    SAP Primavera Integration

    7 June 2012

  • 7/31/2019 SAPPrimavera IntegrationV2.0

    2/14

    Confidential Slide

    Objective

    The Objective of SAP Primavera Integration is to having aCentral Tool which will give the progress status of Project.

    The Progress should get recorded automatically on the basisof events. i.e. PO Creation, GRN,Service Entry, Payments.

    Smooth Planning for Projects using user friendly Primavera.

    Best Reporting from both the Systems.

    2

  • 7/31/2019 SAPPrimavera IntegrationV2.0

    3/14

    Confidential Slide

    Out Come

    Automated Progress Confirmation.

    Real Time validated Progress.

    Single click S-Curve over any level of Hierarchy.i.e. Area,Package, Discipline, Package, Project, etc.

    Primavera and SAPs Best Reports.

    Responsibilities, Priorities, Ownership Information ofdeliverables.

    Highliting Critical focus Points and concerns .

    3

  • 7/31/2019 SAPPrimavera IntegrationV2.0

    4/14

    Confidential Slide

    Key BenefitsPro active Amendment Notification

    The main advantage of integration will be the Pro-activeamendment notification by System.

    i.e. Consider a Work order having one service concreting on three areas

    Cost Progress (SAP) - 2100*15+3500*12+2000*8 = 61 K =67.54 %

    Physical Progress (Primavera)- 50*30%+66.67*40%+40*30% = 66.16 %

    As Cost Progress is too high than the Physical Progress means This will leadto an amendment.

    4

    GCW1

    Admin Building

    Boundry Wall

    Road and darins

    Qty(CUM)

    ServiceRate (Rs)

    WeightagePt

    Progress(CUM)

    Progress%

    2000 15 30% 2100 1.05

    3000 12 40% 2000 .6667

    5000 8 30% 2000.40

  • 7/31/2019 SAPPrimavera IntegrationV2.0

    5/14

    Confidential Slide

    Key Benefits Cont..

    Standerdization of Project Structure for all Systems (SAP andPrimavera).

    Standerdization of Reports.

    Standerdization of Progress Reporting.

    Standerd, On system, One click Report availability.

    5

  • 7/31/2019 SAPPrimavera IntegrationV2.0

    6/14

    Confidential Slide

    Current System Status

    Currently All Financial Activities are happening in SAPSystem as PO/WO Creation,GRN, Service Entry etc.

    While Primavera System having all the Planing Dates,

    MileStone dates and, Activity relations.

    6

    Project Budget

    PO/WO Creation

    Purchase Orders/Work Orders

    GRN / Service Entry

    Payments

    Projects Plan

    Project Dates

    Activity Relations

    MileStones

  • 7/31/2019 SAPPrimavera IntegrationV2.0

    7/14Confidential Slide

    Gaps for Real Time Progress

    To meet the real time progress, the financial events must besynchronized with the Physical progress.

    This means both the Systems must have same structure. i.e.Planning Structure should be same as of Ordering structure.

    Activities should get Synchronized between the systems.

    Currently all activities need to be confirmed manually, whilethey will be get confirmed automatically after Integration

    7

  • 7/31/2019 SAPPrimavera IntegrationV2.0

    8/14Confidential Slide

    System Integration Points

    Project

    Structure

    Package Weightage

    Planning

    Priorities

    Actual Progress

    8

    Projects

    WBS

    POC Points

    Networks

    Activities

    Operations

    Planning Dated

    Actual Progress

    User Fields

    Actual Progress

    Projects

    WBS

    Activities

    Activities Work

    Activity Codes

    Planning Dates

    Relationships

    Actual Progress

  • 7/31/2019 SAPPrimavera IntegrationV2.0

    9/14Confidential Slide

    Planning Process after Integration

    9

  • 7/31/2019 SAPPrimavera IntegrationV2.0

    10/14Confidential Slide

    Progress Structure for Integration

    10

  • 7/31/2019 SAPPrimavera IntegrationV2.0

    11/14Confidential Slide

    SAP Primavera after Integration

    11

    Planning DatesCost Info

  • 7/31/2019 SAPPrimavera IntegrationV2.0

    12/14Confidential Slide

    Project Plan and Progress

    12

    S/N Activity Responsibility Status Date

    1 Project Structure Finalization PMO Team, IT - SAP Completed 06.06.2012

    2 Technology and ToolFinalization

    IT - SAP In Progress 20.06.2012

    3 Primavera Architect PMO Team 22.06.2012

    4 Integration Tool Ordering PMO Team 30.06.2012

    5 Tool Deployement IT - SAP 28.07.2012

    6 Phase -1 :Integration IT - SAP 05.08.2012

    7 Phase-2 : Auto Confirmation IT - SAP 20.08.2012

    8 Phase-3 : Advancement IT - SAP 05.09.2012

  • 7/31/2019 SAPPrimavera IntegrationV2.0

    13/14Confidential Slide

    Challenges and Required Management Support

    Budget for Integration Tool-

    Speciliazed Resource Required

    1. Primavera Architect and Administrator.

    2. SAP Project System Architect.

    Currently there is no Primavera/SAP Architect to support the initiative.

    Nomination for Integration Team.

    13

    S/N Budget Description Amount (Lacs)

    1 Integration Tool , Set up, and Deployement 45

    2 Tool Licencing 25

    3 Primavera Architect 10

    4 SAP Project System Architect 10

    Total 90