![Page 1: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/1.jpg)
Scrutiny Committee
13th February 2020
![Page 2: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/2.jpg)
Purpose
bristoltemplequarter.com
Bristol Temple Quarter AGENDA
• To provide an update to the Growth and Regeneration Scrutiny Committee on: o Progress on current Temple Quarter projects
o Future proposals for Temple Mead station, Temple Quarter, and St Philips Marsh o Develop a scrutiny programme for next year
![Page 3: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/3.jpg)
Overview
bristoltemplequarter.com
Bristol Temple Quarter AGENDA
• Overview of boundaries
• Vision
• Progress so far
• Emerging proposals
• Inclusive growth • Engagement
![Page 4: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/4.jpg)
Bristol Temple Quarter: Masterplan
bristoltemplequarter.com
Area Boundaries
2 km approx.
Temple Meads
Temple Island
TQEC
Glass Wharf
Fruit Market
Spark Evans Park
Holiday Inn
Paintworks
Enterprise Zone Temple Street
Area 3
Area 2
Area 1
![Page 5: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/5.jpg)
Vision
bristoltemplequarter.com
Bristol Temple Quarter AGENDA
“Our vision for the area around Temple Meads and St Philip’s Marsh is to create a sustainable, connected and flourishing quarter: a place that is welcoming to all to live, work, learn, enjoy leisure time and builds on our strengths as a world class city where everyone can share in its success.” - Marvin Rees, Mayor of Bristol
![Page 6: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/6.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Progress to date
![Page 7: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/7.jpg)
Enterprise Zone
bristoltemplequarter.com
Bristol Temple Quarter AGENDA
• Established in 2012 • Extended in 2017 • It has attracted c. 4,000 jobs • It has attracted over 150
businesses • This has been as a result of
businesses choosing to locate in the area as well as existing occupiers expanding
• Temple Quarter EZ has a target of delivering 22,000 new jobs by 2043.
![Page 8: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/8.jpg)
Engine Shed
bristoltemplequarter.com
Bristol Temple Quarter AGENDA
• A collaboration between Bristol City Council, the University of Bristol, the West of England Local Enterprise Partnership
• An enterprise hub providing workspace for a range of high-tech, creative and low carbon businesses, including Bristol SETsquared, the University of Bristol’s award-winning high-tech business incubator.
• Aims to o Drive inward investment o Create jobs o Encourage a new generation of high growth
businesses
• Expansion to the Boxworks and Engine Shed 2
![Page 9: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/9.jpg)
Engine Shed 2
bristoltemplequarter.com
Bristol Temple Quarter AGENDA
• Work continuing to progress on this key site
• Includes the refurbishment, part demolition, extension and change of use of the former Grade II Listed George and Railway Hotel
• Providing some 5,320 sq m of (GIFA) of creative office space along with cycle parking
![Page 10: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/10.jpg)
Demolition of the former Sorting Office
bristoltemplequarter.com
Bristol Temple Quarter
![Page 11: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/11.jpg)
TQEC
bristoltemplequarter.com
Bristol Temple Quarter AGENDA
• Land transferred to the University of Bristol in Jan 2020
• Site of new Enterprise Campus, providing a mix of flexible research and teaching facilities, accommodation for up to 1,500 students and a range of commercial outlets
• Campus will also include a new Quantum Technologies Information Centre and an innovation hub
• Expected to open in 2023
![Page 12: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/12.jpg)
Infrastructure
bristoltemplequarter.com
Bristol Temple Quarter AGENDA
Infrastructure delivered or being progressed to support improved connectivity and growth:
• Cattle Market Road highway improvements
• Temple Gate highway improvements
• Brock’s Bridge
• St Philips footbridge
• Harbour Walkway
• District heating
![Page 13: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/13.jpg)
Temple Island
bristoltemplequarter.com
Bristol Temple Quarter AGENDA
• Proposals for the redevelopment and regeneration of the Temple Island site are being brought forward
• Approved by Cabinet on 4th Feb 2020
![Page 14: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/14.jpg)
Temple Meads Station
bristoltemplequarter.com
Bristol Temple Quarter AGENDA
• Capacity improvements delivered in 2018, including new gate lines
• Funding approved for maintenance and refurbishment of historic roof
• Timetable change and introduction of faster trains to London, and 20,000 extra weekday seats
![Page 15: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/15.jpg)
Masterplan
bristoltemplequarter.com
Bristol Temple Quarter AGENDA
• Study commissioned to develop long term proposals for the area by developing a high quality, deliverable, flexible and phased masterplan, focused on and around Bristol Temple Meads station,
• Building on previous work
• Underpinned by a robust delivery plan.
• This study is ongoing and is due for completion by summer 2020.
![Page 16: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/16.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Emerging Proposals
![Page 17: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/17.jpg)
Bristol Temple Quarter: Masterplan
Area 1 - Northern Gateway • 65% of current passengers use this entrance
• Enhanced subway stair access and gatelines to remove
the existing pinch point and increase capacity
• A new concourse to the station, including enhanced retail, ticket office and passenger facilities
• An improved bus interchange
• Relocation and improvement of cycle parking facilities
• Relocation of car parking to facilitate construction of the entrance and improve the environment of the station
• New forecourt to improve the public realm and ensure safety of passengers
• A relocated drop off facility
![Page 18: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/18.jpg)
Bristol Temple Quarter: Masterplan
Area 1 - Interchange
![Page 19: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/19.jpg)
Area 1 - Eastern Entrance
Bristol Temple Quarter: Masterplan
bristoltemplequarter.com
• Create a new eastern entrance to the station from the existing passenger subway
• Opening out onto the University of Bristol’s new Enterprise Campus
• Unlock connectivity to the east of the city, improving access to good transport links
• Design work underway
• On site planned for 2021
• Works complete in 2022
![Page 20: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/20.jpg)
Area 1 - Potential for new ‘Southern Gateway’
Bristol Temple Quarter: Masterplan
bristoltemplequarter.com
• Unlocks development of the station and Temple Quarter • Potential to be southern gateway and transport interchange
from the A4
• Potential for significant cycle hub
• Potential for direct station access
• Potential for commercial uses
• Real term reduction in parking provision
• Safeguarding vision for future of the site, delivered through incremental change
![Page 21: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/21.jpg)
Potential ‘Southern Gateway’ next steps
Bristol Temple Quarter: Masterplan
bristoltemplequarter.com
• Specification to be developed, considering:
o Multi-use functionality of site/ building
o Long term adaptability of the building
o Access to station, levels, gate line
o Planning, heritage and highways
• Funding mechanism(s)
• Delivery model
• Operating model(s)
![Page 22: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/22.jpg)
Area 1 – Internal station passenger routes
bristoltemplequarter.com
Bristol Temple Quarter AGENDA
• Detailed pedestrian flow analysis has highlighted capacity constraints for passengers moving through the station with projected increases in demand
• A number of options have been reviewed and tested to improve the movement and safety of passengers, including enhancements to subways and new pedestrian bridges
• Options must be further tested and consultation must take place before a preferred option is selected in the next design stage
![Page 23: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/23.jpg)
Area 1 – Further station works
bristoltemplequarter.com
Bristol Temple Quarter AGENDA
A number of further interventions have been identified to increase capacity in the station to meet expected future demand, and to improve passenger facilities and safety, including:
• Platform improvement works, including additional platform passenger facilities
• Platform extensions
• Track and signalling works Delivery timescale for all station components will be up to 15 years
![Page 24: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/24.jpg)
Bristol Temple Quarter: Masterplan
Bristol Temple Meads
Platform Improvement Works:
(Signal alterations, platform extensions, canopies,
passenger facilities)
New Platforms 0/1
Circulation Enhancements 1:
(New Southern Internal Bridge)
West junction Remodelling:
(Track and signalling works)
Circulation Enhancements 0:
(Platform 13/15 Works: Incl. platform
widening, track works and canopy
extension/widening)
Northern Gateway:
(transport interchange, revised
pick-up / drop-off, creation of new
arrivals hall, retail, public realm,
platform access, parking partial
relocation)
Southern Gateway:
(station entrance, transport interchange, extensive
cycle parking, full relocated parking (mobility
impaired, train crew, passengers)) later reuse.
Eastern Entrance:
(New entrance through passenger subway)
bristoltemplequarter.com
![Page 25: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/25.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Area 2 – Friary
Land use • Primarily commercial • Residential block Eb • High quality cycle hub facility integrated within block Ea • Some F&B and retail Area characteristics • Local centre • Animated public realm supporting an 18 hour economy • Public square, Brunel Mile • Quality of people movement • Excellent transport links Phasing/ delivery • 2025 - 2029 Viability • Positive residual land values • Land in public ownership • Could be market led
![Page 26: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/26.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Area 2 – Friary
![Page 27: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/27.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Area 3 – St Philips Marsh
• Full development of St Philips Marsh likely to be longer term, with significant investment required. Key considerations:
- Flood risk
- Existing employment land
- Land assembly
- Planning context
• In the meantime:
- Innovation repurpose/ increased jobs density
- Meaningful and interesting meanwhile use
- Progress flood strategy other infrastructure requirements
- Progress studies for earlier site delivery
- Ongoing engagement with neighbouring communities
- Engagement with businesses/ employment strategy
- Land assembly
- Governance, delivery vehicles, funding for investment for longer term regeneration
![Page 28: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/28.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
The UK’s 1st Climate Adapted
INNOVATION DISTRICT
NANO
ENGINEERING/
MANUFACTURI
NG
BUSINESS
SYNERGIES
BEST IN
CLASS
NEIGHBOURS
EXCELLENT
CONNECTIVITY
A BRISTOL
PLACE
NEW WORK
SPACE
TYPOLOGIES
ADAPTABLE
STREET
BLOCK
STRUCTURE
ECONOMIC ASSETS
NETWORKING ASSETS
PHYSICAL ASSETS
INNOVATION ECOSYSTEM
![Page 29: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/29.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
ADAPTIVE REUSE
![Page 30: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/30.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Inclusive Growth
![Page 31: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/31.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Inclusive Growth
• Economic – ‘jobs’ – working with developments that are coming forward, creating employment, good quality jobs/ on site skills academy, utilizing the pipeline through planning, inward investment, linking with Economic Development and job brokerage.
• Physical – ‘connectivity’ – access to area and jobs, ensuring proposals coming forward connect community to city and reduce severance, overcome physical and perceived barriers, leveraging contributions to create improvements
• Social – ‘ownership/ change perception’ – informed on city developments coming forward, engaged on city issues linking to physical environment, upskilled in planning, design & development, ownership/engagement/employment in meanwhile projects
![Page 32: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/32.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Potential Area 1 & 2 Outcomes
3,300
Significant benefits to be enabled through current planned developments, including TQEC, Temple Island, Engine Shed 2 and other schemes currently in the planning system
70,000
![Page 33: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/33.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Inclusive Growth - Economic
Aims: • Creating the conditions for investment • Developing the offer for inward investors, including marketing • Supporting existing local businesses • Achieving local benefit to surrounding areas
Comprehensive approach to employment: • Managing the pipeline of schemes and employment opportunities coming forward • Considering short, medium and long term jobs, including apprenticeships • Identifying and addressing skills gaps • Linking people to education and employment services
![Page 34: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/34.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Inclusive Growth – Physical connections to neighbouring communities
![Page 35: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/35.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Inclusive Growth – Social
![Page 36: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/36.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Social Inclusion - Commercial
![Page 37: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/37.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Meanwhile – Environmental/ Educational
![Page 38: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/38.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
The Considerate Contractor – Construction Charter
![Page 39: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/39.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Engagement
![Page 40: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/40.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Engagement
![Page 41: Scrutiny Committee th February 2020 - Bristol · 2020-02-05 · Enterprise Partnership • An enterprise hub providing workspace for a range of ... • Animated public realm supporting](https://reader033.fdocuments.in/reader033/viewer/2022050203/5f56aa1ecca1835714750710/html5/thumbnails/41.jpg)
bristoltemplequarter.com
Bristol Temple Quarter
Engagement
• Two rounds of engagement successfully undertaken (Jan - Feb 19 and Sep – Nov 19) with local community groups, businesses, transport networks and other key stakeholders, including an online survey
• Over 900 people engaged, with feedback incorporated into emerging proposals
• Further stages of engagement to take place • Objectives for next stage of engagement:
o Keep existing external stakeholders informed about the next steps and engaged in the project so they
understand the benefits/opportunities of the project and how they can influence future stages
o Engage groups not previously involved (particularly in local communities)
o Engage existing businesses and establish mechanism for continued engagement
o Raise the profile of the vision and opportunities embedded in the Masterplan
o Raise the profile of Masterplan projects due to start in 2020/21
o Develop proposal for on site meanwhile use for continued engagement and to sign post to jobs and opportunities