Scott Transit Plaza Project Presentation Update 12 09 10

download Scott Transit Plaza Project Presentation Update 12 09 10

of 18

Transcript of Scott Transit Plaza Project Presentation Update 12 09 10

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    1/18

    Grand Boulevard Bridge Present

    Narrow sidewalks

    Six undivided

    traffic lanes

    Bus stops in

    traffic lane No shelter forMetro

    customers

    Grand Blvd.

    (looking north)

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    2/18

    City of St. Louis replacing Grand Boulevard

    Bridge in 18 months.

    $24m bridge + $7.3m Metro project = $31.3mimprovements to Grand Boulevard corridor

    6 traffic lanes reduced to 4 divided lanes.

    Sidewalk upgrade and better pedestrian

    accommodations and connections.

    Signature bridge for St. Louis.

    Safe, well-lit, aesthetically-pleasing

    Designed by HDR

    Grand Boulevard Bridge Project

    Beginning Early 2011

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    3/18

    Grand Boulevard Bridge:An early rendering of the new bridge.

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    4/18

    Metro-related bridge improvements

    Bus pullouts added currently busesstop in the traffic lanes.

    Wider, more pedestrian-friendly

    sidewalks installed.

    Elevator towers moved north to a better

    location. Attractive, spacious wind and rain

    shelters for Metro customers .

    Metro-Related Bridge Improvements

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    5/18

    Scott Avenue

    Elevator Tower

    Bus Shelters

    Platform Access

    on east end

    On-street

    parking

    Grand MetroLink Station: Present

    North

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    6/18

    $7.3m Metro project: Change patron access

    from east to west end

    of platform.

    Move elevator towersfor better visibility.

    New stairs & elevators.

    Add parking lot.

    New Horner & Shifrin-designed plaza (with the Lawrence

    Group) and waiting area for Metro customers.

    Construction schedule dependent on Citys bridge

    demolition schedule.

    Grand MetroLink Station Project

    Current crossing with on-street

    parking in the background.

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    7/18

    Create unobstructed view

    and improve line of sight onthe platform by moving the

    elevator towers.

    New pedestrian

    crossing area on westend of platformGrand Boulevard bridge

    MetroLink Platform Improvements(looking west)

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    8/18

    On-street parking willbe replaced.

    Removing some

    existing freight trackthat is no longer used

    to make room for

    parking lot. New lot with 50-70 car

    capacity.

    A New Park-Ride Lot

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    9/18

    New Transit Plaza

    Artist Barbara Grygutis was involved with thedesign for a visually striking plaza with lighted

    sculpture artwork.

    Goal: Provide a comfortable, well-lit and attractivewaiting and service area for customers that

    enhances the Grand Boulevard corridor.

    Project adds new upgraded shelters, seating,

    landscaping, and both decorative and functionalfences.

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    10/18

    Project Area

    Old piers will beremoved.

    (looking north)

    New transit plaza will be

    constructed under the

    bridge when the old

    piers are removed.

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    11/18

    Elevator

    Tower and

    Stairs

    DecorativeFencing

    Seating

    Wall

    New Parking Lot

    MetroLink platform

    Relocated AccessVending Area

    Transit Plaza Design

    North

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    12/18

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    13/18

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    14/18

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    15/18

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    16/18

    Design includestranslucent blue

    stones lit from

    beneath by LED lights

    Colored paving, decorative

    fence, and landscaping create

    organic and welcoming space

    Plaza Art Elements

    19

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    17/18

    Wind and rain shelter

    preliminary rendering.

  • 8/8/2019 Scott Transit Plaza Project Presentation Update 12 09 10

    18/18

    Project Benefits

    Improve Grand Boulevard streetscape andconnections with upgraded facilities for patrons.

    Create a well-lit, pleasant, comfortable experience

    for Metro customers traveling to Grand Center.

    Improve platform visibility & comfort: Remove

    elevator towers & change platform access.

    Provide new bus plaza with seating, shelters, and

    service amenities.

    Add park and ride lot for 50-70 cars.