Scada Systems
-
Upload
sameera-ippili -
Category
Documents
-
view
592 -
download
5
Transcript of Scada Systems
KAKINADA INSTITUTE OF ENGINEERING & TECHNOLOGY
KORANGI,KAKINADA,EAST GODAVARI(Dist)
A MINI PROJECT report ONSCADA in VSP
INRASHTRIYA ISPAT NIGAM LIMITED
(STEEL PLANT) – VISAKHAPATNAM
A Project work done in partial fulfillment for the award of
BACHELOR OF TECHNOLOGYIN
ELECTRONICS & COMMUNICATION
Submitted by: Boorugu.Neelima Ippili.Sameera
Vatada.Venkata Lakshmi B.S.S.S.L.D.Sindhu
III/IV - B.Tech.
CERTIFICATE
This is to certify that the mini project work entitled “SCADA SYSTEM IN VSP” is a bonafied record of work done by Boorugu.Neelima, Ippili.Sameera,Vatada.Venkata Lakshmi, B.S.S.S.L.D.Sindhu students of KAKINADA INSTITUTE OF ENGINEERING & TECHNOLOGY have been sincere, dedicated and the conduct throughout the study has been excellent in partial fulfillment of the requirement for the award of degree in BACHELOR OF TECHNOLOGY under the guidance and supervision in VISAKHAPATNAM STEEL PLANT.
Visakhapatnam Signature of Guide
DATE: M. SRINIVASU
Jr.Mgr (TELECOM)
ACKNOWLEDGEMENT
I hereby take this opportunity to express my sincere gratitude to the
following eminent personalities whose aid and advice helped me to complete
this project work successfully without any difficulty.
I am thankful to Mr. M SRINIVASU, Jr.mgr (Telecom) who has been
with me all through the project to spend his valuable time and to share his
knowledge.
As a token of my feeling, I would like to acknowledge my
sincere regards to Mr. K. Iyapillai, DGM I/c (Telecom), Mr. S. Prasada Rao,
DGM (Telecom) and each and every person of the telecom department who has
directly or indirectly helped me in completing this project.
INDEX
Abstract
Introduction
Major Department in VSP
Communication Systems in VSP
Introduction to SCADA System.
Supervisory Control And Data Acquisition System
Architecture
Remote Terminal Unit (RTU)/PLC
DSL using LAN Extenders
Cables
Master Server
Display units (HMI/Engg Stations)
Conclusion
ABSTRACT
In this modern world of Industrialization and automation, energy plays a major role in
the growth of any organization. The utilization of energy plays an impacting and direct role
in the growth of organizations like Visakhapatnam Steel Plant.
The Telecommunication department plays a vital role in providing & maintaining
different electronic communication systems in various departments to achieve the assigned
targets and accomplishing the desired performance in VSP.
In Vizag Steel Plant, The supervisory control and data acquisition system (SCADA)
is implemented to monitoring the energy network. The objective of this SCADA system is to
monitor the energy usage and demands of various consumers of the plant and exercise
effective control over their energy consumption and optimum utilization of in-house energy
resources.
INTRODUCTION
INTRODUCTION
Visakhapatnam Steel Plant, an integrated steel plant under the corporate entity of
Rashtriya Ispat Nigam Limited (RINL), is the first shore based integrated Steel
Plant in the country, constructed with the then latest state of the art technology.
The Plant with a rated capacity of 3.0 Mt is a producer of steel products in the
longs category like wire rods, re-bars, angles, channels, blooms and billets.
2. EVOLUTION
Visakhapatnam Steel Plant was conceived in the year 1970 as a unit of Steel
Authority of India Limited (SAIL) to augment its long products capacity and to
service the southern markets. Announcement for Visakhapatnam Steel Plant was
made in the Parliament in the year 1970 and the foundation stone was laid in
1971 by the late Prime Minister Smt. Indira Gandhi. The feasibility report of the
plant was made in 1973 and the Indo-Soviet Agreement was signed in 1979. The
comprehensive detailed project report was made in 1980 and the project was
sanctioned by Government of India in 1982. In the same year, a separate
company called Rashtriya Ispat Nigam Limited was formed.
The plant was to be commissioned by 1986 as per original schedule. However,
because of severe cash crunch, in the year 1986, a rationalized concept was
adopted to lower the capital costs. Some of the envisaged facilities were dropped
and the nameplate capacities of steel making and rolling mills were increased for
making revenue generation more attractive.
Finally, the plant was fully commissioned in the year 1992. Due to the long
gestation period of 22 years from concept to commissioning stage, the capital
cost of the project went up from original estimate of Rs.2256 crs in 1979 to
Rs.8594 crs in 1992. As a result of high capital cost and large borrowings the
company had to bear high interest and depreciation burden resulting in
continuous losses. This has resulted in huge cost over runs and high capital
related charges and Visakhapatnam Steel Plant at the time of commissioning
itself had a net loss of over Rs.2000 crs.
While the plant was picking up production, the South East Asian financial crisis
severely affected the steel market which led to continuous drop in steel prices
both in domestic and international markets. Also from 1998, the steel industry,
worldwide, was affected by recession. Steel demand declined, forcing the steel
producers to throttle production levels. Many unviable production units in the
world had to close down. India’s exports were hit adversely and domestic
consumption remained almost stagnant. Sales realizations plummeted and
profitability of the Indian steel producers was adversely affected. All these
conditions brought a tremendous pressure on the financials of the company.
3. THE TURN-AROUND
Despite these adverse conditions, the Vizag Steel collective rose to the occasion
and over the last few years Vizag Steel’s performance has improved on all fronts
including production, techno-economics, marketing and financials. The emphasis
initially had been towards total employee involvement, then to technology up
gradation and process management and then to managing external environment.
At this juncture, the leadership played a crucial role in providing direction focusing
on critical issues and empowering employees. A number of sustenance and
performance improvement programmes were initiated to put the company on the
growth trajectory. The emphasis was on attaining rated capacity at the earliest,
improving techno-economic performance, improving health of equipment, cost
reduction and process innovations. Systematic and standard operation practices
and structured systems were developed and Vizag Steel was the first integrated
steel plant in the country to be accredited with all the three International
Standards for Quality (ISO 9001), for Environment Management (ISO 14001) and
for Occupational Health and Safety (OHSAS-18001).
All these initiatives gave positive results and the company started its journey
to excellence by crossing its rated capacity levels in the year 2001-02.
Since then the company has been operating consistently beyond the
rated capacities. Currently, the plant is operating at 120% of its rated
capacity.
The Plant turned around in the year 2002-03 by achieving for the first
time a net profit of Rs.521 crs. The improved performance saw Vizag Steel
become a Zero debt company and is a net positive company today having
wiped off all its accumulated losses.
All these efforts of Vizag Steel were well recognised by one and all. For its
excellent performance in the year 2002-03, Vizag Steel was conferred with the
Prime Minister’s trophy for the best Integrated steel plant in the
country. During the year 2002, Vizag Steel was awarded with `SCOPE’
excellence award for turnaround for its outstanding performance. Vizag Steel has
been winning the National Energy Conservation award for the last seven years
and has also won the Special Prize for National Energy Conservation for
successfully annexing the first prize for three consecutive years. Vizag Steel has
been constantly achieving excellent MOU rating from the government for its
excellent performance. It was bestowed with the World Quality Commitment
Award at Paris. In 2005, Vizag Steel bagged six Vishwakarma Rashtriya Puraskar
Awards out of the 28 awards announced by Ministry of Labour, a tribute to the
involvement of its employees and participatory approach of the management.
Best Water Management, Best Financial Management and Best Safety &
Occupational health awards from Confederation of Indian Industries are some of
the prestigious awards received.
4. VIZAG STEEL TOMORROW:
Armed with a vision to become world class integrated steel plant, the Vizag Steel
Collective is charged with a steely resolve to face a challenging tomorrow. Some
of the initiatives taken to make Vizag Steel a world class organization are:
Adoption of business excellence through CII-Exim Business Excellence Model.
Initiation for BPR & ERP.
Implementation of Six Sigma methodology.
Implementation of ‘5S’ for outstanding housekeeping.
Bench marking with world class companies.
Introduction of Knowledge Management to harness the inner potential of employees.
Introduction of e-commerce.
Acquisition of captive mines in India and abroad through joint venture, so as to have a level playing field with its competitors.
In line with its vision to become a continuously growing company, Vizag Steel
recast its expansion plan to double its capacity from its present 3 mT to 6.3 mT by
2008-09. The approval for its recast expansion plan was obtained on 28th Oct ’05
in a record time of 10 months. The expansion has been planned to further
strengthen its long product leadership in the country through production of
special bars, wire rods and structurals, in view of its high brand image and also
envisaged demand in line with the infrastructure growth of the country. A
seamless tube plant has been planned for the first time in an integrated steel
plant to cater to the growing oil and gas industry and reduce dependence on
imports of seamless tubes. The next phase of expansion to 10 mT is planned for
completion by 2012-13 which will include flat products also to provide a rich
product mix.
With excellent performance levels continuing during the current year also and the
ensuing expansion wherein Vizag Steel has set up an ambitious target of
completion of its expansion in a record 36 months at international standards,
Vizag Steel looks to new horizons. Vizag Steel collective has proved its mettle
time and again and is all set to take up new challenges and soar to new heights to
emerge as a World Class steel plant.
MAJOR DEPARTMENTS IN VSP
RAW MATERIAL HANDLING PLANT (RMHP) :
The RMHP receives the basic materials iron ore, fluxes (lime stone, dolomite),coking
and non coking coals etc. required for the steel making process from various sources through
wagons which are stacked and reclaimed by stackers-cum reclaimers and distributed to
various departments of Visakhapatnam steel plant through conveyor systems.
COKE OVENS (CO):
Blast furnaces, the mother units of any steel plant require huge quantities of strong,
hard and porous solid fuel in the form of hard metallurgical coke for supplying necessary heat
for carrying of the reduction and refining reactions besides acting as a reducing agent.
Coke is manufactured by heating of crushed coking coal (below 3mm) is in the
absence of air at a temperature of 1000deg centigrade and above for period of 16 hrs to 18
hrs. A coke oven comprises of two hollow chambers namely coal chamber and heating
chamber in the heating chamber a gaseous fuel such as blast furnace gas, coke oven gas etc.
is burnt. The heat so generated is conducted through the common wall to heat and carbonize
the coking coal placed into adjacent coal chamber. Number of ovens built in series one after
the other form a coke oven battery.
At VSP there are three coke oven batteries, 7 meter tall and having 67 ovens each.
Each oven is having volume of 41.6 cu meters and can hold up to 31.6 tonnes of dry coal
charge. The carbonization takes place at 1000 to 1050 deg centigrade in the absence of air for
16 to 18 hours.
Red hot coke is pushed out of the oven and sent to coke dry cooling plants for
cooling to avoid its combustion. There are three coke dry cooling plants (CDCP) each having
four cooling chambers. The capacity of each cooling chamber is 50 to 52 TPH. Nitrogen gas
is used as the cooling medium. The heat recovery from nitrogen is done by generating steam
and expanding in two back pressure turbines to produce 7.5 power each.
The coal chemicals such as benzol, tar, ammonium sulphate etc. are extracted in
coal chemical plant from co gas. After recovering the coal chemicals the gas is used as a
byprioduct fuel by mixing it with gases such as BF gas, LD gas etc. A mechanical, biological
and chemical treatment plant takes care of the effluents.
SINTER PLANT :
Sintering is one of the most widely used and economic agglomeration techniques. Sinter
is a hard and porous lump obtained by agglomeration of fines of iron ore, coke, limestone ,
and metallurgical waste. Sinter increases the productivity of blast furnace, improves the
quality of pig iron and decreases the consumption of coke rate .Two 312 square meter sinter
machines with 420 square meter straight stand type coolers for annual production of 5.26 MT
sinter.
BLAST FURNACE (BF) :
Pig iron or hot metal is produced in the Blast Furnace .The furnace is named as BF as
it is run with blast at high temperature and pressure of 1500 deg. C. Raw materials required
for pig iron and iron are iron making ore, sinter, coke, and lime stone. There are two 3200
cubic meter blast furnace to meet 3.0 MT annual metal requirement. with bell- Each furnace
is provided with a set of four hot blast furnace stoves designed for supplying air blast up to
1300 deg .C. Three turbo blowers, one for each furnace and one stand by common to both
furnaces are provided with 12 MW top pressure recovery turbo generating power. BF gas is
produced from each furnace is being cleaned in gas cleaning plant comprising dust catcher,
high pressure scrubber and is distributed through out the plant as a fuel.
STEEL MELT SHOP (SMS) :
Steel is an alloy iron and carbon, where carbon should be less than 2%. Hot metal
produced in B.F contains impurities like carbon, sulphur, phosphorous, silicon etc., these
impurities will be removed in steel making by oxidation process. These are the three L.D
converters to convert hot metal in to steel. The steel melt shop complex comprising two
1300-ton hot metal mixers, three 130-ton LD converters (two operating) and six 4-stand
bloom casters. Each converter is being provided with gas cleaning plant for cleaning and
recovery of LD gas, which will be used as fuel in plant.
ROLLING MILLS (RM):
Blooms cannot be used as they are in daily like. These blooms have to be reduced in
size and properly shaped to fit for various jobs. Rolling is one of the mechanical processes to
reduce large size sections in to smaller ones. The cast blooms from CCM are heated and
rolled in to long products of different specifications like high capacity, sophisticated high-
speed rolling mills. The rolling mill complex comprises:
Light and medium merchant mill (LMMM)
Wire rod mill (WRM)
Medium merchant and structured mill (MMSM).
Each mill is well equipped with required number of walking beam furnaces for
heating of walking beam furnaces for heating of blooms or billets and except for wire rod
mills, each furnace is provided with evaporative cooling system for generation of steel for
plant consumption.
THERMAL POWER PLANT (TPP) :
The estimated power requirement for V.S.P in 280 at 3.0 MT stages, the peak load
being 292 MW essential loads being 49 MW. The generating capacities 286.5 MW. A
captive power having 3x60 MW turbo-generator sets and 5x330 ton/hr steam generators. In
this plant, 6000 Nm^3/min turbo blowers are being provided for supplying cold air blast
furnaces.
MAIN PRODUCTS OF VSP( PRODUCT MIX)
Unlike many other steel plants VSP is an integrated steel plant , producing many
products like Blooms,Channels,Angles etc., other than these VSP also produces many by-
products that are derived during the production of coke and iron .The main products and the
by-products that are produced are shown in the table below :
TABLE –1 :
Steel products By-Products
Angles Nut coke Granulated slag
Billets Coke dust Lime fines
Channels Coal tar Ammonium sulphatnut
Beams Anthracene oil
Squares HP napthalence
Flats Benzene
Rounds Toluene
Re-bars Zylene
Wire rods Wash oil
COMMUNICATION SYSTEMS IN
VSP
In this modern age of industrialization telecommunications plays a very important
role in coordinating the activities of various departments / sections and in achieving the set
targets and also in improving the performance of the organization. In Visakhapatnam Steel
Plant, different types of communication systems are being used to meet the internal and
external communication needs. These are broadly classified as follow:
a. General purpose communication systems.
b. Process communication systems.
c. Monitoring & Signaling Systems.
Apart from the above facilities Telecom department maintains the following cable
networks also
a) DATACOM cable network.
b) Telephone cable network in plant and township
GENERAL PURPOSE COMMUNICATION SYSTEMS:
The following facilities are provided under category of general purpose communication
systems:
4000 lines IP based Telephone in Plant.
3000 lines Electronic Exchange in Township.
100 lines Electronic Exchange in Visakha Steel General Hospital.
44 lines Electronic exchange in Hill Top Guest House
2500 Lines Electronic Exchange of Bharat Sanchar Nigam ltd (BSNL) in Project
Office is catering to the needs of Plant area and Sectors-I to VII in township. Another 2000
Lines Electronic Exchange of Bharat Sanchar Nigam ltd (BSNL) in Township is catering to
the needs of Sectors-VIII to XI in Township.
The 3000 Lines electronic exchange in plant and 3000 lines exchange in township are
having the following facilities:
Extension (subscriber) to extension call, Auto call back, Hot lines, Music on hold,
Reminder Alarm, Automatic line testing facility, Faults man ring back, Call consult facility,
Malicious call tracing facility, 3 party conference Facility and Howler Tone alert etc. All
exchanges working in the steel plant are interconnected by means of junction lines and have
closed numbering scheme.
The 3000 lines exchange in township is interconnected to the BSNL network. Due to
this interconnection all the subscribers of this exchange can receive incoming calls from any
part of the world. A few subscribers are provided with facility to contact subscribers
connected to the BSNL network and cellular and mobile phones in and around
Visakhapatnam.
PROCESS COMMUNICATION SYSTEMS:
To facilitate coordination, operation & management activities of production,
maintenance & service departments, the following process communication systems are
provided:
a) Dispatcher communication system
b) Loudspeaker intercom systems
c) Loudspeaker broadcasting systems
d) Loudspeaker conference communication system
e) Industrial public address system
f) Hotline communication systems
g) VHF communication systems
A) DISPATCHER COMMUNICATION SYSTEMS :
Initially dispatcher communication is provided with a cordless switch board type
manual exchanges of electromechanical. Since manufacture of such systems and their spares
is discontinued in the country, these dispatcher systems are being replaced by Electronic
exchanges progressively. Except the ones in CCCP other systems have been replaced. These
would also be replaced very soon.
Production coordination at plant level being conducted by ED (Works) with all HOD
s in the morning every day is facilitated with the help of the digital EXCOM system provided
in the plant control room.
B) LOUD SPEAKER INTERCOM SYSTEMS :
Loudspeaker intercom systems are working LMMM & WRM. These systems are used
for communication between various sections of the same production shop. Communication is
made possible using microphones and loudspeakers provided in the subscriber stations. This
system is very useful in noisy environment where conventional telephones are ineffective.
This system helps to establish communication between any two stations having
interconnectivity on selection basis. By using group call facility it is possible to
communicate to all the subscribers in the group at a time.
C) LOUDSPEAKER BROADCASTING SYSTEMS:
This system consists of centralized amplifier rack with amplifiers, desktop micro
phone with press to talk switch and a network of loud speakers connected to the
amplifiers .this is useful to make general announcements to the entire working area as to pass
on important instruction from the control room.
Loudspeaker broad casting systems are provided in C&CCD, BF, SP and SMS
departments.
D) LOUDSPEAKER CONFERENCE COMMUNICATION SYSTEMS:
Loudspeaker conference communication systems are working in CCCP. These
systems are provided with both paging and private channel communication facilities. In case
of paging a general announcement can be made which is heard on all the stations. In the
private mode communication is possible between two selected stations only. Here also
communication is carried out by means of microphones and loudspeakers provided in the
subscriber stations.
E) INDUSTRIAL PUBLIC ADDRESS SYSTEM:
Industrial Public Address System is working in TPP. It is a combination of
loudspeaker broadcasting system and conference communication system. From the main
control room it is possible to make announcements which are heard on the shop floor. From
certain locations the communication can also be established through handsets in private mode
with the main control room.
F) HOTLINE COMMUNICATION SYSTEMS:
To ensure direct telephone communication between closely related critical locations
hot lines are provided. By using the hot lines specified locations are connected permanently.
Communication is possible only between these two locations. When one subscriber lifts his
telephone the other will immediately get a ring and communication can be had without any
loss of time.
This is useful to pass-on urgent messages. These hot lines are initially provided with
direct line communication systems which are electro mechanical systems. Due to
obsolescence electronic systems are now being used for most of the locations. Hot lines are
working in CCCP, BF, SMS, LMMM, WRM, MMSM, TPP, PPM, DNW and WMD
departments.
G) VHF COMMUNICATION SYSTEMS:
VHF communication systems are used in VSP to establish two way communications
between two or more when either or one of them is moving. There are three models working
in our plant. They are hand-held units (Walkie-talkie), vehicle mounted – mobile units and
base station units.
Walkie-talkies are used by operation and service personnel in almost all of the
production shops. Vehicle mounted units are being used by DNW, CISF (Fire) and CISF
(security). Base station units are used by CISF (fire), CISF (Security), Administration, DNW
and largely by CCCP departments. In CCCP these can be seen in pusher cars, charging cars,
door extractors, electric locos, lifters and CDCP areas. These sets are very essential and
useful in answering proper communication and coordination during alignment of oven
machines while charging and pushing the ovens and carrying out these operations safely.
Handheld VHF sets are extensively used for establishing instantaneous
communication and ordination of operation or maintenance activities on different
departments throughout the steel plant.
MONITORING AND SIGNALING SYSTEMS:
To facilitate monitoring production, maintenance & service activities, the following
monitoring and signaling systems are provided:
a) Closed Circuit Television Systems (CCTV)
b) Central fire alarm signaling system
c) SCADA system
d) Shift change Announcement Siren System
A) CLOSED CIRCUIT TELEVISION SYSTEMS (CCTV):
For monitoring critical operations in different production units continuously from the
concerned control rooms / pulpits CCTV systems are used in SP, BF, SMS, LMMM, WRM
and MMSM departments. CCTV system comprises of CCTV camera with a lens and a CCTV
monitor.
In some cases a video switcher, a central control console, pan and tilt head and zoom
lens are also used. These are interconnected by means of control cables and / or coaxial
cables. Necessary protection is provided for the CCTV equipment depending on the locations
where they are used.
B) CENTRAL FIRE ALARM SIGNALING SYSTEM :
The central fire alarm system is provided for communicating the exact location of
outbreak of fire in any part of the steel plant complex to the central fire station and
simultaneous actuation of sirens to alert personnel of the affected plant zone. The system
employs manual call points located all over the plant.
C) SCADA SYSTEM :
To monitor the generation and consumption of various energies by various users in
the plant the SCADA system is provided. Scada system is located at Energy and Telecom
centre.
The system comprises of a master servers ,23 Remote Terminal Units (RTUs)
installed in different plant units and display units. The RTUs will collect the signals from the
tranducers& electrical systems and transmitting to the master servers by means of
cocommunication channel. The RTUs are connected to the master servers by under ground
laid telephone cables.
D) SHIFT CHANGE ANNOUNCEMENT SIREN SYSTEM:
The shift change announcement siren system is provided for ensuring uniform and
accurate shift timings throughout the plant. This system consists of two quartz crystal
controlled master clocks in the Energy & Telecom Centre. The shift timings are programmed
in the Master Clock. At the specified time, the signal will be transmitted for energizing the
sirens located at strategic points in plant area simultaneously at the preset timings.
INTRODUCTION
SCADA SYSTEM:
SCADA is an acronym for Supervisory Control and Data Acquisition system, a computer system for gathering and analyzing real time data. SCADA systems are used to monitor and control a plant or equipment in industries such as water and waste control, energy, oil and gas refining and transportation. A SCADA system gathers information, such as where a leak on a pipeline has occurred, transfers the information back to a central site, alerting the home station that the leak
has occurred, carrying out necessary analysis and control, such as determining if the leak is critical, and displaying the information in a logical and organized fashion. SCADA systems can be relatively simple, such as one that monitors environmental conditions of a small office building, or incredibly complex, such as a system that monitors all the activity in a nuclear power plant or the activity of a municipal water system.
SCADA systems were first invented in the 1960s.
The signals for a plant unit will normally be concentrated in the control room of the unit from where the unit is being operated. PLCs/RTUs of the SCADA will be installed in these main control rooms and the tele- transmission signals identified for the units will be wired to the PLCs/RTUS .
The PLCs/RTUs are micro processor based intelligent units , responsible for Acquisition of inputs from the plant units and convert them in to digital code for Tele -- transmission to the Master station computer of SCADA through the 5 pair telephone cable . Some plant unit where few signals are available for tele – transmission , A junction box will be installed in the control room ( instead of an PLCs) for the termination of inputs and these inputs are further connected to the nearest PLCs through the multi – core control cables.
. The 23 PLC s are located in different parts of the plant are connected to the center Master station through modems. The Master station located in the E&T centre of the Visakhapatnam steel plant will acquire all Information through PLC and LAN and Process the information for displays and report generation .
The SCADA system acquires various electrical & utility parameters for effective monitoring & control operation. The various parameters acquired are electric power , voltages , currents , etc… under electrical monitoring and parameters such as flows , temperatures, pressures , etc
CATEGORY OF ENERGY FORMS IN VSP
Utility systems Electrical systems WATER
UTILITY SYSTEMS:
The utility system covers the services like fuel , gases , stream , compressed air, water etc…. The services covered by the utility systems of CSCS are broadly classified in to following groups.
Fuel gases system : CO, BF ,Mixed & converter gases. Process gas system : Nitrogen, Oxygen ,Argon, Acetylene. Steam Distribution system: Steam at 40 KSCG,13 KSCG. Compressed air system: Compressed air and instrumentation grade air
Chilled water system: Chilled water. Fuel oil system : LSHS,LDO and LTF.
water Water systems: make up water, fire and drinking water
ELECTRICALSYSTEM:
The electrical system covers the complete electrical distribution network inside the Visakhapatnam Steel Plant like 220 KV ,11 KV, 6.6 KV systems in MRS,
LBSS , 1, 2 , 3 , 4 and 5 , LBDSS.For centralized supervisory of above services in utility and electrical systems and also to
exercise control over their optimum utilization, following types of signals are considered for the users.
Analog input (AI) Digital input (DI) EM SIGNALS The input signals acquired by the PLCs are tele-transmitted to the Master station and
are sorted out according to the above subsystem division i.e utility and electrical.
SCADA systems monitor a total of 4000 different signals originating at different depts. in VSP. Among these 4 000 signals, 150 0 signals are catered to monitor utility system and 2 500 signals are electrical system .
ARCHITECTURE OF THE SCADA
ARCHIECTURE OF THE FIELD PLC/RTU’S
PLC – Architecture:
The selected PLC has got powerful processor to take care of the data acquisition
requirements of the VSP. The PLC interfaces with field to acquire the data from various field
instruments. The offered PLC system supports maintenance from the Engineering station
in master station. The PLC will be supplied with ladder programming language for
building local automation sequences. The offered PLC is fully modular and supports
distributed I/O for future expansion. The PLC supports a total of 20,000 I/O ports.
The functional architecture of the PLC system will be as follows. The offered
architecture is latest state-of-the-art in which the PLC processor communicates with
individual I/O stations over a highly reliable Ethernet ring. The extension racks will be
available for any more expansion in I/Os. The system will support a total of 20,000I/O’s.
The PLC presented above shall have the following characteristics: High capacity controller for I/O signals High memory capacity and expandable Input digital signals cards Input analog signal cards Galvanic isolation for the signal. Empty slots for future expansions Ports to connect to field buses (RS232C/RS485) Configurable to standard protocols (MODBUS RTU / Profibus DP) Comprehensive self testing and diagnostic facilities SCADA Master Station over dedicated telephone cables.
HARDWARE COMPONENTS OF THE PLC : 1. Power Supply Unit.2. Programming Unit.3. Central Processing Unit.4. Bus Controller Unit.5. Communication unit to Interface with External Programming unit.6. Input and Output modules.
1.POWER SUPPLY UNIT :
The power supply modules provide the power supply for each rack.
The required power supply standard format or double format model. The mains
electrical supply ~200..240V
Description of the Power Supply Unit:
1. Display blocks comprising. OK lamp (GREEN), if voltages are present and correct. BAT lamp (RED), if the battery is faulty or missing. 24V lamp (GREEN) when sensor voltage is present
2. RESET pencil-point push button causing a warm restart of the application.
3. Slot for a battery which protects the internal RAM memory of the processor.
4. Cover to protect the front panel of the module.
5. Screw terminal for connecting: To mains supply. The alarms relay contact. The sensors power supply for a.c supplies.
6. Opening for cable clamp.
7. Fuse located beneath the module and protecting.
8. 24VR voltage on the non-isolated d.c supply. Primary voltage on the other power supplies.
9. 110/220 voltage selector
CHARACTERISTICS OF THE POWER SUPPLY
The characteristics of the power supply module are
Primary Power supply Module:
Voltage (in V)
Nominal ~100…240
Limit ~85..264
Frequency (in Hz)
Nominal /limit 50…60/47..63
Current (in A)
Nominal input 1ms 0.5 at ~100v0.3 at ~240V
Secondary power supply Module:
OutputNominal voltage 5V
Nominal current 5A
Power 25W
OutputNominal voltage 24V
Nominal current 0.6A
Power (typical) 15 W
Description of the 12 slot Rack Power Supply Unit :
It is possible to constitute a PLC station with premium processors with just a single rack. These racks are connected to each other.
The Racks comprise :
1. Metal frame.2. Slots for anchoring the Module pins.3. 48-way female ½ DIN connectors for module-rack connections4. Locating slot for the power supply module.5. Trapped holes for mounting the module.6. Four holes for mounting the rack.7. Position for rack address label.8. Position for station network address label.9. Two earth terminals for earthing the rack.10. Micro switches for coding the rack address 11. Two 9-way female SUB-D connectors for the remote connection of bus X to another
rack.Rack address :
Address 0: This address is always assigned to the rack which holds the processor.This rack can be located in any position on the line.Adresses 1to 7: These can be assigned in any order to all other extendable racks of the
station.As the two racks with 4,6 or 8 slots which make up each pair can have the same address on
the bus X , position numbers are defined as follows: Rack n “ less- significant “: position 00 to xx; Rack n “ most-significant “; position 08 to yy; Each rack with 12 slots holds an address Specifications of power supply :
Type ModularNo.of Slots 12 slots inclusive of power supply slotDimensions in mm 482.6(W) x 151.5 (H)Reserved slots Slot-1 for power supply
Slot -2,3 for processor
Functions of the power supply module:
Alarm Relay:
The alarm relay located in each power supply module has a volt-free contact which
can be accessed on the connection screw terminal of the module.
Principle:
Module alarm relay on the processor rack (rack 0): In normal operation, PLC in RUN, the alarm relay is activated and its contact is closed. Whenever the application stops, even partially, occurrence of a blocking fault, incorrect output voltages or loss of mains power, the relay de-energizes and the associated contact opens(state 0).
Alarm relay of power supply modules located on the other racks(racks 1to 7).when the module is powered up and if the output voltages are correct, the relay is activated and its contact is closed (state 1).when the mains power is lost or if the output voltages are incorrect, the relay de-energizes (state 0).
Back-up battery:
Each power supply module has a slot reserved for a battery which provides the power
supply to the internal RAM memory located in the processors, in order to ensure that data is
saved when the PLC is switched off. The duration of data back-up is one year. The battery
must be changed as soon as the BAT lamp(RED) on the front panel lights up.
RESET Push button:
Pressing this push button, which located on the front panel of the power supply
module, triggers a sequence of service signals which is the same as that for:
A power breaks when the push button is pressed. A power up when the push button is released.
Sensor power supply:
The sensor power supply (a.c) modules have an integrated power supply which
provides a voltage of 24V to supply the input sensors. Connection to this sensor power supply
can be accessed via module screw terminal.
2. PLC PROGRAMMING
PLC acronym for Programmable Logic Controller is an industrial computer control
system that continuously monitors the input devices and performs a sequence of operations
depending of inputs. The output is user defined through a set of instructions, integrating the
process sequences and interlocks.
Programmable Logic Controller is a solid state device, basically designed to perform
logic decision making for industrial control applications. Sincere their development in early
1970’s PLC have evolved to challenge not only relays but also other discrete control devices
such as stepping switches, drum sequencers etc.
The PLC is composed of electric circuit with a microcomputer centered. However , it
can be equivalently regarded as an integrated body of ordinary relay, timer, counter etc.
There are different methods of programming PLC’s .They are
1. Ladder diagram programming.2. Function blocks programming.3. Instruction list programming.4. Structure text programming.Ladder diagram: It is graphic and very easy to understand. It closely resembles the old
relay logic diagram. Generally shop floor maintenance people easily understand and prefer it. The drawback of this language is, occupies more memory space and slow.
Function diagram: It is also easy to understand and pictorial representation. It closely
resembles the controller programming. This is also very slow. Most of the PLC’s use a combination of ladder and function block programming.
Instruction List: It uses he mnemonic codes of a microprocessor. It is very fast but it
requires familiarity with assembly language programming of microprocessor.Structured text: It is nothing but C language programming. It is a fastest of all languages.
But it requires through knowledge of ‘C’ language programming.
Function of the PLC:
HOUSE KEEPING
INPUT SCAN
LOGIC SCAN
OUTPUT SCAN
SERVICE COMMUNICATIONS
House Keeping: It consists of internal checksums and diagnostics that the processor
executes every scan cycle. These can be done at the beginning or the end of the scan cycle or both depending upon the PLC.
Input Scan: It consists of reading the current state for each input connected to the PLC
system and updating the input memory tables.
Logic Scan: It consists of reading the use program that ahs been stored in the PLC
memory. These programs can be written in ladder logic, instruction list, sequential flow charts, function block, structure test, c code or state logic depending upon their manufacturer of the system. Some system supports programming using combination of languages within the same program.
Output scan: It consists of adjusting the values of outputs connected to the system based
upon the status of inputs and execution of the logic.
Service communications : It consists of opening the window of time for the processor to
communicate to other devices. These can be programming devices, operator interface devices, remote IO controllers, other PLC’s or any devices having communication capability that is compatible with the PLC system.
3. CENTRAL PROCESSING UNIT:
This CPU is a double format high performance processor.
Figure 1
The CPU displays 6 additional display lamps1. RUN lamp (GREEN) : Ethernet TCP/IP port ready. ERR lamp (RED) : Ethernet port fault COL lamp (RED) : Collision detection. STS lamp (YELLOW) : Ethernet link diagnostics. 2, TX and Rx lamp (YELLOW) : Tx/Rx activity.
2. A “Memory Extract” button for extracting the PCMMCIA memory extension card. The associated “Memory extract ready” display lamp indicates that this card can be
extracted safely.
3. RESET button causing a cold restart of the PLC when it is activated.
4.An 8-way female mini-DIN connector marked AUX for connecting a programming adjustment.
5.A USB type connector marked TER for connecting a programming terminal.
6. A PCM CIA slot (no.0) for a memory extension card.
7.A PCM CIA slot (no.1) for a communication card or memory Extension card for storing additional data.
8. NOT APPLICABLE FOR THIS MODEL.
9. An RJ 45 type connector for connection to the Ethernet TCP/IP 10BASE-T/100 BASE-Tx network.
MEMORY STRUCTURE
The application memory is divided into memory areas physically distributed in the internal RAM memory and on 0, 1 or 2 PCMCIA memory extension cards.
1. The application data area, which may be one of 2 possible types, is always in the internal RAM.
Located Data: It is defined by an address (e.g. %MW237) which a symbol may be associated.
Unlocated Data: It is defined by the symbol. This type of symbol addressing removes the memory “memory management” constraints because address is assigned automatically.
2. Area in internal RAM or PCMCIA memory card for the program and symbols. In the event of this area being in internal RAM.
It also supports the area for modifying the program in online mode. This area contains the program’s executable binary code and IEC source code. The user selects the type of information to be stored in the PLC memory.
3. Constants area in the internal RAM or the PCMCIA memory card (slot no .0)
4. Storage area for additional data (slot no. 0 or no.1)Ex: For production data and manufacturing recipes.
Application of the internal RAM: In this case, the application is entirely loaded in the
processor’s internal battery-backed RAM(2). It varies at 96 to 640 Kb.
Application in PCMCIA card: IN this case, the internal RAM is reserved for the
application data. The PCMCIA memory card (slotno.1) contains the program space (programs, symbols and constants areas). It varies at 224 to 7168 Kb.
The internal RAM memory is backed up by an optional battery (3 year’s life) located in the power supply module.
Extension of data storage area : Memory cards reserved for data storage (4096 or 8192 Kb) are used to:
Access the data storage area when the application is entirely supported by the internal RAM. In this case, the data storage memory card is inserted into PCMCIA slot no.0
Free up memory space to provide additional program space when the application is in the PCMCIA card (slot no.0).In this case, the data storage memory card is inserted into PCMCIA slot no.1.
Protecting the application: Regardless of the PLC memory structure (whether it is located in the internal RAM or
in the PCMCIA memory card), it is possible to protect this order to prevent it being accessed (read or modify program) by only loading the executable code on the PLC.
A memory protection bit, set in configuration mode, is also available to prevent any program modification (via the programming terminal or downloads).
Program modification in online mode: The function of this PLC is, it allows program code and data in different parts of the
application to be added or modified in a single modification session. Any program modification made in online mode.
CHARACTERISTICS AND PERFORMANCE
The characteristics and performance are
Functions:
Max No. in Rack
Discrete I/O 2048
Analog I/O 256
Process control channels 20 (up to 60 simple loops)
Application- specific channels (counter, serial links)
64
Integrated ConnectionsEthernet TCP/IP 1
Serial link 1x12 Mbps USB link(TER)1x19.2 Kbps (AUX) link
Maximum no. of connections
Network (Ethernet,TCP/IP,Fipway,Ethway,ModbusPlus)
4;3if integrated Ethernet is used
Memories:
Maximum capacity
Without PCMCIA card (in Kb) 320prog + data
With PCMCIA card (in Kb) 2048 prog, 440 data
Data Storage 16,384 Kb
Execution time: 11.4 Instructions /MsExecution time for 1K instructions: 1/11.4 =0.0877msTotal memory: 324 kb (with CPU) +256kb (with PCMICA memory Card) = 580kbAssuming 50% Program memory loading =290kbScan time 290*0.0877 = 25.433ms Communication protocol with Scada: Modbus TCP/IP.Communication with SCADA: Built –in-Ethernet module
INPUT AND OUTPUT MODULES:
1. Analog Module2. Digital Module
Analog Module : The front panels of analog module comprise
i. A display and module diagnostics block.ii. A connector for receiving the screw terminal block.
iii. A rotating supports containing the module locating device.iv. A removable screw terminal for direct connection of the I/O to the sensors and
preactutators.v. A pivoting cover for accessing the terminal block screws and holding the identification
label.vi. A screw terminal blocks encoder.
vii. A 25-way SUB-D connector for connecting the sensors.
Functions of Analog Module:
1. Scanning of input channels, protection against over voltages, adaptation of signals by analog filtering, scanning by solid state multiplexing.
2. Adaptation to input signals: Gain selection, drift compensation.3. Digitization of signals: 12-bit analog/digital conversion.4. Converting input measurements to user format: recalibration coefficient, filtering,
scaling.5. Module monitoring: conversion circuit test, range overshoot test, terminal block
presence test, “watch dog “test.& fast processing inputsSpecifications:
Channels 16channels
Isolation Between Bus and channelsBetween channels and earth
1000 v RMS1000 v RMS
Resolution 12 bits
Input operating range +/-10 V DC,0-10V,0-5V,1-5V,0-20mA,4-20mA
Maximum Over Voltage +/- 30 V
Maximum Over current +/- 30 Ma
Digital Module :
The front panels of Digital module comprise
Functions of the Digital Module :
I/O assignment : Each module is functionally organized into groups of 8 channels. Each group of channels can
be assigned a specific application task.
Reactivation of Outputs : If a fault has caused an output to trip, output can be reactivated if no other terminal
fault is present. The reactivation command, defined during configuration, can be automatic or
controlled via program. Reactivation is carried out in groups of 8 channels. This function can
be accessed on modules with solid state d.c outputs. For relay and triac output modules
protected by fuse, the same type of reactivation is necessary after replacement of one or more
fuses.
RUN /STOP command : An input can be configured to control the Run /STOP mode for the PLC.
The command is accepted on a rising edge. A STOP command via an input takes priority
over a change to RUN via the terminal or via a network command.
Output Fallback:
When an application is placed in STOP mode, Outputs must be set to a state which is
not harmful to the application. This state known as the fallback position is defined for each
module when its outputs are configured.
This configuration enables the choice between:
Fall back: channels are set to state 0 or 1 depending on the fallback value entered.
Maintain: outputs retain the state they were in before the PLC stopped.
Diagnostic functions:
Module diagnostics: Any exchange fault preventing normal operation of an output module or fast input mode is signaled. Similarly, any internal module fault is signalled. Process diagnostics: Sensor/procurator voltage check, terminal blocks presence check, short –circuit and overload check, preactuator voltage check.
Specification:
Nominal Input Voltage 24 VDCInput characteristics Input voltage On state voltage Off state current On state voltage Off state current
24 V DC>=11 V>= 3mA=<5 V =<1.5 mA
On response time Off response time
4ms
Web servers: The web server module is a stand alone TCP/IP –module gateway module used
to connect a Modbus device to a TCP/IP network. It is a standard device. It has a built in RS 232 serial link which can be used to connect an external modem.
Mainly this module is used to perform the following functions: Modbus messaging over TCP/IP, SMTP service SNMP service. Embedded Web server. Option of having a user web site.
Specifications:
Functions Embedded web server ,Option of having a user websiteModbus messaging over TCP/IP
SMTP serviceSNMP service
No. of Ports 1-RJ 45 connector1-RJ 45 connector for RS 485 linkA 9-pin SUB D connector for a modem link
No. of simultaneous connections 16 Internet browsers
Energy Meters:
The energy meter portable working is a 3 phase portable electronic meter test unit for
use as a working standard to test both single and 3 phase electricity meters on site. This
device allows checking of all meter installation parameters and associated circuits. The
energy meters is available in accuracy classes 0.1.The unit can be used either with a direct
connection in the range 1mA..12A.
Function:
Active, reactive and apparent energy measurement for single phase and 3 phase, 3 or 4 wire circuits with integrated error calculator.
Advantages:
Wide measuring range with auto ranging. Display of vector diagram for analysis of mains conditions and meter connections. Measurements of wave from and harmonics with display. Easy detection of circuit connection faults. Data memory. Small dimensions and light in weight. Serial interface for data transfer.
Application: On site test of electricity meters.
Specifications:
Power consumption 10VACurrent range 1mA….12AVoltage range 10V…..300V
CABLES
In both interrogation and broadcasting mode there is a continuous
transfer of information between the PLC and the MS so there is a necessity of a
physical medium to facilitate the flow of information( Electrical Signal). Cables
perform the job of interconnected the field PLCs and MS.
The inter- connecting cables required for connecting various terminals can be
classified in to 3 categories and the technical specification of various cables are
also given below .
CATEGORY – I :Telephone cables required for inter connection of PLCs and the MS. 5Pair Petroleum jelly filled. Armored. Over all polythene packed. Solid annealed high conductivity copper. Diameter 0.633mm. Resistance 57 ohm /KM.
CATEGORY—II: Twisted pair cables required for the inter connection of remote video terminal
to the master stations . 5Pair. Diameter 7/ 0.2 mm. Individually and over all shielded. Armored cables.
CATEGORY – III :Control cables required for the inter connection of signals from plant units and
junction boxes to the PLCs . # Size 1.5 mm. # Solid annealed copper conductor. # Multi core control cable. # Armored and unarmored. # Thickness 0.8 mm. # Resistance 12.1 ohm / KM. # PVC Insulated.
The cables will be laid partly on cable trays in cable tunnels and balance the directly buried under ground .
LAN EXTENDERS
The RTU’s are connected to the MS by under ground telephone cables with one pair of Lan extenders.Descriptions of Modems.
The SHDSL (Single-Paired High Speed Digital Subscriber Loop) routers/lan
extenders comply with10/100 Base-T auto-negotiation. It provides business-class, multi-
range form64Kbps to 2.304Mbps (for 2-wire mode) or 128kbps to 4.608Mbps (for 4-wire
mode) payload rates over exiting single-pair copper wire. The SHDSL routers are designed
not only to optimize the service bit rate from central office to customer premises also it
integrates high-end Bridging/Routing. Because of rapid growth of network, virtual LAN has
become one of the major new areas in Internetworking industry. The SHDSL routers support
port-based and IEEE 802.1q VLAN over ATM network.
The firewall routers provide not only advanced functions, Multi-DMZ, virtual server
mapping and VPN pass-through but advanced firewall, SPI, NAT, DoS protection serving as
a powerful firewall to protect from outside intruders of secure connection.
The SHDSL routers allow customers to leverage the latest in broadband technologies
to meet their growing data communication needs. Through the power of SHDSL products,
you can access superior manageability and reliability.
Features:1. Easy configuration and management with password control for various applicationEnvironments2. Efficient IP routing and transparent learning bridge to support broadband Internet services3. VPN pass-through for safeguarded connections4. Virtual LANs (VLANs) offer significant benefit in terms of efficient use of bandwidth, flexibility, performance and security.5. Build-in advanced firewall (Firewall router)6. Four 10/100Mbps network connectivity (4-port router)7. Getting enhancements and new features via Internet software upgrade.Specification
Bridging:1. IEEE 802.1D transparent learning bridge2. IEEE 802.1q VLAN3. Port-based VLAN (4-port router)4. Spanning tree protocol
Management:1. Easy-to-use web-based GUI for quick setup, configuration and management2. Menu-driven interface/Command-line interface (CLI) for local console and TelnetAccess3. Password protected management and access control list for administration4. Software upgrade via web-browser/TFTP server
LAN Interface:1. 4-ports switching hub (4-port router)2. 10/100 Base-T auto-sensing and auto-negotiation
LAN –LAN Connection:
Communication Types :
Citect SCADA supports four types of I/O device communication:1. Serial communication2. PLC interface board3. Data acquisition board4. Dynamic data exchange (DDE) Server
Whether the I/O device is local or remote, communicating with I/O devices isusually via a simple serial connection using the RS-232or RS-485 standard .
With Citect SCADA there are many I/O device communications options, through
Citect SCADA computer's COM port, through a high-speed serial board, or through a
communications board supplied by the I/O device manufacturer.
Advantages:1. Flexible.2. Scalable.3. Reliable, low cost.
MASTER STATION/Master server
SERVERS:
WINDOWS based operating software shall be considered as SCADA servers. Servers
shall work on hot redundant server configuration. All the PLCs shall be communicating
directly to both the servers. The data updates taking place in any of the PLCs shall be updated
in both the servers automatically and simultaneously. In the other HMI stations, only client
software shall be loaded. Both servers shall update relevant data (process, configurations,
history etc.) continuously. Necessary
dual redundant network interface modules shall be provided for communication with
PLCs and other peripherals. Other operator station, shall log on to these servers for system &
process operation, data access and other operations. Servers shall be considered with Oracle
database. The system software shall support 10000 tags.
HUMAN MACHINE INTERFACE (HMI) STATIONS:
PC BASED SYSTEMS:
1.2 nos PC based system HMI stations shall be provided for operator interface, data logging,
trending, alarm & graphic generation and Management information system,
Suitable dual redundant network interface units shall be provided for necessary
communication with Ethernet. The SCADA system software offered shall support 10000
tags.
2. 1 HMI shall be provided for connecting to plasma board for the purpose of video mimic.3. 5 nos remote HMIs (work stations) Each HMI shall have high resolution color Flat screen,
which can be chosen, designed to any parameters during formatting. It shall be on line, real
time system for remote operations, control and monitoring of process
functions with facilities for mimic and graphic displays (over view, group, loop, alarms etc.),
data acquisition and logging, trending (real time and historical), realtime report generation,
alarm handling, etc. Client software shall be loaded in all the HMIs. The MRS- HMI station
shall be equipped with dual monitors for simultaneous data monitoring and report browsing /
printing etc. The following shall be the minimum system requirement. The HMIs shall be
supplied with latest configuration at
the time of supply. The HMI shall be mounted in a stand alone metallic desk
HMI SOFTWARE:
Required licensed operating software’s, client software’s for downloading the screens
developed at Servers for day to day monitoring, operation etc., shall be provided.
ENGINEERING STATIONS:
1 no Engineering station shall be provided at the Master Station along with licensed
software for the system administration/database administration/HMI functions. The same
shall be connected on the ETHERNET communication network. The Engineering station
shall be supplied with suitable metallic enclosure.
LAP TOP PC :
LAPTOP PC shall be supplied with latest configuration at the time of supply. It shall
be supplied along with required licensed softwares and all accessories as
required.
PROGRAMMING SOFTWARE :
Each LAP TOP PC shall be loaded with licensed programming software. All software
shall be licensed version. The programming software shall be windows based and shall be
compatible with the systems proposed. The Programming software shall be suitable to
program all the RTUs. In addition to above one licensed RTU/PLC programming software
shall be loaded in the HMI (Telecom) also. It shall be ensured that the healthiness and fault
diagnosis of PLC/RTU cards can be checked / accessed from HMI (Telecom) only.
60” PLASMA Screen:
The HMI shall connect to the 60” PLASMA screen (Video mimic) for viewing of
mimic pages in the control room. The offered mimic screen shall be self-standing type.
INTELLIGENT COMMUNICATION INTERFACE UNIT :
The intelligent communication interface unit shall be serving the purpose of
interfacing between Master station and PLCs with high speed.
The PLCs shall be connected to the Master station utilizing existing telephone cables
with modems at the RTU/PLC end and at Master station end. In the control room of E&T
centre the modems shall be connected to the Intelligent Communication Interface unit. The
data of the PLCs shall be transferred by the intelligent Interface unit to the server without
affecting the process requirement. The communication
from each RTU shall be connected to the Intelligent Interface unit through separate module.
The retrieval of data from the PLCs shall be configured by the servers of Master station.The
intelligent communication interface unit shall be connected to the dual ETHERNET. The
offered interface unit shall connect to all RTUs and 3 nos work station. Over and above the
above 20% spare cards to be provided for future expansion. If the offered interface unit is not
capable of handling all the cards then required number of Intelligent Interface units shall be
included in the scope of work. All the interface units to be connected to the dual ETEHRNET
switch.
ETHERNET SWITCH:
The ETEHRNET SWITCHES shall be redundant. It shall have 24 ports in each
switch. Layer-3 Ethernet switch supporting 10/100/1000 MBPS shall be considered. It shall
be mounted in suitable metallic enclosure.
DIGITAL ENERGY METERS :
The digital Energy Meters shall be with serial interface (RS485) to connect to the
PLC. The energy meters shall be mounted in the field and the maximum distance shall be
considered from the RTU location
This covers design, engineering, manufacture,assemble, inspection and testing before
supply of 110V, 5A/1A and 3 element 4 wire CT
Meters of accuracy class 0.5 capable of performing the functions of metering in all 4
quadrants .The scope also includes commissioning of the meters by dismantling the existing
electromechanical meters, TTB and suitably installing, wiring new meter and commissioning
of the meters at VSP site. Connection to RTU for SCADA connectivity using MODBUS
protocol or otherwise by ensuring 10 meters per serial loop also is included in the scope of
the supplier. The supplier is expected to bring all tools/tackles and instrument etc. required
for commissioning as mentioned in the
specifications.
MODEMS:
The modems located at site shall be suitable for interfacing the PLCs to Master
Station over existing telephone cables. The selected Modem shall be able to send the signals
up to a distance of 15 KM over telephone cables. For this purpose the existing 5 pair PJF
telephone cables of RTUs shall be utilized for connecting the modems as well. Point to point
modems shall be considered. The modems shall be housed in suitable metallic enclosure and
mounted in the RTU/PLC panel in the field and separate panel in E&T centre. The modems
shall be duplex type The modems shall be suitable for the ambient temperature of 45 Deg C
and shall be UL certified. The modems shall be dedicated line type for industrial applications.
The interface shall be as required to connect to the RTU. The modems shall be suitable for
SCADA applications.
UPS SYSTEM:
For RTUs and remote work stations separate UPS systems shall be provided. Total 26
nos UPS systems shall be provided. A feeder with 230V +10% / - 10%,1Phase,
50Hz+/-3% will be made available. UPS rating shall be as per the requirement of
complete equipment covered in tenderer scope + 25% spare capacity. In the proposed UPS
system the batteries should be sealed maintenance free lead acid type. In case of power
failure the backup time of the UPS to be 30 minutes with resistive load (Unity Power factor).
The AH rating of the offered batteries shall be selected accordingly. The batteries shall be
mounted in a suitable metallic enclosure.
COMMUNICATION CABLES:
The communication cables like ETHERNET bus network and Modbus cable shall be
industry standard for process control. All these communication cables shall be routed through
suitable size GI conduits and GI conduits to be included in the scope of work. The OFC cable
between proposed SCADA server and the existing IBM server shall support 1Gbps data
transfer. Same shall be single mode, 6-core armored type. The specifications of PJF armored
cables shall be same as the existing cables.
CONTROL CABLES:
All the control cables shall have spare cores of 20%. The control cable shall be of 1.5
sq.mm size, 1100 V grade,Annealed tinned Copper core, multistrand conductor, PVC
insulated, PVC sheathed, un-armoured cables conforming to IS 1554.
The size of the cables/wires considered for the internal wiring of the PLC panels unto
the terminal blocks shall be as per the PLC manufacturer's standard only.
POWER CABLES:
The power cables shall be ATC copper core, multistrand,PVC insulated, PVC sheathed, un-armoured cables conforming to IS 1554. The size and voltage grade of power cables shall be done as per the requirement and PLC manufacturer's standard only.
CONCLUSION
Supervisory control and data acquisition system is a versatile network of intelligent sub systems, which has brought revolution in the field of monitoring and controlling systems. Further it was a very time consuming process to undo the effect causing the problem (only after making sure the data received is correct). In the mean time a lot of energy is waste and sometimes even unacceptable hazards also used to take place. Also there was no privilege to track the position that is responsible for the error.
The supervisory control and data acquisition system over comes all the above bottlenecks. It has host computer in the master station to store the data for a long period of time so that it can be sued to take strategic decisions sat the time of crisis.
The SCADA System for Vizag Steel Plant shall acquire various electrical and utility parameters for effective monitoring and control operations. The various parameters acquired shall be such as electric power, voltages, currents,flow, temperatures pressures, etc.
These parameters are logged into the system using a suitable database management system. The data is processed and presented in the plant to the concerned officials and operators using user-friendly graphical interfaces.
Advantages of SCADA system are:
High availability of front-end processors to dual access hardware. Scalability due to provision for expansion for Field Remote terminal units, front end
processors, intermediate serial port cards and memory / processors of the host and other computer systems.
Upgradability of hardware and software Standard interfaces like RS 232, LAN etc are provided for interfacing with other
systems and applications. Availability of standard interfaces for interoperability with other systems like central
computer, power plant computer, etc.
Thus SCADA is system has proven that a better technology establishment is a one – time cost but the fruits we see from this are continuous and encouraging.