We are ready to carry out SAT for the system.Find below DCS/PLC SAT agenda.
Period from 28 Aug to 31 Aug 10
28 Aug 10
Time : 10:00 am to 1:00 pm
Activity :
1) DCS/PLC Bill of Material Verification for all units (including Common Area).
Time : 2:30 pm to 6:00 pm
Activity:
1) DCS/PLC cabinet GA/IGA physical verification.2) Console G/A IGA check.3) Software Installation check.
30 Aug 10
Time : 10:00 am to 1:00 pm
Activity :
1) DCS/PLC Power & I/O Redundancy check for all units.
Time : 2:30 am to 6:00 pm
Activity :
1) SCAN time/Processor Loading check for PLC/DCS.2) PLC/DCS System Diagnostic checks. 3) SOE Functionality and station interchangeability check.4) Graphic Check Record Verification5) Third party Interface on MODBUS Check.
31 Aug 10
Time : 10:00 am to 1:00 pm
Activity :
Common area Functionality
1) AIMS/DON functionality.2) OPC connectivity, Report Generation.3) GPS Time Syncroniasation check.4) HMS Installation check.
Time : 2:30 am to 6:00 pm
Activity :
1) Loop Check Record verification.2) Graphic Check Record Verification.3) Interlock/Sequence Check record verification.