SAS Support & PrealignmentStructure Design
Matthew Capstick
2019-07-03
-
Cast Base
-
Base Plates
-
Base Plates - Adjustments
-
Base Plates - Adjustments
6 Degrees of Freedom
-
Integrated Girder Pre-AssemblyIntegrated girder, preassembled off-line:• AS and flexure adjustment• Lateral actuators and flexures• Longitudinal actuator and flexure• WPS• Vertical flexure attachment brackets
-
Girder InstallationGirder assembly positioned within the tunnel in approximately the correct position. Vertical position defined by jacks/spacers.
-
Middle Support Installation
-
Middle Support Installation
-
Middle Support Installation
-
Middle Support Installation
-
Middle Support Installation
-
Middle Support Installation
-
Middle Support Installation
-
Middle Support Installation
-
End Support Installation
-
End Support Installation
-
End Support Installation
-
End Support Installation
-
End Support Installation
-
End Support Installation
-
End Support Installation
-
End Support Installation
-
End Support Installation
-
Installation
-
WPS Location
-
WPS Location - MBQ
-
Installation Method
1. Preinstall base plates within the tunnel
-
Installation Method
1. Preinstall base plates within the tunnel
2. Drop girder assembly into approximately the correct position, height defined by spacers/jacks
-
Installation Method
1. Preinstall base plates within the tunnel
2. Drop girder assembly into approximately the correct position, height defined by spacers/jacks
3. Base plates are adjusted to the position of the girder
-
Installation Method
1. Preinstall base plates within the tunnel
2. Drop girder assembly into approximately the correct position, height defined by spacers/jacks
3. Base plates are adjusted to the position of the girder
4. The girder is mounted to the base plates
-
Installation Method
1. Preinstall base plates within the tunnel
2. Drop girder assembly into approximately the correct position, height defined by spacers/jacks
3. Base plates are adjusted to the position of the girder
4. The girder is mounted to the base plates
5. The base plates are re-adjusted to achieve the girder prealignment