Screwed steel pile NS ECO-PILE Foundation Structure ECO... · NS ECO-PILE is a steel pile with a...
Transcript of Screwed steel pile NS ECO-PILE Foundation Structure ECO... · NS ECO-PILE is a steel pile with a...
Screwed steel pile NS ECO-PILETM
Building and Civil Engineering Method ofNIPPON STEEL & SUMIKINENGINEERING
Foundation Structure
Warnings
The technical information contained in this document explains typical characteristics or performances ofproducts and does not constitute any guarantee or endorsement except for the items listed as "Specification."
We shall not be responsible for any damage or loss resulting from incorrect or inappropriate use of theinformation contained in this document. The information in this document may be changed withoutprior notice.Please contact our section in charge for the latest information.
No unauthorized reprinting or reproduction of any information contained in this document is permitted.
Osaki Center Bldg., Osaki 1-5-1, Shinagawa-ku, Tokyo 140-8604http://www.eng.nssmc.com
This document is printed on 100% recycled paper of 82% whiteness.Cat.No.KC330 2013.11版
Screwed Steel P i le
NS ECO-PILE
○○○改 1 大
Large bearing capacityA large vertical bearing capacity is generated by theconsolidation effect of the ground as the pile is screw-driven into the ground and the base enlarging effect ofthe blade as the blade rotates to drill the ground.
Low noise and low vibrationThe screw piling method with a pile driver or casing rotatorcauses no impact when driving a pile into the ground,minimizing noise and vibration during construction.
No waste soilBy screw-driving the pile without excavating the ground,no waste soil is produced.
Overview of NS ECO-PILE
What is NS ECO-PILE?
Structure of NS ECO-PILE
Construction compared with conventional pile method
Many Advantages
Most of the major cities in Japan are built on alluvial plains at thelower reaches of the rivers. Since alluvium is typically soft ground,structures such as high-rise buildings or expressways need to besupported by piles long enough to reach the hard ground base.Industrial waste such as waste soil or slurry as well as noise andvibration arising during the conventional pile construction methodcreate environmental and social problems. NIPPON STEEL& SUMIKIN ENGINEERING's NS ECO-PILE solves all theseproblems and realizes high bearing capacity, excellent earthquakeresistance, cost effectiveness and shorter construction period.This is the piling method of the future.
NS ECO-PILE is a steel pile with a helical blade welded to theedge. During construction, a pile driver or casing rotator, forexample, rotates the pile, and the blade on the edge performs thedigging that drives the pile into the ground like a wood-screw.
Conventional pile
Driven pile: noise and vibration problems
Conceptual illustration of screw piling
1
p.2 p.3
Characteristics
1
2
Blade diameter (Dw)● ●
Short pipe for edge blade part (the wall can be thicker than that of the lower blank pipe)
Lower blank pipe
Pile diameter (Dp)● ●
Blade
Blade diameter● ●
Note
The maximum difference in wall thickness betweenconnecting blank pipes should be 7 mm or less. When blank pipes of different thickness areconnected,a thick wall part should be considered tomitigate stress concentration. The length of thepart inside the blank pipe shall be not less than4(t1-t2). When (t1-t2) is not more than 2 mm, orwhen (t1-t2) is not more than 3 mm in the case ofboth-side welding of the shop circumferentialweld, the cutting may be omitted.When the site circumferential weld of a pile isconnected to another pile, the wall thickness ofthe piles should be the same.
*1 Temporary pieces for dummy piles may beinstalled inside the steel pipe.
*2 Temporary pieces for chucks are used when pile driving penetrating with a three-point pile driver.
Edge blade part
●
●
Blade
Shopcircumferentialweld
Site circumferential weld(welding of blank pipes of the same thick)
Temporary piece for dummy pile*1
Shop circumferential weld (welding of blank pipes of different wall thickness)
●
●
●
●
●
●
●
Site circumferential weld(welding of blank pipes of the same thick)
●
●
Shop circumferential weld
Cutting edge
Rd= Dw is called the blade diameter ratio.Dp
Hanging hook
Cast-in-place pile:Disposal of slurry and waste soil;sludge; and possible collapse of thebored hole wallBored pile: Disposal of slurry and waste soil; orreduction in the bearing capacity at thebottom due to loosening of the ground
2
3
Large pulling resistance capacityA large pulling resistance capacity is maintained asthe passive soil resistance, which acts on the bladepart as propulsive force as the pile penetrates into theground, is wholly turned into pulling resistance.
4
High qualityAt the final embedment stage, the bearing layer canbe confirmed by the torque, thus constructing a pilefoundation of excellent quality and reliability.
5
Excellent earthquake resistanceThe steel pile foundation is highly resistant to deformationand earthquakes.
6
RecyclingTo remove a pile, it is rotated in the direction opposite tothat when driven, allowing easy recycling of usedpiles. NS ECO-PILES can thus also be used astemporary piles.
7
Short construction periodSince this method uses no concrete or cement milkand therefore does not need to wait for hardening, theconstruction period is far shorter than for cast-in-placepiles or bored piles.
8
Low costThanks to their large bearing capacity, piles of asmaller diameter or fewer piles can be used, thusreducing the size of the footing itself. In addition, costsare lower since there is no need to dispose of slurry orresidual earth and the construction period is shorter.
9
Proximity workAs the method drives piles without excavating theground, the subterranean soil around the piles is notloosened. Therefore, pile-driving can be performedwithout affecting the foundation or buried pipes of anexisting structure nearby.
10
Batter pilesUnlike cast-in-place piling, the method drives pileswithout excavating the ground and so there is no risk ofcollapse of the bored hole wall. In the field of structuraldesign, batter piles can reduce the number of pilesmore economically than vertically straight piles.
11
Small area or under height restrictionsThe equipment for pile driving is small and so themethod can be used in small area such as sitesadjacent to existing structures. For example, piles can bedriven by a casing rotator at a site with limited overheadclearance such as under an elevated bridge or aerialwires.
123 Construction Machinery
Major construction machines used with NS ECO-PILE Method
Type Machine Specifications, standard, etc Remark
Constructionmachine 1
Structure of NS ECO-PILE
Upper blank pipe A
Temporary piece for chuck*2
Temporary piece for chuck*2
Upper pile
Middle pile
Lower pile
Casing rotator, 1500 class Maximum torque: 1150 kN・m (117 t・m) φ500 to φ600 mm in dia. (standard outside pile diameter)
φ700 to φ1200 mm in dia. (standard outside pile diameter)
φ1300 to φ1600 mm in dia. (standard outside pile diameter)
400 mm or less in dia. (standard outside pile diameter)
Maximum torque: 2070 kN・m (211 t・m)
Maximum torque: 5100 kN・m (520 t・m)
Maximum torque: 250 kN・m (25.6 t・m)
Casing rotator, 2000 class
Casing rotator, 2600 class
Three-point pile driver/Compact pile driver
Constructionmachine 2
Type of crane Crawler crane Capacity selectable as required Used for pile installation or heavy machinery relocation
Used for backfilling a vacant hole (after removing the temporary pile)Backhoe
Upper blank pipe B
2
p.5
1
Moving of heavy machine (setting of casing rotator)
Installation of lower pile
Driving of lower pile (screw piling)
Driving of lower pile (screw piling)
Driving of upper pile (screw piling)
Driving of middle and upper pile (screw piling)
Installation of middle / upper pileand site circumferential welding
Installation of middle pile andsite circumferential welding
Driving of dummy pile andpiling completion
Driving of dummy pile andpiling completion
Installation of a lower pile, checking and adjustment of verticality
Setting of deflection stopper andadjustment of verticality
Crawler crane
Middle or upper pile
Blade
S T E P - 1 S T E P - 2 S T E P - 3 S T E P - 4 S T E P - 5 S T E P - 6
▲ ▲ ▲ ▲ ▲
Schematic diagram of NS ECO-PILE (casing rotator) procedure
Schematic diagram of NS ECO-PILE (three-point pile driver)
Casing rotator
Deflection stopper
Blade
Auger
Three-point pile driver
Lower pile
Blade
Middle pile
p.4
Construction Procedure
NS ECO-PILE procedures
Construction
Example of Machine Layout
▼ Diagram of the necessary distance during proximity construction
▼ Example of layout when casing rotator is used
Screwed steel pipe pile
Crawler crane
Backhoe
Operation house
Hydraulic unit
Reaction bar
Crawler crane
Casing rotator, φ2000 class
Casing rotator, φ2000 class
Reaction bar
Operation house
Hydraulic unit
Backhoe
Casing rotator, φ2000 class
Crawler crane
Screwed steel pipe pile
Operation house
Hydraulic unit
Backhoe
For pile outside diameter of 1,200mm or less andcasing rotator with boring diameter of φ2,000 class
For pile outside diameter of 1,200mm or less andcasing rotator with boring diameter of φ2,000 class
3
▼ Example of layout when 3-point pile driver is usedBackhoe
Crawler crane
Three-point pile drier
When the leader is assembled
Material and machine yard Screwed steel pile stock yard
Spiral collar(for casing rotator)This is used to insert an NS ECO-PILEfrom above the machinery (patent no.3484653)
Special Jigs for NS ECO-PILES
For driving NS ECO-PILES, the following jigs are used inaddition to the major machines:
Dummy pileA dummy pile is used when the pile head is lower than the working ground level.
Temporary pieces for dummy pileProtrusion on the pile head on which to apply torque to NS ECO-PILE
Start
Preliminary survey
Execution plan
Selection of construction machines
Driving of test pileforⅠ=1 to n
Setting of piling machine
Installation of lower pile
Installation of upper pile
Verticality adjustment
Screw piling
Welding of piles
Screw piling
Confirmation of the capacity of construction machines
Welding inspection
Confirmation of torque
Change
A
No
Yes
No
Yes
End
Completion of the screw piling according to the flow for piling completion
nextⅠ
B
C
n: no. of piles
Start of screw piling
Completion of the screw piling
Is the pile drivento the design depth?
Screw piling while controlling adequate torque
(working torque lower than the managed upper limit torque)
Yes
Yes
Yes
Is the additional pipe lengthbelow the permitted value?
To To
Yes
Yes
No
No
No
No
Yes
No
No
a
b
c
c c
Has the bearing layerbeen confirmed?
Is the embedment into the bearing layer 1 Dp or more?
Consultation withsupervisor
(to determine, for example, to finish piling
by confirming the working torque)
Confirmation of thebearing layer depth
Is the difference in lengthbelow the permitted value?
Confirmation of the difference in length between actuallength and design length
Continuation of piling(notification to the supervisor)
Consultation withsupervisor
(about considering pile splicing, for example)
Comparison between boring dataand working torque record
Is it appropriate to judge that the bearing layer is reached at that depth?
(notification to supervisor)
Review of the possibility of
buried obstacles
Consultation withsupervisor
(about removing obstacles, for example)
Consultation withsupervisor
(about cutting the steel pipe, for example)
Confirmation of thebearing layer depth
Confirmation of theadditional pile length
p.6 p.7
430
Bottom pile
1~4
Root interval keeping bead or spacer
6 t
0~2.4
t
45°min
25
35
H(
h (
Backing ring(field installation)
T
Top pile
Stopper number(shop assembly)
N
A:Driving of test pile
Example of shape and dimensions of backing ring and stopper
Flow of Construction Management
Construction
Fluctuation of working torque is used for allpiles to check whether a pile has reached thebearing layer. A test pile is driven at each site todetermine the management method to confirmarrival at the bearing layer, and the basiccriterion for completion of piling is when thepile is embedded into the bearing layer to adepth equivalent to the pile diameter (1 Dp) ormore.
Test piles are driven to confirm the degree ofworkability of the actual ground condition at thework site, adequacy of machines selected, and thestatus of torque generation. By comparing the status oftorque generation and the results of boring data, thetorque fluctuation which confirms arrival at the bearinglayer is determined.The number and location of test piles are determined tosuit the position of the boring exploration point and thescale of the number of piles. Some initial permanentpiles may be used as test piles in the vicinity of theboring exploration point.
B:Site circumferential weld
Piles are generally connected with welded joints.The backing ring should be that of a standard jointspecified by the Japanese Industrial Standard (JIS A5525).
Welding work
C:Management of the piling completion
●
Actual bearing layer level
●
flow for piling completion
1...When the actual level is closer to the expected level
Expected (design)bearing layer level
2...When the actual level is deeper than the expected level
3...When the actual level is shallower than the expected level
In the standard procedure, a pile is screwed to the design depth and piling is completed when the pile isembedded into the bearing layer to a depth of 1 Dp or more. But when there is a difference between thedepth of the bearing layer determined by a fluctuation of working torque and the depth of the bearing layerdetermined at the time of design or when the bearing layer is a very hard stratum, the piling can becompleted at a depth shallower or greater than the design depth.
The bearing layer is generally confirmed by the fluctuation of working torque for judging the bearing layerdetermined by the test pile, but if the bearing layer is shallower than expected, it may be difficult topenetrate the pile to the design depth. In such cases, piling is sometimes completed at a depthshallower than the design depth if it can be confirmed that the pile has penetrated the bearing layer to asufficient depth (1 Dp or more) and that torque has been generated.
If the bearing layer is too hard to drive a pile to a depth of 1 Dp or more, piling can be completed at anembedment depth of less than 1 Dp providing it can be confirmed that torque has been generated.