Scharf Cf Breakout Safety90608r00
-
Upload
ayushi-sharma -
Category
Documents
-
view
216 -
download
1
description
Transcript of Scharf Cf Breakout Safety90608r00
1 Mike [email protected]
1Construction SafetyFAC Status Review of the LCLS Project
Construction Safety
M. Scharfenstein - ES&H Coordinator8 June 2009
2 Mike [email protected]
2Construction SafetyFAC Status Review of the LCLS Project
Project ISM Process & ImplementationCivil ConstructionTechnical Systems Installations
Lab shops, subcontractors and collaboratorsCommissioning w/ transition to Operations = ARR’s
Safety Assessment DocumentAccelerator Safety Envelope
ExperienceOverall and detail statisticsConstruction and Installation experience
Lessons Learned Direct subcontractor management Detailed work planning
Previous Review Recommendations
3 Mike [email protected]
3Construction SafetyFAC Status Review of the LCLS Project
Project-specific ISEMS Implementation SLAC Integrated Safety Management Plan
SLAC Work Planning and ControlFormerly LCLS Work Authorization ProcedureScope / Hazard & Control documentation / Authorization & Release
SLAC ES&H ManualFormerly LCLS Project ES&H PlanGC/sub Site Specific Safety Plan Job Safety AnalysisDaily Tailgate Safety MeetingsPM/UTR manages each subcontractCF-5 / Continuous Improvement / Lessons Learned
Management Walkthrough ProcessFormerly LCLS Safe Performance Observation ProcessFocused walkthru to note & promote safe behavior
4 Mike [email protected]
4Construction SafetyFAC Status Review of the LCLS Project
PROJECT SAFETY EXPERIENCEThrough April 2009
Total Project Hours2.19 M Hours workedDART Rate 1.03
SubContractors
599 K Hours workedDART Rate 3.01 (9 Incidents)TRC Rate 4.01 (3 Incidents)
LCLS Collaboration 1,589 K Hours worked DART Rate 0.25 (2 Incidents)
3.2 3
0.31
0
1
2
3
4 ConstructionIndustry
LCLSContractors
LCLSCollaboration
Total Project
DART Rate
Injury rates based on 200 K hours (100 man years) of effort. DOE/SC Goal is a Reportable Case (TRC) rate of < 0.25 and a Days Away, Restricted, or Transferred (DART) rate < 0.65 per 100 FTEs.
5 Mike [email protected]
5Construction SafetyFAC Status Review of the LCLS Project
April 2009 DART Rate Distribution
LCLS 1.589M HrsDART = 0.25TRC = 0.25
TCCo477K Hrs
DART = 3.8TRC = 5.0
LCLS Subs122K HrsDART = 0TRC = 0
6 Mike [email protected]
6Construction SafetyFAC Status Review of the LCLS Project
CF & Technical Systems Stewardship
Excellent Safety Record 120K+ hours w/o injury (TRC or DART)
S20, MMF, Injector, Linac TSI, S522, LTU
Project Managers / UTRs / Installation Managers Direct management of subcontractors
Communicate ES&H Expectations Guide them to success Enforcement when needed
Thorough Work Planning and Control Aggressive ISM management
Issues identified and addressed immediately Positive Results
Ownership of safety
7 Mike [email protected]
7Construction SafetyFAC Status Review of the LCLS Project
CF CMGC StewardshipOctober ’06 thru April ’07 Ramp Up to Full Production : Procedural Violations
Stand Down of Construction Activities : All Hands MeetingReview of Work Planning Process for field work – JSA process inadequate
PMT changesDeficiency Notices
May ’07 thru November ’07 Full Production : DARTsMulti-day Stand Down of Construction Activities : Corrective Action Plan
Paperwork ineffectively utilized by CM/GC and trade contractorsPMT changesDeficiency Notices & FinesCommunication with Corporate TCCoSafety Stewardship Committee EstablishedFull time on-site medic (+30hr OSHA)UTRs added
December ’07 thru April ’08 : Some progress, then… Two DARTs associated with one sub
PM removed Work stopped
May ’08 thru December ’08 : No DARTs Effective work planning & execution sought Plan for joint observation developed
Attendance at daily morning work planning meetings JSA review with workers throughout the day Identification / monitoring of specific trades or tasks for safe work practices
Must communicate with the worker
8 Mike [email protected]
8Construction SafetyFAC Status Review of the LCLS Project
Lessons LearnedCM/GC and/or subcontractor selection criteria
Assessment of EMR and competencies of the PMT
DOE EnvironmentHelp the contractor understand how OSHA is enforcedA CM/GC must closely monitor subcontractor means and methods
Project Safety StandardsClearly define standards that will applyContract clause re most recent standard rev
Initial Work Execution EvaluationInitial work packages are owner reviewed and executed with owner ‘participation’
Partnering and committeesPartnering process at onset of projectSafety StewardshipConflict Resolution Forum
9 Mike [email protected]
9Construction SafetyFAC Status Review of the LCLS Project
Previous Review Recommendations Continue to support Turner with LCLS resources to reduce the risk of additional safety violations and personnel injuries through the completion of the Turner construction scope.
Done – 270 days w/o DART, 184 days w/o TRC
LCLS should take the lead in establishing the safety culture the Laboratory Director has targeted for the Laboratory as a whole.
Done – Developed Construction ES&H Plan, Work Planning & Control Process, Management Walkthrough Process
SLAC safety violations identified during LCLS reviews should be addressed and promptly corrected whether specific to the LCLS project, or SLAC generic.
Done – Three specific issues and process in general
Track and report the precursors to lost time injuries in order to take corrective actions in time to prevent them. DART statistics are not sufficient if zero lost time injuries is the goal, and it is.
Done – had been happening all along project but not communicated
The DOE Lessons Learned database should be utilized as a tool to improve JSA preparation. Further, do not underestimate the time required to prepare safety related documentation and the time it takes for the approval process.
Agreed, still a challenge
10 Mike [email protected]
10Construction SafetyFAC Status Review of the LCLS Project
Conclusion
Integrated Safety and Environmental ManagementFollowing SLAC ISEMS Process
SLAC ES&H Manual Work Planning and Control
Following LCLS ES&H management practices LCLS Requirement, Specification and Interface Documents
Reviews, Authorizations, Continuous Improvement
Experience and Lessons LearnedUnderstanding the National Laboratory EnvironmentPartnering for Success
Recommendations valued & all adopted…almost