SWET GANGA HYDROPOWER & CONSTRUCTION LIMITED Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal Site Office, Sirise Ramechhap SWET GANGA HYDROPOWER &CONSTRUCTION LIMITED Shankha Park, Dhumbarahi, Kathmandu M.C, Ward no.: 04, Nepal G. P.O. Box. 19737, Kathmandu, Nepal Tel: (977-1) 4373030, 4372828, 4015788 Fax: (977-1) 4015799 Email: [email protected], Web: www.sanimahydro.com.np CONSULTANT:SANIMA HYDRO AND ENGINEERING P.LTD LOWER LIKHU HYDROPOWER PROJECT (28.1MW) MONTHLY PROGRESS REPORT # 8 November, 2018

Transcript of Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal...

Page 1: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

SWET GANGA HYDROPOWER & CONSTRUCTION LIMITED Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal Site Office, Sirise Ramechhap

SWET GANGA HYDROPOWER &CONSTRUCTION LIMITED Shankha Park, Dhumbarahi, Kathmandu M.C, Ward no.: 04, Nepal G. P.O. Box. 19737, Kathmandu, Nepal Tel: (977-1) 4373030, 4372828, 4015788 Fax: (977-1) 4015799 Email: [email protected], Web: www.sanimahydro.com.np CONSULTANT:SANIMA HYDRO AND ENGINEERING P.LTD

LOWER LIKHU HYDROPOWER PROJECT (28.1MW)

MONTHLY PROGRESS REPORT # 8 November, 2018

Page 2: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

SWET GANGA HYDROPOWER & CONSTRUCTION LIMITED Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal Site Office, Sirise Ramechhap

SWET GANGA HYDROPOWER &CONSTRUCTION LIMITED Shankha Park, Dhumbarahi, Kathmandu M.C, Ward no.: 04, Nepal G. P.O. Box. 19737, Kathmandu, Nepal Tel: (977-1) 4373030, 4372828, 4015788 Fax: (977-1) 4015799 Email: [email protected], Web: www.sanimahydro.com.np CONSULTANT:SANIMA HYDRO AND ENGINEERING P.LTD

LOWER LIKHU HYDROPOWER PROJECT (28.1 MW)

Rev: _________________________________________________________________

Signature Date

Prepared by:

Ranjeet Nepal 2018-11-30

Checked by:

Sudip Chapagai

Approved by:

Bhoj Raj Paudel

Page 3: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

Lower Likhu Hydropower Project Progress Report November 2018

i Swet Ganga Hydropower & Construction Limited

Table of Contents 1 PROJECT OVERVIEW AND INSTITUTIONAL ARRANGEMENT .......................................... 1

2 KEY DATES ............................................................................................................................. 1

3 CONTRACT PACKAGES AND IMPLEMENTATION .............................................................. 2

4 FINANCING ............................................................................................................................. 2

5 RESOURCES AT SITE ............................................................................................................ 2

6. CIVIL CONSTRUCTION WORK PROGRESS .............................................................................. 4

6.1 HEAD WORKS ...................................................................................................................... 4

6.2 TUNNEL ................................................................................................................................ 4

6.2.1 HRT INLET PORTAL ......................................................................................................... 4

6.2.2 SETI OUTLET PORTAL ..................................................................................................... 5

6.2.3 SETI INLET PORTAL ......................................................................................................... 5

7. SOCIAL AND ENVIRONMENT ..................................................................................................... 6

8. EQUIPMENT BREAKDOWN ........................................................................................................ 6

9. VISITORS OF THE MONTH ......................................................................................................... 6

10. ACCIDENT .................................................................................................................................. 7

11. WORK PROGRESS AT SITE ..................................................................................................... 7

12. PHOTOS ..................................................................................................................................... 8

Page 4: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

Lower Likhu Hydropower Project Progress Report November 2018

ii Swet Ganga Hydropower & Construction Limited

List of Figures Figure 1: A View of flood wall excavation......................................................................................... 4

Figure 2: A View of HRT Inlet Portal Before first Blast ..................................................................... 4

Figure 3: A View of Seti Outlet Portal Before first Blast ................................................................... 5

Figure 4: A View of Seti Inlet Portal Before first Blast ...................................................................... 5

Figure 5: Visitors of Dolma impact fund ........................................................................................... 6

Figure 6: A View of Head works Staff Quarter ................................................................................. 8

Figure 7: Progress on HRT Inlet portal (Left) & Progress on Seti outlet portal (Right) ..................... 8

Figure 8: Progress on Seti inlet portal (Left) & View of Poku outlet portal (Right) ............................ 8

Figure 9: A View of Access road to Poku inlet portal (Left) & View of labor camp at Power house

(Right) .............................................................................................................................................. 9

Figure 10: Progress on river diversion at Headworks area (Left) & View of construction material

(Right) .............................................................................................................................................. 9

Figure 11: A View of rock crusher at Headworks area (Left) & View of crushed aggregate(Right) . 9

Figure 12: A View of contractor camp at Seti (Left) & View of Diesel tank and Diesel generator

(Right) ............................................................................................................................................ 10

Figure 13: Gabion protection work at Poku inlet road (Left) &Gabion protection work at surge shaft

road ................................................................................................................................................ 10

Figure 14: View of Surge shaft Area .............................................................................................. 10

List of Tables Table 1: Civil Contractor Equipment Details .................................................................................... 3

Table 2: Detail of Construction Material Stock ................................................................................. 3

Page 5: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

Lower Likhu Hydropower Project Progress Report November 2018

1 Swet Ganga Hydropower & Construction Limited

1 PROJECT OVERVIEW AND INSTITUTIONAL ARRANGEMENT

Lower Likhu Hydropower Project (LLHP) is a run-of-river (RoR) hydropower project which utilizes 118 m Gross Head and Design Discharge of 29.75 m3/s resulting an installed capacity of 28.1 MW. The entire project area (Headworks to Powerhouse) is located in Likhu Tamakoshi Rural Municipality (Saipu-2 and Bijulikot-4) of Ramechhap Province-3. Geographically, the project lies between longitudes 86°15’38” E to 86°13’17” E and latitudes 27°25’56” N to 27°22’47”N.

Lower Likhu Hydropower Project (LLHP) was identified by Swet Ganga Hydropower & Construction Ltd. which received Generation License from Department of Electricity Development (DoED), the then Ministry of Energy (MoEN), Government of Nepal (GoN on 2nd Baishak 2073 (14th April 2016) for its implementation. The license period of the project is from 28th Chaitra 2072 to 27th Chaitra 2107 B.S Swet Ganga has signed Power Purchase Agreement (PPA) with Nepal Electricity Authority (NEA) on 14th Poush 2073 (29th Dec 2016).

Construction Management:

The Employer/Owner: Swet Ganga Hydropower and Construction Ltd. (SGHCL) The Engineer/Consultant: Sanima Hydro and Engineering (P.) Ltd. (SHEPL) The Contractor (Civil Construction): High Himalaya Hydro Bavari-Construction Jv,

Kathmandu, Nepal

The Contractor (Hydro-mechanical): Negotiation ongoing

The Contractor (Electro-mechanical): PQ documents received

2 KEY DATES

Grid connection agreement 12

th Chaitra 2072 (25

th March 2016)

Generation License issued by Department Electricity Development (DoED), Ministry of Energy (MoEn), Government of Nepal (GoN)

2nd

Baisakh 2073 (14th April 2016)

The license period of the project is from 28

th Chaitra 2072 to 27

th Chaitra 2107 B. S.

Power Purchase Agreement (PPA) with Nepal Electricity Authority (NEA) 14

th Poush 2073 (29

th Dec 2016)

Letter of Acceptance for civil works 7th February 2018

Financial Closure 22th February 2018

Contract of main Civil works Chaitra 2074 (March 2018)

RCOD 1st

December 2021

Page 6: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

Lower Likhu Hydropower Project Progress Report November 2018

2 Swet Ganga Hydropower & Construction Limited

3 CONTRACT PACKAGES AND IMPLEMENTATION

Main Civil construction works: Civil Contractor CONTRACT Package 1 Hydro-mechanical and Penstock: HM Contractor CONTRACT Package 2 Equipment (Electromechanical): EM Supplier CONTRACT Package 3 Power evacuation Transmission: TL Contractor CONTRACT Package 4 Preparatory works, Owner’s housing, Socio-environmental: EmployerDirect

4 FINANCING

Equity: Promoters (SMHL)25% of the total Project Cost Debt: Consortium of Local Banks75% of the total Project Cost: Lead-Laxmi Bank,

Member Banks: Kumari Bank Ltd., HIDCL. Century Bank Ltd., Prabhu Bank Ltd.

5 RESOURCES AT SITE

Employer:

Description Number

Assistant Resident Engineer 1

Assistant Manager 1 Geologist 1 Civil Engineer 3 Admin/Account 1 Sub-Engineer(Overseer) 3 Surveyor 1 Social and Environment officer

1

Social Mobilizer 4 Survey Helper 1 Office Assistant 2 Driver 1 Cook 1 Total: 21

Civil Contractor:

Description Number Project Manager 1 Construction Manager 1 Tunnel Manager 1 Civil Engineer 12 Geologist 2 Surveyor 3 Overseer/Sub-overseer 3 Lab Technician/Helper 2 Skilled Manpower 5 Unskilled Manpower 14 Operator/Driver/Helper 25 Supervisor/Foreman 4 Mechanical/Electrical worker 12 Office/store/Purchase 15

Page 7: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

Lower Likhu Hydropower Project Progress Report November 2018

3 Swet Ganga Hydropower & Construction Limited

Cook/peon/helper 4 Security guards 8 Total 112

Table 1: Civil Contractor Equipment Details

S.N Equipment Name Number Location Condition Remarks

1 Excavator 220 3 HW Working 2 Backhoe Loader (JCB) 2 HW Working 3 Dum Truck 5 HW Working 4 Truck 1 Working 5 Tractor 2 HW Working 6 Generator 62.5KVA 1 HW Working 7 Generator 30KVA 1 Seti Camp Working

8 Generator 125KVA 2 Seti Camp & portal Working

9 Generator 15KVA 1 10 Wheel loader 3 HW Working 11 Light vehicle 4 Working 12 Motor bike 1 Working

13 Concrete mixer(including lab) 3 HW,Seti Working

14 Compressive strength test machine 1 Lab Working

15 Hand drill machine 2 Working 16 Air compressor 2 Seti,HW Working 17 Vibrators 1 Working 18 Water pump 4” 1 HW Working 19 Water pump 1” 3 Working 20 Grinding machine 1 Seti Working 21 Welding machine 4 Seti Working 22 Ply cutter machine (8”/7”) 1 Working 23 Prism with tripod set 3 Working 24 Levelling staff 1 Working 25 Total station 2 Working 26 Auto level 1 Working 27 Shot Crete machine PZ5 2 Seti Working 28 Jack Hammer 18 Working 29 Diesel Tank 16000Ltr 2 Working

Table 2: Detail of Construction Material Stock

Materials Unit Balance Qty Remarks

Cement Bags 242 Diesel Ltrs 13460

Rebar (20mm) Ton 8 Rebar (16mm) Ton 16

Rebar (12mm) Ton 16

Page 8: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

Lower Likhu Hydropower Project Progress Report November 2018

4 Swet Ganga Hydropower & Construction Limited

6. CIVIL CONSTRUCTION WORK PROGRESS

6.1 HEAD WORKS

Excavation for flood wall is going on up to level 729m. Excavation for drainage channel (for river diversion) is continued.

Figure 1: A View of flood wall excavation

6.2 TUNNEL

6.2.1 HRT INLET PORTAL

Five Successful blast have been completed at inlet portal. 5 meter length of tunnel has been excavated. 3 steel ribs has been installed (@1m spacing) and shot Crete work around the tunnel has

been ongoing.

Figure 2: A View of HRT Inlet Portal Before first Blast

Page 9: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

Lower Likhu Hydropower Project Progress Report November 2018

5 Swet Ganga Hydropower & Construction Limited

6.2.2 SETI OUTLET PORTAL

Four successful blast have been completed at seti outlet portal. 4 meter length of tunnel has been excavated. 3 Steel ribs has been installed (@1m spacing) with shot Crete work is ongoing.

Figure 3: A View of Seti Outlet Portal Before first Blast

6.2.3 SETI INLET PORTAL

Four successful blast have been completed at seti inlet portal. 5 meter length of tunnel has been excavated. 3 steel ribs has been installed (@0.5m spacing) with shot Crete work is going on.

Figure 4: A View of Seti Inlet Portal Before first Blast

Page 10: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

Lower Likhu Hydropower Project Progress Report November 2018

6 Swet Ganga Hydropower & Construction Limited

7. SOCIAL AND ENVIRONMENT

Lower Likhu Hydropower has been co-ordinating with local stake holders and representative from elected bodies for the smooth run of the project. As per the request of local community, and as a part of environmental and social works the following activities has been commence at site:

Maintenance of irrigation canal at Sirise bazar. Excavation for drinking water works at Seti. Opening of new track at Dumre besi for the transport of construction materials upto

Auronaday School. Facilitated the upgrading and maintenance of road from Sirise to Poku by providing 100ltr of

diesel. Irrigation canal maintenance at Sathibesi. Road landslide clear at Tarkerabari. Excavation of drinking water tank at Ratmata. Road excavation for materials transport to Gramonadaya school at Khalte Upgrading and maintenance of road at Pokali. 10 m3 Gabion support to kalleri irrigation canal committee at Pokali Upgrading and maintenance of road from Sirise to Gamlangtar.

The civil contractor will extract the construction material within the project boundary as per the approved EIA report without degrading the environment and getting approval from the engineer. 8. EQUIPMENT BREAKDOWN

Frequently problems on Shot Crete machine. Excavator Doosan 225LC’s Bucket is taken to Manthali for Repair on 6th Mangsir.

9. VISITORS OF THE MONTH

CEO of Dolma Impact Fund Visited the site on 14th November 2018.

Figure 5: Visitors of Dolma impact fund

Page 11: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

Lower Likhu Hydropower Project Progress Report November 2018

7 Swet Ganga Hydropower & Construction Limited

10. ACCIDENT

No accidents and casualties in this month.

11. WORK PROGRESS AT SITE

Brick masonry work has been completed up to first floor at head works staff quarter. Second floor Brick masonry work is under-construction at head works staff quarter. Ground floor and first floor painting work is going on at head works staff quarter. Ground floor and first floor wiring work is going on at head works building. Contractor’s main general store has been setup at Seti Area. Construction of contractor camp has been completed at power house. Construction of well has been completed at power house. Layout for tailrace is carried out as per new issued drawing. Construction of guest house building, main workshop is on final stage at Seti Area. Construction of water tank is on final stage at Seti Area. Road diversion work has been completed at Head works inlet portal. Access road from head works to power house has been completed. Construction of water tank is going on at surge shaft area. From Power house to Surge shaft access road is complete. From Power house to Outlet portal access road is complete. Access road maintenance and gabion work is being carried out at Poku inlet portal area. Open blast is ongoing to prepare the portal at the Poku inlet area. Construction of contractor’s store is ongoing at Headworks area. The dry stone works at the Kholsi draining (near the inlet portal) of head works is complete. Hydro mechanical contractor MMM has been visited at site. They had been finalized factory

and material stock area nearby Kabetar. MMM contractor request us to acquire the 12 ropani land and this land shall be leased with local community.

132KVA Transmission line final route survey is ongoing.

Page 12: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

Lower Likhu Hydropower Project Progress Report November 2018

8 Swet Ganga Hydropower & Construction Limited

12. PHOTOS

Figure 6: A View of Head works Staff Quarter

Figure 7: Progress on HRT Inlet portal (Left) & Progress on Seti outlet portal (Right)

Figure 8: Progress on Seti inlet portal (Left) & View of Poku outlet portal (Right)

Page 13: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

Lower Likhu Hydropower Project Progress Report November 2018

9 Swet Ganga Hydropower & Construction Limited

Figure 9: A View of Access road to Poku inlet portal (Left) & View of labor camp at Power house (Right)

Figure 10: Progress on river diversion at Headworks area (Left) & View of construction material (Right)

Figure 11: A View of rock crusher at Headworks area (Left) & View of crushed aggregate(Right)

Page 14: Sankha Park, Dhumbarahi, G.P.O.Box 19737, Kathmandu Nepal ...swetgangahydropower.com/uploads/downloads/Progress... · Lower Likhu Hydropower Project Progress Report November 2018

Lower Likhu Hydropower Project Progress Report November 2018

10 Swet Ganga Hydropower & Construction Limited

Figure 12: A View of contractor camp at Seti (Left) & View of Diesel tank and Diesel generator (Right)

Figure 13: Gabion protection work at Poku inlet road (Left) &Gabion protection work at surge shaft road

Figure 14: View of Surge shaft Area