8/11/2019 SCHM 2301 Case Analysis
1/20
Sonnies Gourmet Sand
CafeAllison Davis and Taylor Aguilar
-
8/11/2019 SCHM 2301 Case Analysis
2/20
Popular new casual restaurant
Located in an outdoor shopping center
Prime lunchtime hours are 11:30 AM - 1:30 PM
Menu:
o 9 standard sandwiches
o Build your own sandwich option
o Side of chips or 4 types of salads
Background Info
-
8/11/2019 SCHM 2301 Case Analysis
3/20
Service Process Matrix
-
8/11/2019 SCHM 2301 Case Analysis
4/20
Part 1: Order Placement Proces
1. Customer enters cafe
2. Employee greets customer and fills out two part paper
order form
3. Employee gives top part of order form to customer and
gives bottom part to the next employee
4. Greeter employee fills beverage order
5. Customer walks to cashier and pays
6. Customer waits for order
-
8/11/2019 SCHM 2301 Case Analysis
5/20
Blueprint 1 - Order Placement
-
8/11/2019 SCHM 2301 Case Analysis
6/20
Part 2: Order Fulfillment Proces
1. First employee puts side on the plate
2. First employee assembles bread, meat and cheese
3. Second employee adds topping and sauces
4. Second employee slices the sandwich
5. Third employee checks for accuracy
6. Third employee moves sandwich to pick-up area, calls custom
-
8/11/2019 SCHM 2301 Case Analysis
7/20
Blueprint 2 - Order Fulfillment
-
8/11/2019 SCHM 2301 Case Analysis
8/20
Current Rate of ServiceStart Order Time
Custom Sandwich = 80 seconds
Standard Sandwich = 60
seconds
Average Start Order Time
80 seconds + 60 seconds =70 seconds
2
Entire Service TimeCustom Sandwich = 415 seconds
Standard Sandwich = 395 seconds
Average Entire Service Time
415 seconds + 395 seconds = 405 seconds
2
Customer Orders St
3600 seconds per hour = 51 c
70 seconds
However, there are a number of cu
orders will be started, but not be fi
there is not enough time within the
order to be completed. There are 4
the hour that orders will be place b
Orders Started, But Not C
405 seconds unavailable
70 seconds (start order)
Completed Customer
51 customer - 6 orders starte
customers
-
8/11/2019 SCHM 2301 Case Analysis
9/20
Line Balancing 1 - Order Placem
-
8/11/2019 SCHM 2301 Case Analysis
10/20
Line Balancing 2 - Order Fulfillm
-
8/11/2019 SCHM 2301 Case Analysis
11/20
-
8/11/2019 SCHM 2301 Case Analysis
12/20
Line Balancing Equations
Takt time = available production per day/output needed per da
Takt time = 120 minutes/40 customers = 3 minutes per wo
(max)
Theoretical number of stations (N) = total number of task times
Theoretical number of stations (N) = 6.75/3 = 2.25 = 2 sta
Efficiency = Sum of all task times/(actual work stations x takt ti
Efficiency = 6.75/(5 x 3) = .45 x 100 = 45%
-
8/11/2019 SCHM 2301 Case Analysis
13/20
Recommendation 1
Eliminate workstation 2
Move cashier behind the counter near the
greeter employee
Benefits:
o Decrease process 1 minute and 30
seconds
o Takes away cashiers idle time of 0.33
minutes
-
8/11/2019 SCHM 2301 Case Analysis
14/20
Blueprint 1 - Order Placement
-
8/11/2019 SCHM 2301 Case Analysis
15/20
Line Balancing 1 - Order Placem
-
8/11/2019 SCHM 2301 Case Analysis
16/20
Recommendation 2
Eliminate Workstation 3
Workstation 2 now will complete
tasks C-F
Benefits
o Decreased idle time from
workstation 2 and 3
-
8/11/2019 SCHM 2301 Case Analysis
17/20
Blueprint 2 - Order Fulfillment
-
8/11/2019 SCHM 2301 Case Analysis
18/20
Line Balancing 2 - Order Fulfillm
-
8/11/2019 SCHM 2301 Case Analysis
19/20
Results
Increase efficiency by 2%
Decrease sandwich making time on average from 6.75 to 5.25
o Decrease waiting time
o Yield more working professionals
Will be able to serve 1 more customer per hour
Save on labor costs because one less employee needed
-
8/11/2019 SCHM 2301 Case Analysis
20/20