CONSTRUCTION OF DAMATURU MAIN DRIANAGE CHANNEL YOBE STATE 2010-2011 Contributions of Adamu Sariki

Transcript of sariki profile

NATIONAL SECURITY COMMUNICATION PROJECT

CONSTRUCTION OF DAMATURU MAIN DRIANAGE CHANNELYOBE STATE2010-2011Contributions of Adamu Sariki

Excavation works

Excavation and taking level along 4km from Kandaha 00km

Challenges in the construction and solutions provided

Buckling of the channel walls due to excess water settlement behind the rip rap

Excess rain water in the channel and sectional pumping out to continue work

Working under an Existing Bridge

Demolition of existing bridge, inside creating a temporary way for water flow

SURVEY and EXCAVATION WORKS

Inside taking of Level for channel walls, surveyor using a GPS to locate the centre line and direction of channel flowTemporary water flow

Stabilization Blinding and Laying of Rebar

Laying of Geotextile for stabilization and blinding

Casting and Construction works

Casting of Walls

Excavation and Casting of RIP RAP

FINISHED SECTION OF BRIDGE AND CHANNEL

NATIONAL SECURITY COMMUNICATION PROJECT CONTRIBUTIONS OF SARIKI ADAMU TO THE PROJECT IN ENGINEERING IMPLEMENTATION SECTION

SARIKI ADAMUID: 10122888Civil EngineerEngineering Implementation sectionRegion (Abuja, Enugu, Bayelsa, Imo, Abia, Rivers, Kogi, Cross River, Akwa Ibom)

Abuja Switch room Fndn Rebar

Abuja P1 Fndn Casting

Abuja Maitama, Zuba Sites, inside Picture with ZTE IT Guys

Abuja Temp. Switch room Fndn

Pictures of Abia switch room

Pictures of Abia Switch room challenges

REGIONS COVERED IN ENUGUEnugu BTS sites with Mr wangEnu-p4Enu-P10Enu-P1 TOWER

Enugu-P10 foundation casting and Enu-P1Fndn on the hill

Abia BTS sites and switch room (18 sites)

Curing 35m tower foundationIron work in Foundation35m, setting of template

Some pictures of Rivers state, Imo, Bayelsa, Abia state works progress

Casting of Riv-N8Fixing of Abia N10 cable tray Abia state university uturu

Some pictures of Rivers state, Imo, Bayelsa, Abia state works progress

Casting of River-P8 and Rivers_p19 pile cap

Fixing of Abia state switch room suspended floor works progress

Some pictures of Rivers state, Imo, Bayelsa, Abia state works progress

Compaction of Umuahia switch room tower fnd.Rumukpakani pile fdn 1

24

Pictures of challenges at site

Resolving communityIssuesCollapsed excavated wallRemoval of existing foundation Abia state switch room

Tower Integrity test

Tower Integrity test

Tower earthing Integrity test

Tower Foundation Construction

Rivers N7 state model primary school rukpoku portharcortFndn rebar, fixing form work and casting

Thank you

Sariki Adamu10122888

Brains and Hammers Real Estate Development, Life campEstate.

Construction of Duplex and 4 Bedroom terrace Buildings with facilities

FEB. 2014 - DATE

Exc. and blinding of trench and pits

Fixing and alignment of columns

Fixing of reinforcements for base and columns alignment

Fixing of reinforcements for base and columns alignment Casting of conc. In fndn

Casting of conc. In fndn

Laying of block work in fndn.

Block work in foundation

Casting of starter columns

Casting of tie beams, and block work to FGL

Casting of ring beams, and block work to FGL40

Casting of tie beams, and block work to FGLGround floor block work

Fixing form work for lintels

Ground floor block work, form work to lintels

External plaster and screeding, lifecamp phase 1

Brains and Hammers Galadimawa

Block work in foundation, Hollow filling, casting of starter columns

Substructure galadimawa project

Ground floor kicker and block forming, 1st floor column alignment

Ground floor block work

Iron work in first floor slabs and beams

Form work and iron work in beams and slab

First and Second floor column alignment and casting

Column alignment

Second floor column alignment and block work

Block work to second floor

Scaffoldings/Roofbeam iron workColumn alignment

Scaffolding and roof parapet fixing

Fixing roof tiles in galadimawa

VITALVOX PROJECTLand reclamationConstruction of estate roads and line drainsConstruction of Box culverts

COMPANYFOUNTAIN CONSTRUCTION COMPANYLocation: Warewa Ogun State(lagos-Ibadan express way)

Using a swamp buggy

Using a swamp buggy to clear and sandfill to reclaim the land for the project 40hecters

FCC yard and batching plant, vitalvox project WAWA Ogun stateReclaimed land for Vitalvox projectFilled area ready for compaction

Dry mix Blinding for laying of line drainsExcavation for line drainsLaying of line drains

Connection of line drain to Box culvertConnection of line drain to Box culvert

Casting of base for precast box culvert

Swamp buggy working on the canal and embankment to the line drainsLaying of precast line drains

Sub-Base along C1 vitalvox prjectLaying of stone-BaseStone-Base and cover slab vitalvox project

Stone base first layer @ vitalvox projectSub-Base along C4 vitalvox prject

Line drain connections through intersections and round about

Work way and roundabout drains

Kerbs at intersections, vitalvox project (the gardens estate)