page 38: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Fiber Protection and Jumpers Routing

38

• The cable-through holes of cabinet should be sealed properly.

• The cable connector in cabinet fixing reliably (especially jumper).

• The pigtail should not be over tight or intersection when layout, the couple pigtail should be tied with proper force in a neat manner

• The pigtails can move freely in the strap ring, right angle of pigtails turning is strictly forbidden.

• There should be no other cable pressing on the pigtail. The pigtail bending diameter should be larger than 80mm.

• The protection hose should be tied with anti-cut protection.

No Protection Tube on Fiber

Protection Tube on Fiber

Page 39: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Labeling

39

• Power cables, grounding cables, E1 cables are labeled at both ends. These labels are pasted and marked neatly in the same position closely to 20mm away from

• All the modules and cables without manufacture labels should be labeled as per TP approved standard.

No Protection Tube on Fiber

Page 40: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

Heat-Shrink Tube

40

• The copper terminal of cable is put up with a heat-shrink tube or wrapped with at least two layers of adhesive insulating tape.

No Protection Tube on Fiber

Heat Shrink Tubes

Heat Gun Not Used

Page 41: SDR by ZTE

Telenor Vega Project

Contents

• Installation of SDR, Rectifier, Battery and IDU

• Fixing of brackets, ODU, RRU with PIMDC

• Cabling, grounding and labeling

• View and neatness of site

Page 42: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

View and neatness of the ground for distributed site

42

• The site should be clean and neat, and such sundries as waste packaging cases should be removed.

• The surplus materials such as excessive black outdoor ties, screws, and metal dross should be removed.

Removed!

Page 43: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

View of the ground for macro site

43

• The site should be clean and neat, and such sundries as waste packaging cases should be removed.

• The surplus materials such as excessive black outdoor ties, screws, and metal dross should be removed.

Page 44: SDR by ZTE

> Telenor Vega Project

© ZTE Corporation. All rights reserved.

View of the tower for distributed site

44

• Zoom in the RRU installation status on the ground clearly.

• Zoom out the tower as site tag

Page 45: SDR by ZTE

www.zte.com.cn