Sau ppt march_2012_final

25
Developing the King-king Cu/Au Deposit A Project for the Philippines Corporate Presentation March 2012 TSX: SAU www.sagcmining.com

Transcript of Sau ppt march_2012_final

Page 1: Sau ppt march_2012_final

Developing the King-king Cu/Au Deposit

A Project for the Philippines

Corporate Presentation – March 2012

TSX: SAU www.sagcmining.com

Page 2: Sau ppt march_2012_final

Forward-Looking Statements

This presentation contains “forward-looking statements” that were based on St. Augustine Gold & Copper Ltd’s expectations, estimates and projections as of the dates which those statements were made. These forward-looking statements include, among other things, statements with respect to St. Augustine Gold & Copper Ltd’s business strategy, plans, outlook and shareholder value, projections, targets, and expectations as to reserves, resources, results of exploration (including targets) and related expenses, mine development, mine operations, mine production costs, drilling activity, sampling and other data, recovery improvements, future production levels, capital costs, cost savings, cash and total costs of production of gold, expenditures for environmental matters, reclamation and other post closure obligations and estimated future expenditures for those matters, completion dates for the various development stages of projects, future gold prices (including the long-term estimated prices used in calculating mineral reserves), and currency exchange rates.

Generally, these forward-looking statements can be identified by the use of forward-looking terminology such as “outlook,” “anticipate,” “project,” “target,” “believe,” “estimate,” “expect,” “intend,” “forecast,” “should,” and similar expressions. Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable, are inherently subject to known and unknown risks, uncertainties, and other factors that may cause St. Augustine Gold & Copper Ltd’s actual results, level of activity, performance, or achievements to be materially different from those expressed or implied by such forward-looking statements.

An NI 43-101 has been prepared by Independent Mining Consultants, Inc with respect to the King-king project. A Preliminary Economic Assessment (PEA) has not yet been prepared and, consequently, any economic estimates, including all assumptions and costs, have yet to be verified.

March 2012 2 TSX: SAU

www.sagcmining.com

Page 3: Sau ppt march_2012_final

A Project for the Philippines

The King-king copper / gold deposit: A Project for the Philippines

Significant social economic benefits to the Philippines and the

residents of Mindanao island with the development of King-king The King-king copper/gold project is one of the largest undeveloped deposits in world

Listed as one of the top priority projects by the Philippine Mines and Geosciences Bureau

43-101 Resources equivalent to 22 million ounces of gold (M&I) 5.4 billion lbs of copper & 10.3 million oz of gold

Deposit contains $24.8 billion in ground metal value (M&I only, $2.50/lb cu/$1,100/oz au)

Independently owned and operated 60% earn-in 2/3 thirds complete with full earn-in upon on completion of Bankable Feasibility Study

Significant exploration upside, see press release dated March 1, 2012

Permitting process expected to be complete by Q3 2012

Experienced Management Team

March 2012 3 TSX: SAU

www.sagcmining.com

Page 4: Sau ppt march_2012_final

Capital Structure

Cash Raised

Price per share

Total Shares

RTO 1/7/2011 $7,210,251 90,000,000

Tranche 1 $25,900,000 $0.30 86,333,334

Tranche 2 $40,016,000 $1.22 32,800,000

Shares Issued to RMMI $0 80,000,000

Private Placement 11/17/2011 $11,790,000 $0.40 29,475,000

Ratel Options exercised after Jan 2011

$0.25 6,650,000

Total Shares Outstanding: 325,258,334

Options 21,291,667

Warrants ($0.75): 14,737,500

Total Shares Fully Diluted: 361,287,501

Spend to date: $68,000,000

Cash on Hand (as of 03/31/2012): $16,000,000

Major Shareholders

RMMI * 27.45%

CGA 21.66%

Wellington / Franklin Templeton / Passport / (others):

25%

74.11%

* Additional 75M shares to be issued to RMMI at Feasibility

March 2012 4 TSX: SAU

www.sagcmining.com

Page 5: Sau ppt march_2012_final

Copper-Gold Project

Comparison

March 2012 TSX: SAU

www.sagcmining.com 5

** Comparative Project Details can be found in the Appendix

As of March 4, 2012

Page 6: Sau ppt march_2012_final

Key Milestones for 2012

March 2012 TSX: SAU

www.sagcmining.com 6

Next Steps Are:

Environmental Impact Statement (EIS) Submittal – February 2012

Declaration of Mine Project Feasibility (DMPF) – May 2012

Prefeasibility Study (PFS), 43-101 compliant – May 2012

Bankable Feasibility Study (BFS) – Dec 2012

Go to production project - In the permitting phase now

Page 7: Sau ppt march_2012_final

Project Description Contents

Benefits to the Philippines

King-king Project Earn-in

King-king Resource

Exploration Upside

Mine Plan & Schedule

Process & Plant, Pit End of Year 5 & 19

World Class Engineering & Sub Contractors

Permitting Process

Management & Board of Directors

King-king Location and History

March 2012 TSX: SAU

www.sagcmining.com 7

Page 8: Sau ppt march_2012_final

Benefits to the Philippines

A Project for the Philippines:

Significant increase in tax and royalty revenue for the government and Indigenous People

Environmental improvements related to small scale mining

Significant high paying jobs for locals with approximately 4,000 jobs during construction and 2,000 careers during operation

Dedicated community development in the areas of education, health care, infrastructure and livelihood as 1.5% of the operating expense is earmark for these investments in community

Training programs developed through a public private participation program in conjunction with the Philippine Technical and Education and Skills Development Authority (TESDA) will be developed to facilitate local hire and a JV will be put in place

Local purchase of goods and services to benefit the local businesses and economy

March 2012 TSX: SAU

www.sagcmining.com 8

For more information on the on-going projects bringing opportunities to the people, visit:

www.pantukansfuture.com

Page 9: Sau ppt march_2012_final

King-king Project Earn-In

March 2012 TSX: SAU

www.sagcmining.com 9

Total Earn-in % Total Earn-in $ Spend to Date Difference

Payment to Nadecor 6% $7.5M $3.4M $4.1M

BFS 45% $43.5M $30.6M $12.9M

Capex 9% $32.0M* $34.0M -2.0M*

Total Earn-In: 60% $83.0M $68.0M $13M

*Will increase on a linear basis based on tpd per MOU with Nadecor. Expected increase of $13.7M for a total $45.7M

Page 10: Sau ppt march_2012_final

King-king Resource

962.3 million tonne M & I resource:

5.4 billion lbs Cu

10.3 million oz Au

Average annual production for first 5 years**

232 million lbs Cu

362,000 oz Au

60,000 tpd milling operation

40,000 tpd leach operation in final evaluation

120,000 milling operation expansion plan under feasibility study

Low net production costs

Low strip ratio for M, I & i resources

Tide water proximity deposit

Resources Ore

(Ktonnes)

Eq Cu

(%)

Total Cu

(%)

Au (g/t) Eq Au

(g/t)

Measured & Indicated 962,252 0.533 0.254 0.334 0.660

Inferred 188,816 0.439 0.215 0.265 0.542

Notes:

Updated Resource based on new data from

ongoing feasibility work

Total Material within a floating cone pit

shell, based on Cu $2.50/lb. and $1100 /

oz. Au prices.

** @ 93,000 tpd

March 2012 10 TSX: SAU

www.sagcmining.com

Page 11: Sau ppt march_2012_final

King-king Geology & Upside Potential

Epithermal Prospect:

Preliminary gold resource: First pass fieldwork showed at least 8 veins with good potential; previous testing confirms assays @4.17-15.37/g/t Au

Epithermal; low sulfidation quartz-carbonate-base metal gold system

Field work confirming multiple epithermal vein targets in Binutaan, Panganson and Diat areas

As described in the March 1, 2012 Press Release:

Initial drill tests results confirm surface sampling and wide intervals of porphyry Au-Cu mineralization 1 km and 4 km northeast of the King-king deposit

Gold-rich porphyry copper deposit with epithermal vein systems (1,656 ha)

Resources based on 291 holes/ 95,651 metres

March 2012 11 TSX: SAU

www.sagcmining.com

Page 12: Sau ppt march_2012_final

Mine Plan & Schedule

Mine Plan Develop a dual processing plant that is built on a high grade front-end mine plan

Plan to deliver 60,000 tonnes per day (tpd) or 21.9 million tonnes per year, to a flotation mill

with a tailing leach circuit

In addition a 40,000 tpd heap leach operation is being evaluated for copper oxide dominant ore

Opportunity to start producing copper via the heap leach - Solvent Extraction and

Electrowinning (SXEW) process before completion of the mill construction, thus generating

early cash flow

Ore Delivery Schedule High grade first 5 year Plan

Heap leach provides early low cost copper production for the first 6 years of mining

20 year Project Life of Mine (LOM) with additional 5 years of processing low grade stockpiles

March 2012 TSX: SAU

www.sagcmining.com 12

Page 13: Sau ppt march_2012_final

Process & Plant

Process Stages:

Primary Crushing (gyrator crusher)

Primary Grinding (SAG and Ball Mills)

Gravity Gold Concentrate Dore to Market

Flotation Cu - Au Concentrate to Smelter

Sulfuric Acid Leach of Flotation Tailing

Liquid Solid Separation (CCD Circuit)

Solvent Extraction for Copper

Electrowinning Cu Cathode to Market

March 2012 13 TSX: SAU

www.sagcmining.com

Page 14: Sau ppt march_2012_final

Pit End of Year 5

(Mined: Ore-171 Mtonnes (0.373% Cu, 0.456 g/t Au), Total - 356 Mtonnes)

Equivalent Copper – 0.666% or

Equivalent Gold – 1.038g/t

March 2012 14 TSX: SAU

www.sagcmining.com

Page 15: Sau ppt march_2012_final

Pit End of Year 19

(Mined: Ore-793 Mtonnes (0.278% Cu, 0.363 g/t Au), Total - 1535 Mtonnes)

Equivalent Copper – 0.511% or

Equivalent Gold – 0.796 g/t

March 2012 15 TSX: SAU

www.sagcmining.com

Page 16: Sau ppt march_2012_final

World-Class Engineering

Sub-Contractors

King-king

Tailing Storage Facility Pit Slope Stability Metallurgy

BFS Contractor Processing Plant Project Economics

Mine Plan & Design Mining Cost Estimate

Baseline Studies Permitting

Port Design Port Cost Estimate

Power Plant Design Power Plant Cost Estimate

Axceltechs DMPF Geotechnical Engineering

ENVIRONMENTAL COUNSELORS, INC.

EIS Preparation Lands Consulting

NAZ-ENVIRONTECHNICS GROUP Air Dispersion Model

March 2012 16 TSX: SAU

www.sagcmining.com

Page 17: Sau ppt march_2012_final

Permitting Process

March 2012 TSX: SAU

www.sagcmining.com 17

Environmental Impact Statement

Environmental Compliance Certificate

Declaration of Mine Project Feasibility

Permits to Operate

Construction

MAJOR PERMITS SCHEDULE

Submit EIS February 2012

Submit Declaration of Mine Project Feasibility App. May 2012

Environmental Compliance Certificate September 2012

Approved Declaration of Mine Project Feasibility December 2012

Page 18: Sau ppt march_2012_final

Management Team

March 2012 TSX: SAU

www.sagcmining.com 18

Andrew Russell, President & CEO

Founder – RMMI VP Project Development – General Moly, Mount Hope and Liberty Projects, bankable feasibility/NEPA Maintenance Superintendent/Mechanical Engineer – Kennecott Copper Refinery, Kidd Creek Process installation Business leader – Honeywell International, Gas Turbine Engine Division

Robert Orr, CFO and VP Business Development BSc – Economics, Chartered Accountant and Chartered Business Valuator; Transaction Partner with PricewaterhouseCoopers, 20 years of public practice experience as a transaction and tax advisor:

Resource clients included: Teck, Goldcorp, Novagold, Eldorado Gold, Quadra FNX Mining Ltd., First Quantum Minerals, Sprott Resources, NewGold, Taseko, Sojitz, Sumitomo

Tom Henderson, COO

VP and GM – Coeur Alaska, Inc. Director of Operations/Mine Manager – Kensington, Coeur Mine Management/Engineering – Robinson Mine, Goldstrike Mine, NV; Grasberg Mine, Indonesia

Jim Moore, VP Technical

Technical Project Manager – General Moly, Mount Hope and Liberty Project and bankable feasibility More than 32 years of experience in mining, metallurgical design, engineering and operations, leaching, SX/EW, concentrating, smelting & refining ZCCM – Nchanga Division and Phelps Dodge

Louis Lazo, VP Human Resources

Independent Human Resources Consultant – Broad based Human Resources consulting including mining project in US, Bolivia, and Ghana Director of International Human Resources – Newmont Mining. Responsible for Human Resources at all international projects including Batu Hijau in Indonesia

Kee Ming Chi, General Counsel

Counsel – O’Melveny and Myers, LLP - specializing in infrastructure, energy, natural resources and technology Includes advising on mergers and acquisitions, public private partnerships, and privatizations Admitted to practice in England, Singapore and Hong Kong, he has experience in multiple jurisdictions (including European, Middle Eastern and Asian countries)

Page 19: Sau ppt march_2012_final

Board of Directors

March 2012 TSX: SAU

www.sagcmining.com 19

Robert Russell – Chairman of the Board Executive VP and GM – Freeport Copper and Gold

VP – Freeport Indonesia

GM – Nchanga Division, Zambian Consolidated Copper Mines

Chairman/CEO/Founder – General Moly/Idaho General Mines

Andrew Russell – Director Founder – RMMI, has led the King-king project since 2009

VP Project Development – General Moly, Mount Hope and Liberty Projects, bankable feasibility/NEPA

Maintenance superintendent/Mechanical engineer – Kennecott Copper Refinery, Kidd Creek Process installation

Max V. Anhoury - Director 20 years of operational, sales and marketing experience

At Lovation, Inc. responsible for Global Sales and Marketing and a member of the Senior Executive Team

Strategic direction as well as managing the day to day operations of a worldwide team

Thomas L. McKeirnan - Director Senior Vice President, General Counsel and Secretary of Red Lion Hotels Corporation since February 2005 executive officer of the

company, involved in all strategic decision-making

Served as Vice President, General Counsel and Secretary of Red Lion Hotels Corporation, and Vice President, Assistant General

Counsel

Terry Krepiakevich, CA – Director Past CFO of SouthGobi Resources Ltd. and is now a senior advisor to the company

Director and Audit Committee Chair of Alexco Resource Corp., Western Lithium USA Corp., Concordia Resource Corp., and

NovaCopper Inc.

Recognized with the British Columbia CFO of the Year Award, for his contribution to SouthGobi's rapid growth

Page 20: Sau ppt march_2012_final

King-king Location

Location: Philippines, Mindanao, Compostela Valley Province

Adjacent to Coastal Plain

Access: About 35 km east-northeast of Davao City by air

By road: about 17 km from Pantukan (92 km from Davao city by paved highway)

March 2012 20 TSX: SAU

www.sagcmining.com

Page 21: Sau ppt march_2012_final

King-king History

March 2012 TSX: SAU

www.sagcmining.com 21

1966 – 1968

NADECOR discovers the King-king mineralization Anomaly

1969 – 1972

Mitsubishi Mining drilled 54 surface diamond drill holes

1981

Nadecor entered into an operating agreement with Benguet Corporation

1981 – 1991

Litigation - ownership did not allow any activity within this project. In 1991, legal issues resolved in favor of Nadecor

1991 - 1994

Benguet drilled 69 DDH & 25 RCH in addition to complete an in-house feasibility study

1992

The Mineral Production Sharing Agreement (MPSA) was signed by Nadecor, Benguet & The Philippines Government

1995 - 1997

Echo Bay drilled ~ 128 holes (52,718 m). All Echo Bay data was acquired by Kinross which waived its option to

proceed with the King-king project

2005

Nadecor & Benguet applied for a conversion of MPSA into a Financial Technical Assistance

Agreement (FTAA)

2008

Nadecor terminated the Operating agreement and applied to have Benguet removed

from MPSA

2009

Nadecor and RMMI reach an agreement to develop the King-king project

2010

Contract consummated with Benguet for

settlement, DENR approves the exploration work

program and program is initiated

2011

RTO of Ratel Gold, final

settlement with Benguet

clearing title

Page 22: Sau ppt march_2012_final

King-king Project Summary

Advanced Stage Deposit with greater than 1.15 billion tonnes M, I & I resource

Significant social economic benefits for the Philippines

Front end high grade

Low strip ratio

Uniquely prime location close to infrastructure

1 of 3 top resource development projects in Philippines

Advanced stage with production planned for 2015

Primary sulfide mineralization with near surface oxide

Oxide resource leach facility provides early low cost, high grade recovery

Next Steps Are:

EIS Submittal – February 2012

DMPF Submittal – May 2012

PFS – May 2012

BFS – 2012

Technical studies essentially complete (mine process and metallurgy, process, tailings,

infrastructure)

Final facility and infrastructure locations defined

Primary & Alterative options developed

March 2012 22

TSX: SAU www.sagcmining.com

Page 23: Sau ppt march_2012_final

Contact Information

March 2012 23 TSX: SAU

www.sagcmining.com

JEANNY SO

CHF INVESTOR RELATIONS

DIRECTOR OF OPERATIONS

T: 416-868-1079 x 225

E: [email protected]

KRISTI HARVIE

MANAGER INVESTOR AND CORPORATE AFFAIRS

T: 509-343-3193

E: [email protected]

Page 24: Sau ppt march_2012_final

Cautionary Note & Compliance

The information contained in this document has not been independently verified. No representation or warranty, express or implied, is made as to, and no reliance should be placed on, the fairness, accuracy, completeness, or correctness of the information or opinions contained herein. Neither St. Augustine Gold & Copper Ltd. nor any of its advisors or representatives shall have any responsibility or liability whatsoever (for negligence or otherwise) for any loss arising from any use of this document or its contents or otherwise arising in connection with this document.

This document does not constitute or form part of, and should not be construed as, an offer, invitation, or inducement to

purchase or subscribe for any securities nor shall it or any part of it form the basis of, or be relied upon in connection

with, any contract or commitment whatsoever.

NATIONAL INSTRUMENT 43-101 COMPLIANCE

Mr. James J. Moore, P.E., the Company's qualified person for this project under NI 43-101, has reviewed and approved

this presentation.

A NI 43-101 compliant technical report entitled “King-king Copper-Gold Project Mindanao, Philippines” dated October

12, 2010 and prepared by Michael G. Hester, FAusIMM of Independent Mining Consultants, Inc., Donald F. Earnest,

P.G., of Resource Evaluation, Inc. and John G. Aronson of AATA International, Inc. has been filed by the Company on

www.sedar.com.

March 2012 24 TSX: SAU

www.sagcmining.com

Page 25: Sau ppt march_2012_final

Appendix – Project Comparative

Details

March 2012 25 TSX: SAU

www.sagcmining.com

Symbol SAU LCC CUU AZC NCU XRC WRN

CompanySt. Augustine

Gold & CopperLumina Copper

Copper Fox

Metals

Augusta

ResourcesNevada Copper

Exeter

Resource

Western

Copper & Gold

Project King-king Taca Taca Schaft Creek  Rosemont  Pumpkin Hollow Caspiche  Casino

Type Cu-Au Au-Cu-Ag-Mo Cu-Au-Mo-Ag Cu Cu-Au-Ag Cu-Au-Ag Cu-Au-Ag

Location Philippines Peru BC, Canada Arizona Nevada Chile Yukon, Canada

Stage PFS PFS PFS PFS FS PFS PFS

Project Comparatives: