Santa Rita Solar Power Project - PG&E, Pacific Gas and ... · Integrated Solar Power Project....
Transcript of Santa Rita Solar Power Project - PG&E, Pacific Gas and ... · Integrated Solar Power Project....
General Services Agency: Slide General Services Agency: Slide 11
Self-Generation Incentive Program (SGIP) WorkshopSan Ramon, CA
Santa Rita Jail Solar Power ProjectA Customer’s Perspective
October 17, 2003
General Services Agency: Slide General Services Agency: Slide 22
What will be CoveredWhat will be Covered
Santa Rita Integrated Solar Power Project Overview
Decision Making Process
Installation Process
Results
Questions?
General Services Agency: Slide General Services Agency: Slide 33
The Largest Rooftop Array in the CountryThe Largest Rooftop Array in the Country
1.18 mW Solar Power Array at Santa Rita Jail
General Services Agency: Slide General Services Agency: Slide 44
Case Study: The Santa Rita Jail Integrated Solar Power ProjectCase Study: The Santa Rita Jail Integrated Solar Power Project
General Services Agency: Slide General Services Agency: Slide 66
The Santa Rita Jail Integrated Solar Power Energy ProjectThe Santa Rita Jail Integrated Solar Power Energy Project
Consisting of Four Energy Conservation Measures
1.18 mW Solar Power Generation: the Nation’s largest roof top solar installation Variable Flow 850-ton Centralized Chilled Water Plant (Air-Conditioning) UpgradeCool Roof ResurfacingSmart Energy Management System for Verification
General Services Agency: Slide General Services Agency: Slide 77
Santa Rita Jail Aerial ViewSanta Rita Jail Aerial View
General Services Agency: Slide General Services Agency: Slide 88
Santa Rita Jail, Dublin, CASanta Rita Jail, Dublin, CA
Construction 1984-1989Occupied Space:
1 million sqft.Peak Electrical Load:
3.2 mW (8/00) 18 Housing Units4300 inmates513 Sheriff’s Dept. staff106 GSA staff
General Services Agency: Slide General Services Agency: Slide 99
Santa Rita Jail’s July 2001 Electric BillSanta Rita Jail’s July 2001 Electric Bill
Billing Summary - E20P Non-FirmService Charge $ 500.00Demand Charges $ 23,554.50Energy Charges $ 65,048.18Economic Stimulus Credit $ -6,048.24Power Factor Adjustment $ 498.13
Total of OAS $ 83,520.57
Non-residential Energy Procurement Surcharge $ 14,047.62Energy Surcharge $ 63,580.19Total Pre-Tax Billed Amount $161,175.38
General Services Agency: Slide General Services Agency: Slide 1010
Decision Making TimelineDecision Making Timeline
May 2000 Powerlight Tours SRJSeptember 2000 Powerlight Submits Initial ProposalNovember 2000 Final Proposal AcceptedDecember 2000: Submitted AB970 Grant BidsDecember 2000: GSA Approves Recommendation to BOSJanuary 2001: BOS Approves Project
General Services Agency: Slide General Services Agency: Slide 1111
How did Alameda County finance this project?How did Alameda County finance this project?
Project Construction Costs1.18 mW Solar Array $8,200,000Chilled Water Plant Retrofit $1,000,000Cool Roof $1,100,000
Total Project Costs $10,300,000
General Services Agency: Slide General Services Agency: Slide 1212
How did Alameda County finance this project?How did Alameda County finance this project?
IncentivesCEC Buydown Grant @ $4.50/W $2,560,000PG&E’s Self-Generation Grant $1,770,000AB970 Grant, Solar $ 306,000AB970 Grant, Smart Controls $ 84,000AB970 Grant, Cool Roofs $ 45,000CPUC Cross-cutting Grant $ 250,000AB29X Early Project Completion $ 30,000Total Incentives $5,045,000
General Services Agency: Slide General Services Agency: Slide 1313
How did Alameda County finance this project?How did Alameda County finance this project?
Cost to the CountyTotal Construction Costs $10,300,000
Less Incentives $5,045,000Energy Fund $1,193,000Major Maintenance $1,800,000First year savings $ 412,000CEC Loan @ 6.0% Interest $ 780,000CEC Loan @ 3.0% Interest $1,070,000
General Services Agency: Slide General Services Agency: Slide 1414
Construction TimelineConstruction Timeline
March 2001: Construction Begins
July 2001: 530 kW Solar Power Operational – Phase 1
August 2001: BOS approves Phase 2 Expansion of the Solar Power Project
October 2001 Solar Power Operational Phase 2
Dec 2001: BOS approves Phase 3 expansion Solar Power Project
April 2002: Solar Power Operational - Phase 3
General Services Agency: Slide General Services Agency: Slide 1515
How are we producing electricity from the sun?How are we producing electricity from the sun?
General Services Agency: Slide General Services Agency: Slide 1616
Simple Installation: No Roof PenetrationsSimple Installation: No Roof Penetrations
General Services Agency: Slide General Services Agency: Slide 1717
Simple Installation: Interconnecting with the Building’s Electrical SystemSimple Installation: Interconnecting with the Building’s Electrical System
General Services Agency: Slide General Services Agency: Slide 1818
Measurement & VerificationMeasurement & Verification
General Services Agency: Slide General Services Agency: Slide 1919
Solar Peak Load Reduction Solar Peak Load Reduction
Utility Company’s Summer Peak Time ScheduleMay 1 - Oct 31, 12:00 noon to 6:00 p.m. M-F
Summer Peak Period Demand Charges$11.80 / kW
Summer Maximum Demand Charges$2.55 / kW
General Services Agency: Slide General Services Agency: Slide 2020
Summer Peak Load ReductionSummer Peak Load Reduction
From Utility Electric Bill for Santa Rita Jail
Prior to Solar Project Installation:August 2000 Peak Demand: 3,212 kW
After Solar Project Installation:August 2003 Peak Demand: 2,154 kW
Total Peak Demand Reduction: August 2000 vs. August 2002: 1,058 kW (-33.0%)
General Services Agency: Slide General Services Agency: Slide 2121
Solar Production: Sunny DayJuly 7, 2003Solar Production: Sunny DayJuly 7, 2003
General Services Agency: Slide General Services Agency: Slide 2222
Summer Load Profile: July 6, 2003Summer Load Profile: July 6, 2003
General Services Agency: Slide General Services Agency: Slide 2323
Solar Production: Rainy DayMarch 3, 2003Solar Production: Rainy DayMarch 3, 2003
General Services Agency: Slide General Services Agency: Slide 2424
Winter Load Profile: March 3, 2003Winter Load Profile: March 3, 2003
General Services Agency: Slide General Services Agency: Slide 2525
Results2003 Solar Generation FactsResults2003 Solar Generation Facts
Peak Solar Electric Demand Generation: 879kWMay 7th @12:15 p.m.
Maximum % of Electricity Supplied by Solar: 45.3%May 9th @12:45 p.m.
Solar Electric Generation To Date: 1,160,737 kWhJanuary 2003 – September 2003:
Solar Electric Cost Savings To Date: $163,817January 2003 – September 2003:
General Services Agency: Slide General Services Agency: Slide 2626
Peak Solar Production: 879 kWMay 7, 2003 @ 12:15 p.m.Peak Solar Production: 879 kWMay 7, 2003 @ 12:15 p.m.
General Services Agency: Slide General Services Agency: Slide 2727
Peak Solar Production: 45.3% of Building Load on May 9, 2003 @ 12:45 p.m.Peak Solar Production: 45.3% of Building Load on May 9, 2003 @ 12:45 p.m.
General Services Agency: Slide General Services Agency: Slide 2828
Solar Peak Load Reduction & Cost SavingsSolar Peak Load Reduction & Cost Savings
May: 598kW, $5,550June: 578kW, $7,891July: 477kW, $6,446August: 359kW, $5,360September: 510kW, $6,725October: 416kW, $6,200 (est.)Total Summer Demand Savings: $38,172
General Services Agency: Slide General Services Agency: Slide 2929
Santa Rita Solar Project FactsSanta Rita Solar Project Facts
1.4 million kWh generated annually and 34.4 million kWh over the 25-year life of the system$211,000 Annual Cost Savings from solar generation and $207,000 in Annual Energy Efficiency Cost SavingsTotal area covers 3 acres of roofMaximum solar generation: 879 kWacMaximum monthly demand savings: 598 kWac$0.053/kWh (fixed) generated electrical power for 25 years with subsidies from the energy efficiency measures
General Services Agency: Slide General Services Agency: Slide 3030
Awards Alameda County’s Energy ProgramAwards Alameda County’s Energy Program
2002 Green Power Leadership Award presented by the U.S. Environmental Protection 2002 Flex Your Power Energy Award presented by the State of California, the 2002 Energy Efficient Building Award for Best Institutional Project from Energy User News2002 Challenge Award at the California State Association of Counties (CSAC) 2002 California Governor’s Environmental and Economic Leadership Award.
General Services Agency: Slide General Services Agency: Slide 3131
Sunset over the Solar Power System at Santa Rita JailSunset over the Solar Power System at Santa Rita Jail
Matthew Muniz, P.E., Energy Program Manager County of Alameda, GSA/TSD, (510) 208-9523email: [email protected]