SAP–Primavera IntegrationV2.0
-
Upload
prashant-sharma -
Category
Documents
-
view
216 -
download
0
Transcript of SAP–Primavera IntegrationV2.0
-
7/31/2019 SAPPrimavera IntegrationV2.0
1/14
SAP Primavera Integration
7 June 2012
-
7/31/2019 SAPPrimavera IntegrationV2.0
2/14
Confidential Slide
Objective
The Objective of SAP Primavera Integration is to having aCentral Tool which will give the progress status of Project.
The Progress should get recorded automatically on the basisof events. i.e. PO Creation, GRN,Service Entry, Payments.
Smooth Planning for Projects using user friendly Primavera.
Best Reporting from both the Systems.
2
-
7/31/2019 SAPPrimavera IntegrationV2.0
3/14
Confidential Slide
Out Come
Automated Progress Confirmation.
Real Time validated Progress.
Single click S-Curve over any level of Hierarchy.i.e. Area,Package, Discipline, Package, Project, etc.
Primavera and SAPs Best Reports.
Responsibilities, Priorities, Ownership Information ofdeliverables.
Highliting Critical focus Points and concerns .
3
-
7/31/2019 SAPPrimavera IntegrationV2.0
4/14
Confidential Slide
Key BenefitsPro active Amendment Notification
The main advantage of integration will be the Pro-activeamendment notification by System.
i.e. Consider a Work order having one service concreting on three areas
Cost Progress (SAP) - 2100*15+3500*12+2000*8 = 61 K =67.54 %
Physical Progress (Primavera)- 50*30%+66.67*40%+40*30% = 66.16 %
As Cost Progress is too high than the Physical Progress means This will leadto an amendment.
4
GCW1
Admin Building
Boundry Wall
Road and darins
Qty(CUM)
ServiceRate (Rs)
WeightagePt
Progress(CUM)
Progress%
2000 15 30% 2100 1.05
3000 12 40% 2000 .6667
5000 8 30% 2000.40
-
7/31/2019 SAPPrimavera IntegrationV2.0
5/14
Confidential Slide
Key Benefits Cont..
Standerdization of Project Structure for all Systems (SAP andPrimavera).
Standerdization of Reports.
Standerdization of Progress Reporting.
Standerd, On system, One click Report availability.
5
-
7/31/2019 SAPPrimavera IntegrationV2.0
6/14
Confidential Slide
Current System Status
Currently All Financial Activities are happening in SAPSystem as PO/WO Creation,GRN, Service Entry etc.
While Primavera System having all the Planing Dates,
MileStone dates and, Activity relations.
6
Project Budget
PO/WO Creation
Purchase Orders/Work Orders
GRN / Service Entry
Payments
Projects Plan
Project Dates
Activity Relations
MileStones
-
7/31/2019 SAPPrimavera IntegrationV2.0
7/14Confidential Slide
Gaps for Real Time Progress
To meet the real time progress, the financial events must besynchronized with the Physical progress.
This means both the Systems must have same structure. i.e.Planning Structure should be same as of Ordering structure.
Activities should get Synchronized between the systems.
Currently all activities need to be confirmed manually, whilethey will be get confirmed automatically after Integration
7
-
7/31/2019 SAPPrimavera IntegrationV2.0
8/14Confidential Slide
System Integration Points
Project
Structure
Package Weightage
Planning
Priorities
Actual Progress
8
Projects
WBS
POC Points
Networks
Activities
Operations
Planning Dated
Actual Progress
User Fields
Actual Progress
Projects
WBS
Activities
Activities Work
Activity Codes
Planning Dates
Relationships
Actual Progress
-
7/31/2019 SAPPrimavera IntegrationV2.0
9/14Confidential Slide
Planning Process after Integration
9
-
7/31/2019 SAPPrimavera IntegrationV2.0
10/14Confidential Slide
Progress Structure for Integration
10
-
7/31/2019 SAPPrimavera IntegrationV2.0
11/14Confidential Slide
SAP Primavera after Integration
11
Planning DatesCost Info
-
7/31/2019 SAPPrimavera IntegrationV2.0
12/14Confidential Slide
Project Plan and Progress
12
S/N Activity Responsibility Status Date
1 Project Structure Finalization PMO Team, IT - SAP Completed 06.06.2012
2 Technology and ToolFinalization
IT - SAP In Progress 20.06.2012
3 Primavera Architect PMO Team 22.06.2012
4 Integration Tool Ordering PMO Team 30.06.2012
5 Tool Deployement IT - SAP 28.07.2012
6 Phase -1 :Integration IT - SAP 05.08.2012
7 Phase-2 : Auto Confirmation IT - SAP 20.08.2012
8 Phase-3 : Advancement IT - SAP 05.09.2012
-
7/31/2019 SAPPrimavera IntegrationV2.0
13/14Confidential Slide
Challenges and Required Management Support
Budget for Integration Tool-
Speciliazed Resource Required
1. Primavera Architect and Administrator.
2. SAP Project System Architect.
Currently there is no Primavera/SAP Architect to support the initiative.
Nomination for Integration Team.
13
S/N Budget Description Amount (Lacs)
1 Integration Tool , Set up, and Deployement 45
2 Tool Licencing 25
3 Primavera Architect 10
4 SAP Project System Architect 10
Total 90
-
7/31/2019 SAPPrimavera IntegrationV2.0
14/14
Thank You
7 June 2012