Scope & Cost Management with P6
A proven way to increase quality & efficiency
9. Primavera Community Day 2016
17. März 2016 Zürich
Hännes Gnädinger (JG) & Sebastian Schweinle (Siemens)
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 2
Scope & Cost Management with P6
The challenging solutions business
Enable the validation of performance to predict a reliable result
1. Paradigm shift: Prepare execution in tendering
Ensure handover of consolidated orders and scheduled key documents
2. Track progress with scheduled key documents
Ensure timely installation
3. Improve competitive advantage continuously
Take advantage of re-use and lessons learned
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 3
The challenging solutions business
Are we able to apply Earned Value Management to validate the cost
and schedule performance in order to predict a reliable result?
The PwC survey shows
62% say that EVM contributes to project success
73% say that EVM is a useful tool to predict success
In companies where EVM tools are used, projects meet their scope
criteria 82% of the time, quality criteria 84% of the time and benefits
targets 80% of the time.
Why is EVM still not used widely?
PwC: PricewaterhouseCoopers
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 4
The challenge: Apply EVM
What prevents EVM?
Project controlling disclose the development of costs not directly related
to work progress.
The disciplines at the locations disclose the work progress without direct
reference to the cost and without the view of the entire project.
Challenge: How to measure and validate the cost and schedule
performance directly related to work progress?
The big potential of earned value management is the right team behavior
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 5
Basics
We want to predict a reliable result based on cost and time performance.
We achieve this if we are able to determine the “Earned Value Cost“.
This requires a systematic approach and supporting SW solutions.
Primavera P6
Make use of the potential of Scope & Cost Management with P6
Forecast
Scope & Cost Management
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 6
Manage dependencies in order to validate
SCOPE Structure
Functional Units P1, P3
Controlling
Equipment OrderScope Item P1-133Scope Item P3-133
Engineering OrderScope Item 133Scope Item xy
Order Management
Scope Items P1-133 & P3-133
PROGRESS
Scheduled key documents
Earned Value Management
Cost & schedule performance validation
Customer
Specification
!
COST
Planning & Control
Functional Unit P1Scope Item P1-133
Functional Unit P3Scope Item P3-133
Order EngineeringScope Item 133
TIME
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 7
Progress: Focus on the critical success factors
What is always critical?
Exchange of right information on time between suppliers and layout planning.
Deliver material/documents and complete civil works for timely installation.
Plan in both directions to ensure timely installation
What should be introduced?
The common language to get the necessary transparency for the information
exchange.
Ein typisches Vorkommnis:
Eine Firma lieferte zwei Kompressoren
in den Ural. Bei der Montage musste
man feststellen, dass die Raumluft-
versorgung zur Kühlung der
Kompressoren vergessen wurde.
Resultat: Terminverzug, Mehrkosten
beim Kunden (Civil Scope) und
Vertrauensverlust.
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 8
Secret of success: Introduce a common language
SCOPE
Structure
PROGRESS
TIMECOST
Common Language: Scope Structure …
… to control orders with scheduled key documents
Quality & Efficiency
will increase significantly
PERFORMANCE
Track progress of orders with scheduled key documents
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 9
Make use of our 30 years experience
In 2012 we have won the Siemens innovation award with Scope & Cost Management
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 10
Example
Project scope structure
Scope configured to consolidate orders
Order 133
System Engineering
Equipment & Order Engineering
Scope Items of Functional Unit
Concept Engineering
Functional Unit P1
Order 133
Functional Unit P3
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 11
Example cost structure
Consolidated orders to calculate and follow up
Scope organized to manage orders
Scope Item
Order
Cost calculation equipment
Cost calculation engineering
Scope Item
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 12
Example time scheduling
Set target dates, plan resources, and control
Systems/Layout
Functional Unit P1 Equipment Scope Item 133
Connection Mat.
Civil Works
Erection
Functional Unit P2 Aux. System
Civil Works
Erection
Functional Unit P3 Equipment Scope Item 133
Connection Mat.
Civil
Erection
HW / Order Engin.
Concepts
Project Scope Structure
Purchasing Design & Manufacturing Transport Erection Commissioning
Engineering Procurement Construction
Concept / Basic / Detail
Order 133
Erection P3
Packing Lists
Completion
Certificate
Handover
Protocol
Inquiry Doc
Issue 1
Order Doc
Studies & Concepts
Test
Report
Techn./Commercial Spec.
Payment Milestones
PaymentMilestone
Start Finish
Progress Payment
Gate Review
% completed?
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 13
Example document control
Track progress
Master Document List to plan and control services & supplies of orders
Scope Item
Progress for “% of completion”
Document Set
Key document folder
Document folder
Document
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 14
Example earned value management
Validate performance and determine forecast
0.6
1.13Gate 1
Forecast
0.98
1.14Gate 2
Margin
Margin
TimeTime
Validation
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 15
Benefit of Scope & Cost Management with P6
Final Margin >10%
6% - 12% Savings of EPC Full Cost 1)
Consequent document control will
• reduce 3rd party order costs by 10% to 20%
(2,5% - 5% of EPC Full Cost)
• eliminate accelerating costs
(3% - 5% of EPC Full Cost)
Scope & time transparency at interfaces will
reduce non conformance cost by 10% to 20%
(1% - 2% of EPC Full Cost).
1) Experience of turnkey power plant provider
Solid margin at contract date
Quality & Efficiency
increased significantly
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 16
Conclusion: Structure scope to apply EVM
Scope & Cost Management with P6 ensure future success
0.6
1.13Gate 1
Forecast
0.98
1.14Gate 2
Margin
Margin
TimeTime
Validation
Gate Reviews
Scope Structure
Divide a big problem into
small ones, in order to
discover dependencies.
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 17
Scope & Cost Management with P6
Feed Primavera P6 with Scope Structure and Orders
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 18
Scope & Cost Management
Configure scope in order to feed P6
Project Scope Structure
Scope items allocated to manage orders
Order Basket
COST
SCOPE
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 19
Scope & Cost Management with P6
Feed P6 WBS with Scope Structure
Target Dates
- Standard project schedule including
- Scope Items
- Costs
- Time Schedule
- Resources
- Documents
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 20
Scope & Cost Management with P6
Add documents to scope items
Documents
- Items and their related documents maintained
as activities
- Responsibility maintained globally
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 21
Scope & Cost Management with P6
Feed P6 with cost structure to manage order baskets
Costs
- “Resource Assignment View” changed to show
- Resource UDFs including
- Order Baskets
- Items
- Planned Costs
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 22
Scope & Cost Management with P6
Maintain scope items of order baskets
Scope Items (master data)
- Created as material resources
- Item attributes maintained
- Additional information maintained as UDF or Code
Restricted @ Engin. Office J. Gnädinger 2015 All rights reserved
JGIngenieurbüro
Page 23
Competitive advantage in global solutions business