Scheduling/Leveling Report - 17-Nov-15 - PM.exe===============================================
Default Project..................................................NEWPROJ-2
Projects: NEWPROJ-2.......................................................
.PLANNING ENGR
Scheduling/Leveling Settings:-----------------------------
General-------Scheduling ......................................................YesLeveling ........................................................YesIgnore relationships to and from other projects .................NoMake open-ended activities critical .............................NoUse Expected Finish Dates .......................................YesSchedule automatically when a change affects dates ..............NoLevel resources during scheduling ...............................YesRecalculate assignment costs after scheduling ...................NoWhen scheduling progressed activities use .......................Retaine
d LogicCalculate start-to-start lag from ...............................Early S
tartDefine critical activities as Total Float less than or equal to .0Compute Total Float As ..........................................Finish
FloatCalendar for scheduling Relationship Lag ........................Predece
ssor Activity CalendarPreserve scheduled early and late dates..........................YesLevel resources only within activity Total Float.................NoLevel Priority 1.................................................Activit
y Leveling Priority - AscendingLevel all resources..............................................Yes
Advanced--------Calculate multiple float paths...................................No
Statistics:-----------
# Projects.......................................................1# Activities.....................................................14# Not Started....................................................14# In Progress....................................................0# Completed......................................................0# Relationships..................................................0# Activities with Constraint.....................................0
Errors:-------Warnings:---------
Activities without predecessors..................................14Project: NEWPROJ-2 Activity: A1002 BLINDING
CONCRETEProject: NEWPROJ-2 Activity: A1003 R.C FOOT
ING
Project: NEWPROJ-2 Activity: A1004 GARDE BEAMS AND WATER TANK
Project: NEWPROJ-2 Activity: A1005 GARDE BEAMS AND WATER TANK
Project: NEWPROJ-2 Activity: A1006 GARDE BEAMS AND WATER TANK
Project: NEWPROJ-2 Activity: A1007 GARDE BEAMS AND WATER TANK
Project: NEWPROJ-2 Activity: A1008 1ST FLOOR COLUMS
Project: NEWPROJ-2 Activity: A1012 EXCATION WORK
Project: NEWPROJ-2 Activity: A1013 BACKFILLING
Project: NEWPROJ-2 Activity: A1180 WATER PROOFING FOR FOOTING
Project: NEWPROJ-2 Activity: A1190 2ND FLOOR COLUMS
Project: NEWPROJ-2 Activity: A1200 3RD FLOOR COLUMS
Project: NEWPROJ-2 Activity: A1210 ROOF FLOOR COLUMS
Project: NEWPROJ-2 Activity: A1220 FINISHES
Activities without successors....................................14Project: NEWPROJ-2 Activity: A1002 BLINDING
CONCRETEProject: NEWPROJ-2 Activity: A1003 R.C FOOT
INGProject: NEWPROJ-2 Activity: A1004 GARDE BE
AMS AND WATER TANKProject: NEWPROJ-2 Activity: A1005 GARDE BE
AMS AND WATER TANKProject: NEWPROJ-2 Activity: A1006 GARDE BE
AMS AND WATER TANKProject: NEWPROJ-2 Activity: A1007 GARDE BE
AMS AND WATER TANKProject: NEWPROJ-2 Activity: A1008 1ST FLOO
R COLUMSProject: NEWPROJ-2 Activity: A1012 EXCATION
WORKProject: NEWPROJ-2 Activity: A1013 BACKFILL
INGProject: NEWPROJ-2 Activity: A1180 WATER PR
OOFING FOR FOOTINGProject: NEWPROJ-2 Activity: A1190 2ND FLOO
R COLUMSProject: NEWPROJ-2 Activity: A1200 3RD FLOO
R COLUMSProject: NEWPROJ-2 Activity: A1210 ROOF FLO
OR COLUMSProject: NEWPROJ-2 Activity: A1220 FINISHES
Out-of-sequence activities.......................................0
Activities with Actual Dates > Data Date.........................0
Milestone Activities with invalid relationships..................0
Scheduling/Leveling Results:
----------------------------# Projects Scheduled/Leveled.....................................1# Activities Scheduled/Leveled...................................14# Relationships with other projects..............................0Data Date........................................................13-Mar-
15Earliest Early Start Date........................................13-Mar-
15Latest Early Finish Date.........................................30-Mar-
15Exceptions:-----------
Critical Activities..............................................1Project: NEWPROJ-2 Activity: A1220 FINISHES
Activities with unsatisfied constraints..........................0
Activities with unsatisfied relationships........................0
Activities with external dates...................................0
Activities delayed due to predecessor delay......................0
Activities delayed due to resource leveling......................0
Activities that cannot be leveled................................0