Scada Report

85
ANNEXURE – VII PROJECT REPORT (Project Semester January-June ) STUDY OF SCADA SYSTEM IN POWER MANAGEMENT Submitted by SACHIN GUPTA Roll No 1040556 AMANDEEP SINGH Roll No 1040544 Under the Guidance of 1

Transcript of Scada Report

Page 1: Scada Report

ANNEXURE – VII

PROJECT REPORT

(Project Semester January-June )

STUDY OF SCADA SYSTEMIN POWER MANAGEMENT

Submitted by

SACHIN GUPTA

Roll No 1040556

AMANDEEP SINGH

Roll No 1040544

Under the Guidance of

Mr. NIRBHAOJAP SINGH Department Of Electrical and instrumentation Engineering

THAPAR INSTITUTE OF ENGINEERING & TECHNOLOGY, PATIALA(Deemed University)

June/December 200ANNEXURE – VIII

1

Page 2: Scada Report

DECLARATION

I hereby declare that the project work entitled (“Title of the project”) is an authentic record of

my own work carried out at (Place of work) as requirements of six months project semester

for the award of degree of B.E. (Civil Engineering), Thapar Institute of Engineering &

Technology (Deemed University), Patiala, under the guidance of (Name of Industry

coordinator) and (Name of Faculty coordinator), during June to December, 2003).

(Signature of student)(Name of Student)

(Roll No.)

Date: ___________________

Certified that the above statement made by the student is correct to the best of our knowledge and belief.

(Name & Designation) (Name & Designation)

Faculty Coordinator Industry Coordinator

2

Page 3: Scada Report

ANNEXURE – VI

CONTENTS OF THE REPORT

1. Cover page – on hard paper2. Inner page – same as cover page but on the soft paper3. Declaration4. Acknowledgement (if any)5. Contents

Summary Introduction Work Industry Review Details of the work including work programme & results Conclusions and Future Scope of Work References (if any)

6. Impediments/difficulties faced during project semester on project work; Suggestions related to work/project semester.

Please note the case of letters in the cover page. The 3rd. line is 16 pt bold and other lines are 12 pt. The page is centered. Department and Institute names are bold.

The matter contained in the report should be typed in MS word (1.5 spacing) Times New Roman, 12 pt or equivalent with other software.

Figures and tables may be inserted in the text as they appear or may be appended in order.

List of references shall be appended at the end.

Subject matter should be typed on both sides.

A total of THREE copies may be prepared – one for the student, second for the industry coordinator and third for the institute.

3

Page 4: Scada Report

INDEXINDEX

1. Summary2. Introduction 3. Work – 4. Industry - 5. Review6. Details of the work including work programme & results 7. Conclusions and Future Scope of Work8. References (if any)9. Impediments/difficulties faced during project semester on project work;

Suggestions related to work/project semester

1) INTRODUTION...........................................................................................................4

2) ABOUT SLDC (PATIALA).....................................................................................4

3) WHAT IS SCADA SYSTEM...................................................................................5

3.1) SUPERVISORY CONTROL.......................................................................................................5

3.2) DATA ACQUISITION................................................................................................................6

4) MAIN FEATURES.....................................................................................................6

5) LIST OF GRID SUB STATIONS AND THERMAL/ HYDRO GENERATING STATIONS COVERED UNDER SLDC PROJECT.................7

6) MAIN OPERATION OF SLDC.............................................................................9

6.1) Frequency Control....................................................................................................................9

6.2) Voltage Control.........................................................................................................................9

6.3) Line loading............................................................................................................................10

6.4) Operating manpower...............................................................................................................11

7) COMPONENTS OF SCADA...............................................................................11

7.1) Transducers.............................................................................................................................11

7.2) Potential Transformers and current Transformers..................................................................12

4

Page 5: Scada Report

7.3) Remote Terminal Unit (RTU).................................................................................................13

7.4) MODEM.................................................................................................................................18

7.5) Power Line Carrier Communication (PLCC).........................................................................19

7.6) FRONT END PROCESSOR..................................................................................................20

7.7) COMMUNICATION BETWEEN SERVER AND RTU:.....................................................20

8) DATA DISPLAYS....................................................................................................20

8.1) Sources & types of Data.........................................................................................................23

9) COMMUNICATION MEDIA...............................................................................25

10) SYSTEM CONFIGURATION..............................................................................25

10.1) RSCC hardware Subsystems description................................................................................27

10.2) Communication Front-Ends....................................................................................................28

10.3) ICCP servers...........................................................................................................................30

10.4) ISR servers..............................................................................................................................31

10.5) DTS server..............................................................................................................................33

10.6) Development server................................................................................................................34

10.7) Operator consoles...................................................................................................................34

10.8) DTS operator consoles............................................................................................................36

10.9) Network Management console...............................................................................................36

10.10) Development Console.............................................................................................................36

10.11) LAN and WAN equipment.....................................................................................................36

10.12) Remote VDUs.........................................................................................................................37

11) SCADA SUBSYSTEM............................................................................................38

11.1) Functional overview................................................................................................................38

11.2) Data acquisition.......................................................................................................................39

11.3) Host SCADA..........................................................................................................................39

11.4) Telemetry Front End...............................................................................................................40

11.5) Communication Front End......................................................................................................40

5

Page 6: Scada Report

11.6) RTU........................................................................................................................................40

11.7) Data flow.................................................................................................................................42

11.8) External data...........................................................................................................................42

11.9) Data processing.......................................................................................................................42

11.10) Data quality checking.............................................................................................................44

11.11) Supervisory control.................................................................................................................45

12) USER INTERFACE MANAGEMENT SYSTEM...........................................46

12.1) Menu Directory display..........................................................................................................47

12.2) System Directory display........................................................................................................47

12.3) Transmission System Overview display.................................................................................47

12.4) Interchange displays...............................................................................................................48

12.5) Substation Graphic Displays Menu display............................................................................49

12.6) Transmission Line Graphic Displays Menu display...............................................................49

12.7) Transmission Line Graphic display........................................................................................49

12.8) Abnormal summary display....................................................................................................50

13) HISTORICAL INFORMATION AND MANAGEMENT............................50

14) UTILITIES USED BY SCADA SYSTEM.........................................................52

14.1) Alarms: -.................................................................................................................................52

14.2) Tagging: -................................................................................................................................52

14.3) Trending: -..............................................................................................................................53

6

Page 7: Scada Report

1)1) INTRODUTION

Power Grid Corporation of India Ltd. has implemented the Unified Load Dispatch &

Communication Project for all the constituents of Northern Region and central sector. Under

this project computerized SCADA/ EMS (Supervisory Control & Data Acquisition/ Energy

Management System) has been installed at SLDC Patiala and two Area Load Dispatch

Centers (ALDCs) at Lalton Kalan (Ludhiana) and Jamsher (Jalandhar). 19 Nos. Remote

Terminal Units (RTUs) have been provided by PGCIL itself under this scheme.

PSEB has already implemented Interim SCADA scheme provided by M/s C-DAC

Bangalore, through which on line data is available at SLDC Ablowal from 15 Nos. RTUs

since 1997-98. On line data with NRLDC is also being exchanged through this scheme. 6

Nos. additional RTUs have recently been provided by PSEB. Thus in total data from 40

Nos. important Sub-Stations and Generating stations of PSEB are available for online

monitoring and Energy Management through SCADA/ EMS system at SLDC Patiala and at

the ALDCs.

From Remote Terminal Units to control center connectivity PLCC, Fiber optics &

Microwave communication network is used, whereas for inter control center connectivity,

wide band trunk line Microwave system is used.

2) ABOUT SLDC (PATIALA)

Power Grid of India Ltd is implementing the unified load DESPATCH &

communication project. For all the constituents of Northern Region & central sector projects

under World Bank funded scheme. Under this project SCADA/EMS (Supervisory Control

& Data Acquisition/Energy Management System) has been installed at SLDC Patiala & two

ALDCs (Area Load DESPATCH Center) at Lalton Kalan (Ludhiana) & Jamsher

(Jalandhar). 19 numbers of Remote Terminal Units are being provided by PGCIL itself

under this scheme.

PSEB has already implemented interim SCADA scheme provided by the M/S C-

DAC Bangalore, through which on line data is available at SLDC Ablowal from 15 nos.

RTUs since 1997-98. Online data with NRLDC is also being exchanged through this

scheme. 6 nos. additional RTUs are being provided by PSEB, thus total data from 40 nos.

important substations & generating stations of PSEB shall be available for monitoring &

Energy Management through SCADA/EMS system at SLDC Patiala.

7

Page 8: Scada Report

3) WHAT IS SCADA SYSTEM?

In the late 1960s and early 1970s SCADA came into existence. SCADA

stands for “Supervisory control and Data acquisition”. This system is

responsible forgathering, processing and displaying information about the state

of monitoring system. From a SCADA control center, operates and application

programs can oversee and change the operating state of monitored devices. It

enables operators to control field devices for their consoles. The system must

be able to acquire & present large amount of data securely, clearly &

coherently so that an operator can make appropriate decision. Thus both

current live data and list data is required here.

In a limited sense, the concept implies a remote controlling station,

which monitors & controls system situated at some distance, in the field of

electrical transmissions and distance networks i.e. multiple substations being

controlled from the control room. In the multi site system, one site is usually

designated as host site, while other are called remote or foreign sites. Host site

is the recipient of data transferred from remote sites. Each site communicates

to its remote terminal units by way of phone lines, microwave or fiber optic

cable.

At the control site, SCADA usually runs on computers. One performs

real time function i.e. gathering, processing and displaying of real time data.

This system is known as primary. The other computer acts as a backup and

referred as secondary. If primary computer fails it take over real time

operations.

3.1) SUPERVISORY CONTROL

SCADAs supervisory control function allows the operator and application

Programmer to control devices in the monitored systems. From the control

center the SCADA operator can issue control commands to change the state of

such devices as circuit breaker and switches.

8

Page 9: Scada Report

3.2) DATA ACQUISITION

Data Acquisition means to collect data and manipulate it or scanning of

data. Remote terminal unit sends the raw data to communicate the front ends

which perform some conversion and checking on the data before sending it to

the telemetry front end and thus to the host.

SCADA performs the following functions to acquire data for devices in the

monitored system:

1) Scan the monitored system at prescribed tomes and receive data from

RTU via CFE (Communication Front End).

2) Perform calculations on the data for other applications programs.

3) Determine the quality of data.

4) SCADA can acquire process and display data from three types of devices

in the monitored system. These device types are:

a) Analog state devices are used for numerical measurement such as

MW, MVAR etc.

b) Status devices have two conditions such as on and off such as

circuit breakers, isolators.

c) Pulse accumulator devices are used for measurement of energy.

4) MAIN FEATURES

The project involves the following main features:-

1) Establishment of a Computer based control center for SCADA/ EMS function at

Patiala (SLDC) and two Area Load Dispatch Centers (ALDCs) at Lalton Kalan

(Ludhiana) and Jamsher (Jalandhar).

2) On-Line acquisition of data viz. MW, MVAR, Direction of Power Flow, Voltage,

Frequency from 40 nos. stations including most of the Generating Stations situated

within Punjab state (List Enclosed)

3) Acquisition of Digital status of all circuit breakers, isolators, tap changers &

Sequence of Event (SOE) recording covered under the scheme.

4) On-Line display at SLDC & ALDCs on Operator Consoles and Magnified Video

Projection Screen at SLDC Patiala.

9

Page 10: Scada Report

5) Provision of Remote Video Display Unit for Head Office for Board Management

reporting purpose.

6) On line acquisition of weather data for load forecasting through a weather station

installed at SLDC

7) Control Operation from remote Control Centers on selective lines/ transformers as

and when required meeting the power system demand.

5) LIST OF GRID SUB STATIONS AND THERMAL/HYDRO

GENERATING STATIONS COVERED UNDER SLDC PROJECT

A) Under Interim SCADA Scheme:

Generating Stations:

1) 220kV sub-station at Ropar Thermal (GGSSTP) Power Station.

2) 220kV sub-station at Bathinda Thermal (GNDTP) Power Station.

3) 132kV sub-station at Shanan Hydel Power House (Joginder Nagar, HP).

4) 132kV sub-station at Anandpur Sahib Hydel Power House No. 2.

5) 132kV sub-station at Mukerian Hydel Power House No. 2.

6) 132kV sub-station at Mukerian Hydel Power House No. 4.

Sub Stations:

7) 220kV Ablowal, Patiala.

8) 220kV Lalton Kalan, Ludhiana.

9) 220kv Jamsher, Jalandhar.

10) 220kV Moga.

11) 220kV Malerkotla.

12) 220kV Gobindgarh-1.

13) 220kV Sarna.

14) 220kV Wadala Granthian.

15) 220kV Mohali.

B) Under Unified SCADA Scheme:

Sub Stations:

16) 220kV Sultanpur.

17) 220kV Patti.

10

Page 11: Scada Report

18) 132kV Verpal.

19) 220kV Verka.

20) 220kV Civil Lines Amritsar.

21) 132kV Batala.

22) 220kV Butari.

23) 132kV Bhogpur.

24) 132kV Mahilpur.

25) 220kV Dasuha.

26) 220kV Goraya.

27) 220kV Nawashahar.

28) 220kV Muktsar.

29) 132 kV Muktsar.

30) 220kV Dhandari Kalan.

31) 220kV Ferozepur.

32) 220 kV Sunam.

33) 220kV Barnala.

34) 220kV Gobindgarh-2.

C) Additional Stations Covered:

Generating Stations:

35) 220kv sub-station at Guru Hargobind Thermal Power Station, Lehra Mahobbat.

36) 220kV sub-station at Ranjit Sagar Hydel Power Plant, Thein (near Pathankot).

37) 132kV sub-station at Anandpur Sahib Hydel Power Plant-1.

Sub Stations:

38) 132 KV Substation, Pathankot.

39) 220 KV Substation, Rajpura.

40) 220 KV Substation, Mansa (near Bathinda).

41) 220 KV Substation, Jagraon (near Ludhiana).

42) 220 KV Sub station, Sahnewal (near Ludhiana).

43) 220 KV Sub station, FatehGarh Churian (near Amritsar).

44) 220 KV Sub station, Kartarpur (near Jalandhar).

45) 220 KV Sub station, Nakodar (near Jalandhar).

46) 132 KV Sub station, Chohal (near Hoshiarpur).

11

Page 12: Scada Report

47) 132 KV Sub station, Kangra (H.P.).

48) 132 KV Sub station, Sarna (near Pathankot).

6) MAIN OPERATION OF SLDC

One of the main assumptions of the power system planner is that the system

parameters viz. frequency, voltage remains close to nominal values. This section lists the

measures to be adopted by the system operators at SLDCs / ISGS / substations for frequency

and voltage control.

6.1) FREQUENCY CONTROL

All the regional constituents would make all possible efforts to ensure the

maintenance of grid frequency within the normal band i.e. 49.0 to 50.5 Hz. This would be

ensured by adhering to the following steps:

1) Each SLDC shall regulate the load / own generation under its control so that it may

not draw more than its net drawl schedule during low frequency conditions and less

than its drawl schedule during high frequency conditions.

2) Sudden reduction in generator output by more than one hundred (100) MW unless

under an emergency condition or to prevent an imminent damage to the equipment

shall be avoided, particularly when frequency is falling below 49.0 Hz.

3) Sudden increase in load by more than 100 MW by any SLDC, particularly when

frequency is falling below 49.0 Hz. and reduction in load by such quantum when

frequency is rising above 50.5 Hz. shall be avoided.

6.2) VOLTAGE CONTROL

As defined in the IEGC section 6.2 (g), the operating range of the voltage at various

voltage levels of grid are as follows:

Voltage in KV (RMS)

Nominal Maximum Minimum

400 420 360

220 245 200

132 145 120

12

Page 13: Scada Report

The maximum and minimum values in the above table are the outer limits and all the

constituents would endeavor to maintain the voltage level well within the above limits.

1) In the event of high voltage (e.g., 400kV bus voltages going above 410kV), the

following specific steps would be taken by the respective grid substations /

generating station at their own, unless specifically mentioned by NRLDC otherwise;

a) The bus reactors be switched in

b) The manually switchable capacitor banks be taken out

c) The switchable line/ tertiary reactors be taken in

d) Operate synchronous condensers for VAR absorption

e) Operate hydro generators / gas turbines as synchronous condenser for VAR

absorption wherever possible

f) Opening of the lightly loaded lines in consultation with NRLDC, keeping in

view the security of the balance network.

2) In the event of low voltage, (e.g., 400kV bus voltages going down below 390kV),

the following specific steps would be taken by the respective grid substations /

generating station at their own, unless specifically mentioned by NRLDC otherwise;

a) The bus reactors be switched out

b) The capacitor banks be switched in

c) The switchable line / tertiary reactors be taken out

d) Operate synchronous condensers for VAR generation

e) Operate hydro generators / gas turbines as synchronous condenser for VAR

generation, wherever possible

f) Closing of lines which were opened to control high voltage, in consultation

with NRLDC

6.3) LINE LOADING

In addition to frequency & voltage control measures outlined above, each system

operator would also have before him the thermal loading limits, surge impedance loading

and the loading permitted from stability considerations for each line listed under important

elements. Each system operator at SLDC / substations would endeavor to keep the line/ ICT

loadings within limits and inform NRLDC in case of overloading of any element. Special

emphasis would be paid by each system operator in identifying credible system

13

Page 14: Scada Report

contingencies & continuously evaluating the system under his control against these

contingencies.

6.4) OPERATING MAN POWER

The control rooms of all SLDCs, power plants, grid substations as well as any other

control centers of regional constituents shall be manned round the clock by qualified and

adequately trained manpower who would remain vigilant and cooperative at all the times so

as to maintain the system safety and security and operate it in a most optimum manner.

7) COMPONENTS OF SCADA

The SCADA system used in the SLDC project consists of:

1) Transducers

2) Potential and Current Transformers

3) Remote Terminal Unit (RTU)

4) MODEM

5) Power Line Carrier Communication (PLCC)

6) Front End Processor

7) LAN

8) Main Server

7.1) TRANSDUCERS

Transducer is a device, which provides a transformed output in response

to a specific measured value given as input.

The basic functions of transducer are:

1) To measure/ to sense the change in parameters.

2) To convert the measured values from one form into another form, that is

useful for further processing.

Depending on the type of the output from the first function, the conversion function

(i.e. conversion into engineering units) may or may not be present. The various

parameters involved in the Power System analysis are: -

1) Active power

2) Reactive power

14

Page 15: Scada Report

3) Voltage

4) Current

5) Status of circuit breakers

Out of these the current and the voltage are stepped down to a value

suited to the respective transducers. The status of the circuit breakers are

sensed using energized relays connected to either the OPEN or CLOSE position

of the circuit breaker. While selecting a transducer for any specific measuring,

one should consider the following criteria.

Type of measuring

1) Number of measurements

2) Sensing element

3) Transduction element

4) Range of measurement

The Conversion is a process, which involves presentation of measured

value in a specific format to the user. They convert the analog input to digital

input to be interfaced to the computer directly. The Transducer Panel at SLDC

has 11 Transducers, out of which 8 are the main Transducers and 2 are voltage

Transducers, and one is frequency Transducer. The main Transducer consists of

4 CTs (only R & B phases), 3 PTs, 1 neutral point, 1 earth point, 2 points for

dc supply (48 V, to energize the T/D), 2 points of Ms, and 2 points for MVARs.

15

Page 16: Scada Report

7.2) POTENTIAL TRANSFORMERS AND CURRENT

TRANSFORMERS

Instrument transformers find a wide application in protection circuits of

power system for the operation of over current, under voltage, earth fault and

various other types of relays. In all these applications the instrument

transformers are used for scaling down the values to an acceptable range. As in

power system, current & voltage handled are very large and therefore the direct

measurement of these quantities is not possible using measuring devices.

Transformers used for the measurement of voltage are called potential

transformers. The primary winding is connected to the voltage being measured

and the secondary winding, to a voltmeter. The PT steps down the voltage to

the level of voltmeter specification used in the project. Here this is 110 KV/

110V.

Transformers used for the measurement of current are called current

transformers. The primary winding of a current transformer is so connected

that the current being measured passes through it and the secondary winding is

connected to an ammeter. The CT steps down the current to a lower level. The

current transformer is used with its primary winding in series with the line

carrying the current to be measured and, therefore the primary current is

dependent upon the load connected to the systems and is not determined by the

load connected on the secondary winding of the CT. The primary winding

consists of very few turns and therefore, there is no appreciable voltage drop

across it. The secondary winding of the CT has large number of turns, the exact

number being determined by the turn’s ratio. The ammeter or wattmeter current

coil is connected directly across the secondary winding terminals.

current transformer a) wire lead b) split core

frequency – 50 -400 hz

16

Page 17: Scada Report

Thus the CT operates with its secondary winding nearly under short

circuit conditions. On the terminal of the secondary winding is earthed so as to

prevent damage to the equipment and personnel in the vicinity in the event of

insulation failure in the CT. Specification used in the substation is 230 KV/

110 KV. The output of PT should be zero when the supply is zero. In order to

nullify the output when the supply is zero, auxiliary supply is used.

Specifications used at SLDC are 600 KV/ 1000 KV.

7.3) REMOTE TERMINAL UNIT (RTU)

Typical RTU has a network interface (usually either Ethernet,

proprietary, or both), a simple processor, some environmental sensors, some

override switches, and a bus, which it uses to communicate with devices and/or

interface, boards. This bus is sometimes called a device bus or a field bus.

Standards include the ISO Controller, Area Network, MODBUS, and others.

Sometimes a device or field bus standard can be used to interconnect RTUs and

host systems as well as field devices and RTUs.

17

Page 18: Scada Report

RTUs are basically distributed SCADA based systems used in remote

locations. They are rugged and should be able to work unattended for a long

duration. There are two modes in which RTUs work:

i. Under command from central computer.

ii. Stand alone mode.

Since these RTUs have to operate for a long duration unattended the

basic requirements would be that they consume minimum power and have

considerable self-diagnostic facility. The main parts of RTUs are:

MAJOR COMPONENT OF SCADA REMOTE TERMINAL UNIT

The RTUs consist of process module, analog and digital input modules and

communication interface, power supply unit and screw termination on the rear of the panel

for field connections. The data is acquired form various stations with the help of RTUs.

The various parameters, which are to be acquired, are first taken from the sub

station/generating station through current transformer and potential transformer and

brought to the control room in the control panels. From these control panels the

connections are taken and given to the transducers, which lower down the energy levels of

the signals. These signals are of two types- digital and analog. RTU support data

transmission at the rate of 50 to 9600 bits per sec.

The basic functions of RTU are:

1) Collect power system data

2) Filter and process the system data

3) Transmit data to control center

4) Receive the control commands

HARDWARE

The general arrangement of sub-system inside the RTU panel is given in figures.

All the sub-systems have been designed in standard 19” rack. The sub systems are

modulated in construction facilitating easy maintenance.

The power supply unit is placed at the top of the panel. The Circuit breakers with

indication lamps are provided for 230V, 48V DC and 24V DC power supplies. A fan tray

is provided below the power supply unit. The 6U rack containing the processor and I/O

module is placed below the fan tray. The 6U rack has a motherboard, which can

accommodate up to 12 I/O modules in addition to processor module (PCU). The sub rack

consists of following hardware modules:

18

Page 19: Scada Report

1) Process control unit (PCU)

2) Digital input card (DI)

3) Analog input card (AI)

19

Page 20: Scada Report

FRONT VIEW OF RTU

20

Page 21: Scada Report

1) PROCESS CONTROL UNIT (PCU)

The PCU module contains a powerful 32-bit processor (CPU), memory, serial

channel interfaces and I/O bus interface. The processor T805 has a built in 64-bit Floating

Point Unit (FPU), 4K bytes of on-chip RAM, 32 bit timer and a micro coded scheduler.

The processor supports multiple CPUs to be connected through links in case higher

computing power is required. Provision has been made to add processor modules in the

TRAM sockets of the PCU board.

The board has 2Mbytes of EPROM to store the program for scanning, limit

checking and engineering unit conversion. It has 4Mbytes of static RAM for storing the

data.

The board supports 4 serial channels, which can be configured as RS232/422/485

to facilitate multi-master communication. It has a real time calendar clock circuit providing

timing for time stamping.

SPECIFICATIONS

1) T805 32 bit CPU with 64-bit Floating Point Unit (FPU).

2) 2MB EPROM.

3) 4MB RAM (Static).

4) Real time calendar clock.

5) 2- RS 232C ports for communication to the master stations.

6) 1-RS 485 / RS 422 port for communication to the console.

7) 1-RS 485 port.

8) 1 parallel port for printer.

9) Power requirements: 5V, 3A.

10)Board size: 220mm x 233.5mm.

2) DIGITAL INPUT CARD

The digital input modules have fully isolated 16 channel digital inputs. All inputs

are protected against high voltage surges. Constant over voltage protection is provided for

all inputs. Input noise suppression and filtering allows reliable operation in hostile

conditions. Galvanic isolation of the field signals from the logic circuitry is obtained

21

Page 22: Scada Report

through the OPTO couplers. A ground line running through the center of optocouplers on

both sides of the PCB physically separates the field bus from the logic circuits and the

front bus. This protects the rest of the systems in case any hazards occur in high field

circuitry. The block diagram is given in figure.

LED indication is provided on the front panel for each channel. It lights on a high

input to the respective channel. The detail of the front panel is given in front panel

diagram.

The processor can access any of the 16 channels through the front I/O bus.

3) ANALOG INPUT CARD

The 16 channel isolated analog input module is a complete fully isolated input

system containing 16 different channels on a 6U Euro board. It is ideal for industrial

applications requiring measurement of non-isolated transmitter signals in the presence of

high common mode voltages and ground loop noise. Each input channel consists of a

highly reliable flying capacitor multiplexer utilizing mercury wetter/dry read relays. These

input channels feed a stable instrumentation amplifier and conversion is accomplished by a

12 bit A/D converter. The result is an input signal having noise immunity up to 100CMV

(Common mode Voltage).

The board accepts 16 channel of analog signal as its input. Depending upon the

particular channel selected, it provides an equivalent 12 bit digital data as output. The

block diagram is given in figure.

The signals are connected to the font D 37 female connecter of the board. When the

board and a particular channel are selected, all the relays are actuated. The capacitor,

which was connected to the selected relay, will now be connected to the input by the

multiplexer ADG508. The change over contacts thus provides necessary isolation during

analog to digital conversion. The output of INA is fed to the input of ADC, which operate

at 0-10V range. The ADC converts this0-10V to its equivalent digital value and store it in

a buffer inside ADC.

COMMUNICATION THROUGH MODEMS:

The Communication at SLDC is possible in two ways:

1) Communication Media like PLCC microwave.

2) Modem

Here I am explaining the Communication through Modems.

22

Page 23: Scada Report

7.4) MODEM

The term MODEM is an acronym for Modulator-Demodulator. The primary

modem function is to convert digital data into analog form, which is suitable for

transmission on common carrier circuits. Modulation is the D/A conversion in which the

digital data is placed on the transmission line by modulation of a tone or carrier

Demodulation is the reverse process. In a data communication system, transmitting and

receiving modems are necessary at each end of the analog transmission line. The output

transmitting circuits and receiving circuits are networks required for transmitting and

receiving analog information to and from the transmission line.

Three modulation techniques are commonly used:

1) Amplitude modulation

2) Frequency modulation

3) Phase modulation

Modems operate with one functioning as an originate unit and the other as an answer

unit. The originate modem transmits on a low frequency channel, using 1.27 KHz for a mark

and a 1.07 KHz for a space. It receives on a high frequency channel using 2.225 and 2.025

KHz respectively for a mark and space. The answer modem transmits on the high frequency

channel and receives on the lower frequency channel. The timing circuit provides the basic

clocking information for both the transmission as well as reception of signals. A crystal

oscillator to within about 0.05% of the normal value usually controls the internal timing.

Modem is used to adjust the output level of data the computer data is converted to

analog waveforms as carries and this composite signal passes through our common

telephone lines to reach the destination, where the carriers is removed and the original data

is given to the computer. Modems are generally used to convert various nodes of data

network. This is connected between computer and telephone lines, in the information

technology industry, computer is known as data terminal equipment (DTE) and modem is

known as data communication equipment (DCE). Modems are classified by their data rates

or by V. (V.DOT) standards. Modem data rates are the number of bits transferred per second

over the communication line. It does not refer to the data rate at which DTE communicate

with DCE.

23

Page 24: Scada Report

7.5) POWER LINE CARRIER COMMUNICATION (PLCC)

Carrier current provides a means of conveying speech; metering indications, control

impulses etc. from one station to another by existing transmission lines without interfacing

with their normal function of transmitting power. The main elements of carrier channel are

sending terminal assembly including line matching and tuning, a coupling capacitor,

receiving station coupling, terminal assembly and the power line.

1) COUPLING CAPACITOR

Coupling capacitor is the most widely used for coupling means. The typical units

range in voltage and capacitance from 46 KV, 0.015 micro farads to 765 KV, 0.004 micro

farads. The capacitor is mounted on a metal base to provide convenient installation and

space for connection to its lower terminal. The base contains 60 Hz drain coil and may also

contain protective gaps, grounding switches and a part or the entire coupling network.

2) LINE TUNING

Line tuning is required to tune out the reactance of a capacitor with a suitable

inductance; the simplest application involves the coupling of a single frequency between a

single line conductor and ground using a single coupling capacitor. It provides an efficient

path for coupling the carrier signal to the line conductor.

Carrier terminal with it co-axial is matched to the impedance of the power line by an

adjustable impedance matching transformer. Impedance matching of the transmitter,

receiver and the transmission line is required to allow maximum transfer of energy.

Therefore where there is more than one transmitter coupled to the line at a common

point there should be a resonant path for each frequency. The practical Upper limit of

resonant tuning is two frequencies. Above this, broadband tuning provides a most

satisfactory solution. Where future expansion is expected, it may be preferable initially to

design the circuit with broadband tuning, since a reasonable number of additional carrier

circuits may then be introduced at any time without disturbing the existing circuits.

3) LINE TRAPS

Line Traps are used to make the transmission line appear as simple two terminal line

used in telephone circuits. They direct the carrier wave over a given circuit, increase the

efficiency, smoothes the frequency characteristics, minimize the interference, prevent the

interruption of the communication channels when the ground switches are closed, block off

he supply lines and allows the transmission during a nearby external fault.

4) ATTENUATION

24

Page 25: Scada Report

Attenuation is the measure of the loss of energy between the transmitting and the

receiving terminals and depends upon many factors like frequency, conductor size and

spacing, line configuration, presence of ground wires or parallel circuits, transpositions,

ground sensitivity and weather conditions. The type of coupling used and the phase to which

it is applied affects the total attenuation from terminal to terminal.

7.6) FRONT END PROCESSOR

1) COMMUNICATION FRONT END

The communication equipment and software that links the computer to RTUs is

referred as communication front end. One RTU is located at the site and other at the

remote station.

Functions of CFE: it drives the serial communication lines connected to the RTUs.

The CFE hardware configures consists of Ethernet controller’s card several serial

communication cards. The number of communication card depends on the number of

RTUs connected to where each card can support up to16 communication lines with RTUs.

2) TELEMETERED FRONT END

The software that communicates between the data server and CFE is called

telemetric front end. In addition to this, TFE also maintains information regarding the

configuration of the communication components and facilitates interfacing with devices

having a variety of communication protocols.

7.7) COMMUNICATION BETWEEN SERVER AND RTU

In SCADA system, each control site has two host computers. There will be two

redundant TFEs, which will both be in communication with operational SCADA. Each

telemetry front end and communication front end functions as independent unit. Host

computer will continue scanning. The host may switch communication from one path to an

alternate path that is on another CFE or TFE without requiring a host failure. The CFEs

communicate with RTUs and performs several functions to minimize data processing on

the host computer.

8) DATA DISPLAYS

There are two types of displays:

25

Page 26: Scada Report

1) Online Display

2) Tabular Display

In a one line or single line display whole network is made up of single

lines and graphical symbol are used for different components. One-line

diagrams give the current state of the operating devices and also give on line

data. We can give command from one line diagram to control the state of the

devices and can change the way of displaying the data.

ONLINE DISPLAY

26

Page 27: Scada Report

Tabular display also gives the state of the operating devices and current

data. But in this case information is in the tabular form i.e. in the form of rows

and columns. Tabular usually contains more information the one line displays.

TABULAR DISPLAY

8.1) SOURCES & TYPES OF DATA

Each piece of data that SCADA acquires has a source from which it is

normally acquired. The normal source of data is the RTU. However, SCADA

may also get data from another SCADA site, a calculation, an operator entry or

another process eternal to SCADA system.

The system has three different types of data:

27

Page 28: Scada Report

1) ANALOG DATA

Analogs are numeric values representing the state of variable-state

devices, such as power lines, transformers and pumps. Analog measurements

are stored in analog records. In the monitored system a transducer usually

measures a physical variable and the output of transducer is passed through an

analog to digital converter in the RTU. The A/D converter produces a number

that the host computer can process. All analog values are converted to host

computer floating-point numbers and adjusted by the host computer to

represent the physical measurements in MWs

For example: Voltage and Current.

2) STATUS DATA

Status values represent the state of discrete state devices, such as C.Bs,

tap changers and valves. SCADA can accept I/Ps represent a simple on/off or

Open /closed input, or a combination of inputs from a three-state device. All

status point values are stored in POINT records in the SCADA database.

For example: Status change of Circuit Breaker.

3) COUNT DATA

A count measurement is a value from pulse accumulator. Pulse

accumulators are often used to measure the total amount of energy, liquid or

gas that has passed by a specific location in the monitored system. The

detection device alternately opens and closes a contact each time a unit of the

measured matter passes by it. The pulse accumulator counts the contacts

changes and passes the count to SCADA, which stores the total accumulation

of counts since the last time the count was reset.

For example: MWH.

DATA QUALITY

Data quality is a catch all term relating to information the SCADA

operator may want to know about the values SCADA is displaying for

monitored devices. So to provide the operator with answers of certain

questions, SCADA has five groups of data quality indicators:

1) Data source flags

2) Detailed data quality flags

28

Page 29: Scada Report

3) Composite data quality flags

4) State estimator flags

5) Data attribute flags

9) COMMUNICATION MEDIA

The data is required from various stations with the help of RTU. The

various parameters, which are to be acquired, are first taken from the

substation/generating station through current transformers and potential

transformer and brought to the control room in the control panels. From these

control panels the connections are taken and given to the transducers, which

lower down the energy levels of the signals. These signals are of two types-

analog and digital. Analog signal comprise of voltage, current, frequency,

active power and reactive power while digital signals are the circuit breaker

position, isolators position and tap changing position. Analog and digital

signals are given to the digital and analog cards. These analog signals are then

converted in to the digital signals. Finally these signals are fed to the modem

and transmitted. This transmission can be done in number of ways such as PLC

and VSAT depending upon the distance and Economy involved.

VSAT - Very Small Aperture Terminal, Communication through antenna.

PLC - Power Line Communication

MICROWAVE - Communication through Satellite.

FIBER OPTICS – Communication through Co-axial cables

10) SYSTEM CONFIGURATION

The purpose of this presentation is to introduce the hardware composing the

SCADA/EMS system for the Northern region. The presentation is made only to the extent

necessary to understand the functioning of the system, and in particular to detail the major

hardware subsystems and the functions assigned to each. The complete and detailed

information on hardware configurations are described in the release C of the document

‘Hardware Configuration for all control centers (ref. NR-A/N-G00-1-A05)’.The hardware

configuration overview is presented successively for each level of the Northern Region

SCADA/EMS hierarchy:

1) RSCC system configuration.

29

Page 30: Scada Report

2) SLDC systems configuration. Minor differences existing between the SLDCs are

also introduced here.

3) Sub-LDCs and CPCC systems configuration.

The distributed hardware configuration of the RSCC SCADA/EMS system includes

the following subsystems:

1) The SCADA/EMS servers that support the following system functions (SCADA,

Real-time Dispatching, Power System Analysis and Operation Scheduling

functions). The SCADA/EMS servers operate in a primary-standby relationship for

redundancy purposes. SCADA/EMS software is active only on the application server

assigned the primary role.

2) The Communication Front-ends that drives the serial communication lines

connected to the RTUs.

3) The ICCP (Inter-Control centres Communications Protocol) servers that support

intersite exchanges with the SLDCs and the CPCC.

4) The ISR server that is used to perform Information Storage and Retrieval functions.

The ISR servers also operate in a primary-standby redundancy.

5) The DTS (Dispatcher Training Simulator) server and its associated DTS

operator consoles that provide the dispatcher’s training capability.

6) The Development Server and its associated development console that provide

software utilities used to develop and maintain the SCADA/EMS software, displays

and databases.

7) The Operator consoles that handle the man-machine interface for system control

and supervision operations.

8) The Network Management Console that provide the Configuration management,

fault management and performance monitoring capabilities.

30

Page 31: Scada Report

9) The WAN routers, in a redundant configuration, that allow several connections with

the other Northern Region control centres (SLDCs and CPCC) and with the Remote

VDU (Video Display Unit) located in PGCIL Headquarters.

10)The Peripheral equipment such as printers, Video projector, satellite time receiver

system, CD/ROM servers. This architecture is presented in the following schematic

diagram:

RSCC HARDWARE CONFIGURATION OVERVIEW

10.1) RSCC HARDWARE SUBSYSTEMS DESCRIPTION

The RSCC hardware subsystems are interconnected through a high-speed (100 Mbps

between the SCADA/EMS servers and 10 Mbps between all other equipments) Local Area

Network (LAN) that uses a dual Ethernet as the interprocessor backbone.

The state of all hardware subsystems is monitored and reported to the configuration

management utility running on the real-time SCADA/EMS servers. This utility provides

synthetic displays that give an instantaneous view of the state of the overall hardware

system. For maintenance purpose, manual failovers can be initiated from these displays by

31

Page 32: Scada Report

supervising staff. The way monitoring is performed vary according to the hardware type. A

node state for example can be determined by periodically checking that it can respond to a

network (DECNET or TCP/IP) request.

The following section details the hardware components of each subsystem:

1) The real-time SCADA/EMS servers form the central core of the system. They

consist of two high performance Digital 64-bit RISC based AXP machines (“Alpha

servers”) in a dual redundant configuration (Primary and Stand-by). Only one of the

two is required to be operational in order for the subsystem functions to be

operational. The configuration management utility is running on those SCADA/EMS

servers. The failure of one of the two servers is immediately detected. If the failed

machine had the primary role, the configuration management utility notifies the

SCADA/EMS applications on the standby server to assume the primary role, and the

standby becomes the primary server.

2) Each SCADA/EMS server is configured with 512 Mbytes of main memory.

3) Application servers use SCSI (Small Computer System Interconnect) disks. Total

Disk capacity is 12 Gbytes (4 GB + 4 GB + 4 GB) per server.

The disk storage is allocated as follows:

1) System disk. This disk contains the OpenVMS operating system files.

2) Backup of global sections. The EMP databases are resident in host CPU memory as

global sections and exist on disks as global section backing files. In addition, they

are duplicated by data transfers using the EMP BACKUP utility to the standby

server (see after).

3) Files - they store non-HABITAT database data (such as historical data, snapshots of

application databases - also called savecases, display definitions and executable

code).

32

Page 33: Scada Report

10.2) COMMUNICATION FRONT-ENDS

The RTU communication function is handled by two Communication Front Ends

(CFEs) linked to the SCADA/EMS servers through the Ethernet LAN.

The CFE hardware configuration consists of a VME chassis containing an Ethernet

controller card and several serial communication cards from Performance Technology

Incorporation (PTI). The chassis is connected to the local area network via the Ethernet

controller card so that TCP/IP can be used to communicate between the Communication

Front End and the chassis.

The CFE communication cards contain an intelligent communication processor. On

each card there are serial I/O ports for communication with RTUs. They handle requests and

responses at the bit and byte level, doing checks and converting responses into a protocol

independent form and passing them to the SCADA/EMS server. A single request from the

SCADA/EMS server can cause the CFE to scan all its communication lines, check for

changes in the reported data, and report back the results.

The number of communication cards depends on the number of RTUs to connect.

Each card can support up to 16 communication lines with the RTUs. The RSCC will need

three communication cards per CFE.

The standard time Interface to the supplied GPS clock for the RTU synchronisation

is provided by a True Time VME bus card installed in the VME chassis, with the IRIG-B

protocol.

The IRIG time codes are a group of rate-scaled serial time formats containing up to

three coded expressions. The first is time-of-year in Binary Coded Decimal (BCD) and

includes days, hours, minutes, seconds, tenths of seconds, and hundredths of seconds. The

second is a set of elements reserved for encoding various identification, control and other

specific functions. The third is a time-of-day code word in Straight Binary Seconds (SBS).

The IRIG time code formats are serial, width modulated codes which can be in either DC

level shift or amplitude modulated (AM) form.

IRIG format B, Signal B000, is mainly composed of:

1) Frame reference marker

2) Binary coded decimal time-of-year cod word (30 bits)

3) Control functions (27 bits)

33

Page 34: Scada Report

4) Straight binary time-of-day code word (17 bits).

Failures of the Communication Front End or of a communication line appear as

communication errors on a particular path to one or multiple RTUs. When any component in

the communication path to an RTU fails, SCADA assigns scanning of the RTU to any other

alternate path available, using if necessary the other Communication Front End .

Each serial port (V24/V28) on each Communication Front End is directly connected

to the data communication network equipment. Each communication line may be accessed

from two different Communication Front Ends. The following schema presents RTUs

connexion to the CFE, for each type of communication link.

DATA COMMUNICATION NETWORK INTERFACE OVERVIEW

Since the communication network is not part of the scope of this contract, it is not

described in this document.

34

Page 35: Scada Report

10.3) ICCP SERVERS

The ICCP servers are used to handle the inter-centre communications functions with

the SLDCs and the CPCC. ICCP servers operate in a master/standby relationship similarly

to real-time SCADA/EMS servers. Data preservation under failure conditions is insured by

the EMP BACKUP utility.

Two Digital DPWau workstations with 128 Mbytes of RAM and 4 Gbytes of disk

storage are used to ensure a redundant configuration.

Each ICCP server is equipped with a CD-ROM drive, and a Digital Audio Tape

(DAT) drive which allows backup/restore operations.

One processor terminal is delivered with each ICCP server. This processor terminal

is a 15” colour monitor, with dedicated keyboard and mouse.

ICCP SERVERS

35

Page 36: Scada Report

10.4) ISR SERVERS

The ISR servers are used to perform historical data archival and data retrieval

functions. Data sampling is performed from the real-time SCADA/EMS servers. A link is

automatically established between the Primary SCADA/EMS server and the Primary ISR

server when the ISR function is initialised. In the case when a failover occurs, either

between the SCADA/EMS servers or between the ISR servers, the data link is automatically

re-established between the two primary servers.

The ISR servers consist of two high performance Digital 64-bit RISC based AXP

machines (“Alphaservers”) in a dual redundant configuration (Primary and Stand-by). They

are configured in a cluster using the Small Computer System Interconnect (SCSI). SCSI

provides shared storage between the two ISR servers. Only one of the two ISR servers is

required to be operational in order for the subsystem functions to be operational.

Each ISR server is configured with 256 Mbytes of main memory.

36

Page 37: Scada Report

OVER VIEW OF OTHER EQUIPMENTS

The disk configuration for the redundant ISR servers is:

1) One local 4 Gbytes system disk for each server

2) Six 4 Gbytes data disks in a RAID-1 configuration shared by the two servers,

offering a redundant disk capacity of 12 Gbytes per ISR server.

Each data server is equipped with a CD-ROM drive, and an Digital Audio Tape

(DAT) drive which allows backup/restore operations.

One processor terminal is delivered with each ISR server. This processor terminal is

a 15” colour monitor, with dedicated keyboard and mouse.

In addition to the storage capacity detailed above, the ISR servers are also equipped

with an optical disk juke-box offering a total capacity of 80 Gbytes.

10.5) DTS SERVER

The dispatcher training simulator (DTS) function resides on a separate server. In

addition to the system layer and to SCADA/EMS functions identical to those implemented

on the SCADA/EMS servers, it includes the DTS specific functions (Power and Hydro

system model, instructor functions), with a similar man-machine interface. This is an off-

line machine. Software in the DTS is started and run under the instructor (or trainee) control.

Data exchanges with real-time applications is performed by the operator through the use of

HABITAT savecases. Data preservation is performed through manual backup on tapes.

The DTS server consists of one high performance Digital 64-bit RISC based AXP

machine (“Alphaserver”).It is equipped with 512 Mbytes of main memory and 12 Gbytes of

disk storage (4 GB + 4 GB + 4GB).

37

Page 38: Scada Report

DATA SERVERS

10.6) DEVELOPMENT SERVER

The Development server provides the software utilities used to develop and maintain

the system software, displays and databases. This includes a DTS, used as a test tool for

software, database and display modifications.

The Development server consists of one high performance Digital 64-bit RISC based

AXP machine (“Alphaserver”).It is equipped with 512 Mbytes of main memory and 12

Gbytes of disk storage (4 GB + 4 GB + 4GB).

The Development server is equipped with a CD-ROM drive, and an Digital Audio

Tape (DAT) drive which allows backup/restore operations.

One processor terminal is delivered with the Development server. This processor

terminal is a 15” colour monitor, with dedicated keyboard and mouse.

10.7) OPERATOR CONSOLES

There are three types of operator consoles: consoles with 2-CRT, consoles with 1-

CRT and operation scheduling consoles with 1-CRT. Those operator consoles contain the

Man Machine Interface (MMI) software that allows operators to interact with the EMP

functions running on the servers.

Operator consoles with 1-CRT.

38

Page 39: Scada Report

OPERATOR CONSOLES

There are 2 operator consoles with one CRT. Each operator console is a Digital

DPWau AXP workstation, with a 21” colour monitor. Each workstation has a redundant

connection to the LAN. Input is accepted via a mouse device, function keys or alphanumeric

keys.

Each workstation is delivered with 64 Mbytes of main memory, and 4 Gbytes of disk

storage. It is also equipped with one CD-ROM drive.

Operator consoles with 2-CRT.

There are 5 operator consoles with two CRTs. Each operator console is a Digital

DPWau AXP workstation, with two 21” colour monitor. Each workstation has a redundant

connection to the LAN. Input is accepted via a mouse device, function keys or alphanumeric

keys.

Each workstation is delivered with 128 Mbytes of main memory, and 4 Gbytes of

disk storage. It is also equipped with one CD-ROM drive.

Operation Scheduling console

This console is dedicated to the Operation Scheduling activities. Besides the

standard Man Machine Interface (MMI) software, it contains a dedicated software for the

Hydro Thermal Coordination Analysis functions (HTC2).

39

Page 40: Scada Report

The Operation Scheduling console consists of one Intel Workstation, delivered with

64 Mbytes of main memory and 4 Gbytes of disk storage.

This Operation Scheduling console is equipped with one 21” colour monitor; one

3.5” floppy drive and one CD-ROM drive. The complete and detailed hardware

configuration for Operation Scheduling console is described in the release C of the

document ‘Hardware Configuration for all control centers (ref. NR-A/N-G00-1-A05)’.

10.8) DTS OPERATOR CONSOLES

Two operator consoles with 2-CRT are dedicated to the DTS functions. Those

consoles are exactly the same as the 2-CRT operator consoles already described.

10.9) NETWORK MANAGEMENT CONSOLE

The Network Management Console is used to monitor and manage the hardware

equipment interconnected to the LAN. In particular it handles the Network Management and

the performance monitoring functions.

The Network Management console consists of one Intel Workstation, delivered with

128 Mbytes of main memory and 4 Gbytes of disk storage.

This Network Management console is equipped with one 21” colour monitor; one

3.5” floppy drive and one CD-ROM drive.

10.10) DEVELOPMENT CONSOLE

This console is used to develop and maintain the system software, displays and

databases.

The development console consists of one Intel Workstation, delivered with 64

Mbytes of main memory and 4 Gbytes of disk storage.

This development console is equipped with one 21” colour monitor; one 3.5” floppy

drive and one CD-ROM drive.

10.11) LAN AND WAN EQUIPMENT

1) LAN and WAN equipment are integrated into the same platform: the Digital

Multiswitch900 chassis. The main characteristics of this chassis are the following:

2) Contains 8 slots than can be used to plug a full range of LAN hub and switches,

WAN routers, Terminal servers.

40

Page 41: Scada Report

3) Includes a built-in SNMP chassis management agent.

4) Accept up to four power modules, in order to provide N+1 redundant AC power.

5) In order to provide a redundant LAN and WAN configuration, two Multiswitch900

chassis are delivered, each one with the following modules:

6) Two LAN switch modules (Digital Multiswitch 612EX), each one offering twelve

Ethernet 10 Mb/s (10baseT) ports and two 100 Mb/s (100Base TX) ports.

7) Three WAN modules (Digital RouteAbout Central EW routers) allowing

connections with the SLDCs, with the CPCC and with the remote VDUs. Each

RouteAbout Central EW router accommodates up to eight serial ports. Thus the total

number of communication lines available for the RSCC is 24 per chassis. The data

transmission speed is 64 Kbytes/sec per communication line. Each WAN module is

connected to the LAN via an Ethernet interface, thus communication between the

ICCP servers and the WAN routers is accomplished via standard Ethernet

connections.

8) One terminal server (Digital DECserver90M) to connect the loggers, the line printers

and the processor terminal to the LAN. Each terminal server provides up to eight

connections

10.12) REMOTE VDUS

The Remote Video Display Units (VDUs) are remote console used for monitoring

purpose only. They will be installed at the headquarters.

Two remote VDUs are delivered with the RSCC system. They consist of Intel

Workstations, delivered with 64 Mbytes main memory and 2 Gbytes disk storage. They are

also equipped with one 21” colour monitor; one 3.5” floppy drive and one CD-ROM drive.

They use the HABConnect software to access to HABITAT databases on the

SCADA/EMS servers. In order to communicate with the SCADA/EMS servers connected to

the LAN, a Digital RouteAbout Access EW router is delivered with each remote VDU. This

router offers two 64 Kbytes/sec communication lines and is connected directly to the remote

VDU via an Ethernet interface.

41

Page 42: Scada Report

11) SCADA SUBSYSTEM

11.1) FUNCTIONAL OVERVIEW

The purpose of the SCADA subsystem is twofold:

1) It maintains an up-to-date picture of the state of the monitored system in its database.

This allows operators to observe the state of the monitored process by simply

examining the database via CRT displays. The SCADA database also provides other

programs in the system access to the real-time SCADA data.

2) It allows operators (and other programs) to interact with the monitored process by

transmitting controls to the process.

3) Besides, the SCADA subsystem provides the following additional functions:

4) The Tagging function permits the placement and removal of tags from devices in the

system.

5) The Loadshed function (load shedding and restoration) is used in emergency

situations to automatically shed load from the power system. It is also used to restore

load manually, breaker by breaker, or on a group basis, after the system returns to

normal.

6) The Historical Data Recording (HDR) function records all changes to selected data

in journal files both during normal and disturbance conditions. Each file contains an

initial snapshot and then a journal of data changes. HDR can optionally reconstruct a

snapshot of any point in time, at a negligible processing cost. HDR also supports

scan-by-scan reconstruction of data and allows the use of any SCADA displays

(including schematic one-line diagrams) for viewing data.

7) The Sequence of Events function provides information (status changes,

instantaneous measured values) with highly accurate time for devices monitored by

suitable RTUs. This information is normally used by operators to determine what

took place during a system disturbance.

8) The Generalized Calculation (GENCALC) function provides a means for the

operator to derive calculations in a real-time environment , with SCADA analog and

42

Page 43: Scada Report

status points as input and output to the calculation, using any combination of logical,

arithmetic, and comparative operations.

SCADA SYSTEM OVERVIEW

11.2) DATA ACQUISITION

Data is retrieved from the monitored network by an integrated combination of

hardware and software in the real-time application server (“host SCADA”), Telemetry Front

End, Communication Front End and the RTUs. The system maintains a communications

statistics database that keeps a record of all communication failures for assisting

maintenance personnel in detecting deteriorating communications facilities.

11.3) HOST SCADA

The Host SCADA runs the code that is responsible for data processing and operator

interface. It maintains the SCADA database as a coordinated overall picture of the

monitored system for use by the operator and by other programming functions. The Host

SCADA maintains the SCADA database, performs conversion to engineering units, checks

limits, processes alarms and performs special calculations. Status data, analog data, and

pulse accumulator data are maintained in the SCADA database. The host SCADA also

43

Page 44: Scada Report

performs reasonability checks on the incoming data, and sets data quality flags to indicate

the reliability of the source of the data.

11.4) TELEMETRY FRONT END

SCADA supports a Telemetry Front End handling the normal data retrieval

function and sending only data changes to the real-time application server (using NETIO).

The primary purpose of the Telemetry Front End is to distribute communication processing

to allow the RTU protocol specific communications to take place without affecting the host

SCADA computer bus. The Telemetry Front End manages communications with

Communication Front Ends and provides communications with Host SCADA on the real-

time application servers.

11.5) COMMUNICATION FRONT END

The Communication Front End is the lowest level of the Telemetry Front End

SCADA system. It is responsible for all communications between the Telemetry Front End

and the RTUs. The Communication Front End consists of a single board VME based

communications processor using a UNIX "STREAMS" kernel from UconX. STREAMS is a

standard I/O interface definition that exists in UNIX System V and is supported in OSF.

The Communication Front End performs two main functions:

1) It translates the RTU communications protocol into a standard protocol to the

Telemetry Front End. This keeps the host SCADA and Telemetry Front End

software standard across any number of different RTU protocols.

2) It concentrates a number of communications lines into a single interface to the

Communication Front End. This greatly reduces the communications loading on the

real-time application servers, freeing computing power for other more important

uses.

11.6) RTU

The Remote Terminal Unit (RTU) is the interface with the monitored process. It

collects three primary types of data: the status of process devices (digital inputs), measures

process variables (analog inputs) and accumulators (pulse inputs). These three types of data

are transmitted to the Communication Front Ends using standard data communication

techniques.

44

Page 45: Scada Report

The first data retrieval function that the Communication Front End requests from its

RTUs is an "Initialization Scan" called also Integrity Scan or General Check. This causes

each of the RTUs to return all of their data. This initialization function allows the

Communication Front End and the host SCADA to initialize their databases with the latest

information available.

This provides the SCADA system with the best starting point. Once the initialization

scan is complete, the periodic scanning functions begin. Data from the RTUs is received by

the host SCADA, processed, and put into the database.

RTU database can be downloaded on operator request, from a PC using the SIM900

software.

RTU protocol chosen for this project is the IEC 870.5.101 unbalanced protocol and

the SINAUT FW-8 protocol for existing SINAUT RTUs.

The software package delivered with S900 RTU allows handling both digital and

analog inputs/outputs. The entities and related functions controlled by the S900 RTU

include:

1) I/O capacity

2) Multiple master station communications

3) Local data logging

4) Archiving

5) Local alarm

6) Synchronization

In addition, the following software tools are delivered:

1) GBD900: It is a Database generator running in a PC environment and using

ORACLE

2) SIM900: It is a master station simulator running in a PC environment.

45

Page 46: Scada Report

11.7) DATA FLOW

The most important role of the RTU is to interface with the monitored system. This

is done through three types of input data: digital inputs, analog inputs, and pulse

accumulator inputs. This data is collected and stored for transmission to the Communication

Front End.

As data is received from the RTUs by the Communication Front End, it is placed in a

buffer for transmission to the Telemetry Front End. The valid reception of the data is the

joint responsibility of the RTU and the Communication front end. Message numbers, error

detection codes, acknowledge and negative-acknowledge codes are exchanged along with

the data to securely transfer the information to the Communication Front End. The

Communication Front End translates the data from the formats returned by RTUs to the

RTU protocol independent format used in the Communication Front End to Telemetry Front

End protocol. The data is sent to the Telemetry Front End for transmission to the host.

Data received from the Telemetry Front End by the host SCADA is entered into the

RTU hierarchy as a 'raw' value. Engineering unit’s conversion is then done, followed by

limit checking. At each step of the processing, quality codes are set, and alarms may be

issued. If the value is valid and not manually overridden, it ends up in the substation

hierarchy (in the "DISPLAY" field). All operational displays run off the substation hierarchy

of the database.

Once the data is in the host, processing into the SCADA database begins.

11.8) EXTERNAL DATA

SCADA also provides an Application Programming Interface (API) that allows

external application programs to provide data to the SCADA system. This allows external

programs to provide SCADA data and have it undergo all of the data processing features

described in the Data Processing section. This includes limit checking, alarming, quality

checking, calculation triggering.

The external program requires no specific knowledge of where the SCADA system

resides since the API provides a consistent interface regardless of the configuration.

11.9) DATA PROCESSING

The major function of the data processing module is to place the data retrieved from

the RTUs in the database. All data is placed into the database in a standard form: digital

46

Page 47: Scada Report

status in a standard two-bit configuration, analog and accumulator data as single-precision

floating point in engineering units. Three types of information are maintained in the

database:

1) Status values, such as circuit breaker position (tripped/closed)

2) Analog values, which are process variables measured by the RTUs (temperature,

pressure etc.)

3) Pulse accumulations, which usually represent quantities delivered (such as

megawatt hours of electricity)

A combination of the RTU identity and the point identity is used for the scanner

module to locate quickly each point in the SCADA database without searching. This method

enables SCADA subsystem to avoid excessive processing overhead. Once located, each

point (status bit or analog value) is processed according to the directions established for that

point.

The following basic data processing functions are provided:

1) Analog value processing - The retrieved values are converted to engineering units

and placed in the database. The system designer can designate a linear or non-linear

conversion method for each individual analog point. The value is checked against

reasonability limits for the point. If the reasonability limits are exceeded, the data is

marked "unreasonable". If the analog is marked for Historical Data Recording

(HDR), the analog value is saved in a Historical Data file with a time tag and a data

quality flag.

2) Pulse Accumulator processing - Pulse Accumulator processing differs somewhat

from normal analog processing. The last retrieved accumulator value is subtracted

from the current reading and adjusted appropriately if the value is negative (a

negative accumulator difference indicates counter wraparound). The difference is

then converted to floating point and scaled using a multiplier.

3) Status processing - The status processing detects the existence of status changes,

and generates alarms accordingly. If no status changes have occurred, no processing

is necessary. However, if an unauthorized (uncommanded by the operator) change is

detected, the state of the point in the database is changed and an alarm is generated.

The point is also checked for a defined "normal" state. If none exists, no further

processing occurs. Otherwise, an abnormal condition either just occurred or was just

cleared. If an abnormal condition occurred, a new message is added to the abnormal

47

Page 48: Scada Report

summary; if an abnormal condition was cleared, the abnormal message is removed

from the abnormal summary. Status points may also be marked for inclusion in the

Historical Data Recording file.

4) Limit Checking - The analog value is compared against the limits (modified by a

deadband), and if a limit is violated, then an alarm is generated. A set of "dynamic

limits" is placed around an analog value by the scanner module, so that, in most

cases only one pair of limits must be checked when an analog value changes, thereby

increasing limit processing efficiency. The limit deadband prevents the generation of

meaningless limit alarms when an analog is subject to slight variations when close to

the limit. Any number of limits can be applied to an analog value as long as space is

available.

11.10) DATA QUALITY CHECKING

For each status point, analog value, or pulse accumulator record, the scanner module

maintains a number of data quality flags which give information about the value(s) stored in

the record. Generally, a data quality flag indicates something about the source of the data or

tells how reliably the value represents conditions in the field. The User Interface

Management System controls the use of the data quality codes in presenting the data to the

operator.

CALCULATED VALUES

SCADA subsystem provides special processing capabilities that support a wide

range of applications. Any analog or status value can be used in calculating other analog or

status values. The result of a calculation is stored in a status or analog record which can be

subjected to the full range of data processing available, i.e. limit checking, alarming,

logging, etc. Calculations can be defined to be performed periodically or automatically

whenever any of the input arguments change.

These calculation functions generally mark the calculated value with the flag of the

worst-quality value used in the computation. This reflects the fact that computed data is only

as valid as the least valid piece of data used to compute it.

48

Page 49: Scada Report

TOPOLOGY PROCESSING

SCADA subsystem features a topology processing capability that is independent of

that provided by the network analysis applications. This allows real-time determination of

the electrical connectivity and energization state of power system devices. These results are

available for SCADA displays, Alarm and Mapboard interfaces.

Topology processing is triggered by switching element status changes.

Each power system device is represented in the topology model as a one or two

terminal segment. Each device may be classified as live, dead, unknown or ambiguous. The

live determination is made using voltage analog measurements. Each terminal of a device

may be classified as open, grounded, or connected. Each substation may be classified as live

(there are islands, or parts of islands with live status present in the substation) or not live

(there are no islands or parts of islands with live status present in the substation).

The sorting algorithms used to determine bus and island assignments, as well as

island energization status, are efficient and completely general. Any sort of bus structure can

be reliably processed and identified. The modelling of the topology is incorporated in the

SCADA database.

11.11) SUPERVISORY CONTROL

Supervisory Control is the SCADA function used to issue control commands to field

equipment (digital devices, set points) under the supervision of the RTUs, from the operator

or from another application through a user-callable Application Programming Interface

(API).

SCADA subsystem supports two types of control commands:

1) Multiple-step command

2) Single-step command

Single-step commands are typically used when inadvertent or erroneous operations

have minor or no ill effects on the operation of the system. Multiple-step commands are

used by the operator to control devices in the field. Multiple-step commands require positive

operator verification for security.

CONTROL COMMAND PERMISSION CHECKS

Several conditions are checked before a requested control action is actually allowed

to be sent to a RTU. When the operator has completed the external command sequence by

49

Page 50: Scada Report

issuing the EXECUTE command, the host performs a number of checks to see if it is valid

to transmit the command to the RTU:

1) RTU Availability - If the RTU is unavailable to perform the requested operation, i.e.

it has been placed out of service

2) Control/Status Point Availability - If the control point is unavailable because it has

been placed out of service, the command is rejected. If the status point used to

monitor the control results is out of service, a warning message is issued that

verification of the control is not possible, but the command is transmitted to the

RTU.

3) Tagged - If the point is tagged to prevent control action, the command is rejected.

4) Command Interlock - A status point can be associated optionally with a control. If

the associated status point is not in the required state, the control is rejected (e.g., a

device can only be operated when the associated device is in a specified state). This

provides a means to interlock controls.

12) USER INTERFACE MANAGEMENT SYSTEM

This section briefly describes the SCADA user interface, focusing primarily on

SCADA displays and alarm functionality.

TYPES OF DISPLAYS

Data in the SCADA database and indications of changes are presented to the

operator through the following major displays:

1) Menu Directory Display - A display that lists all the menu displays.

2) System Directory Display - A display that lists all the SCADA system displays.

3) Transmission System Overview Display - A graphic overview display of the

transmission system (provided by PGCIL)

4) Interchange Displays - A schematic diagram showing power transfer between all

Constituent power systems in the Northern Region, plus four other interchange

displays (provided by PGCIL)

5) Substation Graphic Displays Menu Display - A graphic display which lists all the

existing substation graphic displays.

6) Substation Displays - The major operations displays (provided by PGCIL)

7) Transmission Line Graphic Displays Menu Display - A graphic display which

lists all the transmission lines which can be viewed via a graphic display.

50

Page 51: Scada Report

8) Transmission Line Graphic Displays - A graphic display which shows the entire

line and all of its connections (provided by PGCIL)

9) Abnormal Summary - A compilation of all existing abnormal conditions.

10) Out of Service Summary - A listing by substation of all points removed from

service.

11) Tag Summary - A listing by substation of all tagged devices.

12) Inhibit Summary - A listing by substation of all devices inhibited from generating

alarms.

The Transmission System Overview display gives the operator quick overview and

access to the information describing the entire system. The operator can use it to access the

substation, power station and transmission line displays for detailed information to analyze

and direct operations.

The abnormal summary displays are of particular interest to operators. They give

structured overviews of conditions of interest and unusual conditions in the system. The

remainder of the summaries, the tag summary, the inhibit summary, and the out of service

summary, are useful for reviewing the processing status of the SCADA system itself.

12.1) MENU DIRECTORY DISPLAY

The Menu Directory display lists all the menu displays and provides for each of them

a button for calling up the menu display.

The organization of this display is driven by the database of the MENU application

(tabular display). This organization is made of groups, sub-groups in the group and

functions in the sub-group. Once you select a group button, the sub-groups are listed with

their functions definitions which provide the way to call up the relevant menu display.

12.2) SYSTEM DIRECTORY DISPLAY

The System Directory display lists all the SCADA system displays of a particular

function, and provides for each of them a button for calling up the SCADA system display.

12.3) TRANSMISSION SYSTEM OVERVIEW DISPLAY

The Transmission System Overview display is the most convenient starting point

whenever a new sequence of operations is begun.

51

Page 52: Scada Report

The Transmission System Overview display is a graphic overview display of the

transmission system with substations, power stations and transmission lines. Lines are color

coded by voltage level, and highlighted in case of loading limits exceeded. Substations and

power stations are depicted by symbols in case of alarm presence.

Real and reactive power flows are displayed (a value and a direction arrow) for lines

and power stations. For the power stations, the maximum real power output is also

displayed.

The functionality of this display is carefully designed to give operations personnel a

comprehensive overview into the system. This allows them to analyze quickly system state.

Using the Transmission System Overview display, the operator can see at a glance the

general condition of the entire system by panning and zooming to navigate through the

display. Once the operator has determined what to look at in more details, he can quickly go

to the relevant displays, by selecting a substation, a power station or a transmission line.

12.4) INTERCHANGE DISPLAYS

These displays are the major displays for power transaction control. The following

displays are used:

1) Interchange Display - This is a display that contains the schematic diagram

showing power transfers between all Constituent power systems in the Northern

Region. Each power system is represented by a block. Inside the block, the actual,

scheduled and deviation values of power flows are shown for total generation and

load. Outside the block, the actual, scheduled and deviation values of power flows

are shown for the net interchanges, with direction arrows.

2) Tie-line Display (Generation Tie-line Status) - This is a tabular display that contains

tie-line boundary and exchange data. The tie-line names and voltage levels are

shown, as well as the measured or manually entered real power flow and boundary

values (limits).

3) Transaction Schedule Display (Start/Stop Transaction Schedules) - This is a

display that provides the ability to enter and display constituent hourly interchange

transaction schedules.

4) Central Sector Shares Display - This is a display that provides the ability to enter

and display the Constituent percentage shares for each Central Sector project as

allocated by employer.

52

Page 53: Scada Report

5) System Frequency Display - This is a display that contains the schematic diagram

showing the geographical location of the tie-line substations. For each of them,

telemetric frequency buses are shown, and the frequency value displayed.

12.5) SUBSTATION GRAPHIC DISPLAYS MENU DISPLAY

The Substation Graphic Displays Menu display lists all the Substation Graphic

displays and provides for each of them a button for calling up the Substation Graphic

display.

The organization of this display is driven by the SCADA database (tabular display).

SUBSTATION DISPLAYS

These displays are the major operating displays for dispatching personnel. They

contain the most detailed information about the system and allow control operations to

change the system. These displays are organized by substation, and each substation's

displays are closely linked together as a coherent group. The following general display

layout is used:

1) Substation Graphic Display - This is a display that contains the detailed graphic

one-line diagram of the substation. It contains most of the information known about

the substation. Controls may be issued from it.

2) Substation Tabular Display - Accessible from any other substation display, this is

generally the most complete listing of the data known about the substation. Although

controls can also be issued from here, they are generally used for entry of operational

data (limits for example).

12.6) TRANSMISSION LINE GRAPHIC DISPLAYS MENU DISPLAY

The Transmission Line Graphic Displays Menu display is a tabular display that lists

all Transmission Line Graphic displays. Several views of the display are available,

according to the voltage level. In a voltage level view, the data are driven by the SCADA

database, and show the tie-line and the associated substation names. These names are

displayed inside buttons, and allow the navigation to the relevant displays (Transmission

Line Graphic displays and Substation Graphic displays).

53

Page 54: Scada Report

12.7) TRANSMISSION LINE GRAPHIC DISPLAY

The Transmission Line Graphic display is a graphic display of a transmission line. It

presents telemetric, manually entered and calculated power system data on a one-line

diagram that shows the entire line and all of its connections. At each end of the line, the

diagram shows the line breakers and the bus to which the breakers are connected, plus the

substation name.

The substation name button provides the way to call up the relevant substation

graphic display for more detailed information.

The user is able to perform any user interaction with the power system data and the

line breakers (e.g., manual replacement of a value, or control of a breaker).

12.8) ABNORMAL SUMMARY DISPLAY

These summaries are lists by substation and by time of the conditions in the system

that are unusual (abnormal). This is an important list for the operator for several reasons.

First, the system was engineered to operate in a specific manner (e.g. some switches should

be open and some switches should be closed). The operator has a picture in his mind of the

normal operating configuration of the system. The abnormal summary updates the

operator's mental picture about the configuration of the system.

Second, when an operator comes on shift, the abnormal summary helps inform the

operator of the changes that have taken place in the system since last viewed.

The following data is shown as a part of the abnormal summary:

1) Time and Date - The time and date that the abnormal condition occurred.

2) Identity - The identity of the device in an abnormal condition.

3) Status - The current state of the device. Although this is somewhat redundant, the

actual state of the device is shown (e.g. open/closed for example).

13) HISTORICAL INFORMATION AND MANAGEMENT

Historical information and management is also called HIM. HIM consists

of two data servers. One is real time data server and second is informational

storage & retrieval or ISR server.

Real time data server stores data of all substations after each 10-second.

One file can store data for approximately 37 minutes. Real time data server can

store data for maximum of 4 months then it will delete. So back up is necessary

54

Page 55: Scada Report

ISR server stores data of all substations after each 15 minutes. It can store data

for maximum two years.

The whole Database is Oracle based. Real time data server collects data

periodically, changes it in to specified database and sends it to the HIM

recorder. ISR can achieve and restore data. One can store data in magnetic tape

and jukebox or optical disc as backup data. Data can be restored from tape and

jukebox to the relational database on users demand.

Data files like HDR, HABITAT databases; SAVECASES can be

restored on the server on users demand. ALARM application on real time data

server send the alarm & events data to the ASCII files. Then these files are

stored in ISR server and restored in relational database. Then these files are

removed from real time data servers. One can check the data history for load

forecasting. Sequential query language interacts between operator consoles and

HIM.

Operator console is the key with which operator interacts with the

database

HISTORICAL DATA RECORDING

55

Page 56: Scada Report

REASONS FOR FAILING THE CONTROL

1) RTU may not in service

2) Device is in local control mode

3) Control point is not in service

4) Control point is attached with safety tagged

5) A Control request is already pending on the device

14) UTILITIES USED BY SCADA SYSTEM

There are various utilities used by the SCADA system. But main utilities

are:

14.1) ALARMS

If there is abnormal condition in the monitored system, it can respond by

taking various actions to alert the operator of the condition. The response of

SCADA to a specific condition occurring on a specified point is defined in the

database. When a normally closed circuit breaker trips, system causes an

audible alarm to be issued for that breaker, SCADA can detect problems that

occur for status, analog and count points, RTU and other equipment in the

communication system and software. SCADA can issue alarm when status point

returns to normal form an illegal state or an abnormal state or a communication

path to a SCADA site comes up or goes down. Alarm is also issued when

scanning of data fails.

Each alarm belongs to a category. There should be a proper location of

an alarm in the SCADA system. For other alarms, typically designated the

name of the EMS subsystem that issues the alarm. Alarms should be grouped

per area i.e. transmission area, distribution area etc.

14.2) TAGGING

A tag is placed on a device for both safety and informational purposes.

Tagging enables us to place tags on status devices modeled in SCADA. These

tags can prevent a device from tripping and display a comment about the

56

Page 57: Scada Report

device. Its tag type determines the effect of a giving tag on a device. Tags of

different types prevent device from tripping.

TAGGING

14.3) TRENDING: -

The purpose of trending is to reconstruct the post status of SCADA data.

One should select the point for trending and define sampling rate and scale

values also assign the point to a console for trending. It shows us how the

different parameters behaving in the system.

57

Page 58: Scada Report

58

Page 59: Scada Report

59