Saverio Minutoli INFN Genova
1
T1 Electronic status
Electronic items involved:
Anode Front End Card Cathode Front End
Card Read-Out Control card Slow Control Ring
T1 Trigger Architecture
H.V. Distribution T1 mini DAQ
Cern Collab. Meeting 12 Sept 2007
Saverio Minutoli INFN Genova
2
Ten different types (dimensions and connections).
All schematics and layouts done. Ready for the mass production
Production of some pcb types will start next week Preproduction of CSC-5P done.
Installed on two CSCs at GIF and H8. Static tests done
Routing and VFAT Hybrid Mech. matching Dynamic tests (to be complete):
Compatibility with VFAT Preamp. stage Grounding and Shielding
AFEC
Saverio Minutoli INFN Genova
3
CFEC (CMS chips) (1)
Manage 64 chs The board has been
completely debugged with a Digital Mezzanine developed by the Genoa group.
The results obtained are compliant with the requirements.
We have 8 cards fully equipped, enough to read-out 1.5 CSCs.
To be tested with the digital VFAT.
Minor pcb modifications for the mass production in progress.
New version will hosts the R.H. low voltages regulator.
Saverio Minutoli INFN Genova
4
CFEC (VFAT hybrid) (2) Manage 128 chs Static tests done
Routing and VFAT Hybrid Mech. Matching
Dynamic tests (to be done): Compatibility with VFAT Preamp.
stage. new CFEC layout following the AFEC
rules.
We have 10 cards fully equipped, enough to read-out 3 CSCs.
To be tested with the analog VFAT Hybrid.
Saverio Minutoli INFN Genova
5
ROC (1)
The design is almost fixed. Need some confirmations from W.S. or G.A about parts of the circuit !!!!!!
Layout within 1 month board could be available middle/end of October. The ROC board manage two CSCs detectors. Collect the serial data streams coming out from the VFAT hybrids and
transmit them to the Counting Room, via an optical link (1 GOH). Also the trigger bits are sent via optical links (2 GOHs). Hosts the Slow Control Ring node (CCUM), distribute to the FE electronic
cards the I2C control line. Distribuite the power supply and the I2C lines to the new TOTEM DOHM. Control and generate the trigger bits logic transmission signal, and perform
the trigger bits synchronization circuitry. Distribute and regenerate the Clock and T1 Fast Commands to all the FE
boards. Hosts dedicate spy connectors for a mezzanine, in order to emulate the
CCUM functions and acquire all the data and trigger bits coming out from the FE cards. The schematic is in progress, it inherits the skeleton of the T1 Digital
Mezzanine design.
Saverio Minutoli INFN Genova
6
ROC (2)
CSCn
CSCn+1
TR_VFAT
BC0
TR_MUXDAV
CRT4T
CRT4T
DAV_REDUNDANCY
LVDS2
CMOS
138
10
DAVs
1/0
Saverio Minutoli INFN Genova
7
ROC (3)
BC0b
IDLEb/ON
TR_GOH_DAV
I/O CCUM
MUX
CSC1
A
DATA_GOH_DAV
I/O CCUM
MUX
MUX
MUX
I/O CCUM
CSC2
A
K
K
K
TRIGGER
DAV
DATA
DAV
Has been tested
(W.S.) ???
Saverio Minutoli INFN Genova
8
Slow Control Ring (1)
Based on the new TOTEM DOHM design (G.A.) Distributes the 40MHz LHC clock and serial Fast
Commands (labeled as T1). Each SCR node manage and distribute the I2C
communications lines. The I2C is the only way through what we can modify
the setting parameters of the major electronic devices (VFAT included) involved in the FE Totem project.
According documentation the I2C limitations are: The maximum number of nodes (~11). The maximum cable length (50cm/branch, 2-3m in
total).
Saverio Minutoli INFN Genova
10
T1 Trigger Architecture (1)
All the trigger bits generated by the T1 detector are sent to the Totem Trigger System via optical link.
T1 detector modularity is ¼, this means 15 CSCs chambers.
Each CSC generate 16 trigger bits 1 GOL. Globally ¼ T1 needs 15 fibers to be able to transfer all the trigger information. No spare GOL channels available.
The trigger bits sent to the Counting Room, will be collected on the Trigger TOT-FED, that can manage 36 fibers, shared in three groups of 12 fibers each.
We have 15 fibers per each ¼ T1. In order to merge and manipulate with a dedicate algorithm all the trigger bits, we will need a mezzanine (to be defined) to add to the Trigger TOT-FED.
The trigger system is not completely fixed, need some more iterations within the trigger group.
Saverio Minutoli INFN Genova
11
T1 Trigger Architecture
~6kwires
CSC
ROC
T1 ARM
8
1x22
30
~6kwires
CSC
ROC
T1 ARM
8
1x2 2
x15 30
T1 TRG_TOTFED
12 1233
T1 TRG_TOTFED
1212 3 3
GLOBALTRG_TOTFED
8bits
X XCOUNTING ROOM
CAVERN
Trigger Bits 2 x 480 = 960
x15
x2 x2
(Needs TRG algo.)LV1
Y
(16bits)VFAT
(16bits) 8bitsVFAT
Saverio Minutoli INFN Genova
12
CSC#1
CSC#15
HV ch#1
HV ch#15
Patch Panel on 6th frame
Patch Panel on T1 Platform
A1
55
0P
-Ca
en
HV
24
ch
sH
V P
.S.
100m HV Cable
15m HV Cable
Counting Room
T1 Rack Platform
T1 ¼
Ma
in F
ram
eS
Y1
52
7
Inside T1 1/4
T1 ¼ HV cabling schematicS.M. 24/04/2007
Saverio Minutoli INFN Genova
13
T1 mini DAQ back-up (1)
In order to have a back-up solution for H8 and bld.188, we are setting up a small and portable DAQ system to read one VFAT hybrid.
The system performs the I2C protocol functionalities. The slow commands are managed through a PC and a custom software.
The implementation of the all VFAT commands is in progress. The system hosts a DCU device to read back the VFAT internal DACs
registers. The VFAT serial data-out will be acquired by a FPGA that decodes the
data and sends the information out to the PC via an USB port. The trigger bits are manipulated by the same FPGA. The system can generate the clock and T1 commands locally or
remotely. The system is based on the T1 Digital Mezzanine. A possible extension of the system to read an entire chamber (using
several T1 D.M. already available) is under evaluation. Most of the pieces are available (HW, FW), expected to be available
within October.
Saverio Minutoli INFN Genova
15
VFAT CSC compatibility verification AFEC ready CFEC (both types) need to be tested with CSC
New designs can be ready within a month. ROC available middle/end October Mini DAQ ready within October H.V.(CAEN) and L.V.(WIENER) ready to be purchased Need to procure the CERN components:
R.H. logic devices (lvds_mux, lvdsbuf, crt902, crt4t, crt245 …) GOH 7.3, etc….
CSCs test in progress to the H8 test beam Finally some inputs have been read with VFAT through the
DAQ in H8 Small, but important results obtained.
Conclusions